16-002843
Department Of Transportation vs.
Zfi Engineering And Construction, Inc.
Status: Closed
Recommended Order on Wednesday, October 12, 2016.
Recommended Order on Wednesday, October 12, 2016.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8DEPARTMENT OF TRANSPORTATION,
11Petitioner,
12vs. Case No. 1 6 - 2843
19ZFI ENGINEERING AND
22CONSTRUCTION, INC.,
24Respondent.
25_______________________________/
26RECOMMENDED ORDER
28D. R. Alexander, Administrative Law Judge of the Division
37of Administrative Hearings (DOAH ) , conducted a hearing in this
47case on July 18 and 19 , 2016, by video teleconferencing at sites
59in Lakeland an d Tallahassee, Florida.
65APPEARANCES
66For Petitioner : Ri chard E. Shine, Esquire
74Department of Transportation
77Mail Station 58
80605 Suwannee Street
83Ta llahassee, Florida 32399 - 0458
89For Respondent: April A. Atkins, Esquir e
96Kirwin Norris, P.A.
99Suite 301
10115 West Church Street
105Orlando, Florida 32801 - 3351
110STATEMENT OF THE ISSUE
114The issue is whether Respondent's constructi on activities
122vi olate d Department standards and create d an unsafe road
133condition , as alleged in the Department's Amended Violation and
142Notice to Show Cause - Non - Compliance with Permit Conditions
153(Notice to Show Cause) issued on March 1, 2016.
162PRELIMINARY STATEMENT
164The Notice to Show Cause alleg es Respondent , an engineering
174firm, violated the terms of two construction permits and created
184an unsafe road condition while performing work on State Road 655
195in Polk County (County) . It f urther alleges Respondent's
205construction activities violated in nine respects Florida
212Administrative Code Rules 14 - 96.007(8) and 14 - 96.011(1)(b). The
223Notice to Show Cause require s that Respondent demonstrate
232satisfactory progress of the road construction within 60 days or
242Department action w ill be initiated to require the Construction
252Performance Bond insurance company to complete the work .
261Respondent timely requested a hearing and the matter was
270transmitted by the Department to DOAH to schedule a formal
280hearing.
281At the hearing, the Department presented the testimony of
290two witnesses. Department Exhibits 1 through 6, 7 - 1, 7 - 2, 7 - 6,
3067 - 8, 7 - 9, 8, 9, 11, and 12 were accepted in evidence.
321Respondent presented the testimony of five witnesses .
329Respondent's Exhibits A1 , A2, A4 through A 7 , B1 through B6, C1,
341C3, D1 through D6, and Rebuttal Exhibits 1 through 3 were
352accepted in evidence.
355A four - volume T ranscript of the hearing was prepared.
366Proposed f indings of f act and c onclusions of law (PROs) were
379filed by the parties, and they have been considered in the
390preparation of this Recommended Order.
395FINDINGS OF FACT
398A. Background
4001. The Department is the state agency responsible for
409regulating access to the state highway s ystem . See § 335.182,
421Fla. Stat. T o ensure that the motoring public is safe , t he
434Department has adopted and incorporated by reference design
442standards, standard specifications, and a Plans Preparation
449Manual (PPM) that must be adhered to by contractors when working
460on state roads . See Fla. Admin. Code R. 14 - 96. 008 .
4742. Respondent is an Orlando engineering firm whose
482principal is Zhi "George" Guo, a registered professional
490engineer. The Guo family is the fee simple owner of a 37 - acre
504tract of land located at 5615 Recker Highway (State Road 655) in
516an unincorporated part of the Coun ty .
5243. Around eight years ago, Mr. Guo began t he process of
536developing the family property as a business park to be known as
548the Recker Highway Business Park Development . To provide access
558to the property from State Road 655, Mr. Guo was required to
570cons truct turn lanes, widen from two lanes to four lanes around
5821,700 feet of road way , construct pave d and unpaved shoulders,
594and install guardrails and sod. The Department considers road
603widening to be a major project. Because all work was within the
615Depart ment's right - of - way, a driveway connection permit and
627drainage connection permit were required. The project begins at
636Station 594.00 and ends at Station 611.00 on State Road 655.
6474 . O n October 16, 2008, Mr. Guo submitted to the
659Department an Access A ppli cation for a driveway connection
669permit.
6705. Among other things, the Access A pplication identifies
679the engineer of record (EOR) , general contractor (GC) , and
688certified engineer inspector (CEI) on the project. The EOR
697signs the plans and verifies that al l work will be in accordance
710with Department standards. The GC is essentially the manager of
720the project and is responsible for its overall coordination.
729The CEI is responsible for making all inspection work on the
740project to ensure that the GC is perfor ming work according to
752the permitted plans. This requires th at the CEI be on the job
765site to observe and verify work done by the GC. The CEI must
778also submit daily reports to the Department documenting
786activities that take place each day while work is be ing
797performed . When all work is completed, t he CEI requests that
809the Department make a final inspection and issue a final
819acceptance of the work . Although the CEI is normally one
830person, t he CEI can be a combination of multiple people if they
843have a Cons truction Training and Qualification Program (CTQP)
852certification required to complete the components of the work ,
861e.g. , earthwork, asphalt, and maintenance of traffic (MOT).
8696 . Mr. Guo's Access Application indicated he would serve
879as EOR and GC . It did n ot identify who would be the CEI, but
895Mr. Guo does not deny that he served as CEI. Notably, Mr. Guo
908submitted daily reports and assumed the duties and
916responsibilities normally associated with that position.
922Mr. Guo has never managed a highway constr uction project such as
934this , although he has done design work on several highway
944projects, mainly related to drainage - improvement work . As the
955GC, Mr. Guo signed and sealed the permitted drawings.
9647. As a general rule, different individuals serve as th e
975EO R , GC, and CEI . If the CEI is also the GC, there are no
991checks and balances to ensure the project is built according to
1002the permitted plans. According to the Department's expert, it
1011is unethical for one person to serve as GC, EO R , and CEI on the
1026same project. However, t he expert had no explanation as to why
1038the Department issued a permit to Mr. Guo under these
1048circumstances , and the Department cited no rule or statute that
1058prohibits this arrangement . The charging document does not
1067allege any wrongdo ing in this respect.
10748. Mr. Guo was concerned about an apparent conflict of
1084interest created by him being the owner of the property, EOR,
1095GC, and CEI. Accordingly, he hired two outside laboratories to
1105perform materials testing, and he used two of his emp loyees , one
1117certified in earthwork and the other in MOT , but neither in
1128asphalt , to act in his stead. There is no evidence that Mr. Guo
1141informed the Department that he had delegated any CEI inspection
1151responsibilities to other individuals. A lthough he as serts a
1161request was made for the Department to inspect the paving
1171progress as it was installed , there is no record of such a
1183request. Indeed, Mr. Guo had no reason to assume, as he did,
1195that the Department permit inspector would "fully perform the
1204inspect ion work ." If this were so, there would be no need for
1218the CEI to perform any inspections on asphalt work.
12279. After being informed by the Department that a drainage
1237construction permit was required, o n January 28, 2009, Mr. Guo
1248filed a second application for that type of permit.
125710 . After additional information was provided by the
1266applicant , o n December 14, 2012, or around four years later,
1277the Department issued to Mr. Guo Driveway/Connection Permit
1285No. 2008 - A - 190 - 0071 and Drainage Connection Permi t No. 2009D -
1301190 - 0003 . The permit conditions required , among other things,
1312that all work be performed in accordance with current Department
1322standards, specifications, and permit provisions; the driveway
1329connection not be used until final acceptance was giv en by the
1341Department ; the applicant be totally responsible for the cost of
1351all work performed inside the Department's right - of - way; and t he
1365applicant accept all conditions of the permit, once work began.
1375At hearing, Mr. Guo agreed t hat he must comply with all permit
1388conditi o ns.
13911 1 . A pre - construction meeting was conducted on January 2,
14042014. Mr. Guo attended the meeting and acted as the EOR, GC,
1416and C EI for the applicant. Among other things, t he purpose of a
1430pre - construction meeting is to discuss the conditions in the
1441permit and to answer any questions that an applicant may have
1452before work beg ins . See also Fla. Admin. Code R. 14 - 96.003(2).
1466At the meeting, Mr. Guo was given a copy of the construction
1478guidelines , which spell out exactly what a contrac tor must do
1489before, during, and after construction. He was also given a
1499copy of " Minimum CEI On Site Inspections and Notifications , "
1508which identif ies the specific duties of the CEI . These
1519documents are also attached to his permits.
15261 2 . A t the heart of t his controversy is a dispute over the
1542actions taken by the Department's permit inspector while
1550monitoring the project . A permit inspector is assigned to
1560monitor the work on all state highway projects. The
1569Department's Bartow District Office has only one permit
1577inspector , Steve Logan, who is responsible for 400 lane miles of
1588road in the County. Mr. Logan must drive through all the jobs
1600that are under construction in the County and bring matters to
1611the attention of the CEI on each project to ensure complia nce
1623with the Department's permitted plans, including items such as
1632traffic control, lane closures, and spot slope measurements. He
1641must also observ e and verify the work done by the CEI , accept
1654and review the daily reports submitted by the CEI , forward th o s e
1668reports to the p ermits d irector at the District Office , and work
1681as the Department's communication contact with the contractor.
1689He also receives asphalt mix designs from the CEI and forwards
1700them to the Materials Depart ment for approval.
170813. M r. Logan replaced another permit inspector in
1717February 2015, or just before the friction course of asphalt was
1728placed on the roadway. The friction course is the third and
1739final layer of road surface . When he assumed the position,
1750Mr. Logan understood the Depar tment had previously inspected the
1760first two layers of road surface , i.e., the installation of an
1771eight - inch lime rock base and a one and one - half inch s tructural
1787asphalt layer. However, he knew that no final acceptance had
1797been given since all work was n ot yet completed.
18071 4 . Mr. Logan holds an asphalt level 1 CTQP certification ,
1819is currently an engineer intern, and is scheduled to take the
1830professional engineer examination in April 2017. The
1837certification means that Mr. Logan is qualified to perform
1846acc eptance tests for asphalt work on highways.
18541 5 . Mr. Logan does not have authority to accept or reject
1867any of the roadway construction on a permitted project.
1876Authority to issue a final acceptance letter l ies w ith the
1888p ermits d irector in the District Off ice. A letter is normally
1901issued after the p ermits director , permit inspect o r , CEI,
1912contractor , and Department maintenance team jointly inspect the
1920project after all work is completed. Mr. Logan himself made no
1931final inspection.
1933B. The Work To Date
19381 6 . The asphalt paving work began in March 201 4 , the final
1952course was laid in March 2015, and the last corrective work was
1964completed in July 2015 . Mrs. Asphalt, LLC, was the paving
1975contractor used on the job. Although a final inspection was
1985never performed, one of Respondent 's employees made final
1994payment and released Mrs. Asphalt after the July 2015 corrective
2004work was completed . A release and final payment are normally
2015given after all paving work has been approved and accepted by
2026the Department. Although he was not on the site in July 2015,
2038Mr. Guo contends Mr. Logan gave final approval for the work at
2050that time .
205317. In April, May, October, and November 2015, the
2062Department sent a punch list of items to Mr. Guo to be completed
2075by his firm. A punch list identifies deficiencies that need to
2086be corrected before a final inspection is made. It does not
2097inform the CEI on how to resolve the deficiencies , and it places
2109the permittee on notice that final acceptance will not be given
2120until the items o n the list a re corrected . Slope deficiencies
2133were not noted until several months after the corrective work
2143was completed when a Department project administrator happened
2151to be driving on the road a fter a heavy rain and observed
2164ponding on many sections of the roadway .
21721 8 . Mr. Guo met with the Department in early December 2015
2185in an effort to address not only the items in the punch lists
2198but also the sloping concerns . O n December 11, 2015, he
2210submitted an alternative solution of spot repair. The
2218Department rejected this proposal, as th e proposed repairs would
2228negatively impact surrounding asphalt that was constructed at a
2237different slope. Mr. Guo submitted a second alternative
2245solution, which would allow him to mill out (remove) 1.5 inches
2256of pavement and overlay th e friction course at 1.5 inches with a
2269two percent slope. The Department rejected this proposed
2277solution , as the best solution was to "remove what was out
2288there."
22891 9 . The Department has never issued a final acceptance
2300letter for the project.
230420. The Not ice to Show Cause , as amended, was issued on
2316March 1, 2016.
2319C . The Charges
23232 1. The Department is authorized to initiate an
2332enforcement action whenever work on a state road does not
2342conform to the permitted plans or violates the PPM . See Fla.
2354Admin. C ode R. 14 - 96.007(8). The Notice to Show Cause alleges
2367that "the majority of paved areas, paved and unpaved shoulders,
2377slopes, guardrail and other items" do not comply with Department
2387standards or abide by the permitted plans. It further alleges
2397this crea tes "an unsafe road condition" and constitutes a
2407violation of Department rules. The Department estimates the
2415cost to correct these violations is between $4 3 0,000.00 and
2427$650,000.00. Although Respondent disputes this amount , it is
2436unnecessary to resolve t hat issue at this time.
244522 . State Road 655 is an undivided , two - lane arterial
2457highway probably built around 100 years ago when different
2466design standards applied . According to current PPM standards, a
2476two - lane state highway must have a minimum eight - foot - wide
2490shoulder that includes a minimum five - foot - wide paved section
2502constructed with a two percent negative slope for the turn lane
2513and a six percent negative slope for the paved shoulder area .
2525See Dep't Ex. 8. The negative slopes allow water to drain of f
2538the road. A construction tolerance of no more than .2 percent
2549is allowed. Id. To conform to these s tandards, Respondent's
2559permitted plans call for the same slopes on travel lanes and
2570shoulders.
257123. Although State Road 655 probably had a slope of one to
2583one and one - half percent when it was first built, and paving
2596slopes on the pre - existing lanes b eing widened are not exactly
2609two percent, any current overlaying of the road requires a two
2620percent slope. Mr. Guo contends he was told by two permit
2631ins pectors, "Chris" and Steve, that a slope of two percent or
2643less was acceptable. Mr. Logan denies this assertion.
26512 4 . There are nine items in the charging document , which
2663identify necessary changes to reduce the hazard ous roadway
2672conditions and correct th e improper construction . Items one,
2682two, four, and seven relate to improper pavement slope s and
2693improper paved and unpaved shoulder slopes on both the east and
2704west sides of the roadway. Item three identifies a missing
2714paved shoulder on the west side of the roadway . Item s five and
2728six identify the absence of a stabilized shoulder (material
2737placed adjacent to a paved shoulder) on the east side of the
2749roadway and the lack of any sod on the same shoulder. Item
2761eight alleges the guardrail in front of the cr oss drain is
2773deficient. To avoid flooding, i tem nine alleges the shallow
2783ditch on the east side of the roadway should be relocated closer
2795to the Department's right - of - way line and the roadside slopes
2808should be modified, as shown in the permitted drawings. While
2818not containing a specific charge, a tenth item warns Respondent
2828that other issues may arise before final acceptance is given.
28382 5 . T he more persuasive evidence s upports a finding that
2851the slopes and shoulders identified in items one, two, four, and
2862seven do not conform to the plans or PPM . Mr. Guo's own daily
2876reports for the friction course corroborate th is finding. Those
2886reports reflect the slopes are two percent or less for the
2897travel lanes and four percent for the shoulder slopes. Th is is
2909cont rary to the plans , which call for a two percent slope for
2922travel lanes and a six percent slope for shoulders , with not
2933more than a .2 percent deviation . The absence of appropriate
2944negative slopes can create dangerous ponding conditions on the
2953highway. Th erefore, the charges in items one, two, four, and
2964seven have been proven.
29682 6 . The more persuasive evidence s upports a finding that
2980the work described in items five, six, and eight has not been
2992performed . If not co mpleted , t hese deficiencies can create a
3004safety hazard and cause soil erosion. The refore, the charges in
3015these three items have been proven. At hearing, Respondent
3024admit ted that this work has not been performed and agrees to
3036complete the work after the paving dispute is resolved .
30462 7 . The m ore persuasive evidence supports a finding that
3058the charge in item nine has been proven. W hen a roadway is
3071widened, and a drainage ditch is located adjacent to the
3081original roadway, to avoid possible flooding, the ditch must be
3091relocated closer to the Dep artment's right - of - way and roadside
3104slopes must be modified . Although Mr. Guo contends otherwise,
3114t his work is an integral part of any road construction project.
3126Mr. Guo has proposed an alternate design to address this item.
3137D . Respondent's Contention s
31422 8 . Respondent first contends that sections of other
3152nearby state roads are not built to current s tandards and
3163therefore the exact standards required by the PPM should not
3173apply. Respondent identified various locations on State Road
3181655 and other state roads within a five - mile radius of the
3194project that do not have an exact two percent slope . See Resp.
3207Ex. C1, pp. 1 - 6 ; Resp. Rebut. Ex. 2. B ecause of this slope
3222variation, Respondent asserts strict compliance with the PPM and
3231plans should not be require d. Consistent with this argument,
3241Respondent admits that any pre - existing travel lanes on State
3252Road 655 with slopes of 1.6 to 1.8 percent were overlaid with
3264new asphalt using the same slope measurements. But t his concern
3275s hould have been raised at the p re - con struction meeting before
3289work began, and not after the paving was completed and a Notice
3301to Show Cause i ssued. The contention is rejected, as the
3312evidence supports a finding that a permittee is required to
3322build to current standards, regardless of t he condition of the
3333existing roadway.
33352 9 . In its PRO, Respondent argues the Department is
3346equitably estopped from enforcing the requirement that the final
3355paved surface have a slope of exactly two percent; the
3365Department waived the requirement that the final paved surface
3374have a slope of exactly two percent through representations made
3384by Department employees; its liability, if any, was extinguished
3393because Mr. Logan accepted the work; and the actions and
3403representations of Mr. Logan render the Departmen t liable for
3413the as - built conditions. 1/ These contentions are based mainly on
3425the premise that Mr. Logan made representations to the
3434subcontractor and/or Respondent's employees regarding the
3440quality of the paving work and gave final approval after the
3451cor rective w ork was completed in July 2015 .
346130 . The friction course was installed over a three - day
3473period during the week of March 18, 2015. The asphalt was
3484installed by Mrs. Asphalt. On the first day, Mr. Guo arrived on
3496site two hours after work began an d on the other days he was not
3511on site at a ll times . However, James Bearden, who is
3523Respondent's foreman , and one other employee , Kerry Bearden,
3531were on site at all times . Neither is certified to inspect
3543asphalt. Except for the afternoon of the second d ay, Mr. Logan
3555was present at all times.
356031. Using a four - foot calibrated smart level, Mr. Logan
3571performed spot checks on the slopes while the asphalt was being
3582laid , while J ames Bearden made slope checks every 25 feet or so .
3596Mr. Bearden c onfirmed that Mr. Logan did not "check it as often"
3609as he did. Although the spot checks he made appeared to be
"3621acceptable," Mr. Logan did not perform any spot check s after
3632the rolling was completed , and he did not write down any
3643measurements that he took. At one poin t, Mrs. Asphalt's foreman
3654request ed information regarding the target slope . Mr. Logan
3664informed him he should check with the c lient to obtain that
3676information. Mr. Logan did not advise anyone that the work
3686w ould pass final inspection .
369232. During th e Ma rch paving work , Mr. Guo took no
3704measurements, but after the paving was completed, he was
3713observed making a few sloping measurements. Normally, the CEI
3722will make numerous checks while the paving is being laid to
3733ensure that the subcontractor is providing quality work and the
3743equipment is adequate to perform the job.
375033. Respondent asserts , unpersuasively, that by allowing
3757Mr. Logan to inspect the asphalt paving , function as the asphalt
3768inspector on site, and give final approval, the Department
3777interfere d with the road construction. The facts belie this
3787contention. At no time did Mr. Logan interfere with, or
3797prevent, the contractor from taking slope or depth measurements.
3806Although Mr. Logan would sometimes tell the subcontractor that
3815work was not accep table , h e did not order the subcontractor to
3828fix the unacceptable work. This is the responsibility of the
3838CEI.
38393 4 . Mr. Logan told Mrs. Asphalt's foreman that the
3850July 2015 corrective work looked "good," but he was not asked by
3862anyone if the subcontra ctor could be paid and released , or if
3874his characterization of the work as "good" constituted final
3883acceptance of the work. Contrary to Respondent's assertion, no
3892representation was made by Mr. Logan that he was giving final
3903approval. In fact, t here has never been a request by the CEI
3916for the Department to make a final inspection.
39243 5 . It is evident from Mr. Guo's testimony that he either
3937misunderstood the type of oversight provided by a permit
3946inspector, or he never sought clarification on that issue bef ore
3957the work began. It is the CEI's responsibility to be present on
3969the job site to observe and verify the GC's work. This means
3981that Mr. Guo , or his certified designees , if any, and not the
3993Department, are responsible for all inspections and to provide
4002daily reports documenting the work activities that take place
4011each day.
40133 6 . Mr. Guo believed the subcontractor "only listen[s] to
4024Steve," and the subcontractor "report[ed] directly to Mr. Logan"
4033for "quality [control] decisions" rather than the CEI . As to
4044the July 2015 corrective work , Mr. Guo instructed " the
4053subcontractors [to] completely follow the instruction[s] from
4060Steve" in making the necessary corrections to the slopes. He
4070also believed, incorrectly, that all asphalt inspection work had
4079been del egated to Mr. Logan and assumed that Mr. Logan was
4091essentially supervising the project. In other words, he turned
4100over all responsibility for inspecting the asphalt to the permit
4110inspector. But as the record shows, Mr. Logan only made
4120sporadic measuremen ts, he had no authority to approve the work,
4131and he did not direct the subcontractor's performance, reject
4140its work, or put a stop work order on the project.
41513 7 . James Bearden attended a meeting with Department
4161personnel in November 2015 . He recalled tel ling John Hayes, a
4173Department construction engineer, that he paid and released the
4182subcontractor after Mr. Logan "okayed the work." Mr. Hayes
4191responded that "Steve didn't have authority to authorize that
4200asphalt." Mr. Hayes did not testify, and Mr. Beard en's
4210representation to Mr. Hayes that the work had been approved is
4221incorrect.
4222CONCLUSIONS OF LAW
42253 8 . The Department has the burden of proving by a
4237preponderance of the evidence the violations in the Notice to
4247Show Cause should be sustained . See Fla. Dep 't of Transp. v.
4260J.W.C. Co., Inc. , 396 So. 2d 778 , 788 (Fla. 1st DCA 1981) (as the
4274party asserting the affirmative of the issue, DOT has burden of
4285proving its entitlement to the requested relief ).
42933 9 . The Department has developed and adopted uniform
4303mini mum standards and criteria for the design and construction
4313of public roads , including standards, specifications, and a PPM .
4323See § 3 34.044(10)(a ) , Fla. Stat. ; Fla. Admin. Code R. 14 - 96.008.
4337Respondent has agreed to abide by these standards and criteria.
43474 0 . The Department alleges in its charging document that
4358Respondent has violated in nine respects rules 14 - 96.007 (8) and
437014 - 96.011 (1)(a),(b) and (c) .
437841 . Rule 14 - 96.007(8) provides in pertinent part as
4389follows:
4390(8) Failure by the applicant to abide by
4398th e conditions that are applicable after
4405permit issuance shall be just cause for the
4413Department to or der alteration of the
4420connection, or to revoke the permit and
4427close the connection at the expense of the
4435applicant, subject to the provisions of this
4442rule ch apter, or for the Department to have
4451the necessary modifications made and seek
4457payment from the applicant. The permit
4463requirements shall be binding on the
4469applicant, the applicant's successor's heir,
4474and assigns . . . .
44804 2 . Rule 14 - 96.011 provides in re levant part as follows:
4494(1) Validity of existing permits. All
4500connection permits issued by the Department
4506after July 1, 1988, remain valid until
4513modified pursuant to the criteria set forth
4520in this rule chapter. The Department will
4527initiate action to mod ify any permit or
4535existing permitted connection if any of the
4542following occurs:
4544(a) A significant change.
4548(b) The connection was not constructed at
4555the location or in accordance with the
4562design specified in the permit.
4567(c) Permit conditions are not m et by the
4576permittee.
45774 3 . By a preponderance of the evidence, the Department has
4589proven the charges in the Notice to Show Cause.
45984 4 . Respondent contends, however, that the Department is
4608equitably estopped from requiring a correction to the paving
4617slope because Mr. Logan represented that the paving looked
"4626good" when it was completed in July 2015.
46344 5 . In order for the doctrine to apply, th ree elements
4647must be present: (a) a representation as to a material fact
4658that is contrary to a later asserted pos ition; (b) reliance on
4670that representation; (c) a change in position detrimental to the
4680party claiming estoppel, caused by the representation and
4688reliance thereon. See, e.g. , Hoffman v. Dep't of Mgmt. Servs. ,
4698964 So. 2d 163 , 166 ( Fla. 1st DCA 2007 ). Thes e elements must be
4714proven by clear and convincing evidence. Castro v. E. Pass
4724Enterprises, Inc. , 881 So. 2d 699, 700 (Fla. 1st DCA 2004).
4735Equitable estoppel will apply against a governmental entity only
4744in rare instances and under exceptional circumstanc es. Ass 'd
4754Indus. Insur. Co. v. Dep't of Labor & Emp . Sec. , 923 So. 2d
47681252, 1255 (Fla. 1st DCA 1994).
47744 6 . The evidence shows that after the last corrective work
4786was completed in July 2015 , Mr. Logan informed Respondent that
4796the paving looked "good , " ba sed upon some spot checks made
4807before the new asphalt was rolled. There is no evidence , much
4818less clear and convincing evidence, that Mr. Logan gave final
4828acceptance for the project, or represented that the work would
4838pass final inspection at a later time . Because no
4848representation was made, t he do ctrine does not apply.
48584 7 . Respondent also argues that the Department waived the
4869right to require the final paved surface to have a slope of
4881exactly two percent slope . Waiver is commonly defined as the
4892intenti onal or voluntary relinquishment of a known right , or
4902conduct giving rise to an inference of the relinquishment of a
4913known right . Sentry Ins. v. Brown , 424 So. 2d 780, 784 (Fla.
49261st DCA 1982). The question of waiver is an issue of fact.
4938Davis v. Davis , 123 So. 2d 377, 381 (Fla. 1st DCA 19 60 ).
49524 8 . Respondent argues that waiver applies because the
4962Department failed to maintain a two percent slope on pre -
4973existing lanes of traffic on State Road 655 , Mr. Logan gave
4984final approval for all paving work , two p ermit inspectors
4994allegedly told Mr. Guo that slopes of two percent or less would
5006be acceptable , and the Department failed to enforce th e two
5017percent requirement on several nearby roadway projects .
502549. The facts previously found support a conclusion that
5034the Department did not intentionally or voluntarily waive its
5043right to require th at all work be performed in accordance with
5055the plans and PPM . The argument is rejected.
506450 . All other arguments not specifically addressed have
5073been considered and rejecte d.
5078RECOMMENDATION
5079Based on the foregoing Findings of Fact and Conclusions of
5089Law, it is
5092RECOMMENDED that the Department of Transportation e nter a
5101final order sustaining the charges in the Notice to Show Cause
5112and requiring Respondent , within 60 days, to de monstrate
5121satisfactory progress in completing the road construction .
5129Otherwise, the Department may initiat e action to effect the
5139satisfactory completion of the work at Respondent's expense .
5148DONE AND ENTERED this 12th day of October, 2016 , in
5158Talla hassee , Leon County, Florida.
5163S
5164D . R. ALEXANDER
5168Administrative Law Judge
5171Division of Administrative Hearings
5175The DeSoto Building
51781230 Apalachee Parkway
5181Tallahassee, Florida 32399 - 3060
5186(850) 488 - 9675
5190Fax Filing (850) 921 - 6847
5196www.doah.state.fl.us
5197Filed with t he Clerk of the
5204Division of Administrative Hearings
5208this 12 th day of October , 2016.
5215ENDNOTE
52161/ These contentions were not stated in legalistic form until the
5227PRO was filed. Apparently w ithout the benefit of counsel,
5237Mr. Guo prepared and filed bot h his request for a hearing and a
5251unilateral pre - hearing statement. Three working days before the
5261hearing, he requested a continuance in order to initiate
5270discovery. Because no emergency was shown, and given the
5279Department 's concern that the corrective w ork should be completed
5290as quickly as possible, the request was denied. The next day, a
5302former employee, Yanling "Caroline" Wang, was authorized to
5310appear as a qualified representative on behalf of Respondent.
5319Later that day, Respondent's counsel filed a notice of
5328appearance .
5330COPIES FURNISHED:
5332James C. Boxold, Secretary
5336Department of Transportation
5339Mail Station 57
5342605 Suwannee Street
5345Tallahassee, Florida 32399 - 0450
5350(eServed)
5351Andrea Shulthiess , Clerk of Agency Proceedings
5357D epartment of Transportatio n
5362Mail St ation 58
536660 5 Suwannee Street
5370Tallahassee, Florida 32399 - 0 4 5 0
5378(eServed)
5379T om Thomas , General Counsel
5384Department of Transportation
5387Mail St ation 58
5391605 Suwannee Street
5394Tallahassee, Florida 32399 - 0450
5399(eServed)
5400Richard E. Shine, Esquire
5404Departme nt of Transportation
5408Mail St ation 58
5412605 Suwannee Street
5415Ta llahassee, Florida 32399 - 0458
5421(eServed)
5422April A. Atkins, Esquire
5426Kirwin Norris, P.A.
5429Suite 301
543115 West Church Street
5435Orlando, Florida 32801 - 3351
5440(eServed)
5441NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5447All parties have the right to submit written exceptions within
545715 days of the date of this Recommended Order. Any exceptions to
5469this Recommended Order should be filed with the agency that will
5480render a final order in this matter.
- Date
- Proceedings
- PDF:
- Date: 11/16/2016
- Proceedings: Department of Transportation's Response to Exceptions Filed by ZFI Engineering and Construction filed.
- PDF:
- Date: 11/16/2016
- Proceedings: ZFI Engineering & Construction, Inc.'s Exceptions to ALJ's Recommended Order filed.
- PDF:
- Date: 10/17/2016
- Proceedings: Transmittal letter from Claudia Llado forwarding Respondent's Exhibit to the agency.
- PDF:
- Date: 10/12/2016
- Proceedings: Recommended Order (hearing held July 18 and 19, 2016). CASE CLOSED.
- PDF:
- Date: 10/12/2016
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 09/19/2016
- Proceedings: ZFI Engineering & Construction, Inc.'s Proposed Recommended Order filed.
- PDF:
- Date: 09/19/2016
- Proceedings: Florida Department of Transportation's Proposed Recommended Order filed.
- PDF:
- Date: 09/14/2016
- Proceedings: Notice of Filing Legible Copy of Respondent, Department of Transportation's, Exhibit 3 filed.
- PDF:
- Date: 09/09/2016
- Proceedings: Order Granting Unopposed Motion for Extension of Time to File Proposed Recommended Order.
- PDF:
- Date: 09/08/2016
- Proceedings: Unopposed Motion for Extension of Time to File Proposed Recommended Order filed.
- PDF:
- Date: 08/15/2016
- Proceedings: Letter to Judge Alexander from April Atkins enclosing Rebuttal Exhibits1-3 that were admitted at hearing filed (not available for viewing).
- Date: 08/12/2016
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 08/12/2016
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 07/18/2016
- Proceedings: CASE STATUS: Hearing Held.
- Date: 07/15/2016
- Proceedings: Petitioner's Proposed Exhibits filed (exhibits not available for viewing).
- PDF:
- Date: 07/15/2016
- Proceedings: ZFI Engineering & Construction, Inc.'s Motion to Allow Telephonic Testimony at Final Hearing filed.
- PDF:
- Date: 07/15/2016
- Proceedings: Amended Department of Transportation Statement of Position filed.
- PDF:
- Date: 07/14/2016
- Proceedings: Order Granting Request for Representation by Qualified Representative.
- PDF:
- Date: 07/14/2016
- Proceedings: Petitioner ZFI Engineering and Construction, Inc.'s Request for Representation by Qualified Representative filed.
- PDF:
- Date: 07/13/2016
- Proceedings: Petitioner's answers to Department's First Request for Admissions to Petitioner filed.
- PDF:
- Date: 07/13/2016
- Proceedings: Petitioner ZFI Engineering and Construction, Inc.'s Motion for Continuance of the July 18, 2016 Hearing Date and to Compel Deposition Dates from Respondent filed.
- PDF:
- Date: 07/12/2016
- Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for July 18 and 19, 2016; 9:30 a.m.; Lakeland and Tallahassee, FL; amended as to video teleconference and venue).
- PDF:
- Date: 07/08/2016
- Proceedings: Second Amended Notice of Hearing (hearing set for July 18 and 19, 2016; 9:30 a.m.; Bartow, FL; amended as to hearing room location).
- PDF:
- Date: 07/06/2016
- Proceedings: Amended Notice of Taking Deposition Duces Tecum (of Zhi Guo) filed.
- PDF:
- Date: 07/06/2016
- Proceedings: Amended Notice of Hearing (hearing set for July 18 and 19, 2016; 9:30 a.m.; Bartow, FL; amended as to hearing room location).
- PDF:
- Date: 05/26/2016
- Proceedings: Notice of Hearing (hearing set for July 18, 2016; 9:30 a.m.; Bartow, FL. The morning of July 19, 2016, is also reserved if necessary).
Case Information
- Judge:
- D. R. ALEXANDER
- Date Filed:
- 05/23/2016
- Date Assignment:
- 05/23/2016
- Last Docket Entry:
- 11/16/2016
- Location:
- Lakeland, Florida
- District:
- Middle
- Agency:
- Other
Counsels
-
April A Atkins, Esquire
Address of Record -
Richard E Shine, Assistant General Counsel
Address of Record -
Richard E. Shine, Assistant General Counsel
Address of Record -
April A. Atkins, Esquire
Address of Record -
Richard E Shine, Esquire
Address of Record