16-003530BID
Cyriacks Environmental Consulting Services, Inc. vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, December 30, 2016.
Recommended Order on Friday, December 30, 2016.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8CYRIACKS ENVIRONMENTAL
10CONSULTING SERVICES, INC.,
13Petitioner,
14vs. Case No . 16 - 0769BID
21DEPARTMENT OF TRANSPORTATION,
24Respondent,
25and
26DB ECOLOGICAL SERVICES, INC.,
30Intervenor.
31_______________________________/
32CYRIACKS ENVIRONMENTAL
34CONSULTING SERVICES, INC.,
37Petitioner,
38vs. Case No . 16 - 3530BID
45DEPARTMENT OF TRANSPORTATION,
48Respondent.
49_______________________________/
50RECOMMENDED ORDER
52A hearing was conducted in this case pursuant to
61sections 120.569 , 120.57(1), and 120.57(3), Florida Statutes
68(2016), 1/ before Cathy M. Sellers, an Administrative Law Judge
78( " ALJ " ) of the Division of Administrative Hearings ( " DOAH " ), on
91September 14, 15, and 16, 2016, in Tallahassee, Florida, and by
102video teleconference on September 19 and 20 , 2016, at sites in
113Fort Lauderdale and Tallahassee, Florida.
118APPEARANCES
119For Petitioner: Joseph A. Sorce, Esquire
125Jo seph A. Sorce & Associates, P.A.
1323211 Ponce de Leon Boulevard , Suite 200
139Coral Gables, Florida 33134
143For Respondent: Richard E. Shine , Esquire
149Department of Transportation
152605 Suwannee Street, Mail Stop 58
158Tallahassee, Florida 32399
161For Intervenor: Gigi Rollini, Esquire
166Messer Caparello, P.A.
1692618 Centennial Place
172Tallahassee, Florida 32308
175STATEMENT OF THE ISSUE S
180The issues in these consolidated cases are: (1) w hether
190the decision by Respondent, Department of Transportation, to
198reject all bids for the contract at issue was illegal,
208arbitrary, dishonest, or fraudulent; and (2) if so , whether
217Respondent ' s action s in cancelling the notice of intent to award
230the contract at issue to Cyriacks Environmental Consulting
238Services, Inc., (" CECOS ") and requiring the submittal of new
249price proposals were clearly erroneous, contrary to competition,
257arbitrary, or capricious. 2/
261PRELIMINARY STA TEMENT
264On October 1, 2015, Respondent , Department of
271Transportation, issued Request for Proposal RFP - DOT - 15/16 - 4004PM
283( the " RFP " ) for the District - wide Mitigation, Wildlife, and
295Environmental Support Services contract ( " Contract " ) for
303Respondent's District IV .
307On November 3, 2015, Respondent posted its i ntent to a ward
319the C ontract to CECOS .
325On November 5, 2015, Intervenor , DB Ecological Services,
333Inc. ( " DB " ) , filed a Notice of P rotest , notifying Respondent of
346its intent to chal lenge the award of the C ontract to CECOS .
360That same day, Respondent posted a c ancellation of the intent to
372a ward the C ontract to CECOS .
380On November 9, 2015, Respondent issued an addendum to the
390RFP, addressing an ambiguity in the price proposal provisions
399for a specific section of the RFP and requesting the vendors who
411previously had submitted proposals in response to the RFP to
421submit new price proposals . Also on November 9, 2015, DB
432withdr ew its Notice of Protest to the i ntent to a ward the
446C ontract to CECOS .
451On November 13, 2015, CECOS filed a Notice of Protest of
462Respondent's action in issuing an addendum to the RFP to r equir e
475the vendors to s ubmit new p rice proposals. Thereafter, o n
487Nov ember 23, 2015, CECOS filed a Petition for Formal Hearing
498( " First Petition " ) challenging Respondent ' s decision s to cancel
510the notice of intent to award the Contract to CECOS and
521requiring the vendors to submit new price proposal s .
531O n December 17, 2015, Respondent posted notice that it had
542rejected all proposals and that a new procurement would be
552undertaken for the Contract. On December 22, 2015, CECOS filed
562a Notice of Protest regarding Respondent's decision to reject
571all proposals . O n January 4, 2016, CECOS fil ed a Petition for
585Formal Hearing ( " Second Petition " ) challenging Respondent ' s
595decision to reject all bids and re - solicit the C ontract. The
608Second Petition was referred to DOAH on February 12, 2016, and
619has been assigned Case No . 16 - 0769. Intervenor became a party
632to that case on February 29, 2016. The final hearing initially
643was scheduled for March 7 and 8, 2016, but was continued until
655April 25 and 26, 2016.
660Meanw h ile , o n January 4, 2016, Respondent issued an Order
672of Dismi ssal Without Prejudice ( " First Order of Dismissal " ) ,
683dismissing the First Petition on the basis that because
692Respondent had decided to reject all bids ( which it
702characterized as having " cancelled the procurement and rescinded
710all agency action " ), Respondent's action s in cancelling the
720intent to award the Contract to CECOS and requiring the
730submittal of new price proposal s were " extinguished and CECOS '
741protest was moot. " Th e First Order of Dismissal gave CECOS ten
753days to file " written evidence of why the matter [ was ] not
766moot. " In response, CECOS filed a Motion to Immediately
775Consolidate and Refer Protest and This Motion to DOAH t o Have a
788Settlement Meeting, t o Show Cause and to Vacate Order on
799January 14, 2016. On January 29, 2016, Respondent i ssued an
810Amended Final Order dismissing CECOS' First Petition as moot.
819CECOS appealed Respondent ' s dismissal of its First Petition to
830the First District Court of Appeal ; that case was assigned Case
841No. 1D16 - 0810.
845Pursuant to motion, o n April 11, 2016, the ALJ then
856assigned to Case No. 16 - 0769 stayed that proceeding pending the
868outcome of the appeal in Case No. 1D16 - 0810 . Therea fter, CECOS
882dismiss ed its appeal in Case No. 1D16 - 0810 and Respondent
894referred CECOS' First Petition to DOAH ; that case was ass igned
905Case No. 16 - 3530 and has been consolidated with Case
916No. 16 - 0769.
920On August 30, 2016, the consolidated cases were set for
930final hearing to be conducted on September 14 and 15, 2016.
941On September 13, 2016, the cases were transferred to the
951undersi gned to conduct the final hearing and prepare this
961Recommended Order.
963The final hearing was held on September 14, 15, 16, 19,
974and 20, 2016. Pursuant to the parties' stipulation, Joint
983Exhibits 1 through 30 were admitted into evidence. CECOS
992presented the testimony of Wendy Cyriaks, Mary Clark, Gui llermo
1002Guzman , Jessica Rubio, Steven Braun, Margaret Simpkins, and
1010Christine Perret t a. CECOS ' Exhibits 8, 9, and 10 were admitted
1023without objection, and CECOS 's Exhibits 2, 3, 4, 11 , and 18 were
1036adm itted into evidence over objection. 3/ CECOS proffered one
1046exhibit that was not admitted into evidence . 4/ Respondent
1056presented the testimony of Jessica Rubio and Ann Broadwell.
1065DB presented the testimony of Christine Perretta.
1072The eight - volume T ranscript was filed on October 10, 2016,
1084and the parties initially were given ten days, until October 20,
10952016, to file proposed recommended orders. Thereafter, CECOS
1103requested a ten - day extension of the time in which to file
1116proposed recommended orders. T his request was granted, and the
1126parties were given until October 27, 2016 , to file their
1136proposed recommended orders. The parties' proposed recommended
1143orders were timely filed and duly considered in preparing this
1153Recommended Order. 5 /
1157FINDINGS OF FACT
1160I. The Parties
11631 . Respondent is the state agency that issued the RFP to
1175procure the Contract for Respondent's District IV .
11832. CECOS is an environmental consulting and services firm
1192that submitted a response to the RFP , seeking award of the
1203C ontract.
12053. DB is an e nvironmental consulting and services firm
1215that submitted a response to the RFP , seeking award of the
1226Contract . DB was granted party status to DOAH Case No. 16 - 0 769
1241by Order dated February 29, 2016 , and by Order dated March 9,
12532016, was det ermined to have standing in that case as a party
1266whose substantial interests were affected by Respondent's
1273decision to reject all proposals.
1278II. Overview of t he Procurement Process for the Contract
12884. Respondent issued the RFP on or about October 1, 2015 .
1300The RFP sought to obtain support services related to
1309environmental impacts review for projects in Respondent's
1316District IV work program; wetland mitigation design;
1323construction, monitoring, and maintenance; permitting of
1329mitigation sites; exotic veg etation control and removal in
1338specified locations; relocation of threatened, endangered, or
1345rare flora and fauna; permit compliance monitoring; and other
1354services specified in the RFP. The RFP stated Respondent's
1363intent to award the Contract to the respo nsive and responsible
1374proposing vendor 6 / whose proposal is determined to be most
1385advantageous to Respondent.
13885. The responses to the RFP were scored on two components:
1399a technical proposal, worth a total of 60 points, that addressed
1410the proposing vendo r's experience, qualifications, and
1417capabilities to provide high - quality desired services; and a
1427price proposal, worth a total of 40 points, that addressed the
1438proposed price without evaluation of the separate cost
1446components and proposed profit of the pro posing vendor, compared
1456with that proposed by other vendors.
14626. The price proposal evaluation was based on the
1471following formula: (Low Price/Proposer's Price) X Price Poi nts
1480= Proposer's Awarded Points .
14857. The Special Conditions section of the Advert isement
1494portion of the RFP , paragraph 3, stated in pertinent part :
1505In accordance with section 287.057(23),
1510Florida Statutes, respondents to this
1515solicitation or persons acting on their
1521behalf may not contact, between the release
1528of the solicitation and the end of the 72 -
1538hour period following the agency posting the
1545notice of intended award, . . . any employee
1554or officer of the executive or legislative
1561branch concerning any aspect of this
1567solicitation, except in writing to the
1573procurement officer or as provided in the
1580solicitation documents. Violation of this
1585provision may be grounds for rejecting a
1592response.
1593The period between the release of the solicitation and the
160372 - hour period after posting of the intended award is commonly
1615referred to as the " cone of silence."
16228. The Special Conditions section of the Advertisement
1630portion of the RFP, paragraph 19, informed vendors that
1639Respondent reserved the right to reject a ny or all proposals it
1651received .
16539. Exhibit B to the RFP, addressing compensation, limited
1662compensation for all authorizations for work performed under the
1671Contract to a total of $5,000,000. Exhibit B stated that the
1684schedule of rates listed in the Pri ce Proposal Form C ( i.e., the
1698rates submitted for the sections comprising Exhibit C to the
1708RFP) would be used for establishing compensation.
171510 . On October 7, 2015, Respondent issued Ad dendum 1 to
1727the advertised RFP. Addendum 1 revised Exhibit A to the RFP ,
1738the Scope of Services ; and also revised Exhibit C to the RFP ,
1750the Bid Sheet, to provide it in Excel format. A s revised by
1763Addendum 1, Exhibit C consists of an Excel spreadsheet comprised
1773of six sections, each of which was to be used by the responding
1786vendors to propose their rates for the specified services being
1796procured in each section of the Bid Sheet .
18051 1 . Section 6 of t he Excel spreadshee t, titled " Trees,
1818Schrubs [sic], and Ground Cover, consist s of eight columns and
1829258 rows, each row constituting a plant item on which a price
1841proposal was to be submitted. The columns are titled, from left
1852to right: No. ; Scientific Name ; Common Name ; Un it ; Estimated of
1863[sic] number of Unites [sic] ; Rate; Extension (Unit X Rate) ; and
1874Multiplier 2.5 (Price X 2.5). Each row of the spreadsheet in
1885Section 6 identifie d , as a fixed requirement for this portion of
1897the proposal, the specified type of plant, unit (i.e., plant
1907size ) , and estimated number of units (i.e., number of plants) .
19191 2 . For each row of the Section 6 spreadsheet , only the
1932cell s under the " Rate " colu mn could be manipulated . Vendor s
1945were to insert in the " Rate " cell, for each row, the proposed
1957rate for each plant item. The cells under all other columns for
1969each row were locked, and the RFP stated that any alteration of
1981the locked cells would disquali fy the vendo r and render its
1993proposal non - responsive.
19971 3 . The instructions to Exhibit C, Section 6 7 / state d :
2012Trees, S c hrubs [sic] , and Ground Cover
2020Price of plants shall include project
2026management, field supervision, invoicing,
2030installation, mobilization of traffic, water
2035throughout the warranty period, fertilizer
2040and [sic] six (6) month and demobilization,
2047minor maintenance guarantee. Installation
2051of plant material shall be per the Scope of
2060Services. All planting costs shall include
2066the cos t to restore area to pre - existing
2076conditions (i.e., dirt, sod, etc.).
20811 4 . On October 20, 2015, Respondent issued Addend um 2 , and
2094on October 29, 2015, Respondent issued Addendum 3 . Both addend a
2106changed Respondent's schedule for reading the technical pro posal
2115scores, opening the sealed price proposals, and posting the
2124intended awards.
21261 5 . Addend a 1, 2, and 3 were not challenged .
21391 6 . H owever, a key dispute in these consolidated
2150proceedings is whether the Addendum 1 Bid Sheet in Section 6 and
2162the instructions for completing th at Bid Sheet were ambiguous ,
2172or whether Respondent reasonably believed them to be ambiguous.
21811 7 . The vendors were to submit their responses to the RFP,
2194consisting of their technical proposals and price proposals , by
2203October 16, 2015. CECOS, DB, and four other vendors timely
2213submitted re sponses to the RFP.
22191 8 . On November 2, 2015, the scores for the technical
2231proposals submitted by the vendors were presented to the
2240Selection Committee ( " SC " ) at a noticed meeting. DB received
2251the highest number of points on the technical proposal portion
2261of the RFP .
22651 9 . The SC met again on November 3, 2015 . At th at time,
2281Respondent's Procurement Officer , Jessica Rubio, rea d the total
2290awarded points for each vendor's price proposal, as well as each
2301vendor's total combined points ÏÏ i.e., total points for technical
2311proposal and price proposal .
231620 . C ECOS received the highest number of points for the
2328price proposal portion of the RFP , and also received the highest
2339total combined point s.
23432 1 . Respondent recommended, and the SC concurred, that
2353Respondent should award the Contract to CECOS .
23612 2 . At 10:00 a.m. on November 3, 2015, Respondent posted
2373the Proposal Tabulation, constituting its notice of intent that
2382CECOS would be awarded the Contract. 8 /
23902 3 . CECOS submitted a price proposal of $4,237,603.70 .
2403DB submitted a price proposal of $9,083,042.50. The other four
2415vendors ' price proposals ranged between $4,540,512.90 and
2425$5,237,598.55.
24282 4 . The " cone of silence " commenced upo n Respondent's
2439posting of the Proposal Tabulation, and ended 72 hours later, on
2450November 6, 2015, at 10:00 a.m.
24562 5 . As discussed in greater detail below, after the
2467Proposal Tabulation was posted , Respondent discovered an
2474apparent ambiguity in Exhibit C, Section 6, regarding the
2483instructions to that section and the inclusion of the " 2.5
2493Multiplier " column on the Bid Sheet . A fter an internal
2504investigation , Respondent decided to cancel its intent to award
2513the Contract to CECOS.
25172 6 . On November 5, 2015, Respondent posted a notice that
2529it was cancelling the intent to a ward the Contract to CECOS .
25422 7 . O n November 5, 2015, DB filed a Notice of Protest ,
2556stating its intent to challenge the award of the Contract to
2567CECOS . Thereafter, o n November 9, 2015, DB contacted Respondent
2578by electronic mail ( " email " ) to withdra w its Notice of Protest . 9 /
25942 8 . Due to the apparent ambiguity in Exhibit C, Section 6 ,
2607on November 9, 2015, Respondent issued Addendum 4 to the RFP .
2619Addendum 4 required t he responding vendors to submit new price
2630proposals for all sections (i.e., sections 1 through 6) of
2640Exhibit C to the RFP. Addendum 4 also established a new
2651timeline for a mandatory pre - bid conference to be held on
2663November 12, 2016 ; set a sealed price proposal due date of
2674November 19, 2016; and identified new dates for open ing the
2685price proposals and posting the Notice of Intended Award of the
2696Contract.
26972 9 . On November 12, 2015, Respondent conducted a mandatory
2708pre - bid conference to address Addendum 4. T he participating
2719vendors expressed confusion and posed numerous questions
2726regarding the submittal of new price proposals and their
2735technical proposals .
273830 . Immediately f ollowing the pre - bid conference,
2748Respondent issued Addendum 5 , which consist ed of a revised
2758Exhibit A, S cope of S ervices; revised Exhibit C, Bid Sheet in
2771Excel format for all six sections ; and responses to the
2781questions po sed at the pre - bid conference. 10 /
27923 1 . T he Addendum 5 Bid Sheet comprising Exhibit C ,
2804Section 6 , was substantially amended from the version that was
2814published in Addendum 1 . Specifically, the column previously
2823titled "Rate" was changed to "Rate Per Unit " ; the "Extension
2833(Unit X Rate) " and "Multiplier 2.5" column s w ere deleted; and a
2846new column titled " Pr oposed Cost (Rate per Unit X Est. No. of
2859Units)" was added. Additionally, the instructions for Section 6
2868were substantially amended to read: " ' Rate Per Unit ' must
2879include all costs associated with the purchase, installation,
2887watering, fertilization, project management, field supervision,
2893travel, invoicing, labor, maintenance of traffic, mobilization
2900and demobilization, staking and guying, maintenance of planti ng
2909site throughout the 180 [ - ] day plant warranty." These amendments
2921were intended to clarify that the proposed rate for each plant
2932unit was to include all overhead costs associated with
2941performance of the Contract with respect to that particular
2950unit.
29513 2 . On November 13, 2015, CECOS filed a Notice of Protest
2964to Respondent's issu ance of Addendum 4 , requiring the vendors to
2975submit new price proposals .
29803 3 . Thereafter, o n November 23, 2015, CECOS filed the
2992First Petition challenging Respondent's decision , announced in
2999Addendum 4 , to require the responding vendors to submit new
3009proposals for the price proposal portion of the RFP , and its
3020decision to cancel the notice of intent to award the Contract to
3032CECOS . 11 /
30363 4 . Once CECOS filed its Notice of Protest on November 13,
30492015 , Respondent ceased all procurement activity directed to ward
3058award ing the Contract.
30623 5 . On December 17, 2015, Respondent posted notice that it
3074was reject ing all proposals and that the Contract would be re -
3087advertised through issu ance of a new RFP .
30963 6 . On December 22, 2015, CECOS filed a Notice of Protest,
3109and on January 4, 2016, filed its Second Petition challenging
3119Respondent's decision to reject all proposals and re - advertise
3129the Contract.
3131III. Bases for Respondent's Actions
31363 7 . Shortly a fter Respondent posted the Proposal
3146Tabulation noticing its intent to award the Contract to CECOS ,
3156Chr istine Perretta, owner and p resident of DB, sent an email to
3169Respondent, then called Rubio to inquire about Respondent's
3177decision to award the Contract to CECOS. The evidence shows
3187that these contacts occurred sometime on or around November 3,
31972016. 1 2 /
32013 8 . In her telephone discussion with Rubio, Perretta
3211inquired about how to file a notice of protest 1 3 / and also asked
3226whether Respondent had reviewed the vendors' price propos als for
3236correctness or accuracy, or had simply chosen the lowest price
3246proposal. In the course of the discussion , Perretta informed
3255Rubio that DB had submitted a " loaded " rate for each plant unit
3267ÏÏ meaning that DB's rate proposed for each plant item in the
" 3279Rate " column on the Section 6 Bid Sheet consisted not only of
3291the cost of the plant item, but also the cost for all associated
3304overhead services listed in the instructions to Section 6 and in
3315the RFP Advertisement, paragraph 18(v) , plus compensation . 1 4 /
33263 9 . Rubio could not clearly recall whether , in the course
3338of their discussion , Perretta had inquired about the use of the
33492.5 multiplier , and t here is conflicting evidence as to whether
3360Perretta related her view that CECOS may not be able to perform
3372the Contract based on the price proposal it had submitted . I n
3385any event, as a result of Rubio's discussion with Perretta ,
3395Rubio determined that she needed to review Exhibit C, Section 6 .
340740 . In the course of her investigation, Rubio called Wendy
3418Cyriaks , owner and president of CECOS . 1 5 / Cyriaks confirmed that
3431CECOS had submitted an " unloaded " rate for each plant item ÏÏ
3442meaning that it had included only the cost of each plant item in
3455the " Rate " column on the Section 6 Bid Sheet , and had not
3467included, in the proposed rate for each plant item , the cost of
3479the associated overhead services listed in the instructions to
3488Section 6 or RFP Advertisement, paragraph 18(v), or
3496compensation. Cyriaks t old Rubio that CECOS expected that it s
3507overhead costs and compensation for each item would be covered
3517through use of the 2.5 m ultiplier .
35254 1 . Also i n the course of her investigation, Rubio asked
3538Bogardus whether he had intended the 2.5 multiplier to be used
3549to cover all costs , including vendor compensation, associated
3557with obtaining, installing, and maintaining the plant items
3565listed in Section 6 . Bogardus initially con firmed that his
3576intent in including the 2.5 multiplier o n the Section 6 Bid
3588Sheet was to cover all of the overhead costs and compensation .
3600However, the persuasive evidence establishes that Bogardus
3607subsequently agreed with Rubio that the 2.5 multiplier should
3616not have been included in Section 6.
36234 2 . Pursuant to her discussions with Perretta and Cyriaks,
3634Rubio realized that the wide discrepancy between DB's and CECOS'
3644price proposals was due to their differing interpretations of
3653th e instructions in Section 6 regarding plant item rates and the
3665inclusion of the " 2.5 Multiplier " col umn i n the
3675Section 6 Bid Sheet .
36804 3 . Rubio testified , persuasively, that the inclusion of
3690the " 2.5 M ultiplier " column rendered Exhibit C, Section 6 , of
3701the RFP ambiguous . To that point, t he RFP does not contain any
3715instructions or discussion on th e use of the 2.5 multiplier .
3727Therefore, to the extent the multiplier was intended to be used
3738by the vendors to build overhead costs and compensation in to
3749their price proposal s , the RFP fails to explain that extremely
3760important intended use ÏÏ leaving the significanc e and use of the
3772multiplier open to speculation and subject to assumption by the
3782vendors in pr eparing their price proposals. Rubio reasonably
3791viewed DB's and CECOS' divergent interpretations of the
3799instructions and the inconsistent use of the 2.5 multipli er as
3810further indication that Section 6 w as ambiguous. She explained
3820that in order for Respondent to ensure that it is procuring the
3832most advantageous proposal for the State, it is vitally
3841important that the RFP be clear so that responding vendors
3851clearly understand the type of information the RFP is
3860requesting , and where and how to provide that information in
3870the ir price proposals .
38754 4 . Rubio persuasively testified that in her view, the
3886instructions in Section 6 had, in fact, called for a loaded
3897rat e, but that CECOS had erroneously assumed, based on the
3908inclusion of the " 2.5 Multiplier " column in the Section 6 Bid
3919Sheet, that overhead and compensation for each plant item would
3929be covered through use of the 2.5 multiplier, and that as a
3941consequenc e, CECOS incorrectly proposed unloaded rates for the
3950plant items. In Rubio's view, CECOS' error was due to t he
3962ambiguity created by the unexplained and unsupported inclusion
3970of the 2.5 multiplier in Section 6 . Rubio testified that C ECOS
3983had been awarded the Contract because it had submitted the
3993lowest price proposal , but that its proposal was based on an
4004unloaded rate for the plant items, contrary to the instructions
4014for Section 6. I n Rubio's view, CECOS' price proposal was
4025unresponsive , and CECO S should not have been awarded the
4035Contract.
40364 5 . Rubio also testified , credibly and persuasively, that
4046the use of the 2.5 multiplier in Section 6 for compensation
4057purposes render ed the RFP arbitrary. Respondent's District IV
4066historically has not used a 2.5 multiplier for c ompensation
4076purposes for commodities contracts , and no data or analys e s
4087exist to support such use of a 2.5 multiplier . 16 / This render ed
4102the RFP both arbitrary and unverifiable with respect to whether
4112it was structured to obtain the most advantageous proposal for
4122the State .
41254 6 . To this point, Rubio credibly explained that
4135Respondent's existing environmental mitigation services contract
4141with Stantec was procured through the " Inv itation to Negotiate "
4151( " ITN " ) process. In that procurement, Respondent negotiated to
4161obtain the best value for the S tate. The ITN bid sheet
4173contained a 2.5 multiplier that was used only for weighting
4183purposes to evaluate and determine which firms would b e " short -
4195listed " for purposes of being invited to negotiate with
4204Respondent for award of the contract. Importantly ÏÏ and in
4214contrast to the RFP at issue in this case ÏÏ the multiplier in the
4228ITN was not used to determine the final prices , including
4238compensation, to install trees, shrubs, and ground cover under
4247that contract.
42494 7 . Rubio also testified, credibly, that the Bid Sheet was
4261structurally flawed because it did not allow the vendor to
4271clearly indicate the " unit price " inclusive of all overhead
4280cost s , and that this defect would result in Respondent being
4291unable to issue letters of authorization to pay invoices for the
4302cost of installing the plant items or compensating for work
4312performed .
43144 8 . For these reasons, Respondent dete rmined that it
4325needed to cancel the intent to award the Contract to CECOS . As
4338noted above, Respondent posted the c ancellation of the i ntent to
4350a ward the Contract on November 5, 2015.
43584 9 . At a meeting of the SC conducted on November 9, 2015,
4372Respondent's procurement staff explained that the intent to
4380award the Contract had been cancelled due to ambiguity in the
4391instructions and the Bid Sheet for Exhibit C, Section 6 .
4402Ultimately, t he SC concurred with Respondent's cancellation of
4411the intent to award the Contract to CECOS and agreed that the
4423vendors should be required to submit new price proposals .
443350 . Thereafter, on November 9, 2015, Respondent issued
4442Addendum 4, announcing its decision to solicit new price
4451proposa ls from the responding vend ors .
44595 1 . Respondent conducted a pre - bid meeting with the
4471vendors on November 12, 2015, and immediately thereafter, issued
4480Addendum 5, consisting of a revised Scope of Services and a
4491substantially revised Bid Sheet for all six sections of
4500Exhibit C .
45035 2 . As previously discussed, the Section 6 Bid Sheet
4514issued in Addendum 5 was revised to , among other things, delete
4525the " 2.5 Multiplier " column and the column previously titled
"4534Rate" was changed to "Rate Per Unit . " Also as discussed abov e,
4547the instructions to Section 6 were revised to clarify that the
" 4558Rate Per Unit " provided for each plant unit must contain all
4569costs associated with the purchase, installation, watering,
4576fertilization, project management, field supervision, invoicing,
4582lab or, maintenance of traffic, and other costs specified in the
4593instructions ÏÏ i.e, constitute a loaded rate. All of t hese
4604changes were made in an effort to clarify , f or the benefit of
4617all vendors , the specific information that Respondent needed to
4626be provide d in the price proposals.
46335 3 . Rubio testified, credibly, that in requiring the
4643vendors to submit new price proposals pursuant to revised
4652Exhibit C, Respondent did not give, or intend to give, any
4663vendor a competitive advantage over any of the other vendors,
4673nor did Respondent place, or intend to place, CECOS at a
4684competitive disadvantage by requiring the vendors to submit new
4693price proposals pursuant to revised Exhibit C.
47005 4 . As noted above, o nce CECOS filed its Notice of
4713Protest , Respondent ceased all procurement activity directed
4720toward awarding the Contract. Consequently, the vendors did not
4729submit new price proposals and the scheduled meetings at which
4739the new price proposals would be opened and the intended awardee
4750announced were cancelled.
47535 5 . On December 17, 2015, Rubio briefed the SC regarding
4765the problems with the RFP and described her concerns about
4775proceeding with the procurement . S he explained that
4784Respondent's procurement staff was of the view that the
4793instructions in Section 6, as previously published in
4801Addendum 1, were ambiguous because they did not clearly provide
4811direction on how to complete the Bid Sheet for that section.
4822Additionally, the Section 6 Bid Sheet , as structured in
4831Addendum 1 , did not allow the vendor s to provide a plant unit
4844rate that was inclusive of all overhead costs. T o this point,
4856she noted that unless the vendors provid ed a loaded rate ÏÏ i.e.,
4869one that include d all overhead costs ÏÏ Respondent would not be
4881able to issue work orders for any plant items in Section 6. 17/
4894She explained that these flaws constituted the bases for
4903Respondent's decision , announced on November 9, 2015, to require
4912the submittal of new price proposals .
49195 6 . Rubio further explained that in Respondent's rush to
4930issue a revised Sc ope of Services as part of Addendum 5,
4942mistakes had been made 1 8 / and Respondent's Environmental Office
4953needed more time to carefully review the Scope of Services and
4964Bid Sheet, to ensure the RFP was correctly drafted and
4974structured so that the Contract could be accurately solicited
4983and procured. Additionally, the vendors ÏÏ including Mark Clark
4992of CECOS ÏÏ had expressed confusion regarding the revised Bid
5002Sheet and submitting new price proposals , and some vendors had
5012inquired about submit ting new technical proposals . Further ,
5021under the revised procurement schedule issued as part of
5030Addendum 4 on November 9, 2015, the vendors had a very
5041compressed timeframe in which to prepare and submi t their new
5052price proposals , heightening the potential for mistakes to be
5061made .
50635 7 . Because of these substantial problems and concerns
5073with the RFP, Rubio recommended that Addendum 5 be rescinded,
5083that all vendor proposals (both technical and price) be
5092rejected, and that the entire procurement process be re - started .
5104The SC concurred with her recommendation.
51105 8 . As noted above, on December 17, 2015, Respondent
5121rejected all proposals and announced that the Contract would be
5131re - solicited in the futur e through issuance of a nother RFP.
5144IV. CECOS' Position
51475 9 . CECOS takes the position that the RFP and the
5159Section 6 Bid Sheet published in Addendum 1 were not ambiguous .
5171Specifically, CECOS contends that the use of the 2.5 multiplier
5181in Section 6 clearly indicated that Respondent was seeking an
5191unloaded rate for the plant items listed on the Section 6 Bid
5203Sheet . In support of this position , CECOS notes that all of the
5216vendors other than DB had submitted unloaded rates for the plant
5227items in Sectio n 6 . CECOS contends that this shows that
5239Section 6 was not ambiguous, and that DB simply did not follow
5251the RFP instructions ÏÏ of which it was fully aware ÏÏ in preparing
5264and submitting its price proposal . 1 9 /
527360 . CECOS also contends that Rubio's failure to contact
5283the other vendors to determine if they found the instructions or
5294use of the 2.5 multiplier in Section 6 ambiguous evidences that
5305Rubio's conclusion that S ection 6 was ambiguous lack ed any
5316factual basis , so was itself arbitrary.
532261 . CECOS asserts that Bogardus' intent to use a
53322.5 multiplier for compensation purposes was evidenced by its
5341inclusion o n the Section 6 Bid Sheet, that its use on the
5354Section 6 Bid Sheet did not render the RFP flawed, and that
5366Bogardus' intent to compensate using the multiplier shou ld
5375control the structure of compensation paid under Section 6 . 20 /
53876 2 . CECOS also notes that the use of the 2.5 multiplier on
5401the Section 6 Bid Sheet mirrors the 2.5 multiplier in the
5412existing environmental mitigation support servic es contract with
5420the current contractor . 21 / CECOs further contends that there was
5432no material difference , with respect to structuring compensati on
5441for the plant items, between the ITN process used for procuring
5452the existing contract and the RFP process used to procure this
5463Contract . As additional support for its argument that the us e
5475of the 2.5 multiplier in Section 6 was valid , CECOS points to a
5488request for proposal for environmental mitigation services
5495issued by Respondent's District VI . In that cont ract, a
55062.5 multiplier was used for compensation purposes , albeit for
5515specific plant item s that were not contained in the original
5526list of specific plant items for which rate proposals had been
5537solicited in the request for proposal.
55436 3 . CECOS further contends that Respondent ÏÏ and, most
5554particularly, Rubio ÏÏ did not conduct a thorough investigation
5563into the historic use of 2.5 multipliers in Respondent's
5572commodities contracts. CECOS argues that as a consequence ,
5580Respondent's determination that the use o f the 2.5 multiplier
5590rendered the Section 6 Bid Sheet structurally flawed and
5599arbitrary was unsupported by facts , so was itself arbitrary and
5609capricious.
56106 4 . CECOS asserts that cancelling the notice of intent to
5622award the Contract to CECOS and requiring the vendors to submit
5633new price proposals placed CECOS at a competitive disadvantage
5642and was contrary to competition because once the Proposal
5651Tabulation was posted, the other vendors were informed of the
5661price that CECOS had bid, so knew the price they h ad to beat
5675when the Contract was re - solicited.
56826 5 . CECOS also points to what it contends are procedural
5694irregularities with respect to Respondent's treatment of, and
5702communication with, CECOS and DB once Respondent decided to
5711cancel the notice of inten t to award the Contract to CECOS.
5723Specifically, CECOS contends that Respondent did not respond to
5732its calls or email asking why the intent to award the Contract
5744to CECO S had been cancelled . CECOS also contends that
5755R espondent communicated with DB on substantive matters during
5764the " cone of silence . " CECOS further notes that Respondent did
5775not convene a resolution meeting within the statutorily -
5784established seven - day period after CECOS filed its First
5794Petition , but instead held the meeting over 60 days later, on
5805January 28, 2015, and that even then, Respondent did not engage
5816in good faith negotiation to resolve the challenge.
58246 6 . Finally, CECOS contends that Respondent's decision to
5834reject all proposals and start the procurement process anew was
5844predicated on a series of arbitrary and erroneous decisions
5853( discussed above ) that created confusion , so that Respondent's
5863ultimate decision to reject all proposals was itself arbitrary
5872and capricious.
58746 7 . CECOS asserts that it followed the instructions in the
5886RFP in preparing its price proposal , submitted the lowest price
5896proposal , and is ready, willing, and able to perform the
5906Contract at the rates it proposed in its response for Section 6 .
5919On that basis, CECO S contends that it is entitled to the award
5932of the Contract.
5935V. Findings of Ultimate Fact
59406 8 . CECOS bears the burden in this proceeding to prove
5952that Respondent's decision to reject all proposals was
5960arbitrary, illegal, dishonest, or fraudulent . 22/ Even if CECOS
5970were t o meet this burden, in order to prevail it also must
5983demonstrate that Respondent's actions in cancelling the intent
5991to award the Contract and requir ing the submittal of new price
6003proposals were clearly erroneous, arbitrary, capricious, or
6010contrary to competiti on. For the reasons discussed herein , it
6020is determined that CECOS did not meet either of these burden s .
6033The Multiplier Rendered Section 6 Ambiguous, Arbitrary,
6040and Structurally Flawed
604369 . As discussed in detail above, Respondent decided to
6053cancel the intent to award the Contract to CECOS and to require
6065the submittal of new price proposals by the vendors only after
6076it had conducted an extensive investigation that included a
6085careful review of numerous provisions in the RFP and the
6095instruct ions to Section 6 and had a naly zed the structure of
6108Se ction 6 in relation to other provisions in the RFP .
61207 0 . That investigation showed that nowhere in the RFP was
6132the use of the 2.5 multiplier in Exhibit C, Section 6 , discussed
6144or explained . Thus, t o the extent the multiplier was to be used
6158in determining reimbursement for overhead costs and
6165compensation, the RFP fail ed to explain this extremely important
6175point , leaving the multiplier's purpose, use, and significance
6183open to speculat ion and assum ptio n by the vendors in submitting
6196their price proposals. This rendered the multiplier's use in
6205Section 6 ambiguous. This ambiguity is further evidenced by
6214DB's and CECOS's widely divergent price proposals for Section 6 ,
6224and the credible testimony of Perret ta and Cyriaks regarding
6234the ir differing views of the purpose of the 2.5 multiplier .
62467 1 . The credible, persuasive evidence establishes that th e
6257ambiguity in Section 6 caused the vendors to have differing
6267interpretations of the manner in which they were to propose
6277plant unit rates in Section 6 ; that the vendors submitted plant
6288price proposals predicated on differing assumptions ; and that
6296this resulted in Respondent bein g unable to fairly compare the
6307price proposals for purposes of obtaining the most advantageous
6316proposal for the State.
63207 2 . On th e s e bas e s, Respondent reasonably concluded 23/ that
6336the inclusion of the 2.5 multiplier in Section 6 , rendered that
6347portion of the RFP ambiguous.
63527 3 . As extensively discussed above, t he credible,
6362persuasive evidence also establishes that Respondent concluded ,
6369based on its investigation and review of Section 6, that
6379inclu sion of the 2.5 multiplier rendered Section 6 both
6389arbitra ry and structurally flawed. 24/
63957 4 . T he credible, persuasive evidence further establishes
6405that Rubio investigated Respondent's use of multipliers in
6413commodities procurements and contracts to the extent necessary
6421and appropriate for her to reasonably conclude that the use of
6432the 2.5 multiplier in Section 6 rendered this portion of the RFP
6444ambiguous, arbitrary, and structurally flawed. 25/
64507 5 . In sum, the credible, persuasive evidence establishes
6460that Respondent engaged in a tho rough and thoughtful
6469investigation before concluding , reasonably, that the inclusion
6476of the 2.5 multiplier in Exhibit C, Section 6 rendered that
6487portion of the RFP ambiguous .
6493Respondent's Action s Were Not Contrary to Competition
65017 6 . Although the evidence shows that CECOS may suffer some
6513competitive disadvantage because competing vendors were informed
6520of the lowest " bottom line " price they would have to beat, it
6532does not support a determination that Respondent's decision s to
6542cancel the intent t o award the Contract to CECOS and require the
6555vendors to submit new price proposals were contrary to
6564competition. To that point, in Addendum 5, Respondent
6572substantially restructured the Section 6 Bid Sheet and also
6581amended the Bid Sheet comprising the oth er price proposal
6591sections in Exhibit C , so that CECOS' and the other vendors'
6602price proposals submitted in response to Addendum 5 may have
6612substantially changed from those submitted in response to
6620Addendum 1. In any event , it cannot be concluded that
6630Res pondent's decision s to cancel the intent to award the
6641Contract to CECOS and require submittal of new price proposals
6651are contrary to competition such that they should be overturned
6661in this proceeding.
6664Procedural Irregularities
66667 7 . CECOS also point s to c ertain procedural irregularities
6678in Respondent's treatment of, and communication with, CECOS once
6687Respondent decided to cancel the notice of intent to award the
6698Contract to CECOS and require submittal of new price proposals .
6709CECOS apparently raises these issues in an effort to show that
6720Respondent's actions were clearly erroneous, contrary to
6727competition, arbitrary, or capricious.
673178. The undisputed evidence establishes that Rubio
6738communicate d with both DB and CECOS during the " cone of silence "
6750following the posting of its intent to award the Contract to
6761CECOS. The undersigned determines that the " cone of silence "
6770applie d to Rubio and her communications with DB and CECOS within
6782the 72 - hour period following Respondent's posting of the inten t
6794to award the Contract. Specifically, s he is an employee of
6805Respondent's District IV Office , so is an employee of the
6815executive branch of the State of Florida. Further , the evidence
6825shows that her communications with both DB and CECOS during the
" 6836cone of sil ence " period dealt specifically with substantive ,
6845rather than " administrative " issues regarding t he RFP and the
6855vendors' price proposals . Accordingly, it is determined that
6864these communications did, in fact, violate the " cone of
6873silence."
687479. However, this does not require that Respondent's
6882decision to cancel the intent to award the C ontract to CECOS be
6895overturned . The credible, persuasive evidence shows that while
6904DB's conversation with Rubio may have spurred Rubio to decide
6914she should invest igate the Section 6 instructions and use of the
69262.5 multiplier, it was not the reason why Respondent ultimately
6936determined that the intent to award the Contract should be
6946cancelled . R ather, Respondent's discovery of the ambiguity and
6956structural flaws in S ection 6 , through Rubio's investigation,
6965was the reason that Respondent determined that the intent to
6975award the Contract to CECOS should be cancelled .
698480. In sum, t he credible, persuasive evidence shows that
6994notwithstanding Rubio's communications on su bstantive matters
7001during the " cone of silence " with both DB and CECOS, t he
7013integrity of the procurement process was not undermined such
7022that Respondent's decision to cancel the int ent to award the
7033Contract to CECOS was clearly erroneous, contrary to
7041compet ition, arbitrary, or capricious.
70468 1 . CECOS failed to present persuasive evidence
7055establishing that other procedural irregularities rendered
7061Respondent's actions in cancel ling the intent to award the
7071Contract to CECOS and requir ing the vendors to submit new price
7083proposals were clearly erroneous, contrary to competition,
7090arbitrary, or capricious .
7094Respondent's Decisions to Cancel Intent to Award the Contract
7103and Require Submittal of New Price Proposals
711082. Based on the foregoing, it is determined that CECOS
7120did not meet its burden to show t hat Respondent's decisions in
7132cancelling the intent to award the Contract to CECOS and
7142requiring the vendors to submit new price proposals were clearly
7152erroneous, contrary to competition, arbitra ry, or capricious.
7160R es pondent's Decision to Reject All Proposals
71688 3 . As noted above, CECOS contends that Respondent's
7178decision to reject all proposals and start the procurement
7187process anew was predicated on a series of arbitrary and
7197erroneous decisio ns that created confusion, so that Respondent's
7206ultimate decision to reject all proposals was itself arbitrary
7215and capricious. However, the credible, persuasive evidence
7222shows that Respondent's ultimate decision to reject all bids was
7232factually supported and was reasonable.
72378 4 . As discussed above, Respondent initially decided to
7247cancel the intent to award the Contract to CECOS and to require
7259the vendors to submit new price proposals after it discovered
7269t he ambiguity and structural flaws resulting from th e use of the
72822.5 multiplier in Section 6. At that point, rather than
7292rejecting all proposals, which would require the vendors to go
7302to the time and expense of preparing completely new proposals,
7312it decided to instead only require the vendors to submit new
7323price proposals.
73258 5 . Due to the interrelated nature of the six sections of
7338Exhibit C comprising the complete price proposal for the RFP,
7348Respondent determined revision of Section 6 would al so require
7358revision of the other five sections of Exhibit C , in order to
7370ensure that they were internally consistent with each other.
73798 6 . At the mandatory pre - bid meeting preceding the
7391issuance of Addendum 5, t he participating vendors had numerous
7401quest ions about the sweeping revisions to all six sections of
7412Exhibit C , and they expressed co nfusion about the revisions and
7423their effect on preparati on of new price proposals. Some
7433vendors also expressed concern that they may have to change
7443their personnel i n order to be able to accurately prepare new
7455price proposals , raising the question whether the technical
7463proposal s needed to be revised .
74708 7 . As a result of vendor confusion and concern, and also
7483because Respondent's Environmental Office needed addition al time
7491to carefully review and revise the RFP as needed, Respondent
7501decided to reject all proposals and to start the procurement
7511process anew.
75138 8 . Respondent's decision to reject all bids was made
7524after fully considering all of the pertinent informati on
7533regarding the ambiguity and structur al flaws in Section 6,
7543vendor confusion and concern caused by Respondent's revisions to
7552Exhibit C needed to address the ambiguity and flaws in
7562Section 6 , and Respondent's need for additional time to ensure
7572that its RFP accurately and clearly solicited the needed
7581environmental mitigation support services.
75858 9 . Accordingly, Respondent did not act arbitrarily in
7595deciding to reject all bids.
760090 . Further, n o persuasive evidence was presented to show
7611that Respondent's decision to reject all bids was illegal,
7620dishonest, or fraudulent.
7623CONCLUSIONS OF LAW
76269 1. DOAH has jurisdiction over the subject matter of, and
7637parties to, this proceeding, pursuant to secti ons 120.569 and
7647120.57(1) .
76499 2. These consolidated proceedings entail challenges to
7657two public procurement decisions made by Respondent regarding
7665the award of the Contract pursuant to the RFP. As discussed
7676above, these decisions were , first, to cancel th e notice of
7687intent to award the Contract to CECOS and require the submittal
7698of new price proposals , and, ultimate ly, to reject all proposals
7709and re - start the procurement process.
77169 3. As the entity initially awarded the Contract at issue
7727in these proceed ing, CECOS has standing to challenge
7736Respondent's decisions at issue in Case Nos. 16 - 0769 and Case
7748No. 16 - 3530, which resulted in CECOS not being awarded the
7760Contract as initially announced. B y Order issued March 9, 2016,
7771DB was determined to have standing in Case No. 16 - 3530 . 26/
77859 4 . Th e s e consolidated proceeding s are governed by
7798section 120.57(3 ) , which states in pertinent part:
7806(3) ADDITIONAL PROCEDURES APPLICABLE TO
7811PROTESTS TO CONTRACT SOLICITATION OR AWARD. Ï
7818Agencies subject to this chapter shall use
7825the uniform rules of procedure, which
7831provide procedures for the resolution of
7837protests arising from the contract
7842solicitation or award process. Such rules
7848shall at least provide that:
7853(a) The agency shall provide notice of a
7861decision or intended decision concerning a
7867solicitation, contract award, or exceptional
7872purchase by electronic posting. This notice
7878shall contain the following statement:
" 7883Failure to file a protest within the time
7891pres cribed in section 120.57(3), Florida
7897Statutes, or failure to post the bond or
7905other security required by law within the
7912time allowed for filing a bond shall
7919constitute a waiver of proceedings under
7925chapter 120, Florida Statutes. "
7929(b) Any person who is ad versely affected by
7938the agency decision or intended decision
7944shall file with the agency a notice of
7952protest in writing within 72 hours after the
7960posting of the notice of decision or
7967intended decision. With respect to a
7973protest of the terms, conditions, an d
7980specifications contained in a solicitation,
7985including any provisions governing the
7990methods for ranking bids, proposals, or
7996replies, awarding contracts, reserving
8000rights of further negotiation, or modifying
8006or amending any contract, the notice of
8013protest shall be filed in writing within 72
8021hours after the posting of the solicitation.
8028The formal written protest shall be filed
8035within 10 days after the date the notice of
8044protest is filed. Failure to file a notice
8052of protest or failure to file a formal
8060writt en protest shall constitute a waiver of
8068proceedings under this chapter. The formal
8074written protest shall state with
8079particularity the facts and law upon which
8086the protest is based. Saturdays, Sundays,
8092and state holidays shall be excluded in the
8100computati on of the 72 - hour time periods
8109provided by this paragraph.
8113(c) Upon receipt of the formal written
8120protest that has been timely filed, the
8127agency shall stop the solicitation or
8133contract award process until the subject of
8140the protest is resolved by final a gency
8148action, unless the agency head sets forth in
8156writing particular facts and circumstances
8161which require the continuance of the
8167solicitation or contract award process
8172without delay in order to avoid an immediate
8180and serious danger to the public health,
8187safety, or welfare.
8190* * *
8193(f) In a protest to an invitation to bid or
8203request for proposals procurement, no
8208submissions made after the bid or proposal
8215opening which amend or supplement the bid o r
8224proposal shall be considered. In a protest
8231to an invitation to negotiate procurement,
8237no submissions made after the agency
8243announces its intent to award a contract,
8250reject all replies, or withdraw the
8256solicitation which amend or supplement the
8262reply shall be considered. Unless otherwise
8268provided by sta tute, the burden of proof
8276shall rest with the party protest ing the
8284proposed agency action. In a competitive -
8291procurement protest, other than a rejection
8297of all bids, proposals, or replies, the
8304administrative law judge shall conduct a de
8311novo proceeding to determine whether the
8317agency ' s proposed action is contrary to the
8326agency ' s governing statutes, the agency ' s
8335rules or policies, or the solicitation
8341specifications. The standard of proof for
8347such proceedings shall be whether the
8353proposed agency action was c learly
8359erroneous, contrary to competition,
8363arbitrary, or capricious. In any bid -
8370protest proceeding contesting an intended
8375agency action to reject all bids, proposals,
8382or replies, the standard of review by an
8390administrative law judge shall be whether
8396the a gency ' s intended action is illegal,
8405arbitrary, dishonest, or fraudulent.
84099 5 . As the party challenging Respondent's proposed agency
8419action s at issue , CECOS bears the burden of proof in these
8431proceedings . § 120.57(3)(f), Fla. Stat.; State Contracting and
8440Eng 'g . Corp. v. Dep't of Transp. , 709 So. 2d 607, 609 (Fla. 1st
8455DCA 1998).
845796. As an overarching principle, public bodies in Florida
8466are legislatively afforded wide discretion in soliciting and
8474accepting bids and proposals, and th eir procurement decisions,
8483when based on an honest exercise of that discretion, will not be
8495overturned, even if the decisions may appear erroneous and even
8505if reasonable persons may disagree. Liberty Cnty. v. Baxter's
8514Asphalt & Concrete, Inc. , 421 So . 2d 505, 506 (Fla. 1982).
852697. In Caber Systems, Inc. v. Department of General
8535Services , 530 So. 2d 325 , 336 (Fla. 1st DCA 1988) , the court
8547held that even if a protest ha s been filed challenging an
8559agency's decision regarding the award of a contract, the
8568stat utory provision 27 requiring the agency to stop the
8578solicitation or contract award process pending resolution of the
8587protest only means that the agency cannot continue the
8596procurement process leading to the award of the contract; it
8606does not mean that the agency is precluded from thereafter
8616rejecting all bids. See LabCorp. V. Dep't of Health , Case No.
862712 - 0846 (Fla. DOAH May 7, 2012; Fla. DOH Jun. 21,
86392012) (confirming agency authority to reject all bids after a
8649no tice of award has been announced and bids have been made
8661public). Accordingly, in this case, the threshold question is
8670whether CECOS has demonstrated that Respondent's action in
8678rejecting all proposals violated the applicable standard of
8686review.
86879 8 . Th e standard of review applicable to CECOS' challenge
8699to Respondent's action reject ing all proposals is whether that
8709action was illegal, arbitrary, dishonest, or fraudulent . Id. ;
8718Dep't of Transp. v. Groves - Watkins Constructors , 530 So. 2d 912,
8730914 (Fla. 1988).
873399 . This is a stringent burden. As the court stated in
8745Gulf Real Properties, Inc. v. Department of Health and
8754Rehabilitative Services , 687 So. 2d 1336, 1338 (Fla. 1st DCA
87641997), an agency's rejection of all bids must stand, absent a
8775showing tha t the purpose or effect of the rejection is to defeat
8788the object and integrity of competitive bidding.
8795100 . For the reasons discussed above, CECOS failed to meet
8806its burden to show that Respondent's action rejecting all bids
8816was illegal, arbitrary, dish onest, or fraudulent. To the
8825contrary, the evidence shows that Respondent's decision to
8833reject all bids was not arbitrary, 28/ and CECOS presented no
8844evidence establishing that Respondent's action was illegal,
8851dishonest, or fraudulent.
8854101 . If it had be en determined that Respondent's action in
8866rejecting all bids was illegal, arbitrary, dishonest, or
8874fraudulent, then the question would become whether Respondent's
8882action in cancelling its statement of intent to award the
8892Contract to Petitioner was clearly erroneous, contrary to
8900competition, arbitrary, or capricious.
8904102 . Although not necessary to address because CECOS
8913failed to prevail on the threshold issue regarding Respondent's
8922decision to reject all bids, it is also concluded that CECOS
8933failed to show that Respondent's decisions to cancel the award
8943of the Contract to CECO S and require the vendors to submit new
8956price proposals was not clearly erroneous, contrary to
8964competition, arbitrary, or capricious. To the contrary, as
8972discussed above, the evid ence established that Respondent's
8980decision was correct, was not contrary to competition, and was
8990rationally reached following a thorough investigation and
8997analysis, so was not arbitrary or capricious.
9004103 . Accordingly, CECOS failed to meet the applica ble
9014burden s in both Case No. 16 - 0769 and in Case No. 16 - 3530.
9030RECOMMENDATION
9031Based on the foregoing Findings of Fact and Conclusions of
9041Law, it is hereby RECOMMENDED that the Department of
9050Transportation :
90521. I ssue a final order in Case No. 16 - 0769 fin ding that
9067the rejection of all proposals in response to Request for
9077Proposal RFP - DOT - 15/16 - 4004PM was not illegal, arbitrary,
9089dishonest, or fraudulent; and
90932. Issue a final order in Case No. 16 - 3530 finding that
9106the decisions to cancel the award of the C ontract for Request
9118for Proposal RFP - DOT - 15/16 - 4004PM to CECOS and to require the
9133vendors to submit new price proposals for Request for Proposal
9143RFP - DOT - 15/16 - 4004PM were not clearly erroneous, contrary to
9156competition, arbitrary, or capricious.
9160DONE AN D ENTERED this 30th day of December , 2016 , in
9171Tallahassee, Leon County, Florida.
9175S
9176CATHY M. SELLERS
9179Administrative Law Judge
9182Division of Administrative Hearings
9186The DeSoto Building
91891230 Apalachee Parkway
9192Tallahassee, Florida 32399 - 3060
9197(850) 488 - 9675
9201Fax Filing (850) 921 - 6847
9207www.doah.state.fl.us
9208Filed with the Clerk of the
9214Division of Administrative Hearings
9218this 30th day of December , 2016 .
9225ENDNOTES
92261/ All references are to Florida Statutes 2016 unless otherwise
9236stated.
92372/ In Case No. 16 - 3530, CECOS has challenged both Respondent's
9249decision announced on November 5, 2015, to cancel the intent to
9260award the contract at issue to CECOS, and Respondent's d ecision
9271announced on November 9, 2015, in Addendum 4, to require the
9282submittal of new price proposals. Although CECOS did not file a
9293Notice of Protest within 72 hours of Respondent's posting of the
9304cancellation of intent to award the Contract to CECOS, th e
9315cancellation cannot be fairly read to provide a clear point of
9326entry notifying CECOS and the other vendors of their right to
9337challenge the cancellation of the intent to award. Respondent's
9346cancellation of the intent to award consisted of three
9355documents . One was an Advertisement issued on November 5, 2015,
9366at 5:14:25 p.m., identifying the Commodity Number, posting a
9375link to the document constituting the cancellation of intent to
9385award, and stating that the Advertisement ended on November 9,
93952015, at 5:0 6 p.m. Another listed the project number and
9406project description, and stated that the posting of the intent
9416to award was cancelled and would be reviewed by the Selection
9427Committee on Monday, November 9, 2015. The third document
9436consisted of the Proposal Tabulation that previously had been
9445posted, with "CANCELLED" written across the face. Although the
9454Proposal Tabulation notified the vendors of the right to
9463challenge the Proposal Tabulation and the timeframe for doing
9472so, no separate notice language was p rovided for Respondent's
9482cancellation of the intent to award. Further, given that one of
9493the cancellation documents stated that the matter would be
"9502reviewed" at a subsequent meeting, it was reasonable for CECOS
9512to assume that the cancellation decision ma y be reversed. Under
9523these circumstances, it cannot be concluded that Respondent
9531provided a clear point of entry that informed the vendors of
9542their right to challenge the cancellation of the intent to
9552award. See Fla. Optometric Ass'n v. Bd. of Optometry , 567 So.
95632d 928, 935 (Fla. 1st DCA 1990)(for a notice to be legally
9575sufficient to provide a clear point of entry, it must clearly
9586inform regarding the nature of the agency's decision, as well as
9597the process and timeframe for challenging that decision).
9605Ac cordingly, the 72 - hour timeframe for CECOS to file a Notice of
9619Protest to challenge the cancellation of the intent to award the
9630Contract did not commence, so did not expire. See Manasota - 88
9642v. Dep't of Envtl. Reg. , 417 So. 2d 846 (Fla. 1st DCA 1982).
9655The refore, CECOS timely asserted its challenge to that action in
9666the Petition for Formal Hearing filed on November 23, 2015,
9676which challenges both Respondent's decision to cancel the intent
9685to award the Contract to CECOS, and Respondent's decision to re -
9697solic it the price proposals for the RFP.
97053/ For purposes of evidentiary rulings in the record, CECOS'
9715exhibit numbers were keyed to its exhibit numbers on the table
9726included in the parties' Joint Pre - hearing Stipulation, rather
9736than to the numbers on the bin der tabs in CECOS' exhibits
9748notebook.
97494/ This exhibit, which consisted of the Joint Response to
9759Petitioner's Amended Motion to Compel Discovery and Petitioner's
9767Amended Response to Department's Motion for Protective Order,
9775was excluded on relevance gro unds.
97815/ The parties waived the 30 - day deadline for issuance of this
9794Recommended Order.
97966/ Proposing and responding vendors are collectively referred to
9805as "vendors" in this Recommended Order.
98117/ The instructions for Section 6, as published in Addendum 1,
9822were not revised from those initially published for that
9831section.
98328/ The Proposal Tabulation states, in pertinent part:
9840X [placed next to the awardee's name ÏÏ here,
9849CECOS] indicates apparent a warded vendor,
9855but does not constitute an acceptance of any
9863offer created by the vendor's proposal. No
9870binding contract will be deemed to exist
9877until such time as a Purchase Order or
9885written acceptance by the [D]epartment has
9891been issued. If irregulariti es are
9897subsequently discovered in the vendor's
9902proposal . . . or otherwise fails to comply
9911with the request for proposal requirements,
9917the Department has the [r]ight to . . .
9926reject all proposals, or act in the best
9934interest of the Department.
99389/ DB with drew its Notice of Protest by email sent at 8:52 a.m.,
9952shortly before the SC's November 9, 2015, meeting which started
9962at 9:00 a.m. Respondent's clerk's office stamped a paper copy
9972of DB's email at 11:10 a.m.; however, there is no persuasive
9983evidence show ing that DB did not, in fact, send its email
9995withdrawing its Notice of Protest before the SC meeting convened
10005at 9:00 a.m. Furthermore, even if it were determined that DB
10016did not withdraw its Notice of Protest by the start of the SC
10029meeting, there was no persuasive evidence presented showing that
10038this short time discrepancy of slightly more than two hours, in
10049any way tainted the fairness of the procurement process in these
10060proceedings.
1006110/ Addendum 5 was not challenged.
1006711/ See supra note 2.
1007212/ There is no dispute that Perretta's email contact and
10082telephone discussion with Respondent occurred during the "cone
10090of silence."
1009213/ Rubio directed Perretta to Respondent's O ffice of General
10102Counsel where she obtained information regarding filing a noti ce
10112of protest.
1011414/ As discussed below, Perretta testified, credibly, that she
10123did not interpret the 2.5 multiplier column as constituting the
10133means by which the vendors were to include their overhead costs
10144and compensation, because the "2.5 M ultiplier" column was not
10154manipulable on the Bid Sheet, no other section in Exhibit C had
10166a multiplier column, and the RFP did not include any discussion
10177about the use of the multiplier. Perretta testified, credibly,
10186that to the extent she considered the purpose of the "2.5
10197Multiplier" column on the Section 6 Bid Sheet, she assumed that
10208it was an internal weighting factor to be used by Respondent in
10220evaluating the price proposals.
1022415/ Rubio's discussion with Cyriaks also took place during the
"10234cone of silence."
1023716/ Rubio testified, credibly, that Respondent previously has
10245used multipliers in RFPs to assign different relative weights to
10255specific RFP sections for purposes of evaluating proposals, but
10264that they do not use multipliers in commodities for compensation
10274purposes in contracts. Based on her discussion with Bogardus,
10283she realized that in this case, the 2.5 multiplier in Section 6
10295had not been included as a weighting factor, but instead had
10306been included to be used for compensation purposes, without
10315support ing data to show that its use in the RFP would secure the
10329most advantageous proposal for the State.
1033517/ In response, CECOS asserts that Respondent could
10343mathematically calculate its unit price for each plant item in
10353Section 6, and that it would have to do so for invoicing
10365purposes in any event. However, Rubio credibly testified that
10374this would constitute manipulating CECOS' price proposal to
10382render it responsive to the RFP requirements, and that
10391Respondent is prohibited by law from doing so.
1039918/ For example, the RFP, as initially published, had
10408erroneously included a discussion of engineering services in the
10417Scope of Services Section. That discussion had been removed as
10427part of Addendum 1, but had inadvertently been added back into
10438the RFP in Addend um 5.
1044419/ To this point, CECOS notes that the RFP expressly limited
10455the total compensation for work performed under the Contract at
10465$5,000,000, so DB should have known that its price proposal of
10478$9,083,042.50 was not in conformance with the RFP requirements.
10489CECOS dismisses DB's interpre tation of the 2.5 m ultiplier as
10500being the mistake of an inexperienced proposing vendor.
1050820/ However, as discussed above, the credible evidence shows
10517that Bogardus subsequently agreed with Rubio that the 2.5
10526multiplier should not have been included in the Section 6 Bid
10537Sheet.
1053821/ In essence, CECOS argues that its interpretation of the
10548purpose of the 2.5 multiplier in Section 6 is correct because it
10560is consistent with CECOS' prior experience with the use of
10570multipliers in other contracts with Respondent, including the
10578existing environmental services contract with Stantec. However,
10585as discussed herein, the terms of the RFP document provided no
10596reasonable basis for CECOS to assume that the 2.5 multiplier was
10607being used in this pro curement in the same manner in which it
10620had been used in prior procurements.
1062622/ See paragraph 97 , infra.
1063123/ The evidence establishes that Rubio diligently investigated
10639the ambiguity issue before concluding that the 2.5 multiplier
10648rendered Section 6 ambiguous. Once she had determined, by
10657reviewing the RFP document itself, that two vendors had
10666reasonably interpreted the multiplier to have different
10673meanings, it was unnecessary for her to poll the other vendors
10684for their views on that issue. To that p oint, Rubio did not
10697rely solely on CECOS' or DB's opinions as to whether inclusion
10708of the multiplier rendered Section 6 ambiguous; she also
10717reviewed the RFP document in arriving at her conclusion that
10727including the 2.5 multiplier rendered Section 6 ambiguo us.
1073624/ On this point, Rubio credibly distinguished the District VI
10746environmental services procurement and contract on which CECOS
10754relies to bolster its position that the use of the 2.5
10765multiplier in Section 6 of the RFP was valid. In the District
10777VI pr ocurement and contract, the 2.5 multiplier is used for
10788compensating vendors for specific plant items that were not
10797included in the list of specified plant items in the RFP. Rubio
10809explained, persuasively, that under those limited circumstances,
10816the vendor may need to act on short notice to obtain plant items
10829that were not specifically identified in the RFP, so are paid an
10841administrative fee consisting of the price of the plant unit
10851multiplied by a 2.5 multiplier. This administrative fee covers
10860the cost of, and compensates the vendor for, obtaining these
10870items only under these limited circumstances. For this reason,
10879the use of the 2.5 multiplier in the District VI procurement
10890document is not comparable to, so cannot be to support the
10901validity of, the use of the 2.5 multiplier in the RFP at issue
10914in these proceedings.
1091725/ Rubio has served as Respondent's District IV Procurement
10926Officer (i.e., as manager of the District IV Procurement Office)
10936for eight years and has reviewed numerous procurement
10944instruments during her tenure, so she is extremely knowledgeable
10953regarding the range of procurement instruments. Based on her
10962extensive knowledge and experience, as well as her investigation
10971of Section 6 of the RFP, it is determined that Rubio's decision
10983regarding th e invalidity of use of the 2.5 multiplier in
10994Section 6 was not arbitrary or capricious.
1100126/ CECOS did not appeal the March 9, 2016, Order regarding DB's
11013standing and DB's standing was not raised in the Joint Pre -
11025hearing Stipulation as an issue that woul d be tried in the final
11038hearing.
1103927/ This provision currently is codified at section
11047120.57(3)(c). At the time Caber was decided, that provision was
11057codified at sectio n 120.53(5)(c) .
1106328/ An arbitrary decision is one that is not supported by facts
11075or logic, or is despotic . Agrico Chem. Co. v. Dep't of Envtl.
11088Reg. , 365 So. 2d 759, 763 (Fla. 1st DC A 1982).
11099COPIES FURNISHED:
11101Joseph A. Sorce, Esquire
11105Joseph A. Sorce & Associates, P.A.
111113211 Ponce de Leon Boulevard , Suite 200
11118Coral Gables, Florida 33134
11122(eServed)
11123Richard E. Shine, Esquire
11127Department of Transportation
11130605 Suwannee Street, Mail Stop 58
11136Tallahassee, Florida 32399
11139(eServed)
11140Nona R. Schaffner, Esquire
11144Department of Transpo rtation
11148605 Suwannee Street , Mail Stop 58
11154Tallahassee, Florida 32399
11157(eServed)
11158Jeremy C. Daniels, Esquire
11162Daniels Kashtan
111644000 Ponce de Leon Boulevard , Suite 800
11171Coral Gables, Florida 33146
11175(eServed)
11176Gigi Rollini, Esquire
11179Messer Caparello, P.A.
111822618 Centennial Place
11185Tallahassee, Florida 32308
11188(eServed)
11189Robert A. McNeely, Esquire
11193Messer Caparello, P.A.
111962618 Centennial Place
11199Tallahassee, Florida 32308
11202(eServed)
11203Melanie R. Leitman, Esquire
11207Messer Caparello, P.A.
112102618 Centennial Place
11213Tallahassee, Flo rida 32308
11217(eServed)
11218Andrea Shulthiess, C lerk of
11223Agency Proceedings
11225Department of Transportation
11228Haydon Burns Building
11231605 Suwannee Street, M ail Stop 58
11238Tallahassee, Florida 32399 - 0450
11243(eServed)
11244James C. Boxold, Secretary
11248Department of Transportation
11251Haydon Burns Building
11254605 Suwannee Street, Mail Stop 57
11260Tallahassee, Florida 32399 - 0450
11265(eServed)
11266Tom Thomas, General Counsel
11270Department of Transportation
11273Haydon Burns Building
11276605 Suwannee Street, Mail Stop 58
11282Tallahassee, Florida 32399 - 0450
11287(eServed)
11288NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
11294All parties have the right to submit written exceptions within
1130410 days from the date of this Recommended Order. Any exceptions
11315to this Recommended Order should be filed with the agency that
11326will iss ue the Final Order in this case.
- Date
- Proceedings
- PDF:
- Date: 01/24/2017
- Proceedings: Department's Response to CECO's Exceptions to the Recommended Order filed.
- PDF:
- Date: 12/30/2016
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 12/30/2016
- Proceedings: Recommended Order (hearing held September 14-16, 19 and 20, 2016). CASE CLOSED.
- PDF:
- Date: 12/07/2016
- Proceedings: Order Memorializing Parties' Stipulation to Extend Deadline for Issuance of Recommended Order.
- PDF:
- Date: 11/18/2016
- Proceedings: Order Memorializing Parties' Stipulation to Extend Deadline for Issuance of Recommended Order.
- PDF:
- Date: 11/04/2016
- Proceedings: CECO'S Response to DB Ecological, Inc.'s Motion for Attorney's Fees and Costs filed.
- PDF:
- Date: 10/27/2016
- Proceedings: Intervenor's Motion for Attorneys' Fees and Costs Against Petitioner, Cyriacks Environmental Services, Inc. filed.
- PDF:
- Date: 10/27/2016
- Proceedings: Intervenor's Amended Proposed Recommended Order (correcting pleading title only) filed.
- PDF:
- Date: 10/20/2016
- Proceedings: Order Memorializing Parties' Stipulation to Extend Deadline for Issuance of Recommended Order.
- PDF:
- Date: 10/17/2016
- Proceedings: CECOS' Motion for Enlargement of Time for Parties to Submit Proposed Orders filed.
- Date: 10/10/2016
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 09/19/2016
- Proceedings: CASE STATUS: Hearing Held.
- Date: 09/16/2016
- Proceedings: CASE STATUS: Hearing Partially Held; continued to September 19, 2016; 9:30 a.m.; Fort Lauderdale, FL.
- Date: 09/14/2016
- Proceedings: CASE STATUS: Hearing Partially Held; continued to September 16, 2016; 9:30 a.m.; Tallahassee, FL.
- PDF:
- Date: 09/13/2016
- Proceedings: Notice of Filing of Joint Stipulated Exhibits as Described in Pre-Hearing Stipulation Filed Jointly by all Parties filed.
- PDF:
- Date: 09/13/2016
- Proceedings: Unoppossed Joint Motion to Extend Time to File Joint Pre-Trial Stipulation filed.
- Date: 09/12/2016
- Proceedings: Notice of Filing (Petitioner's Proposed Exhibits; exhibits not available for viewing) filed.
- Date: 09/09/2016
- Proceedings: Respondent's Proposed Exhibits filed (1 binder of exhibits not available for viewing).
- PDF:
- Date: 09/09/2016
- Proceedings: Notice of Filing DOT's and DB Ecological Services, Inc.'s Joint Hearing Exhibits and DOT's Hearing Exhibits filed.
- PDF:
- Date: 09/08/2016
- Proceedings: Motion to Quash Subpoenas for Hearing Scheduled for September 14 and 15, 2016 filed.
- PDF:
- Date: 09/06/2016
- Proceedings: Notice of Taking Deposition Duces Tecum (Christine Perretta) filed.
- PDF:
- Date: 09/02/2016
- Proceedings: Amended Notice of Taking Deposition Duces Tecum - As to time only filed.
- PDF:
- Date: 08/30/2016
- Proceedings: Amended Notice of Hearing by Video Teleconference (hearing set for September 14 and 15, 2016; 9:30 a.m.; Lauderdale Lakes and Tallahassee, FL; amended as to tallahassee hearing location, video teleconferencing, and exhibit submission).
- PDF:
- Date: 08/30/2016
- Proceedings: Notice of Filing Authority Cited in Pleadings on Motion for Protective Order filed.
- Date: 08/29/2016
- Proceedings: CASE STATUS: Motion Hearing Held.
- PDF:
- Date: 08/26/2016
- Proceedings: Respondent, Department of Transportation's Amended Notice of Taking Deposition Duces Tecum (Wendy Cyriacks) filed.
- PDF:
- Date: 08/26/2016
- Proceedings: Respondent, Department of Transportation's Amended Notice of Taking Deposition Duces Tecum (Mark Clark) filed.
- PDF:
- Date: 08/26/2016
- Proceedings: Respondent, Department of Transportation's Amended Notice of Taking Deposition Duces Tecum (Guillermo Guzman) filed.
- PDF:
- Date: 08/26/2016
- Proceedings: Notice of Telephonic Motion Hearing (motion hearing set for August 29, 2016; 10:00 a.m.).
- PDF:
- Date: 08/26/2016
- Proceedings: Notice of Filing Attachments to Supplement to Motion for Protective Order of DB Ecological Services, Inc., filed.
- PDF:
- Date: 08/26/2016
- Proceedings: CECOS' Notice of Filing Objections to Department's Notices of Taking Depositions Duces Tecum filed.
- PDF:
- Date: 08/26/2016
- Proceedings: CECOS' Preliminary Response to Supplement to Motion for Protective Order of DB Ecological Services, Inc.,filed.
- PDF:
- Date: 08/25/2016
- Proceedings: Supplement to Motion for Protective Order of DB Ecological Services, Inc., filed.
- PDF:
- Date: 08/25/2016
- Proceedings: Notice of Taking Deposition Duces Tecum (Margaret Simpkins) filed.
- PDF:
- Date: 08/25/2016
- Proceedings: Notice of Withdrawl of Notices of Taking Deposition Duces Tecum filed.
- PDF:
- Date: 08/24/2016
- Proceedings: Department's Notice of Serving Amended Answers to Petitioner's First Request for Interrogatories filed.
- PDF:
- Date: 08/24/2016
- Proceedings: CECOS' Motion to Compel Depositions of DB's Representatives in Broward County, Florida filed.
- PDF:
- Date: 08/19/2016
- Proceedings: Respondent, Department of Transportation's Notice of Taking Deposition Duces Tecum (of Guillermo Guzman) filed.
- PDF:
- Date: 08/19/2016
- Proceedings: Respondent, Department of Transportation's Notice of Taking Deposition Duces Tecum (of Mark Clark) filed.
- PDF:
- Date: 08/19/2016
- Proceedings: Respondent, Department of Transportation's Notice of Taking Deposition Duces Tecum (of Wendy Cyriacks) filed.
- PDF:
- Date: 08/17/2016
- Proceedings: Letter to Judge McKinney from Joseph Sorce (Cyriacks Environmental Services, Inc.) requesting rulings and order on the enclosed related matters filed.
- PDF:
- Date: 08/10/2016
- Proceedings: Amended Final Order (Amended as to Notice of Appellate Rights) (filed in Case No. 16-003530BID).
- PDF:
- Date: 08/10/2016
- Proceedings: CECOS' Response to Notice Filed by DB Ecological Services, Inc. and Department of Transportation Filed on August 8, 2016 filed.
- PDF:
- Date: 08/08/2016
- Proceedings: Notice of Failure to Enter Into an Agreed Upon Stipulation to Resolve Petitioner's Motion and Amend Motion to Compel Discovery filed.
- PDF:
- Date: 08/05/2016
- Proceedings: Petitioner's Amended Response to Respondent's First Request for Production filed.
- PDF:
- Date: 08/05/2016
- Proceedings: Petitioner's Notice of Serving Amended Answers to Respondent's First Set of Interrogatories filed.
- PDF:
- Date: 08/05/2016
- Proceedings: Notice of Unavailability of Counsel for Intervenor from August 6, 2016 through August 14, 2016 filed.
- PDF:
- Date: 08/01/2016
- Proceedings: Letter to Judge McKinney from Joseph Sorce enclosing petitioner's proposed exhibits filed (exhibits not available for viewing).
- PDF:
- Date: 07/27/2016
- Proceedings: Amended Notice of Telephonic Motion Hearing (motion hearing set for August 1, 2016; 3:00 p.m.; amended as to hearing date and time).
- PDF:
- Date: 07/26/2016
- Proceedings: Notice of Telephonic Motion Hearing (motion hearing set for July 27, 2016; 11:00 a.m.).
- PDF:
- Date: 07/15/2016
- Proceedings: Joint Response to Petitioner's Amended Motion to Compel Discovery and Petitioner's Amended Response to Department's Motion for Protective Order filed.
- PDF:
- Date: 07/12/2016
- Proceedings: Joint Request to Respond to CECOS' Amended Motion to Compel and Amended Response filed.
- PDF:
- Date: 07/05/2016
- Proceedings: Joint Objection to Consideration of CECOS' Amended Motion to Compel and Amended Response to Department's and Intervenor's Motions for Protective Order, or in the Alternative, a Request for Extension of Time to File Response to These Filings filed.
- PDF:
- Date: 06/29/2016
- Proceedings: Cecos' Amended Motion to Compel and Amended Response to Department's and Intervenor's Motions for Protective Order filed.
- PDF:
- Date: 06/24/2016
- Proceedings: Notice of Hearing (hearing set for September 14 and 15, 2016; 9:30 a.m.; Lauderdale Lakes, FL).
- PDF:
- Date: 06/22/2016
- Proceedings: Motion to Consolidate by Respondent State of Florida Department of Transportation filed.
- PDF:
- Date: 06/22/2016
- Proceedings: BY ORDER OF THE COURT: Appeal dismissed pursuant to Florida Rule of Appellate Procedure 9.350(a).
- PDF:
- Date: 06/22/2016
- Proceedings: Motion to Consolidate by Respondent State of Florida Department of Transportation filed.
- PDF:
- Date: 06/22/2016
- Proceedings: Amended Final Order (Amended as to Notice of Appellate Rights) filed.
Case Information
- Judge:
- CATHY M. SELLERS
- Date Filed:
- 06/22/2016
- Date Assignment:
- 09/13/2016
- Last Docket Entry:
- 02/23/2017
- Location:
- Lauderdale Lakes, Florida
- District:
- Southern
- Agency:
- ADOPTED IN TOTO
- Suffix:
- BID
Counsels
-
Nona R. Schaffner, Esquire
Department of Transportation
Mail Stop 58
605 Suwannee Street
Tallahassee, FL 32399
(850) 414-5372 -
Joseph A Sorce, Esquire
Joseph A. Sorce & Associates, P.A.
Suite 200
3211 Ponce de Leon Boulevard
Coral Gables, FL 33134
(305) 529-8544 -
Nona R. Schaffner, Esquire
Address of Record -
Joseph A Sorce, Esquire
Address of Record -
Nona R Schaffner, Esquire
Address of Record