16-002843 Department Of Transportation vs. Zfi Engineering And Construction, Inc.
 Status: Closed
Recommended Order on Wednesday, October 12, 2016.


View Dockets  
Summary: The Department of Transportation established that Respondent violated Department rules and created an unsafe road condition on a road widening project in Polk County.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8DEPARTMENT OF TRANSPORTATION,

11Petitioner,

12vs. Case No. 1 6 - 2843

19ZFI ENGINEERING AND

22CONSTRUCTION, INC.,

24Respondent.

25_______________________________/

26RECOMMENDED ORDER

28D. R. Alexander, Administrative Law Judge of the Division

37of Administrative Hearings (DOAH ) , conducted a hearing in this

47case on July 18 and 19 , 2016, by video teleconferencing at sites

59in Lakeland an d Tallahassee, Florida.

65APPEARANCES

66For Petitioner : Ri chard E. Shine, Esquire

74Department of Transportation

77Mail Station 58

80605 Suwannee Street

83Ta llahassee, Florida 32399 - 0458

89For Respondent: April A. Atkins, Esquir e

96Kirwin Norris, P.A.

99Suite 301

10115 West Church Street

105Orlando, Florida 32801 - 3351

110STATEMENT OF THE ISSUE

114The issue is whether Respondent's constructi on activities

122vi olate d Department standards and create d an unsafe road

133condition , as alleged in the Department's Amended Violation and

142Notice to Show Cause - Non - Compliance with Permit Conditions

153(Notice to Show Cause) issued on March 1, 2016.

162PRELIMINARY STATEMENT

164The Notice to Show Cause alleg es Respondent , an engineering

174firm, violated the terms of two construction permits and created

184an unsafe road condition while performing work on State Road 655

195in Polk County (County) . It f urther alleges Respondent's

205construction activities violated in nine respects Florida

212Administrative Code Rules 14 - 96.007(8) and 14 - 96.011(1)(b). The

223Notice to Show Cause require s that Respondent demonstrate

232satisfactory progress of the road construction within 60 days or

242Department action w ill be initiated to require the Construction

252Performance Bond insurance company to complete the work .

261Respondent timely requested a hearing and the matter was

270transmitted by the Department to DOAH to schedule a formal

280hearing.

281At the hearing, the Department presented the testimony of

290two witnesses. Department Exhibits 1 through 6, 7 - 1, 7 - 2, 7 - 6,

3067 - 8, 7 - 9, 8, 9, 11, and 12 were accepted in evidence.

321Respondent presented the testimony of five witnesses .

329Respondent's Exhibits A1 , A2, A4 through A 7 , B1 through B6, C1,

341C3, D1 through D6, and Rebuttal Exhibits 1 through 3 were

352accepted in evidence.

355A four - volume T ranscript of the hearing was prepared.

366Proposed f indings of f act and c onclusions of law (PROs) were

379filed by the parties, and they have been considered in the

390preparation of this Recommended Order.

395FINDINGS OF FACT

398A. Background

4001. The Department is the state agency responsible for

409regulating access to the state highway s ystem . See § 335.182,

421Fla. Stat. T o ensure that the motoring public is safe , t he

434Department has adopted and incorporated by reference design

442standards, standard specifications, and a Plans Preparation

449Manual (PPM) that must be adhered to by contractors when working

460on state roads . See Fla. Admin. Code R. 14 - 96. 008 .

4742. Respondent is an Orlando engineering firm whose

482principal is Zhi "George" Guo, a registered professional

490engineer. The Guo family is the fee simple owner of a 37 - acre

504tract of land located at 5615 Recker Highway (State Road 655) in

516an unincorporated part of the Coun ty .

5243. Around eight years ago, Mr. Guo began t he process of

536developing the family property as a business park to be known as

548the Recker Highway Business Park Development . To provide access

558to the property from State Road 655, Mr. Guo was required to

570cons truct turn lanes, widen from two lanes to four lanes around

5821,700 feet of road way , construct pave d and unpaved shoulders,

594and install guardrails and sod. The Department considers road

603widening to be a major project. Because all work was within the

615Depart ment's right - of - way, a driveway connection permit and

627drainage connection permit were required. The project begins at

636Station 594.00 and ends at Station 611.00 on State Road 655.

6474 . O n October 16, 2008, Mr. Guo submitted to the

659Department an Access A ppli cation for a driveway connection

669permit.

6705. Among other things, the Access A pplication identifies

679the engineer of record (EOR) , general contractor (GC) , and

688certified engineer inspector (CEI) on the project. The EOR

697signs the plans and verifies that al l work will be in accordance

710with Department standards. The GC is essentially the manager of

720the project and is responsible for its overall coordination.

729The CEI is responsible for making all inspection work on the

740project to ensure that the GC is perfor ming work according to

752the permitted plans. This requires th at the CEI be on the job

765site to observe and verify work done by the GC. The CEI must

778also submit daily reports to the Department documenting

786activities that take place each day while work is be ing

797performed . When all work is completed, t he CEI requests that

809the Department make a final inspection and issue a final

819acceptance of the work . Although the CEI is normally one

830person, t he CEI can be a combination of multiple people if they

843have a Cons truction Training and Qualification Program (CTQP)

852certification required to complete the components of the work ,

861e.g. , earthwork, asphalt, and maintenance of traffic (MOT).

8696 . Mr. Guo's Access Application indicated he would serve

879as EOR and GC . It did n ot identify who would be the CEI, but

895Mr. Guo does not deny that he served as CEI. Notably, Mr. Guo

908submitted daily reports and assumed the duties and

916responsibilities normally associated with that position.

922Mr. Guo has never managed a highway constr uction project such as

934this , although he has done design work on several highway

944projects, mainly related to drainage - improvement work . As the

955GC, Mr. Guo signed and sealed the permitted drawings.

9647. As a general rule, different individuals serve as th e

975EO R , GC, and CEI . If the CEI is also the GC, there are no

991checks and balances to ensure the project is built according to

1002the permitted plans. According to the Department's expert, it

1011is unethical for one person to serve as GC, EO R , and CEI on the

1026same project. However, t he expert had no explanation as to why

1038the Department issued a permit to Mr. Guo under these

1048circumstances , and the Department cited no rule or statute that

1058prohibits this arrangement . The charging document does not

1067allege any wrongdo ing in this respect.

10748. Mr. Guo was concerned about an apparent conflict of

1084interest created by him being the owner of the property, EOR,

1095GC, and CEI. Accordingly, he hired two outside laboratories to

1105perform materials testing, and he used two of his emp loyees , one

1117certified in earthwork and the other in MOT , but neither in

1128asphalt , to act in his stead. There is no evidence that Mr. Guo

1141informed the Department that he had delegated any CEI inspection

1151responsibilities to other individuals. A lthough he as serts a

1161request was made for the Department to inspect the paving

1171progress as it was installed , there is no record of such a

1183request. Indeed, Mr. Guo had no reason to assume, as he did,

1195that the Department permit inspector would "fully perform the

1204inspect ion work ." If this were so, there would be no need for

1218the CEI to perform any inspections on asphalt work.

12279. After being informed by the Department that a drainage

1237construction permit was required, o n January 28, 2009, Mr. Guo

1248filed a second application for that type of permit.

125710 . After additional information was provided by the

1266applicant , o n December 14, 2012, or around four years later,

1277the Department issued to Mr. Guo Driveway/Connection Permit

1285No. 2008 - A - 190 - 0071 and Drainage Connection Permi t No. 2009D -

1301190 - 0003 . The permit conditions required , among other things,

1312that all work be performed in accordance with current Department

1322standards, specifications, and permit provisions; the driveway

1329connection not be used until final acceptance was giv en by the

1341Department ; the applicant be totally responsible for the cost of

1351all work performed inside the Department's right - of - way; and t he

1365applicant accept all conditions of the permit, once work began.

1375At hearing, Mr. Guo agreed t hat he must comply with all permit

1388conditi o ns.

13911 1 . A pre - construction meeting was conducted on January 2,

14042014. Mr. Guo attended the meeting and acted as the EOR, GC,

1416and C EI for the applicant. Among other things, t he purpose of a

1430pre - construction meeting is to discuss the conditions in the

1441permit and to answer any questions that an applicant may have

1452before work beg ins . See also Fla. Admin. Code R. 14 - 96.003(2).

1466At the meeting, Mr. Guo was given a copy of the construction

1478guidelines , which spell out exactly what a contrac tor must do

1489before, during, and after construction. He was also given a

1499copy of " Minimum CEI On Site Inspections and Notifications , "

1508which identif ies the specific duties of the CEI . These

1519documents are also attached to his permits.

15261 2 . A t the heart of t his controversy is a dispute over the

1542actions taken by the Department's permit inspector while

1550monitoring the project . A permit inspector is assigned to

1560monitor the work on all state highway projects. The

1569Department's Bartow District Office has only one permit

1577inspector , Steve Logan, who is responsible for 400 lane miles of

1588road in the County. Mr. Logan must drive through all the jobs

1600that are under construction in the County and bring matters to

1611the attention of the CEI on each project to ensure complia nce

1623with the Department's permitted plans, including items such as

1632traffic control, lane closures, and spot slope measurements. He

1641must also observ e and verify the work done by the CEI , accept

1654and review the daily reports submitted by the CEI , forward th o s e

1668reports to the p ermits d irector at the District Office , and work

1681as the Department's communication contact with the contractor.

1689He also receives asphalt mix designs from the CEI and forwards

1700them to the Materials Depart ment for approval.

170813. M r. Logan replaced another permit inspector in

1717February 2015, or just before the friction course of asphalt was

1728placed on the roadway. The friction course is the third and

1739final layer of road surface . When he assumed the position,

1750Mr. Logan understood the Depar tment had previously inspected the

1760first two layers of road surface , i.e., the installation of an

1771eight - inch lime rock base and a one and one - half inch s tructural

1787asphalt layer. However, he knew that no final acceptance had

1797been given since all work was n ot yet completed.

18071 4 . Mr. Logan holds an asphalt level 1 CTQP certification ,

1819is currently an engineer intern, and is scheduled to take the

1830professional engineer examination in April 2017. The

1837certification means that Mr. Logan is qualified to perform

1846acc eptance tests for asphalt work on highways.

18541 5 . Mr. Logan does not have authority to accept or reject

1867any of the roadway construction on a permitted project.

1876Authority to issue a final acceptance letter l ies w ith the

1888p ermits d irector in the District Off ice. A letter is normally

1901issued after the p ermits director , permit inspect o r , CEI,

1912contractor , and Department maintenance team jointly inspect the

1920project after all work is completed. Mr. Logan himself made no

1931final inspection.

1933B. The Work To Date

19381 6 . The asphalt paving work began in March 201 4 , the final

1952course was laid in March 2015, and the last corrective work was

1964completed in July 2015 . Mrs. Asphalt, LLC, was the paving

1975contractor used on the job. Although a final inspection was

1985never performed, one of Respondent 's employees made final

1994payment and released Mrs. Asphalt after the July 2015 corrective

2004work was completed . A release and final payment are normally

2015given after all paving work has been approved and accepted by

2026the Department. Although he was not on the site in July 2015,

2038Mr. Guo contends Mr. Logan gave final approval for the work at

2050that time .

205317. In April, May, October, and November 2015, the

2062Department sent a punch list of items to Mr. Guo to be completed

2075by his firm. A punch list identifies deficiencies that need to

2086be corrected before a final inspection is made. It does not

2097inform the CEI on how to resolve the deficiencies , and it places

2109the permittee on notice that final acceptance will not be given

2120until the items o n the list a re corrected . Slope deficiencies

2133were not noted until several months after the corrective work

2143was completed when a Department project administrator happened

2151to be driving on the road a fter a heavy rain and observed

2164ponding on many sections of the roadway .

21721 8 . Mr. Guo met with the Department in early December 2015

2185in an effort to address not only the items in the punch lists

2198but also the sloping concerns . O n December 11, 2015, he

2210submitted an alternative solution of spot repair. The

2218Department rejected this proposal, as th e proposed repairs would

2228negatively impact surrounding asphalt that was constructed at a

2237different slope. Mr. Guo submitted a second alternative

2245solution, which would allow him to mill out (remove) 1.5 inches

2256of pavement and overlay th e friction course at 1.5 inches with a

2269two percent slope. The Department rejected this proposed

2277solution , as the best solution was to "remove what was out

2288there."

22891 9 . The Department has never issued a final acceptance

2300letter for the project.

230420. The Not ice to Show Cause , as amended, was issued on

2316March 1, 2016.

2319C . The Charges

23232 1. The Department is authorized to initiate an

2332enforcement action whenever work on a state road does not

2342conform to the permitted plans or violates the PPM . See Fla.

2354Admin. C ode R. 14 - 96.007(8). The Notice to Show Cause alleges

2367that "the majority of paved areas, paved and unpaved shoulders,

2377slopes, guardrail and other items" do not comply with Department

2387standards or abide by the permitted plans. It further alleges

2397this crea tes "an unsafe road condition" and constitutes a

2407violation of Department rules. The Department estimates the

2415cost to correct these violations is between $4 3 0,000.00 and

2427$650,000.00. Although Respondent disputes this amount , it is

2436unnecessary to resolve t hat issue at this time.

244522 . State Road 655 is an undivided , two - lane arterial

2457highway probably built around 100 years ago when different

2466design standards applied . According to current PPM standards, a

2476two - lane state highway must have a minimum eight - foot - wide

2490shoulder that includes a minimum five - foot - wide paved section

2502constructed with a two percent negative slope for the turn lane

2513and a six percent negative slope for the paved shoulder area .

2525See Dep't Ex. 8. The negative slopes allow water to drain of f

2538the road. A construction tolerance of no more than .2 percent

2549is allowed. Id. To conform to these s tandards, Respondent's

2559permitted plans call for the same slopes on travel lanes and

2570shoulders.

257123. Although State Road 655 probably had a slope of one to

2583one and one - half percent when it was first built, and paving

2596slopes on the pre - existing lanes b eing widened are not exactly

2609two percent, any current overlaying of the road requires a two

2620percent slope. Mr. Guo contends he was told by two permit

2631ins pectors, "Chris" and Steve, that a slope of two percent or

2643less was acceptable. Mr. Logan denies this assertion.

26512 4 . There are nine items in the charging document , which

2663identify necessary changes to reduce the hazard ous roadway

2672conditions and correct th e improper construction . Items one,

2682two, four, and seven relate to improper pavement slope s and

2693improper paved and unpaved shoulder slopes on both the east and

2704west sides of the roadway. Item three identifies a missing

2714paved shoulder on the west side of the roadway . Item s five and

2728six identify the absence of a stabilized shoulder (material

2737placed adjacent to a paved shoulder) on the east side of the

2749roadway and the lack of any sod on the same shoulder. Item

2761eight alleges the guardrail in front of the cr oss drain is

2773deficient. To avoid flooding, i tem nine alleges the shallow

2783ditch on the east side of the roadway should be relocated closer

2795to the Department's right - of - way line and the roadside slopes

2808should be modified, as shown in the permitted drawings. While

2818not containing a specific charge, a tenth item warns Respondent

2828that other issues may arise before final acceptance is given.

28382 5 . T he more persuasive evidence s upports a finding that

2851the slopes and shoulders identified in items one, two, four, and

2862seven do not conform to the plans or PPM . Mr. Guo's own daily

2876reports for the friction course corroborate th is finding. Those

2886reports reflect the slopes are two percent or less for the

2897travel lanes and four percent for the shoulder slopes. Th is is

2909cont rary to the plans , which call for a two percent slope for

2922travel lanes and a six percent slope for shoulders , with not

2933more than a .2 percent deviation . The absence of appropriate

2944negative slopes can create dangerous ponding conditions on the

2953highway. Th erefore, the charges in items one, two, four, and

2964seven have been proven.

29682 6 . The more persuasive evidence s upports a finding that

2980the work described in items five, six, and eight has not been

2992performed . If not co mpleted , t hese deficiencies can create a

3004safety hazard and cause soil erosion. The refore, the charges in

3015these three items have been proven. At hearing, Respondent

3024admit ted that this work has not been performed and agrees to

3036complete the work after the paving dispute is resolved .

30462 7 . The m ore persuasive evidence supports a finding that

3058the charge in item nine has been proven. W hen a roadway is

3071widened, and a drainage ditch is located adjacent to the

3081original roadway, to avoid possible flooding, the ditch must be

3091relocated closer to the Dep artment's right - of - way and roadside

3104slopes must be modified . Although Mr. Guo contends otherwise,

3114t his work is an integral part of any road construction project.

3126Mr. Guo has proposed an alternate design to address this item.

3137D . Respondent's Contention s

31422 8 . Respondent first contends that sections of other

3152nearby state roads are not built to current s tandards and

3163therefore the exact standards required by the PPM should not

3173apply. Respondent identified various locations on State Road

3181655 and other state roads within a five - mile radius of the

3194project that do not have an exact two percent slope . See Resp.

3207Ex. C1, pp. 1 - 6 ; Resp. Rebut. Ex. 2. B ecause of this slope

3222variation, Respondent asserts strict compliance with the PPM and

3231plans should not be require d. Consistent with this argument,

3241Respondent admits that any pre - existing travel lanes on State

3252Road 655 with slopes of 1.6 to 1.8 percent were overlaid with

3264new asphalt using the same slope measurements. But t his concern

3275s hould have been raised at the p re - con struction meeting before

3289work began, and not after the paving was completed and a Notice

3301to Show Cause i ssued. The contention is rejected, as the

3312evidence supports a finding that a permittee is required to

3322build to current standards, regardless of t he condition of the

3333existing roadway.

33352 9 . In its PRO, Respondent argues the Department is

3346equitably estopped from enforcing the requirement that the final

3355paved surface have a slope of exactly two percent; the

3365Department waived the requirement that the final paved surface

3374have a slope of exactly two percent through representations made

3384by Department employees; its liability, if any, was extinguished

3393because Mr. Logan accepted the work; and the actions and

3403representations of Mr. Logan render the Departmen t liable for

3413the as - built conditions. 1/ These contentions are based mainly on

3425the premise that Mr. Logan made representations to the

3434subcontractor and/or Respondent's employees regarding the

3440quality of the paving work and gave final approval after the

3451cor rective w ork was completed in July 2015 .

346130 . The friction course was installed over a three - day

3473period during the week of March 18, 2015. The asphalt was

3484installed by Mrs. Asphalt. On the first day, Mr. Guo arrived on

3496site two hours after work began an d on the other days he was not

3511on site at a ll times . However, James Bearden, who is

3523Respondent's foreman , and one other employee , Kerry Bearden,

3531were on site at all times . Neither is certified to inspect

3543asphalt. Except for the afternoon of the second d ay, Mr. Logan

3555was present at all times.

356031. Using a four - foot calibrated smart level, Mr. Logan

3571performed spot checks on the slopes while the asphalt was being

3582laid , while J ames Bearden made slope checks every 25 feet or so .

3596Mr. Bearden c onfirmed that Mr. Logan did not "check it as often"

3609as he did. Although the spot checks he made appeared to be

"3621acceptable," Mr. Logan did not perform any spot check s after

3632the rolling was completed , and he did not write down any

3643measurements that he took. At one poin t, Mrs. Asphalt's foreman

3654request ed information regarding the target slope . Mr. Logan

3664informed him he should check with the c lient to obtain that

3676information. Mr. Logan did not advise anyone that the work

3686w ould pass final inspection .

369232. During th e Ma rch paving work , Mr. Guo took no

3704measurements, but after the paving was completed, he was

3713observed making a few sloping measurements. Normally, the CEI

3722will make numerous checks while the paving is being laid to

3733ensure that the subcontractor is providing quality work and the

3743equipment is adequate to perform the job.

375033. Respondent asserts , unpersuasively, that by allowing

3757Mr. Logan to inspect the asphalt paving , function as the asphalt

3768inspector on site, and give final approval, the Department

3777interfere d with the road construction. The facts belie this

3787contention. At no time did Mr. Logan interfere with, or

3797prevent, the contractor from taking slope or depth measurements.

3806Although Mr. Logan would sometimes tell the subcontractor that

3815work was not accep table , h e did not order the subcontractor to

3828fix the unacceptable work. This is the responsibility of the

3838CEI.

38393 4 . Mr. Logan told Mrs. Asphalt's foreman that the

3850July 2015 corrective work looked "good," but he was not asked by

3862anyone if the subcontra ctor could be paid and released , or if

3874his characterization of the work as "good" constituted final

3883acceptance of the work. Contrary to Respondent's assertion, no

3892representation was made by Mr. Logan that he was giving final

3903approval. In fact, t here has never been a request by the CEI

3916for the Department to make a final inspection.

39243 5 . It is evident from Mr. Guo's testimony that he either

3937misunderstood the type of oversight provided by a permit

3946inspector, or he never sought clarification on that issue bef ore

3957the work began. It is the CEI's responsibility to be present on

3969the job site to observe and verify the GC's work. This means

3981that Mr. Guo , or his certified designees , if any, and not the

3993Department, are responsible for all inspections and to provide

4002daily reports documenting the work activities that take place

4011each day.

40133 6 . Mr. Guo believed the subcontractor "only listen[s] to

4024Steve," and the subcontractor "report[ed] directly to Mr. Logan"

4033for "quality [control] decisions" rather than the CEI . As to

4044the July 2015 corrective work , Mr. Guo instructed " the

4053subcontractors [to] completely follow the instruction[s] from

4060Steve" in making the necessary corrections to the slopes. He

4070also believed, incorrectly, that all asphalt inspection work had

4079been del egated to Mr. Logan and assumed that Mr. Logan was

4091essentially supervising the project. In other words, he turned

4100over all responsibility for inspecting the asphalt to the permit

4110inspector. But as the record shows, Mr. Logan only made

4120sporadic measuremen ts, he had no authority to approve the work,

4131and he did not direct the subcontractor's performance, reject

4140its work, or put a stop work order on the project.

41513 7 . James Bearden attended a meeting with Department

4161personnel in November 2015 . He recalled tel ling John Hayes, a

4173Department construction engineer, that he paid and released the

4182subcontractor after Mr. Logan "okayed the work." Mr. Hayes

4191responded that "Steve didn't have authority to authorize that

4200asphalt." Mr. Hayes did not testify, and Mr. Beard en's

4210representation to Mr. Hayes that the work had been approved is

4221incorrect.

4222CONCLUSIONS OF LAW

42253 8 . The Department has the burden of proving by a

4237preponderance of the evidence the violations in the Notice to

4247Show Cause should be sustained . See Fla. Dep 't of Transp. v.

4260J.W.C. Co., Inc. , 396 So. 2d 778 , 788 (Fla. 1st DCA 1981) (as the

4274party asserting the affirmative of the issue, DOT has burden of

4285proving its entitlement to the requested relief ).

42933 9 . The Department has developed and adopted uniform

4303mini mum standards and criteria for the design and construction

4313of public roads , including standards, specifications, and a PPM .

4323See § 3 34.044(10)(a ) , Fla. Stat. ; Fla. Admin. Code R. 14 - 96.008.

4337Respondent has agreed to abide by these standards and criteria.

43474 0 . The Department alleges in its charging document that

4358Respondent has violated in nine respects rules 14 - 96.007 (8) and

437014 - 96.011 (1)(a),(b) and (c) .

437841 . Rule 14 - 96.007(8) provides in pertinent part as

4389follows:

4390(8) Failure by the applicant to abide by

4398th e conditions that are applicable after

4405permit issuance shall be just cause for the

4413Department to or der alteration of the

4420connection, or to revoke the permit and

4427close the connection at the expense of the

4435applicant, subject to the provisions of this

4442rule ch apter, or for the Department to have

4451the necessary modifications made and seek

4457payment from the applicant. The permit

4463requirements shall be binding on the

4469applicant, the applicant's successor's heir,

4474and assigns . . . .

44804 2 . Rule 14 - 96.011 provides in re levant part as follows:

4494(1) Validity of existing permits. All

4500connection permits issued by the Department

4506after July 1, 1988, remain valid until

4513modified pursuant to the criteria set forth

4520in this rule chapter. The Department will

4527initiate action to mod ify any permit or

4535existing permitted connection if any of the

4542following occurs:

4544(a) A significant change.

4548(b) The connection was not constructed at

4555the location or in accordance with the

4562design specified in the permit.

4567(c) Permit conditions are not m et by the

4576permittee.

45774 3 . By a preponderance of the evidence, the Department has

4589proven the charges in the Notice to Show Cause.

45984 4 . Respondent contends, however, that the Department is

4608equitably estopped from requiring a correction to the paving

4617slope because Mr. Logan represented that the paving looked

"4626good" when it was completed in July 2015.

46344 5 . In order for the doctrine to apply, th ree elements

4647must be present: (a) a representation as to a material fact

4658that is contrary to a later asserted pos ition; (b) reliance on

4670that representation; (c) a change in position detrimental to the

4680party claiming estoppel, caused by the representation and

4688reliance thereon. See, e.g. , Hoffman v. Dep't of Mgmt. Servs. ,

4698964 So. 2d 163 , 166 ( Fla. 1st DCA 2007 ). Thes e elements must be

4714proven by clear and convincing evidence. Castro v. E. Pass

4724Enterprises, Inc. , 881 So. 2d 699, 700 (Fla. 1st DCA 2004).

4735Equitable estoppel will apply against a governmental entity only

4744in rare instances and under exceptional circumstanc es. Ass 'd

4754Indus. Insur. Co. v. Dep't of Labor & Emp . Sec. , 923 So. 2d

47681252, 1255 (Fla. 1st DCA 1994).

47744 6 . The evidence shows that after the last corrective work

4786was completed in July 2015 , Mr. Logan informed Respondent that

4796the paving looked "good , " ba sed upon some spot checks made

4807before the new asphalt was rolled. There is no evidence , much

4818less clear and convincing evidence, that Mr. Logan gave final

4828acceptance for the project, or represented that the work would

4838pass final inspection at a later time . Because no

4848representation was made, t he do ctrine does not apply.

48584 7 . Respondent also argues that the Department waived the

4869right to require the final paved surface to have a slope of

4881exactly two percent slope . Waiver is commonly defined as the

4892intenti onal or voluntary relinquishment of a known right , or

4902conduct giving rise to an inference of the relinquishment of a

4913known right . Sentry Ins. v. Brown , 424 So. 2d 780, 784 (Fla.

49261st DCA 1982). The question of waiver is an issue of fact.

4938Davis v. Davis , 123 So. 2d 377, 381 (Fla. 1st DCA 19 60 ).

49524 8 . Respondent argues that waiver applies because the

4962Department failed to maintain a two percent slope on pre -

4973existing lanes of traffic on State Road 655 , Mr. Logan gave

4984final approval for all paving work , two p ermit inspectors

4994allegedly told Mr. Guo that slopes of two percent or less would

5006be acceptable , and the Department failed to enforce th e two

5017percent requirement on several nearby roadway projects .

502549. The facts previously found support a conclusion that

5034the Department did not intentionally or voluntarily waive its

5043right to require th at all work be performed in accordance with

5055the plans and PPM . The argument is rejected.

506450 . All other arguments not specifically addressed have

5073been considered and rejecte d.

5078RECOMMENDATION

5079Based on the foregoing Findings of Fact and Conclusions of

5089Law, it is

5092RECOMMENDED that the Department of Transportation e nter a

5101final order sustaining the charges in the Notice to Show Cause

5112and requiring Respondent , within 60 days, to de monstrate

5121satisfactory progress in completing the road construction .

5129Otherwise, the Department may initiat e action to effect the

5139satisfactory completion of the work at Respondent's expense .

5148DONE AND ENTERED this 12th day of October, 2016 , in

5158Talla hassee , Leon County, Florida.

5163S

5164D . R. ALEXANDER

5168Administrative Law Judge

5171Division of Administrative Hearings

5175The DeSoto Building

51781230 Apalachee Parkway

5181Tallahassee, Florida 32399 - 3060

5186(850) 488 - 9675

5190Fax Filing (850) 921 - 6847

5196www.doah.state.fl.us

5197Filed with t he Clerk of the

5204Division of Administrative Hearings

5208this 12 th day of October , 2016.

5215ENDNOTE

52161/ These contentions were not stated in legalistic form until the

5227PRO was filed. Apparently w ithout the benefit of counsel,

5237Mr. Guo prepared and filed bot h his request for a hearing and a

5251unilateral pre - hearing statement. Three working days before the

5261hearing, he requested a continuance in order to initiate

5270discovery. Because no emergency was shown, and given the

5279Department 's concern that the corrective w ork should be completed

5290as quickly as possible, the request was denied. The next day, a

5302former employee, Yanling "Caroline" Wang, was authorized to

5310appear as a qualified representative on behalf of Respondent.

5319Later that day, Respondent's counsel filed a notice of

5328appearance .

5330COPIES FURNISHED:

5332James C. Boxold, Secretary

5336Department of Transportation

5339Mail Station 57

5342605 Suwannee Street

5345Tallahassee, Florida 32399 - 0450

5350(eServed)

5351Andrea Shulthiess , Clerk of Agency Proceedings

5357D epartment of Transportatio n

5362Mail St ation 58

536660 5 Suwannee Street

5370Tallahassee, Florida 32399 - 0 4 5 0

5378(eServed)

5379T om Thomas , General Counsel

5384Department of Transportation

5387Mail St ation 58

5391605 Suwannee Street

5394Tallahassee, Florida 32399 - 0450

5399(eServed)

5400Richard E. Shine, Esquire

5404Departme nt of Transportation

5408Mail St ation 58

5412605 Suwannee Street

5415Ta llahassee, Florida 32399 - 0458

5421(eServed)

5422April A. Atkins, Esquire

5426Kirwin Norris, P.A.

5429Suite 301

543115 West Church Street

5435Orlando, Florida 32801 - 3351

5440(eServed)

5441NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

5447All parties have the right to submit written exceptions within

545715 days of the date of this Recommended Order. Any exceptions to

5469this Recommended Order should be filed with the agency that will

5480render a final order in this matter.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 11/16/2016
Proceedings: Department of Transportation's Response to Exceptions Filed by ZFI Engineering and Construction filed.
PDF:
Date: 11/16/2016
Proceedings: ZFI Engineering & Construction, Inc.'s Exceptions to ALJ's Recommended Order filed.
PDF:
Date: 11/16/2016
Proceedings: Agency Final Order filed.
PDF:
Date: 11/15/2016
Proceedings: Agency Final Order
PDF:
Date: 10/19/2016
Proceedings: Motion to Withdraw filed.
PDF:
Date: 10/17/2016
Proceedings: Transmittal letter from Claudia Llado forwarding Respondent's Exhibit to the agency.
PDF:
Date: 10/12/2016
Proceedings: Recommended Order
PDF:
Date: 10/12/2016
Proceedings: Recommended Order (hearing held July 18 and 19, 2016). CASE CLOSED.
PDF:
Date: 10/12/2016
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 09/19/2016
Proceedings: ZFI Engineering & Construction, Inc.'s Proposed Recommended Order filed.
PDF:
Date: 09/19/2016
Proceedings: Florida Department of Transportation's Proposed Recommended Order filed.
PDF:
Date: 09/14/2016
Proceedings: Notice of Filing Legible Copy of Respondent, Department of Transportation's, Exhibit 3 filed.
PDF:
Date: 09/09/2016
Proceedings: Order Granting Unopposed Motion for Extension of Time to File Proposed Recommended Order.
PDF:
Date: 09/08/2016
Proceedings: Unopposed Motion for Extension of Time to File Proposed Recommended Order filed.
PDF:
Date: 08/15/2016
Proceedings: Letter to Judge Alexander from April Atkins enclosing Rebuttal Exhibits1-3 that were admitted at hearing filed (not available for viewing).
Date: 08/12/2016
Proceedings: Transcript of Proceedings (not available for viewing) filed.
Date: 08/12/2016
Proceedings: Transcript of Proceedings (not available for viewing) filed.
PDF:
Date: 08/10/2016
Proceedings: Notice of Filing Rebuttal Exhibits filed.
Date: 07/18/2016
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 07/18/2016
Proceedings: ZFI/Repondent's Exhibits filed.
Date: 07/15/2016
Proceedings: Petitioner's Proposed Exhibits filed (exhibits not available for viewing).
PDF:
Date: 07/15/2016
Proceedings: ZFI Engineering & Construction, Inc.'s Motion to Allow Telephonic Testimony at Final Hearing filed.
PDF:
Date: 07/15/2016
Proceedings: Attachment to Departments Amended Position Statement filed.
PDF:
Date: 07/15/2016
Proceedings: Amended Department of Transportation Statement of Position filed.
PDF:
Date: 07/14/2016
Proceedings: Amended Notice of Appearance (April Atkins) filed.
PDF:
Date: 07/14/2016
Proceedings: Notice of Appearance (April Atkins) filed.
PDF:
Date: 07/14/2016
Proceedings: Amended Pre-hearing Stipulation filed.
PDF:
Date: 07/14/2016
Proceedings: Order Granting Request for Representation by Qualified Representative.
PDF:
Date: 07/14/2016
Proceedings: Petitioner ZFI Engineering and Construction, Inc.'s Request for Representation by Qualified Representative filed.
PDF:
Date: 07/14/2016
Proceedings: Pre-hearing Stipulation filed.
PDF:
Date: 07/13/2016
Proceedings: Petitioner's answers to Department's First Request for Admissions to Petitioner filed.
PDF:
Date: 07/13/2016
Proceedings: Order Denying Continuance of Final Hearing.
PDF:
Date: 07/13/2016
Proceedings: Petitioner ZFI Engineering and Construction, Inc.'s Motion for Continuance of the July 18, 2016 Hearing Date and to Compel Deposition Dates from Respondent filed.
PDF:
Date: 07/12/2016
Proceedings: Department of Transportation's Position Statement filed.
PDF:
Date: 07/12/2016
Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for July 18 and 19, 2016; 9:30 a.m.; Lakeland and Tallahassee, FL; amended as to video teleconference and venue).
PDF:
Date: 07/08/2016
Proceedings: Second Amended Notice of Hearing (hearing set for July 18 and 19, 2016; 9:30 a.m.; Bartow, FL; amended as to hearing room location).
PDF:
Date: 07/06/2016
Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Zhi Guo) filed.
PDF:
Date: 07/06/2016
Proceedings: Amended Notice of Hearing (hearing set for July 18 and 19, 2016; 9:30 a.m.; Bartow, FL; amended as to hearing room location).
PDF:
Date: 07/01/2016
Proceedings: Notice of Taking Deposition Duces Tecum (of Zhi Guo) filed.
PDF:
Date: 06/14/2016
Proceedings: Department's First Request for Admissions to Petitioner filed.
PDF:
Date: 05/26/2016
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 05/26/2016
Proceedings: Notice of Hearing (hearing set for July 18, 2016; 9:30 a.m.; Bartow, FL. The morning of July 19, 2016, is also reserved if necessary).
PDF:
Date: 05/26/2016
Proceedings: Joint Response to Initial Order filed.
PDF:
Date: 05/23/2016
Proceedings: Initial Order.
PDF:
Date: 05/23/2016
Proceedings: Amended Violation and Notice to Show Cause -Non- Compliance with Permitted Conditions filed.
PDF:
Date: 05/23/2016
Proceedings: Petition for Formal Administrative Hearing filed.
PDF:
Date: 05/23/2016
Proceedings: Agency referral filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
05/23/2016
Date Assignment:
05/23/2016
Last Docket Entry:
11/16/2016
Location:
Lakeland, Florida
District:
Middle
Agency:
Other
 

Counsels

Related DOAH Cases(s) (1):

Related Florida Statute(s) (3):

Related Florida Rule(s) (1):