19-000754BID Social Sentinel, Inc. vs. State Of Florida, Department Of Education
 Status: Closed
Recommended Order on Wednesday, April 17, 2019.


View Dockets  
Summary: DOE's failure to meet statutory deadline for procurement of social media monitoring tool does not constitute illegality so as to require setting aside of its reject-all decision.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8SOCIAL SENTINEL, INC. ,

11Petitioner,

12vs.

13STATE OF FLORIDA, DEPARTMENT OF

18EDUCATION , Case No. 19 - 0754BID

24Respondent ,

25and

26ABACODE, LLC ; and ZEROFOX,

30INC.,

31Intervenors.

32_______________________________/

33RECOMMENDED ORDER

35On March 7, 2019 , Robert E. Meale, Administrative Law Judge

45of the Division of Administrative Hearings (DOAH), conducted the

54final hearing in Tallahassee, Florida.

59APPEARANCES

60For Petitioner: Thomas P. Crapps, Esquire

66Kirsten H. Mathis, Esquire

70Joy Ryan, Esquire

73Meenan, P.A.

75300 South Duval, Suite 4 1 0

82Tallahassee, Florida 32301

85For Respondent : Jason D. Borntreger, Esquire

92James L. Richmond, Esquire

96Department of Education

99325 West Gaines Street, Suite 1244

105Tallahassee, Florida 32399 - 0400

110For Intervenors: J. Riley Davis, Esquire

116Akerman, LLP

118106 East College Aven ue, Suite 1200

125Tallahassee, Florida 32301

128STATEMENT OF THE ISSUE

132The issue is whether Respondent 's decision to reject all

142replies to Invitation to Negotiate 2019 - 44, Social Media

152Monitoring (ITN) , is arbitrary or illegal , within the meaning of

162section 120.57(3)(f), Florida Statutes .

167PRELIMINARY STATEMENT

169By ITN issued on August 3, 2018, Respondent solicited

178replies to negotiate the procurement of a web - based s ocial media

191monitoring tool (Monitoring Tool) to examine social media posts

200to enhance school safety . On December 10, 2018, Respondent

210issued an Intent to Award to Intervenor Abacode, LLC (Abacode).

220On December 13, 2018, Petitioner filed a Notice of Protest,

230and, on December 21, 2018, Petitioner filed a Formal Written

240Protest and Petition for Administrative Hearing, as well as a

250bond. On January 3, 2019, Respondent issued an Amended Agency

260Decision t o reject all replies.

266On January 7, 2019, Petitioner issued a Second Notice of

276Protest, and, on January 16, 2019, Petitioner filed a Formal

286Written Protest and a Petition for Administrative Hearing

294(Petition).

295The Petition alleges that Respondent's rejec tion of all

304replies is contrary to a statutory deadline of December 1, 2018,

315for making the Monitoring Tool available for use by school

325districts, and Respondent should instead award the contract to

334Petitioner. The Petition alleges that Respondent's rejec tion of

343Petitioner's reply is arbitrary due to the absence of a stated

354logical reason for the rejection and illegal because it is

364contrary to the purpo se of a competitive procurement. As to the

376latter point, the Petition alleges that , by proposing an awar d

387and then rejecting all replies, Respondent allowed the replies to

397become public record, so that other vendors could examine the

407previously confidential replies of their competitors. The

414Petition requests a recommended order directing Respondent to

422a wa rd the contract to Petitioner.

429In the Pre - h earing S tipulation filed on March 5, 2019 ,

442Petitioner clarified the Petition. First, Petitioner sought

449alternative relief to an awar d of the contract to Petitioner: a

461reopening of the procurement to allow the eight vendors to submit

472replies to the ITN, as revised by Respondent in the manner set

484forth below , and a rescoring of the new replies.

493Second, a lthough Petitioner continued to allege that

501Respondent's reject - all decision is arbitrary and illegal,

510Petitioner revised its bases for these grounds. Petitioner

518claimed that the reject - all decision is arbitrary because

528Respondent failed to meet the December 1 statutory deadline;

537Respondent failed to state a reason for t he reject - all decision;

550and Respondent tardily made the reject - all decision following an

561award decision, so that the replies of Petitioner and other

571vendors became nonexempt public record s , thus undermining the

580integrity of the competitive procurement. Pe t itioner claimed

589that the reject - all decision is illegal because Respondent failed

600to meet the December 1 statutory deadline and Respondent tardily

610made the reject - all decision following an award decision, so that

622the replies of Petitioner and other vendor s became nonexempt

632public record s, thus undermining the integrity of the competitive

642procurement.

643Respondent transmitted the file to DOAH on February 14,

6522019. A Motion to Intervene was filed February 25, 2019, by

663Abacode and its partner, ZeroFox, Inc. 1 / By response filed

674February 28, 2019, Petitio ner objected to the motion. The

684administrative law judge granted the Motion to Intervene by Order

694entered on March 1, 2019 .

700At the hearing, Petitioner called one witness and offered

709into evidence 14 exh ibits: Petitioner Exhibits 1 through 14 .

720Respondent called two witness es and offered into evidence two

730exhibits : Respondent Exhibits 1 and 2 . Intervenors called no

741witnesses and offered into evidence no exhibits. The parties

750jointly offered 19 exhibits: Joi nt Exhibits 1 through 19. All

761exhibits were admitted.

764The court reporter filed the transcript on April 4 , 2019 .

775Each party filed a propose d recommended order on April 15 , 2019 .

788Petitioner's proposed recommended order does not contend that

796Respondent's r eject - all decision is illegal, but does not

807withdraw this claim, so it is addressed below.

815FINDING S OF FACT

8191. In response to the tragi c shootings at Marjorie Stoneman

830Douglas High School in February 2018, the legislature enacted,

839effective Marc h 9, 2018, the Marjorie Stoneman Douglas High

849School Public Safety Act (the Act). A mong other things, the Act

861authorizes Respondent to spend $3 million for the 2018 - 19 fiscal

873year "to competitively procure . . . [a] centralized data

883repository and analytics resourc es pursuant to s. 1001.212,

892Florida Statutes[,]" and provides that Respondent " shall make

901such resources available to the school districts no later than

911Dec ember 1, 2018." Ch. 2018 - 3, §§ 50 and 52, Laws of Fla.

9262. Within one month after the passage of the Act,

936Respondent confirmed that the above - quoted language mandated the

946procurement of two systems and that "analytics resources" refer s

956to the Monitoring Tool. Respondent researched the relevant

964technology and draf ted an ITN, which it issued on August 3, 2018.

9773. In general, the ITN requires each vendor to submi t , by

989September 6, 2018 , a reply consisting of a tech nical reply and a

1002price reply and provides that Respondent will evaluate the

1011replies by September 10, 2018. ITN sectio n 3.4 states that the

1023Negotiation Committee will commence negotiations on or about

1031September 24, 2018, and the winning vendor or vendors will

1041commence work on October 19, 2018.

10474. ITN section 8.1.2 , which contains the "Criteria for

1056Evaluation," states that Respondent will score each reply based

1065on a maximum of 70 points for the technical reply and 30 points

1078for the price reply. Section 8.1.2 states that, after

1087negotiati ons, Respondent anticipates awarding the contract, if

1095any, to not more than three vendors that Respondent has

1105determined provide the best value to the state. ITN section 8.3

1116provides that, after Respondent awards a contract to each of up

1127to three vendors, "[s]chool districts will then choose from these

1137approved vendors to determine which [Monitoring Tool] is used in

1147their district."

11495. ITN section 8.1.3, which contains the "Criteria for

1158Negotiations," broadly authorizes Respondent to negotiate

1164revisions to each vendor's technical reply, as required to serve

1174the best interest of the state. S ection 8.1.3.E. also authorizes

1185Respondent to revisit each vendor's price reply: "[Respondent]

1193reserves the right to negotiate differe nt terms and related price

1204adjustments if [Respondent] determines that it is in the state's

1214best interest to do so."

12196. ITN Attachment B is the " Price Reply. " The first

1229paragraph of Attachment B states: "There shall be no additional

1239costs charged for work performed under this I TN. The [school]

1250district price on this page will be used for evaluation and

1261scoring purposes." The second paragraph, which is titled,

"1269Assessment Instrument," add s : "Respondent shall provide a cost

1279for the Social Media Monitoring instrument and service s in

1289subsequent contract." Immediately below this statement is the

1297following price form :

1301Description Cost

1303Social Media Monitoring Contract 10/19/18 - 6/30/19 $ ____

1312instrument and services Period 7/1/19 - 6/30/20 $ ____

13212018 - 2021 7/1/20 - 6/30/21 $ ____

1329Social Media Monitoring Optional 7/1/21 - 6/30/22 $ ____

1338instrument and services Renewal 7/1/22 - 6/30/23 $ ____

1347Years 7/1/23 - 6/30/24 $ ____

1353Grand Total Cost* $____ $ ____

13597. The price form fails to reveal if the "Grand Total Cost"

1371and annual costs are per - district prices or gross price s ,

1383regardless of the number of school districts choosing to use the

1394Monitoring Tool . The asterisk is meaningless because the ITN

1404contains no explanation as to its meaning . The second blank line

1416to the right of "Grand Tot al Cost" is consistent with an

1428extension of a per - district price, but the document does not

1440direct the vendor to perform such an extension, which would be

1451impossible because, as noted above, the multiplier is unknown

1460until districts contract to use a speci fic Monitoring Tool .

14718. On August 22, 2018, Respondent issued ITN Addendum #1,

1481which answers questions posed by vendors. Through this means,

1490Respondent informed vendors that school districts are not

1498required to use the Monitoring T ool, Addendum #1, p. 3; it is

1511impossible to determine the volume of usage of the Monitoring

1521T ool among over 4000 schools serving about 3 m illion students,

1533Addendum #1, p. 3; replies may include more detailed pricing

1543schedules, such as "pricing based on dif fering user counts and/or

1554number of schools or districts, " Addendum #1, p. 4; and the

1565Monitoring Tool may be used by as many as 67 school districts

1577plus six university - affiliated l ab or charter schools,

1587Addendum #1, p. 6.

15919. On August 30, 2018, Respondent issued ITN Addendum #2,

1601which makes two changes to Attachment B. Addendum #2 deletes the

1612second blank line to the right of "Grand Total Cost" and explains

1624the asterisk by stating , "Points awarded will be based on this

1635price." Neither change resolves the ambiguity as to whether the

1645quoted price s are per - district or gross price s .

165710. Eight vendors , including Petitioner, timely submitted

1664replies. Petitioner is a responsible vendor and its reply is

1674responsive.

167511. It appears that Responde nt completed scoring of all of

1686the technical and price replies of the eight vendors in

1696substantial conformity with the September 10 deadline stated in

1705the ITN . As provided by the ITN, f ive of Respondent's employees

1718scored the technical replies , staff scored the price replies , and

1728the five employees who scored the technical replies formed the

1738negotiating team .

174112. One of the technical evaluators failed to discharge his

1751responsibilities. Appearing not to have read or understood the

1760basics of Petitioner 's reply, which describes a Monitoring Tool

1770already in use by several Florida school districts, the evaluator

1780wrongly concluded that Petitioner's reply did not offer a

1789Monitoring Tool and improperly assigned a low score to its reply.

1800This evaluator abrupt ly quit the day after turning in his

1811evaluations, and Respondent's negotiating team was reduced to the

1820four remaining evaluators.

182313. Based on the scoring of the replies , Respondent

1832selected three ve ndors with which to negotiate: Abacode,

1841Veratics, Inc. (Veratics), and NTT Data Inc. (NTT Data).

185014. Abacode re solved the ambiguity of the price form in

1861Attachment B by adding to the price form language stating that

1872its price is a per - district price. For the three years of the

1886base contract and three option al renewal years, Abacode's

"1895Per - District Grand Total Cost" was $68,350 , meaning that, even

1907ignoring the lab schools , the gross price would slightly exceed

1917$4.5 million, if all 67 school districts chose Abacode's

1926Monitoring Tool for six years. Abacode off ered a 15% discount i n

1939the unlikely event that all 73 school districts and lab schools

1950chose to use its Monitoring Tool .

195715. Veratics did not alter the price form and offered a

"1968Grand Total Cost" of $143,325.18 for the three years of the base

1981contract and three optional renewal years. This appears to be a

1992per - district price , so the gross price would slightly exceed

2003$9.6 million, if all 67 school districts chose Veratics'

2012Monitoring Tool for six years .

201816. NTT Data likewise completed the price form without

2027alterations, showing a "Grand Total Cost" of $88,454 for the

2038three years of the base contract and three optional renewal

2048years. An additional page entitl ed, "Additional Pricing Detail "

2057c onfirms that the "Gran d Total Cost" is a per - district price , so

2072the gross price would slightly exceed $5.9 million, if all

208267 school districts chose NTT Data's Monitoring Tool for six

2092years .

209417. Negotiations with the three vendors commenced in late

2103October 2018. During negotiations , Respondent's negotiating team

2110realized that the ITN failed to convey adequately Respondent 's

2120requirement to receive the notifications that the Monitoring T ool

2130transmits to the contracting school district , as vendors had not

2140included this serv ice in their price replies .

214918. A t some point, the negotiating te am also realized that

2161the price form was ambiguous as to per - district or gross pricing.

2174O n November 13, 2018, Respondent's procurement officer sent to a

2185member of the negotiating team a draft revised price form that

2196specified per - district pricing for the base years, but not for

2208the optional renewal years. After further revisions by the

2217recipie nt of the email , Respondent distributed a revised price

2227form to the three vendors, but not the five vendors that it had

2240not selected for negotiations.

224419. As applicable to both the base and optional renewal

2254period s , the revised price form requires an annual price for

2265notifications to Respondent; a one - time price for the "Initial

2276Districts [sic] firs t six (6) months " ; and "Costs per additional

2287district," which are classified by " Small," "Medium," and

"2295Large." The revised price form also includes a list of all

230667 districts with their 2017 - 18 enrollments and classifies each

2317district as "Small," "Medium," or "Large."

232320. The three vendors timely submitted revised p rice

2332replies with the following "Grand Total Costs": Abacode --

2342$4.6 million, Veratics -- $34.4 million, and NTT Data -- $6.0

2353million. The price replies of Abacode and NTT Data increased by

2364relatively modest amounts , but the price reply of Veratics , which

2374increased by nearly $25 million over the six years of the

2385procured servi ce, itemized about $5.5 million for the first year.

2396Hurdling past the $3 million authorized for the procurements of

2406the Monitoring Tool and a centralized data repository, Veratics

2415implicitly eliminated itself as a vendor.

242121. On December 10, 2018 -- nine d ays after the statutory

2433deadline for making the Monitoring Tool(s) available to school

2442districts -- Respondent issued a Notice of Intent t o Award the

2454contract to Abacode. Petitioner timely filed a Notice of Protest

2464and Formal Written Protest, which includes a Petition for

2473Administrative Hearing. The petition details, among other

2480things, the ambiguity in the original price form as to

2490per - d istrict or gross pricing and alleges that Respondent failed

2502to perform the necessary conversions to compare price replies

2511accurately. Addressing the negotiations, the petition notes,

2518among other things, that the three selected vendors were allowed

2528to chan ge their price replies and submitted what the petition

2539describes only as "higher" pricing -- certainly, a charitable

2548understatement as applied to Veratics. For relief, Petitioner

2556requested recommended and final orders directing that Respondent

2564award the con tract to Petitioner, "or, alternatively, that

2573[Respondent] reject all Replies and conduct a new procurement."

258222. On January 3, 2019, Respondent did just that:

2591Respondent issued an Amended Agency Decision rejecting all

2599replies and advising that it would reissue the ITN in a second

2611attempt to procure the Monitoring Tool. However, Petitioner

2619timely filed a Second Notice of Intent t o Pro test and Formal

2632Written Protest, as well as the Petition, which, as noted above,

2643requests a recommended order awarding the contract to Petitioner.

265223. Due to the school - safety issues involved in the subject

2664procurement, Commissioner of Education Richard Corcoran issued a

2672memorandum on February 13, 2019, authorizing Respondent to

2680proceed with the second procurement "to avoid an immediate and

2690serious danger to the public health, safety or welfare," as

2700provided by section 120.57(3)(c). On the same date, Governor Ron

2710DeSantis issued Executive Order 19 - 45, which, among other things,

2721characterizes as "unacceptable" Respondent's fa ilure to meet the

2730December 1 statutory deadline and orders Respondent to

"2738immediately take any and all steps necessary to implement [the

2748Act] to provide . . . [the Monitoring Tool] . . . by August 1,

27632019."

276424. The new invitation to negotiate is s imilar to the ITN,

2776except that its definition of "Notifications" in the scope of

2786services clearly defines the need to transmit notifications to

2795Respondent, as well as to the contracting school district , and

2805the price form i n Attachment B bases the evaluation on gross

2817prices.

281825. Respondent's decision to reject all replies is

2826supported by five facts: 1) the irrational scoring of

2835Petitioner's reply by one evaluator; 2) the potential confusion

2844caused among potential vendors, including the eight vendors that

2853submitted replies, by the ambiguity contained in the price form

2863in Attachment B; 3) the revision of the price form for the three

2876selected vendors to clarif y that the pricing was on a

2887per - district basis; 4) the effective loss of one of the thre e

2901selected vendors upon receipt of pricing replies to the revised

2911price form ; and 5) the capacity to resolve the then - pending

2923protest by acceding to Petitioner's demand for a reject - all

2934decision .

293626. As for the first reason, Petitioner objected at hearing

2946to testimony from one of Respondent's witnesses pertaining to

2955this matter because, on deposition, Respondent's agency

2962representative failed to identify the irrational scoring as a

2971factor in the reject - all decision. As discussed in the

2982Conclusions of Law, section 120.57(3)(f) requires a determination

2990of whether an agency's reject - all decision "is," not "was,"

3001arbitrary. Thus, all facts may be considered, regardless of

3010whether an agency witness cited them in a deposition or, more

3021broadly, whether an agency cited them at the time of making the

3033reject - all decision. Additionally , despite the failure of the

3043deposition witness to identify this factor, P etitioner mentioned

3052in the Pre - h earing Stipulation "incorrect evaluations" by at

3063least one evaluator, so Petitioner was aware of this ba sis for

3075the reject - all decision, even though Pe titioner may not have been

3088aware that Respondent relied on t his factor in making the

3099reject - all decision.

310327. As for the third reason, as noted above, the ITN

3114permits Responden t to negotiate new items and, if so, obtain

3125revised price replies from the vendors with which it is

3135negotiating. These provisions cover the addition of the

3143notification to Respondent, which Respondent substantially

3149omitted from the ITN. However, resoluti on of a basic element of

3161any bid 2 / solicitation -- here , whether the price form calls for

3174per - district or gross pricing -- does not fall within these

3186provisions, so Respondent's decision to provide this revision

3194only to the three selected vendors raises compet itive concerns.

320428. As for the fourth reason, the ITN p ermits Respondent to

3216have selected two vendors for negotiations in the first place.

3226But this does not mean that the effective loss of a selected

3238vendor is not available as a legitimate reason to re ject all

3250replies. Also, Veratics' jarring price increase indicates either

3258that one of the successful vendors failed to appreciate the scope

3269of the procurement or did not wish to participate in the

3280procurement any further -- either reason signaling a potential

3289problem with the procurement , so that Respondent rationally may

3298have decided to reject all replies .

330529. As for the fifth reason, Respondent had already missed

3315the December 1 statutory deadline, and a reject - all decision

3326represent ed the quic ker route to comp leting this procurement

3337because of the above - cited flaws in the initial procurement; the

3349school - safety issue , which authorizes the immediate commencement

3358of a second procurement for the Monitoring Tool ; and, as

3368discuss ed in the Conclusions of Law, a reject - all decision is

3381easier to defend than an award decision.

338830. In the Pre - h earing Stipulation, Petitioner requested

3398relief in the form of a reopening of the procurement process

3409following a clarification from Respondent -- presumably, as to the

3419pricing ambiguity in the original price form and the need to

3430provide notifications to Respondent; an opportunity for all eight

3439vendors to submit new replies; and the scoring of the new

3450replies.

345131. First, Petitioner did not seek this relief in its

3461initial petition protesting the award decision or even in the

3471Petition protesting the reject - all decision. So, when making the

3482reject - all decision, Respondent was acceding to the only

3492alternative posed by Petitioner that did not result in an award

3503to Petitioner . By doing so, as explained above, Respondent

3513rationally pursued an expeditious resolution of the then - pending

3523protest and, thus, the procurement of the Monitoring Tool. Had

3533Respondent chosen an opt ion not presented by Petitioner,

3542Respondent had no assurance that its choice would have induced

3552Petitioner to dismiss its first protest.

355832. Second, even if Respondent should have assumed that a

3568restart of the first procurement would have resolved Petitio ner's

3578then - pending protest, as it accomplishes the same thing as a

3590reject - all decision followed by a rebid, the focus is on whether

3603Respondent made a rational choice, not whether it made the best

3614choice. By this point, at least , Respondent was trying to h urry

3626along the procurement , and a reject - all decision would achieve

3637this end, even if a restart of the first procuremen t might have

3650been resulted in an earlier award.

365633. Under the circumstances, Respondent's decision in

3663January 2019 to cut its losses and reject all replies, clean up

3675the documents, and rebid the procurement is not arbitrary .

368534. As discussed in the Conclusions of Law, no further

3695analysis is required of Petitioner's claim that the reject - all

3706decision is arbitrary fo r the additional reason that the sequence

3717of events -- an award decision, a re ject - all decision, and a

3731rebid -- has resulted in the disclosure of each vendor's reply and

3743undermined the integrity of the procurement process. The point

3752is that the reject - all dec ision is rational -- not, as discussed

3766above, whether Respondent could have made a better decision or,

3776in connection with a claim of arbitrariness , whether the effect

3786of the agency's decisionmaking sequence may also have undermined

3795the integrity of the procu rement process.

3802CONCLUSIONS OF LAW

380535 . DOAH has jurisdiction. §§ 120.569 and 120.57(1)

3814and (3) , Fla. Stat. Petitioner and Abacode are "adversely

3823affected" by the reject - all decision. § 120.57(3)(b).

383236. The burden of proof is on Petitioner. § 120.57(3)(f).

3842Section 120.57(3)(f) identifies what Petitioner must prove in

3850order to prevail in a bid case based on an award decision or a

3864reject - all decision :

3869In a competitive - procurement protest, other

3876than a rejection of all bids, proposals, or

3884replies, the administrative law judge shall

3890conduct a de novo proceeding to determine

3897whether the agencyÓs proposed action is

3903contrary to the agencyÓs governing statute s,

3910the agencyÓs rules or policies, or the

3917solicitation specifications. The standard of

3922proof for such proceedings shall be whether

3929the proposed agency action was clearly

3935erroneous, contrary to competition,

3939arbitrary, or capricious. In any bid - protest

3947pro ceeding contesting an intended agency

3953action to reject all bids, proposals, or

3960replies, the standard of review by an

3967administrative law judge shall be whether the

3974agencyÓs intended action is illegal,

3979arbitrary, dishonest, or fraudulent.

398337. Section 120.5 7(3)(f) requires deference to an agency's

3992decision in any bid case and greater deference to an agency's

4003decision in a reject - all case than an award case. 3 / I n an award

4020case , the role of the administrative law judge is to conduct a

4032de novo hearing and apply a standard of proof, but the standards

4044of proof and criteria for overturning the proposed award decision

4054are deferential. I n a reject - all case, the role of the

4067administrative law judge is to conduct a hearing , impliedly not

4077entirely de novo, and app ly a standard of review , not proof, and

4090the criteria for overturning the proposed reject - all decision are

4101even more deferential. In both c ases, the deferential

4110criteria -- and, in the award case, the deferential standards of

4121proof -- apply only to the agency' s intended 4 / action. 5 /

413538. A close reading of section 120.57(3)(f) is unnecessary

4144to reject Petitioner's claim that Respondent's intended agency

4152action to reject all replies is arbitrary. In general, an

"4162arbitrary" decision is a decision unsupported by logic or the

4172necessary facts. See § 120.52(8)(e) ( defining "arbitrary" as

4181criterion for invalidating a rule); Agrico Chem. Co. v. Dep't of

4192Envtl. Reg. , 365 So. 2d 759, 763 (Fla. 1st DCA 1978 ) ( arbitrary

4206means "despotic" or not supported by facts or logic). As an

4217appellate standard of review, the "arbitrary and capricious"

4225standard subjects an agency's decisionmaking "only to the most

4234rudimentary command of rationality[, requiring] an inquiry into

4242the basic orderliness of the [decisionmaking] process, and

4250authoriz[ing] the courts to scrutinize the actual [decision] for

4259signs of blind prejudice or inattention to crucial facts." Ad am

4270Smith Enters. v. State Dep't of Envtl. Reg. , 553 So. 2d 1260,

42821273 (Fla. 1st DCA 1989) (construing former statute governing

4291direct appeals of legislative rulemaking by agencies).

429839. The language of section 120.57(3)(f) requires a

4306determination of whether the intended agency action to reject all

4316replies "is" arbitr ary. This implies that the determination is

4326based on the facts available at the time of the hearing,

4337regardless of whether the agency relied on them when making its

4348reject - all decision. Regardless of whether Respondent rejected

4357all replies, in part, due to the irrational scoring of one

4368evaluator , am ple additional reasons support Respondent's

4375reject - all decision, as set forth in the Findings of Fact.

4387Petitioner thus has failed to prove that Respondent's reject - all

4398decision is arbitrary.

440140. A close reading of section 120.57(3)(f) is not

4410necessary to reject one of Respondent's claim s that the intended

4421agency action to reject all replies is illegal. Section

4430120.57(3) does not define "illegal," but a common definition of

4440the term is "not accord ing to or authorized by law." Merriam

4452Webste r online dictionary . 6 / Justice Canady has cited a similar

4465definition, which states that "illegal means 'contrary to, or

4474forbidden by, law.' 7 The Oxford English Dictionary 652 (2d ed.

44851989)." State v. McMahon , 94 So. 3d 468, 479 (Fla. 2012)

4496(Canady, J., dissenting).

449941. There is nothing even literally illegal in the sequence

4509of the procurement, which consists of an award decision, a

4519disclosure of the replies of all of the vendors, a reject - all

4532decision, and a reissuance of substantially the same ITN. As

4542P etitioner contends, by law, the subject procurement required a

4552competitive sealed reply, § 287.057, and the replies remained

4561exempt public records under certain conditions. § 119.071(1)(b).

4569The effect of en tire sequence of events res ulted in the loss of

4583the public - records exemption prior to the issuance of the new

4595invitation to negotiate , but this represents nothing more than

4604the interplay of the laws governing competitive proc urement and

4614the laws governing public records, including replies to an

4623invitation to negotiate. 7 / Petitioner thus has failed to prove

4634that Respondent's reject - all decision is illegal due to the

4645disclosure of the contents of Petitioner's reply .

465342. However, a close reading of section 120.57(3)(f) is

4662necessary to address the other illegality claim , which is

4671predicated on Respondent's failure to complete the procurement by

4680the statutory deadline of December 1, 2018. The facts support

4690this claim. It i s undisputed that the procurement has missed the

4702statutory deadline -- as of this date, by over four months on a

4715procurement that, from start to finish, was allotted nine months.

4725It is undisputed that time is of the essence in this procurement,

4737which, by le gislative mandate, was to enhance school safety on a

4749sche dule enacted by the legislature .

475643. It is necessary to distinguish between the claim and

4766the relief sought by Petitioner. Claiming that the failure to

4776meet the statutory deadline satisfies the criterion of

4784illegality, so as to necessitate the setting aside of the

4794reject - all decision, Petitioner variably has reques ted an award

4805of the contract, a restart of the procurement, or, at least

4816implicitly, a remand of the matter for Respondent to reconsid er

4827its reject - all decis ion, freed of whatever illegality attached to

4839its January 3 reject - all decision.

484644. It is irrelevant that Petitioner has failed to

4855recognize the power of its claim. If the failure to meet the

4867statutory deadline satisfies the meani ng of illegality in section

4877120.57(3)(f), this is a condition that cannot be cured. In other

4888words, i f Respondent's failure to make available a Monitoring

4898Tool to the school districts by December 1 is illegal, all acts

4910after December 1, 2018, to procure the Monitoring Tool may be set

4922aside, if challenged by an adversely affected person , 8 / unless the

4934legislature reinstates the procurement.

493845. The question is whether this claim is supported by the

4949law. B etween the utter irrationality of arbitrariness and the

4959deception or corruption associated with dishonesty or fraud lie

4968bidding mishaps arising from an agency's inattention to detail:

4977within this spacious middle ground, an agency's intended action

4986may giv e rise to claims of illegality.

499446. A literal d efinition of illegal contradicts the

5003structure of section 120.57(3)(f). A violation of law, at least

5013as applicable to bidding, is well described by the three criteria

5024for setting aside an award decision: a violation of statute,

5034rule or policy, or, treating the invitation to bid as a contract

5046binding on the agency , the specification document. If "illegal"

5055covers substantially the s ame ground, then a reject - all case may

5068be easier to win for a protestor, which, if unable to prove

5080illegality, may show one of the other criteria; of course, such a

5092situation would undermine section 120.57(3)(f), which secure s

5100greater deference to an agenc y decision not to do business with

5112any vendor than an agency decision to do business with a vendor.

512447. T he source of the legislative enactment of i l legality

5136as a criterion for setting aside a reject - all decision was a

5149then - recent Florida Supreme Court case, which, in turn, relie d on

5162other decisions. But none of these cases sets aside an agency

5173bid decis ion based on a literal definitio n of illegal ity .

518648. Enacted in 1996, 9 / the reject - all provisions of section

5199120.57(3)(f) codified Departm ent of Transportation v. Groves -

5208Watkins Constructors , 10 / whi ch held that an agency's reject - all

5221decision may not be overturned absent a finding of "'illegality,

5231fraud, oppression, or misconduct,'" 11 / as the Court had earlier

5243held in Liberty County v. Baxter's Aspha lt & Concrete, Inc. 12 /

525649. Groves - Watkins was an illegality case that,

5265unfortunately, was treated as an arbitrariness case by the Court,

5275the lower court, and the hearing officer. In Groves - Watkins , the

5287agency reject ed all bids to construct a complex highway

5297interchange and immediately reissued the same invitation to bid.

5306The agency based its reject - all decision on the fact that the

5319lowest bid exceeded the agency's projected costs by 29% .

5329However, the large discrepancy was due to the agency 's

5339miscalculation of projected cost s, which, when corrected,

5347substantially eliminated any difference between the projected

5354costs and the bid amount . Because the agency's policy was

5365automatically to award a bid if the lowest bid was less than 7%

5378more than pro jected costs, the hearing officer concluded that the

5389reject - all decision was arbitrary and capricious and recommended

5399that the agency issue a final order setting aside the reject - all

5412decision and awarding the bid to the lowest bidder.

542150. The agency iss ued a final order rejecting the

5431recommended order and affirming its reject - all decision .

5441Reversing, the First District Court of Appeal concluded that the

5451agency's reject - all decision was arbitrary and capricious. 13 / In

5463dissent, Judge Ervin stated that there was no finding of

"5473'illegality, fraud, oppression or misconduct'" and, if there

5481were one, it would have lacked a sufficient evidentiary basis,

5491implying that he was not equating "illegality" with literal

5500illegality . Judge Ervi n reviewed case law from other

5510jurisdictions that, notwithstanding some conflicting decisions ,

5516provided that an agency enjoys "unbridled discretion" to reject

5525all bids, so as always to reserve for the agency the right to

5538redesign its procurement to reduce costs . Ultimately retreating

5547from this position , Judge Erving concluded that a reject - all

5558decision must be sustained, as long as it is free from " the

5570Liberty County standard of . . . f raud, oppression, or

5581misconduct, " 14 / this time omitting from his restatement of the

5592Liberty County criteria the troublesome criterion of illegality.

560051. Reversing the First District, the Florida Supreme Court

5609held that the Liberty County criteria conform to "the majority

5619view that . . . judicial inte rvention to prevent the rejection of

5632a bid should occur only when the purpose or effect of the

5644rejection is to defeat the object and i ntegrity of competitive

5655bidding . " Ignoring the Liberty County criterion of illegality,

5664the Court understandably found t hat budgetary concerns arising

5673from an "honest mistake" by the agency in projec ting costs

5684insulated the reject - all decision from a claim of arbitrariness.

569552. In support of its holding , the Court cited , among other

5706sources, a Third Circuit Court of Appeal s decision, Sea - Land

5718Service, Inc. v. Brown , 15 / for the principle that "only [a]

5730showing of clear illegality will entitle an aggrieved bidder to

5740judicial relief." 16 / The Court did not explain how a violation of

5753the 7% policy did not constitute "clear illegality " or explain

5763the meaning of "clear illegality."

576853. The Sea - Land Service d ecision equates a "showing of

5780clear illegality " with "no r ational basis" for the decision , 17 / so

5793as to treat illegality and arbitrariness synonymously . But, a s

5804Groves - Watkins itself illustrates , a reject - all decision may be

5816illegal without being arbitrary. In any case , neither

5824Groves - Watkins nor Sea - Land Services offers any support for a

5837literal interpretation of illegal ity , and their common use of

"5847clear illegality" suggests a judicial intent to require

5855illegality plus something unspecified by the courts.

586254. More recent federal procurement cases have identified a

5871factor to be added to literal illegality: prejudice to the

5881protestor . I n Caddell Construction Co. v. U nited States , 18 / the

5895court summarized the applicable law for setting aside an agency's

5905decision in a bid case:

5910As the [federal Administrative Procedure Act

5916in determining whether to

5920set aside agency action, the Court shall

5927take "due account . . . of the rule of

5937prejudicial error." 5 U.S.C. § 706. In the

5945seminal case of Kentron Hawaii, Ltd. v.

5952Warner , [ 19 / ] . . . the United States Court of

5965Appeals for the Dist rict of Columbia Circuit

5973emphasized that to be remediable, a

5979procedural procurement error had to result

5985in a "prejudicial violation of applicable

5991statute or regulations," or an irrational

5997award decision. 480 F.2d 1166, 1169, . . .

6006(D.C. Cir. 1973). Thus, when an irrational

6013or arbitrary and capricious agency action

6019has occurred, prejudice is presumed, but

6025when a violation of statute or regulation

6032has occurred, there must be a separate

6039showing of prejudice. See generally Centech

6045Grp., Inc. v. United States , 554 F.3d 1029,

60531037 (Fed. Cir. 2009) (recognizing that "a

6060reviewing court may set aside a procurement

6067action if the procurement official's

6072decision lacked a rational basis or for a

6080challenge involving "a violation of

6085regulation or procedure . . . the

6092dis appointed bidder must show a clear and

6100prejudicial violation of applicable statutes

6105or regulations.") (emphasis added) (internal

6111citations omitted); Banknote Corp. of Am.

6117Inc. v. United States , 365 F.3d 1345, 1351

6125(Fed. Cir. 2004) (recognizing that under t he

6133APA standard applied in [ Administrative

6139Dispute Resolution Act of 1996 ] cases "a bid

6148award may be set aside if either (1) the

6157procurement official's decision lacked a

6162rational basis; or (2) the procurement

6168procedure involved a violation of regulation

6174or procedure . . . . When a challenge is

6184brought on the second ground, the

6190disappointed bidder must show a clear and

6197prejudicial violation of applicable statutes

6202or regulations.") (emphasis added) (internal

6208citation and quotation marks omitted). [ 20 / ]

6217O ther federal decisions require a showing of prejudice , wit hout

6228regard to the fe deral APA, evidently based on the application of

6240common law to federal procurements . See, e.g. , TRW Envtl. Safety

6251Sys., Inc. v. U.S. ; 21 / Data Gen. Corp. v. Johnson . 22 /

626555. None of these definitions works. The literal

6273definition destroys the structure of section 120.57(3)(f) and its

6282establishment of different levels of deference. Examined from

6290the perspectives o f Respondent's failure to comply with the

6300statutory deadline, a hypothetical failure to coordinate the

6308procurement of the Monitoring Tool with the Florida Department of

6318Law Enforcement and school districts, and the Groves - Watkins

6328facts, proposed agency action in each of these cases would be

6339illegal, and each of these procurements could not proceed.

634856. The "clearly illegal" definition lacks meaning ,

6355although the Court 's reference to the object of competitive

6365bidding implies the exclusion of literal illegality . It would

6375ma ke little sense if the Court were referring to the probability

6387of illegality. Factfinding is by degree, but judicial

6395conclusions of law are not. Once the facts are found by the

6407agreed - upon evidentiary standard, an act or omission is legal or

6419it is not, and labeling the act or omission as "clearly illegal"

6431adds nothing. For example , treating the standard of illegality

6440as "certainly illegal," the proposed agency action would be

6449illegal in this case, the coordination hypothetical, and

6457Groves - Watkins , just as the proposed agency action would be using

6469a literal definition of illegal.

647457. Literal illegality plus prejudice achieves greater

6481deference because the proposed agency action in the three

6490scenarios would be illegal only in Groves - Watkins . In the

6502pres ent case, Petitioner's claims arising out of the disclosure

6512of its reply involve prejudice, but not prejudice arising from

6522Respondent's failure to comply with the statutory deadline.

6530However, prejudice is extrinsic to illeg ality, not part of

6540illegality, s o as likely to require legislation to be added to

6552section 120.57(3)(f).

655458. A nother definition preserves the structure of section

6563120.57(3)(f) and , if not precisely co - extensive with literal

6573illegality, introduces no extrinsic elem ents, while achieving at

6582least the deference of literal illegality plus prejudice . 23 / The

6594definition is a departure from the essential requirements of law ,

6604which is the primary criterion used by courts to review , by

6615certiorari, quasi - judicial actions of agencies that are not

6625subject to chapter 120 when no other method of review is

6636available. Haines City Cmty. Dev. v. Heggs , 658 So. 2d 523, 530

6648(Fla. 1995). Although more frequently applied to certiorari

6656review of local land use decisions, this deferential criterion

6665ha s been applied to a bid decision of an agency not covered by

6679chapter 120. Biscayne Marine Partners, LLC v. City of Miami ,

66892 019 Fla. App. LEXIS 2122, pp. 7 - 8 (Fla. 3d DCA 2019) (discussion

6704of the four Liberty County criteria in analysis of whether a

6715proposed bid award constituted a departure from the essential

6724requirements of law) .

672859. Specifically, a departure from the essential

6735requirements of law is :

6740an inherent illegality or irregularity, an

6746abuse of judicial p ower, an act of judicial

6755tyranny perpetrated with disregard of

6760procedural requirements, resulting in a

6765gross miscarriage of justice. The writ of

6772certiorari properly issues to correct

6777essential illegality but not legal error.

6783Heggs , 658 So. 2d at 527 - 28 (citing Jones v. State , 477 So. 2d

6798566, 569 (Fla. 1985) (Boyd, C.J., concurring specially) ) .

6808Consistent with the reference to the object of competitive

6817bidding in Groves - Watkins , t his is the meaning of illegality in

6830section 120.57(3)(f).

683260. Assessed by this definition, Respondent's failure to

6840meet the statutory deadline is not an inherent or essential

6850illegality , and proceeding with the procurement after December 1,

68592018, is not an abuse of administrative power of any sort , nor a

6872miscarriage of justice. Thus, the failure to meet the statutory

6882deadline is not a departure from the essential requirements of

6892law, so it does not constitute illegality within the meaning of

6903section 120.57(3)(f).

690561. Respondent's violation of the stat utory deadline is not

6915a departure from the essential requirements of law, in part,

6925because the legislature imposed no penalty on Respondent's

6933violation of the statutory deadline , notwithstanding its

6940materiality . 24 / As noted above, the Governor and Commissioner of

6952Education have inferred that the procurement may continue --

6961implicitly recogniz ing that it is illogical, when a statutory

6971deadline is violated, to impose draconian consequences, not

6979specified by statute, so as to defeat the objective of the

6990statutory deadline in the first place -- here, to secure the

7001Monitoring Tool, sooner rather than later . 25 / A literal

7012definition of illegality in section 120.57(3)(f) would write into

7021the Act a draconian penalty for Responden t's violation of the

7032statutory deadline in defiance of common sense.

703962. Petitioner thus has failed to prove that Respondent's

7048r eject - all decision is illegal because Respondent violated the

7059statutory deadline.

7061RECOMMENDATION

7062It is

7064RECOMMENDED that the Department of Education enter a final

7073order dismissing the Petition.

7077DONE AND ENTERED this 1 7 th day of April , 2019 , in

7089Tallahassee, Leon County, Florida.

7093S

7094ROBERT E. MEALE

7097Administrative Law Judge

7100Division of Administrative Hearings

7104The DeSoto Building

71071230 Apalachee Parkway

7110Tallahassee, Florida 32399 - 3060

7115(850) 488 - 9675

7119Fax Filing (850) 921 - 6847

7125www.doah.state.fl.us

7126Filed with the Clerk of the

7132Division of Administrative Hearings

7136this 1 7 th day of April , 2019 .

7145ENDNOTES

71461 / All references to "Abacode" include ZeroFox, Inc.

71552 / All references to "bid" are to all types of procurements,

7167including an invitation to negotiate.

71723 / The statutory analysis in this recommended order does not rely

7184on legislative intent, except where explicitly so stated.

7192Instead, the statutory analysis defines the key word,

"7200illegality," based, not on its liter al meaning in isolation, but

7211on:

7212the entire text of a statute, including its

7220structure and the physical and logical

7226relation of its many parts, when applying

7233the language of the statute to a set of

7242facts. See Scalia & Garner, Reading the

7249Law: The Interpr etation of Legal Texts ,

7256p. 167 (2012) ("Perhaps no interpretative

7263fault is more common than the failure to

7271follow the whole - text canon, which calls on

7280the judicial interpreter to consider the

7286entire text, in view of its structure and of

7295the physical and lo gical relation of its

7303many parts.").

7306Hous. Opportunities Project v. SPV Realty, LC , 212 So. 3d 419, 421

7318(Fla. 3d DCA 2016).

7322Adherence to the whole - text canon avoids any conflict between

7333the legislative intent and the statutory language, although some

7342decisions hold that legislative intent may override the "strict

7351letter of the statute." See, e.g. , Vildibill v. Johnson , 492 So.

73622d 1047, 1048 (Fla. 1986); State v. Webb , 398 So. 2d 820 (Fla.

73751981). The First District Court of Appeal has limited these

7385Florida Supreme Court holdings to cases in which a literal

7395construction would lead to "absurd or unreasonable

7402unconstitutional resu lts" or "ambiguity, absurdity, or

7409unreasonableness on the face of the statute." Kuria v. BMLRW,

7419LLLP , 101 So. 3d 425, 426 - 27 (Fla. 1st DCA 2012). However, this

7433may be a misreading of Vildibill , which consists of two

7443independent parts: first, the crediti ng of le gislative intent,

7453even when it may contradict th e strict letter of the statute, and,

7466second, the reading of a statute to harmonize it with the

7477constitution. See also Byrd v. Richardson - Greenshields Secur.,

7486Inc. , 552 So. 2d 1099 (Fla. 1989); State v. Webb , 392 So. 2d 820

7500(Fla. 1981); Dep't of Prof' l Reg. v. Fla. Dental Hygienist Ass'n ,

7512612 So. 2d 646 (Fla. 1st DCA 1993).

75204 / Section 120.57(3)(f) addresses "proposed" agency action in the

7530award case and "intended" agency action in the reject - all case .

7543The administrative law judge is unaware of any difference in

7553meaning between "proposed" and "intended" agency action. Perhaps

7561the statute uses the two terms to emphasize the distinction

7571between the award case and the reject - all case. This recommended

7583order uses the terms interchangeably.

75885 / Because the deferential standards and criteria apply to the

7599proposed agency action, the administrative law judge may find

7608direct evidentiary facts based on the preponderance standard.

7616§ 120.57(1)(j). Such facts would include what was said at a

7627bidders' conference, when a bidder submitted a bid, or an

7637evaluator's explanation for a score. The agency may make some

7647intermediate - level determinations, such as whether a variance is

7657a minor irregularity and, if so, whet her to waive it, that may

7670also be addressed under the deferential standards and criteria

7679because they are not direct evidentiary facts.

76866 / "Illegal," merriam - webster.com, https://www.merriam -

7694webster.com/dictionary/illegal (last visited April 15 , 2019).

77007 / As an aside, it does not appear that any vendor availed itself

7714of the opportunity to protect the confidentiality of any trade

7724secrets, as provided by section 815.045. See Managed Care of

7734N. Am., Inc. v. Fla. Healthy Kids Corp. , 2019 Fla. App. LEXIS

774640 39 (Fla. 1st DCA 2019) (not yet final).

77558 / The inclusion of a statutory deadline for a procurement may

7767not be common, so the inability to cure a violation may be an

7780unusual situation. The Act also requires Respondent, in

7788preparing the ITN, to coordinate with the Florida Department of

7798Law Enforcement and the school districts. If a protestor proved

7808a claim that Respondent failed to do so and a literal definition

7820of illegality applied, Respondent's failure to coordinate would

7828constitute a literal illegalit y, but presumably could be remedied

7838by later coordination with these entities and making revisions to

7848the ITN, as necessary or advisable.

78549 / Ch. 1996 - 159, § 19, Laws of Fla.

786510 / 530 So. 2d 912 (Fla. 1988). Donna E. Blanton, Florida's

7877Revised Administra tive Procedure Act, 70 Fla. B.J., July/Aug.

78861996, at 30, 35 .

789111 / Groves - Watkins , 530 So. 2d at 914 ( citing Liberty C nty . v.

7908Baxter's Asphalt & Concrete, Inc. , 421 So. 2d 505, 507 (Fla.

79191982) ) . As to the addition of the criterion of illegality, see

7932preceding endnote.

793412 / 421 So. 2d 505, 507 (Fla. 1982).

794313 / Some of the above - cited facts are found only in the

7957intermediate appellate decision, Groves - Watkins Constructors v.

7965Dep't of Transp. , 511 So. 2d 323 (Fla. 1st DCA), reh. denied with

7978opinion , 511 So. 2d 323 (Fla. 1st DCA 1987) (discussions of,

7989among other things, the effect of agency's proceeding with second

7999procurement during a pending bid protest and the power of court

8010to direct agency to award contract to a vendor).

801914 / Groves - Watkins , 511 So. 2d at 330, 332 (Ervin, J.,

8032dissenting).

803315 / 600 F.2d 429 (3d Cir. 1979).

804116 / Groves - Watkins , 530 So. 2d at 913.

805117 / Sea - Land Service , 600 F.2d at 434.

806118 / 125 Fed. Cl. 30 (2016).

806819 / 480 F.2d 1166 (D.C. Cir. 1973). This case is cited by

8081Sea - Land Services .

808620 / Caddell Constr. , 125 Fed. Cl. at 50.

809521 / 18 Cl. Ct. 33, 65 (1989).

810322 / 78 F.3d 1556 (Fed. Cir. 1996).

811123 / Defining illegality as a departure from the essential

8121requirements of law may even preserve the agency's re ject - all

8133decision o n the Groves - Watkins facts, although it is a close

8146call. If not, the only standard that would preserve the

8156reject - all decisio n would be Judge Ervin's "unfetter ed

8167discretion" standard, which reads out of the law all four Liberty

8178County criteria.

818024 / Using simil ar reasoning, Florida courts traditionally have

8190examined the history and subject matter of a statutory deadline

8200and, if the statute did not explicitly restrain the performance

8210of the act after the deadline and the statute was not

8221jurisdictional, declined t o enforce a statutory deadline because

8230the statute was directory rather than mandatory. See, e.g. ,

8239Schneider v. Gustafson Indus . , Inc. , 139 So. 2d 423, 425 (Fla.

82511962); First Providian, L.L.C. v. Evans , 852 So. 2d 908 (Fla. 4th

8263DCA 2003).

826525 / In the unlikely event that the legislature were to take a

8278different view, it could easily terminate the procurement by not

8288authorizing or appropriating funding for years after the 2018 - 19

8299fiscal year.

8301COPIES FURNISHED:

8303Jason D. Borntreger, Esquire

8307James L. Richmond, Esquire

8311Department of Education

8314325 West Gaines Street, Suite 1244

8320Tallahassee, Florida 32399 - 0400

8325(eServed)

8326Thomas P. Crapps, Esquire

8330Joy Ryan, Esquire

8333Meenan P.A.

8335300 South Duval Street, Suite 410

8341Tallahassee, Florida 32301

8344(eServed)

8345Kirsten H. Mathis, Esquire

8349Meenan, P.A.

8351300 South Duval Street, Suite 410

8357Tallahassee, Florida 32301

8360J. Riley Davis, Esquire

8364Akerman, LLP

8366106 East College Avenue, Suite 1200

8372Tallahassee, Florida 32301

8375(eServed)

8376Chris Emerson, Agency Clerk

8380Department of Education

8383Turlington Building, Suite 1520

8387325 West Gaines Street

8391Tallahassee, Florida 32399 - 0400

8396(eServed)

8397Matthew Mears, General Counsel

8401Department of Education

8404Turlington Building, Suite 1244

8408325 West Gaines Street

8412Tallahassee, Florida 32399 - 0400

8417(eServed)

8418NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

8424All parties have the right to submit written exceptions within

8434ten days from the date of this Recommended Order. Any exceptions

8445to this Recommended Order should be filed with the agency that

8456will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 04/17/2019
Proceedings: Recommended Order
PDF:
Date: 04/17/2019
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 04/17/2019
Proceedings: Recommended Order (hearing held March 7, 2019). CASE CLOSED.
PDF:
Date: 04/15/2019
Proceedings: Proposed Recommended Order filed.
PDF:
Date: 04/15/2019
Proceedings: Respondent's Proposed Recommended Order filed.
PDF:
Date: 04/15/2019
Proceedings: Intervenors' Proposed Recommended Order filed.
PDF:
Date: 04/08/2019
Proceedings: Notice of Filing Transcript.
Date: 04/04/2019
Proceedings: Transcript of Proceedings (not available for viewing) filed.
PDF:
Date: 03/08/2019
Proceedings: Notice of Filing (attached Exhibit A) filed.
PDF:
Date: 03/08/2019
Proceedings: Notice of Appearance (Thomas Range) filed.
Date: 03/07/2019
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 03/07/2019
Proceedings: Petitioner's Motion in Limine to Exclude Respondent's Witnesses and/or Exclude Duplicative Testimony filed.
PDF:
Date: 03/05/2019
Proceedings: Petitioner's Motion in Limine to Exclude Intervenor's Witnesses and/or Restrict Testimony to Suport Department's Decision to Reject All Replies and Exclude testimony regarding Responsiveness and Responsibleness of Abacode Bid Response filed.
PDF:
Date: 03/05/2019
Proceedings: [Joint] Pre-hearing Stipulation filed.
PDF:
Date: 03/04/2019
Proceedings: Petitioner's Response to Respondent's Motion to Quash Deposition Duces Tecum and Request for Protective Order and Motion to Compel filed.
PDF:
Date: 03/01/2019
Proceedings: Order Granting Motion to Intervene.
PDF:
Date: 03/01/2019
Proceedings: Respondent's Motion to Quash Deposition Duces Tecum and Request for Protective Order filed.
PDF:
Date: 02/28/2019
Proceedings: Petitioner Social Sentinel, Inc.'s Response and Objection to Motion for Leave to Intervene filed.
PDF:
Date: 02/28/2019
Proceedings: Petitioner, Social Sentinel, Inc.'s Notice of Taking Deposition Duces Tecum filed.
PDF:
Date: 02/28/2019
Proceedings: Petitioner, Social Sentinel, Inc.'s Notice of Filing Answers to Respondent, Department of Education filed.
PDF:
Date: 02/25/2019
Proceedings: Motion for Leave to Intervene filed.
PDF:
Date: 02/25/2019
Proceedings: Order Granting Motion to Reschedule Hearing (hearing set for March 7 and 8, 2019; 9:00 a.m.; Tallahassee, FL).
PDF:
Date: 02/25/2019
Proceedings: Petitioner's Motion to Reschedule Formal Administrative Hearing to Begin on March 7, 2019, filed.
PDF:
Date: 02/19/2019
Proceedings: Amended Notice of Hearing (hearing set for March 6 through 8, 2019; 9:00 a.m.; Tallahassee, FL; amended as to Authority).
PDF:
Date: 02/18/2019
Proceedings: Notice of Hearing (hearing set for March 6 through 8, 2019; 9:00 a.m.; Tallahassee, FL).
PDF:
Date: 02/18/2019
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 02/15/2019
Proceedings: Petitioner's Motion to Expedite Formal Administrative Hearing, and Request for Case-Management Hearing filed.
PDF:
Date: 02/14/2019
Proceedings: Formal Written Protest and Petition for Administrative Hearing, dated January 16, 2019 filed.
PDF:
Date: 02/14/2019
Proceedings: Second Notice of Intent to Protest, dated January 7, 2019 filed.
PDF:
Date: 02/14/2019
Proceedings: ITN 2019-44 Amended Agency Decision; dated January 3, 2019 filed.
PDF:
Date: 02/14/2019
Proceedings: Formal Written Protest, dated December 21, 2018 filed.
PDF:
Date: 02/14/2019
Proceedings: Notice of Intent to Protest, dated December 13, 2018 filed.
PDF:
Date: 02/14/2019
Proceedings: ITN 2019-44 Intent to Award, dated December 10, 2018 filed.
PDF:
Date: 02/14/2019
Proceedings: ITN 2019-44 Addendum #2, dated August 30, 2018 filed.
PDF:
Date: 02/14/2019
Proceedings: ITN 2019-44 Addendum #1, dated August 22, 2018 filed.
PDF:
Date: 02/14/2019
Proceedings: ITN 2019-44, dated August 3, 2018 filed.
PDF:
Date: 02/14/2019
Proceedings: Agency referral filed.

Case Information

Judge:
ROBERT E. MEALE
Date Filed:
02/14/2019
Date Assignment:
02/15/2019
Last Docket Entry:
04/17/2019
Location:
Tallahassee, Florida
District:
Northern
Agency:
Department of Education
Suffix:
BID
 

Counsels

Related Florida Statute(s) (6):