19-005130 Network Engineering Services, Inc., D/B/A Bolton Perez And Associates vs. Department Of Transportation
 Status: Closed
Recommended Order on Friday, April 17, 2020.


View Dockets  
Summary: DOT's reliance on the OSHA report and NTSB's investigation into the FIU bridge collapse was insufficient "good cause" to deny BPA's request for qualification for 2019. DOT failed to demonstrate BPA failed to exercise independent judgment as a CEI.

1S TATE OF F LORIDA

6D IVISION OF A DMINISTRATIVE H EARINGS

13N ETWORK E NGINEERING S ERVICES , I NC .,

22D/B/A B OLTON P EREZ A ND A SSOCIATES ,

31Petitioner ,

32Case No. 19 - 5130

37vs.

38D EPARTMENT OF T RANSPORTATION ,

43Respondent .

45/

46R ECOMMENDED O RDER

50Pursuant to notice, a formal administrative hearing was conducted before

60Administrative Law Judge ( " ALJ " ) Mary Li Creasy in Tallahassee, Florida,

72on February 13, 14, and 17, 2020.

79A PPEARANCES

81For Petit ioner: George Richard Truitt, Esquire

88Anthony Lopez, Esquire

91Cole, Scott & Kissane, PA

969150 South Dadeland Boulevard, Suite 1400

102Miami, Florida 33156

105For Respondent: George Spears Reynolds, IV, Esquire

112John Ashley Peacock, Esquire

116Florida Department of Transportation

120605 Suwannee Street, Mail Stop 58

126Tallahassee, Florida 32399 - 0450

131S TATEMENT OF T HE I SSUE

138The issue in this administrative proceeding is whether the Florida

148Department of TransportationÔs ( " DO T " or " the Department " ) denial of

160PetitionerÔs, Network Engineering Services, Inc. d/b/a Bolton Perez &

169Associates ( " BPA " ) , 2019 application for qualification pursuant to section

180337.105, Florida Statutes, and Florida Administrative Code Chapter 14 - 75,

191was for good cause due to PetitionerÔs participation in the construction of the

204Florida International University ( " FIU " ) City Prosperity Project ( " FIU Bridge

216p roject " ).

219P RELIMINARY S TATEMENT

223On July 11, 2019, DOT issued a Notice of Intent to Deny Request for

237Qualification ( " NOID " ) to BPA. The NOID removed BPA from consideration

249for award of professional service contracts with DOT. DOT issued the NOID

261based upon BPAÔs failure to appropriately exercise independent professional

270judgment required of a constructio n engineering and inspection firm ( " CEI " ) ,

283as evidenced by the reports issued by the Occupational Safety and Health

295Administration ( " OSHA " ) and the investigation of the National

305Transportation Safety Board ( " NTSB " ) concerning the collapse of the FIU

317Bridge p roject on March 15, 2018.

324On August 1, 2019, BPA filed a Petition for Formal Administrative

335Hearing. On September 24, 2019, the petition and accompanying documents

345were filed with DOAH.

349A formal hearing was held as scheduled on February 13, 14, and 17, 2020,

363in Tallahassee, Florida. At the final hearing, BPA presented the testimony of

375Joaquin " Jake " Perez, BPAÔs President and Director of Engineering ; Jose

385Morales, BPAÔs CEI Services Manager ; and Gustavo Quesada, BPAÔs expert

395witness. BPAÔs Exhibi ts 5, 7, 9, 11 through 18 , 29 through 32, 39, and 40

411were admitted into evidence.

415DOT presented the testimony of William Watts, P.E., Chief Engineer for

426the Departmen t ; Robert V. Robertson, Jr., P.E., State Structures Design

437Engineer for the Departmen t ; and Carlos Chapman, BPAÔs S enior I nspector.

450DOTÔs Exhibits 1, 6, 9 through 16(c), 18 through 29, 33, and 34 were admitted

465into evidence. DOT's deposition designations of BPAÔs corporate

473representatives, Mr. Perez and Mr. Morales were also admitted and acce pted

485into evidence.

487DOT marked the OSHA report as Exhibit 2 for identification. BPA

498objected to the admissibility of the OSHA and NTSB reports as unreliable

510hearsay expert testimony and objected to the admissibility of the statements

521within the report a s hearsay within hearsay. Prior to the final hearing, by

535O rder dated January 24, 2020, the undersigned ALJ , upon motion filed by

548Petitioner, took official recognition of both the OSHA and the NTSB reports.

560However, despite multiple references to it, the OS HA report was neither

572moved nor admitted into evidence.

577The six - volume final hearing Transcript was filed on February 26, 2020.

590The parties requested and were granted several extensions of time within

601which to file proposed recommended orders. Both partie s submitted proposed

612recommended orders which were considered in the drafting of this

622Recommended Order. All references to statutes refer to the 2019 version ,

633unless otherwise specified.

636F INDINGS OF F ACT

641T HE P ARTIES

6451. DOT is the state agency responsible for coordinating the planning,

656construction, and maintenance of a safe, viable, and balanced state

666transportation system. DOT relies on qualified contractors and professional

675consultants to provide services for FloridaÔs transportation needs.

6832. Section 28 7.055(3), Florida Statues, requires that any firm or individual

695desiring to provide professional serv ic es to a governmental agency must first

708be certified by the agency as qualified , pursuant to law and the regulations of

722the agency. The agency must find t hat the firm or individual to be employed

737is fully qualified to render the required service. Among the factors to be

750considered in making this finding are the capabilities, adequacy of personnel,

761past record, and experience of the firm or individual. Each agency is also

774required to evaluate professional services, including capabilities, adequacy of

783personnel, past record, and experience of the firm or individual.

7933. Section 337.105 and Florida Administrative Code Chapter 14 - 75 also

805govern s the qualification s of professional consultants and other contractual

816services providers to DOT. Section 337.105 authorizes DOT to deny or

827suspend an application for qualification based upon a determination of " good

838cause , " which includes, but is not limited to, nine illust rative examples

850specified in s ection 337.105(1)(a) Ï (i) . DOT may, for good cause, deny or

865suspend for a specified period of time a person or firm from consideration for

879award of a professional service contract for a particular type of work.

8914. BPA is a mult idiscipline engineering firm specializing primarily in

902transportation related engineering services, including bridge design, roadway

910design, civil works, construction engineering inspection ( " CEI " ), and program

921and construction management. At the time of t he hearing, BPA had

933approximately 38 employees. BPA was formed by Joaquin " Jake " Perez, P.E. ,

944and John Bolton, P.E. , in 1997 to provide transportation - related engineering

956services.

9575. BPAÔs CEI qualifications are independent from, and do not necessarily

968m irror, BPAÔs design qualifications. In some instances, BPA was qualified to

980serve as a CEI for categories of structures that the firm was not qualified to

995design. This is because BPA was internally divided into two core groups:

1007design and CEI. Since incept ion, BPAÔs design group was and continues to be

1021headed by Mr. Perez, and the CEI group headed by Mr. Bolton.

10336. The operations of BPAÔs CEI and design groups were completely

1044segregated within the firm. CEI personnel did not work on design projects,

1056and des ign personnel did not work on CEI projects. As President, Mr. Perez

1070was involved in pursuing contracts for CEI services, but CEI services were

1082provided only by CEI personnel.

10877. In or about 1999 or 2000, BPA first became qualified to respond to

1101DOTÔs requ est for qualifications to provide professional services to DOT.

1112Mr. Bolton qualified the firm to provide CEI services, and Mr. Perez qualified

1125it to provide design services. BPA remained qualified with the Department on

1137an annual basis for both CEI and des ign work for nearly 20 years until

1152July 2019. At that time, DOT issued a NOID removing BPA from

1164consideration for award of professional service contracts with DOT for 2019 -

11762020. DOT issued the NOID based solely upon a report issued by OSHA and

1190the investig ation of NTSB regarding the collapse of the FIU Bridge p roject on

1205March 15, 2018.

1208T HE F IU P EDESTRIAN B RIDGE P ROJECT

12188. In 2014, DOT entered into a Local Agency Program ( " LAP " ) Agreement

1232with FIU for its pedestrian bridge project, a Category II, complex bri dge, that

1246would be constructed along Southwest 109 th Avenue and Southwest 8 th

1258Street in the City of Sweetwater, Florida (the " project " ). As the supervising

1271agency of the LAP program, DOT was responsible for supervising and

1282authorizing work by the local age ncy.

12899. The design of a Category II structure required an independent peer

1301review by a firm with no other involvement in the project, which was

1314prequalified with DOT. In September 2016, FIGG Bridge Engineers, Inc.

1324( " FIGG " ), the Engineer of Record ( " EOR " ) f or the project, hired Louis Berger

1341to review FIGGÔs plans for bridge foundation, substructure (end bents and

1352center tower), and superstructure. Those plans included construction

1360sequencing (including construction sequence drawings), the covered main

1368span p re - casting, transport of main span, and placement of the main span

1383between end bent 1 (south pier) and the pylon pier. The plans also included

1397the post - tensioning stressing and destressing sequences.

140510. As the Local Agency, FIU was in responsible charge o f the day - to - day

1423activities, including project safety issues. Alfredo Reyna, P.E. , was the

1433DepartmentÔs LAP Coordinator for the project. Mr. Reyna is a licensed

1444professional engineer, although he is not a structural engineer.

14531 1. In January 2016, FIU ente red into a design - build contract 1 with

1469Munilla Construction Management, LLC ( " MCM " ) , to design the bridge and

1481to perform all work and furnish all materials, equipment, supplies, and labor

1493necessary to construct the project. The bridge was designed by FIGG, a

1505member of the MCM design - build team and the EOR. FIGG is a reputable

1520designer who has been recognized internationally for its work. FIGG has

1531experience in designing complex bridges, such as the Sunshine Skyway

1541Bridge near Tampa, Florida.

154512. On Septembe r 23, 2016, FIU entered into a Standard Professional

1557Services Agreement with BPA for CEI services (the " CEI Contract " ). At the

15701 The interaction of the local agency, contractor, designer, EOR , DOT, and the CEI is

1585different between a " conventional " and a " design build " bridge project. In a conventional

1598project, the designer is hired by DOT or owner to cr eate a new bridge. The design goes

1616through a review process at DOT and a final set of plans goes to bid for a contractor. By the

1636time the contractor is selected, the EOR has completed the plans. The EOR is essentially " on

1652call " for the construction phase o f the project because the design work is complete. The CEI

1669begins its work when the contractor begins construction. If there is a question in the field,

1685the CEI makes a request for information from the EOR. DOT supplies design and

1699construction managers thr oughout the process.

1705In contrast, for a " design build " project, the owner has a conceptual plan for the project.

1721The designer and contractor bid for the job based on the preliminary conceptual plan. The

1736Designer/EOR and contractor work hand in hand from the beginning of the project and are in

1752constant communication. The CEI begins work when the contractor starts work on the

1765project. The CEI facilitates the resolution of any issues between the EOR/designer and the

1779contractor who continue to plan thro ughout the duration of the project. Like a conventional

1794build project, DOT has construction managers and design project managers involved from

1806the beginning of the project.

1811If concrete cracking occurs , it is the CEI's obligation to document the crack ing and speak

1827to people in the process who can assess and address the cracking. For a conventional build

1843bridge, if cracking is observed, the CEI documents it, copies DOT , and sends it to the EOR

1860for assessment. The EOR provides an assessment by conducting a site visit. The EOR then

1875prepares an Engineering Assessment Report (EAR) for the project team. In a design build

1889bridge job, if cracks are observed, they are documented by the CEI who notifies the EOR. The

1906EOR, who is already on the job site, assesses t he cracks and works with the contractor to

1924devise a solution.

1927time, John Bolton was the CEI qualifier for BPA. As CEI, BPA was to act as

1943the liaison between the project owner (FIU) and the co ntractor (MCM). The

1956CEI handles quality control, materials, schedules, payments, documents the

1965entire process, and monitors the project.

197113. Jose Morales, P.E. , worked under John Bolton as the Senior Project

1983Engineer for the project. Mr. Morales first obta ined his professional

1994engineerÔs license in 2006. He had approximately 12 years of CEI experience

2006at the time of the collapse. Although he was the Senior Project Engineer for

2020the project, Mr. Morales had little - to - no design experience.

203214. Mr. Morales was first involved in the early stages of pursuing the CEI

2046Contract for the project. After the project was awarded, BPA was not involved

2059in the design phase, but was later brought back into the fold beginning in

2073October 2016, when BPA received the Notice to Pr occed and fully staffed its

2087CEI scope of services when construction was scheduled to begin in or about

2100March of 2017.

210315. The " Scope of Services " section (Exhibit B) to the CEI Contract

2115required BPA to be prequalified with the Department in the following w ork

2128categories: Work Type 10.1 -- Roadway CEI ; Work Type 10.4 -- Minor Bridge

2141and Miscellaneous Structures CEI ; and Work Type 10.5.1 -- Major Bridge CEI -

2154- Concrete. For the FIU bridge project, Categories 10.1 and 10.4 were

2166considered to be the " major " type of wor k while 10.5.1 was considered to be

2181the " minor " type of work. As expressly permitted by the Standard

2192Professional Services Agreement, BPA satisfied the 10.5.1 prequalification

2200requirement through its sub - consultant, The Corradino Group, Inc.

2210( " Corradino " ).

221316. BPAÔs scope of services for the project did not include any design

2226responsibilities. BPA performed constructability review of the plans as part of

2237its CEI scope of work, but it did not review the plans or drawings on a

2253technical level.

225517. The FIU bri dge was a Complex Category II structure as defined by the

2270DepartmentÔs Design Manual. The structure had a unique, complex design

2280that was meant to be a signature, architectural feature for the area.

229218. The relevant construction sequence for the main span (Span 1) of the

2305FIU bridge consisted of:

2309a. c asting the main span superstructure in the casting yard;

2320b. i nstalling post - tension bars in the diagonal and vertical members of

2334the structure;

2336c. s tressing of the main - span post - tensioning while the main span i s in

2354the casting yard;

2357d. r emoving the temporary formwork and supports;

2365e. t ransporting the main span from the casting yard using a self -

2379propelled modular transporter and placing the structure in a " simply

2389supported " condition on the south pier and pylon p ier; and

2400f. d e - tensioning truss members 2 and 11 .

241119. Generally, cracks in concrete are common and are not, in and of

2424themselves, a cause for concern. On a design - build job, when cracks manifest

2438themselves in a concrete element, the CEI must document the c racking and

2451report it to the design - build team, which includes the EOR. Depending on the

2466nature of the cracks, the CEI may request an EAR from the EOR. This

2480process is set out in s ection 400, subsection 400 - 21, of DOTÔs Standard

2495Specifications for Road and Bridge Construction (the " Standard

2503Specifications " ).

250520. DOT's Construction Project Administration Manual ( " CPAM " ) includes

2515the procedures to be followed by a CEI in addressing cracks in concrete. The

2529CPAM requires that the CEI identify and document its o bservations and

2541convey the information to the EOR for a final disposition as to the potential

2555danger of the crack or the need for further evaluation.

2565The FIU Bridge Cracking and Inspections by BPA

257321. On or about February 6, 2018, while Span 1 of the brid ge was still in

2590the casting yard, BPA became aware of certain cracks that had developed in

2603the structure. Mr. Morales personally inspected the structure after the

2613tendons on truss members 2 and 11 were stressed, and he noted that cracks

2627had developed in ot her locations on the bridge. The cracks observed were very

2641small, approximately 0.004 of an inch wide.

264822. On February 13, 2018, BPA submitted Crack Report # 1 to MCM, FIU,

2662and Corradino, documenting the cracks that had developed in the concrete

2673truss membe rs after completing the post - tensioning operations in the casting

2686yard. Despite the small size of the cracks, BPA requested that the EOR

2699provide an assessment of the cracks.

270523. FIGG, the EOR, responded to BPAÔs request by stating that the

2717current conditio n observed was temporary in nature and that the cracks were

2730not an issue.

273324. BPA exercised independent professional judgment when it exceeded

2742the requirements of s ection 400 of the Standard Specifications and the CPAM

2755by documenting and reporting these in itial cracks.

276325. In late February 2018, before the placement of the main bridge span

2776on the permanent pylon and south pier supports, cracks were observed in

2788certain truss members. BPA prepared and submitted Crack Report # 2 to FIU

2801and MCM on February 28, 2 018, documenting the size and location of these

2815cracks and requested that FIGG evaluate the cracks and provide a

2826disposition.

282726. In its report, BPA called attention to certain cracks that were

2839significant in size. As CEI, BPA was not qualified to determin e whether these

2853larger cracks posed an imminent danger of collapse. Further, BPAÔs design

2864team was not involved in the design of the bridge and was not qualified to

2879evaluate these cracks from a design engineering perspective due to the

2890category and complex ity of the bridge.

289727. At this point, the cracks were not " structural " as defined by

2909Section 400 of the Standard Specifications. Cracks more than one - half inch in

2923depth are deemed " structural " and trigger the obligation of the CEI to notify

2936the EOR. Nevert heless, BPA, again, exercised its independent professional

2946judgment above and beyond the requirements of the Standard Specifications

2956and CPAM by requesting that the report be forwarded to the EOR and

2969requesting that the EOR provide a response and dispositi on of the cracks.

298228. On March 7, 2018, FIGG replied to Crack Report # 2, stating, in part,

2997that the cracks appeared small, that they were not concerned about these

3009types of cracks in the particular region shown in the report, and that MCM

3023would need to sea l the cracks in accordance with the DepartmentÔs

3035specifications. As the EOR, FIGG did not have any structural concerns

3046regarding the cracks in Crack Report #2.

305329. On March 7, 2018, FIGG representatives were on site and observed

3065the cracks referenced in Cr ack Report #2. After observing the cracks, FIGG

3078did not delay the bridge movement that was scheduled to take place three

3091days late r on March 10th.

309730. As of March 8, 2018, BPA had no concerns regarding the integrity of

3111the structure or public safety becaus e the EOR had looked at the cracks in -

3127person and assured the project team that the cracks were not a safety issue

3141or structurally significant. These assurances came two to three days prior to

3153the bridge being moved over Southwest 8 th S treet and placed on t he

3168permanent pylon and pier supports. The bridge movement was not delayed

3179due to the cracks observed by the EOR.

318731. On March 10, 2018, Span 1 was moved from the casting yard and

3201placed on the permanent pylon and south pier supports. After the placement

3213an d de - tensioning of diagonal members 2 and 11, cracks began to appear at

3229the construction joint of diagonal 11, the deck, and at the top of diaphragm II.

324432. At approximately 11 :00 a.m. on March 13, 2018, two days before the

3258collapse, BPA circulated a draft of Crack Report #3 to MCM, recommending

3270further monitoring and documenting of the cracks to determine whether they

3281were active or dormant, and requesting that BPA be informed of the outcome

3294of the EORÔs EAR and course of action. At 5:18 p . m . on March 13, 2018, the

3313EOR responded to MCM with additional recommendations and stated

" 3322[a]gain, we have evaluated this further and confirmed that this is not a

3335safety issue. "

333733. Because BPAÔs design team was not involved in the project, no BPA

3350design personnel were a ware of the documented cracking on the structure

3362until sometime after Crack Report #3 was generated. At that time,

3373Mr. Morales provided Mr. Perez with a copy of a draft of Crack Report #3.

3388Mr. Perez briefly reviewed the draft report and confirmed with Mr. Morales

3400that the CEI team had elevated the issue to the EOR.

341134. At all times in the documented communication relating to the cracks,

3423the EOR and members of the FIGG design team represented to BPA that the

3437cracks were not a safety concern, without reservat ion.

344635. Starting on March 13, 2018, FIGG directed MCM to implement an

3458initial, temporary measure to address observed cracking in the member 11/12

3469nodal region. At that time, BPA was not aware of this communication

3481between the EOR and the c ontractor. To re store the temporary support

3494conditions when the structure was in the casting yard, MCM placed shims

3506between diaphragm II and the pylon on March 13, 2018.

351636. FIGG also directed re - tensioning the post - tensioning rods in truss

3530member 11 to begin on March 15, 2018. The re - tensioning operation was

3544made as a " rushed request " to the post - tensioning subcontractor by MCM on

3558March 14, 2018. " FIGG recommends to stress these PT bars as soon as

3571possible but again, this is not a safety concern. "

3580M ARCH 15, 2018 , A ND T HE B RIDGE C OLLAPSE

359237. Rather than waiting for the EAR, BPA once again exercised its

3604independent , professional judgment and went above and beyond the

3613requirements of the Standard Specifications, CPAM, and Contract

3621Documents when it further escalated the issu e of the cracks by calling for a

3636meeting with the EOR. On the morning of March 15, 2018, a meeting

3649requested by BPA and coordinated by MCM, was held in Miami, Florida.

3661Representatives of FIGG, MCM, DOT, FIU, and BPA were present.

367138. At the March 15 th meet ing, BPA first became aware of the EORÔs

3686instruction to MCM to proceed with a second temporary measure. This

3697subsequent temporary measure was to reinstate the post - tensioning

3707compression force back in member 11 as per the previous construction phase.

3719As ex plained by the EOR, both temporary measures (shims and re -

3732tensioning) were intended to restore the temporary support conditions when

3742the structure was in the casting yard.

374939. Prior to the start of the meeting, the EOR, other FIGG engineers, and

3763DOTÔs LAP Coordinator inspected the bridge and the cracks in the nodal

3775region of members 11/12.

377940. Only FIGG had structural engineers at the meeting. No other

3790engineers present at the meeting had a background in structural

3800engineering, including those in attendance on behalf of BPA. The meeting

3811was called for purposes of discussing the concrete cracking on Span 1, and

3824specifically the concrete cracking in nodal connection between truss members

383411 and 12 and the bridge deck. At this meeting, BPA informed FIGG that th e

3850cracks in the bridge were lengthening and growing daily. Though not

3861formally invited, Mr. Reyna attended this meeting in his capacity as DOTÔs

3873consultant/Assistant LAP Coordinator.

387641. At the March 15 th meeting, the EOR presented FIGG's assessment of

3889the cracking after having reviewed the three BPA crack reports and having

3901personally inspected the cracks on at least the following two occasions:

3912( 1) prior to the bridge being moved from the casting yard over Southwest 8th

3927S treet; and ( 2) on the morning of t he March 15 th meeting. The EORÔs

3944presentation consisted of a lengthy and comprehensive PowerPoint slide

3953presentation on the conditions of the bridge, structural analysis by

3963calculation s and 3D modeling of the loads and forces the area of member

397711/12 nodal region cracks, and an evaluation of the safety of the span over

3991Southwest 8 th Street for workers and the public.

400042. Throughout the March 15 th meeting, BPA exercised its independent

4011professional judgment by actively participating in the EORÔs presentation ,

4020questioning and challenging the EOR. For example, BPA:

4028a. inquired as to whether temporary shoring was needed;

4037b. sought clarification regarding the mechanism being used to

4046capture the load from the node and whether it would have to be

4059integrated with th e pylon diaphragm;

4065c. requested clarification on the amount of transferred post -

4075tensioning assumed for the nodal shear stability analysis;

4083d. inquired as to whether there were any restrictions on load;

4094e. inquired as to whether there would be a crack mon itoring plan;

4107f. requested a copy of the EORÔs presentation;

4115g. inquired as to whether it had been peer reviewed and commented

4127that it wanted more eyes on the presentation calculations; and

4137h . BPA requested a copy of the stressing procedure that was bei ng

4151recommended by the EOR.

415543. Throughout the presentation, and during the question and answer

4165phase of the meeting, the EOR assured BPA and the other attendees that the

4179structure was safe. These assurances were based on statements made by the

4191EOR as well as its calculations and modeling, which were part of its slide

4205presentation at the meeting.

420944. In the presentation on the slide entitled " Safety, " FIGG stated that

" 4221È[it] had conducted sufficient supplemental/independent computations to

4228conclude that ther e is not any concern with safety of the span suspended over

4243the road. " At the end of the presentation, the EOR concluded the meeting

4256with " [b]ased on conservative calculations, it is concluded that the design

4267meets LRFD strength requirements for this tempo rary condition and

4277therefore there is no safety concern relative to the observed cracks and minor

4290spalls. "

429145. During the meeting, the EOR stated that some cracking similar to the

4304ones on the structure , were expected. The EOR further stated during the

4316meet ing that the top deck spalls could not be replicated, but that the spalled

4331areas were minor and they should be repaired during the next phase of work

4345when the pylon concrete was to be placed.

435346. No engineer at the meeting, including DOT's representative,

4362Mr. Reyna, requested or recommended a complete road closure to protect the

4374public safety or that the bridge be shut down. BPA had no reason to request a

4390full road closure of Southwest 8 th S treet. There was no preplanned complete

4404road closure, there was no maintenance of traffic ( " MOT " ) deficiency, and,

4417based on the EORÔs presentation, BPA was reasonably satisfied that no

4428safety issues required a road closure.

443447. Towards the end of the meeting on March 15 th , MCM informed BPA

4448that a specialty contractor, Str uctural Technologies ( " VSL " ), was already

4460onsite to conduct the re - tensioning operation. Without BPAÔs knowledge, VSL

4472had already mobilized on site to perform the remedial re - tensioning. BPA was

4486not involved in pre - coordination for the re - tensioning operat ion. Therefore,

4500BPAÔs sub - consultant, Corradino, was not onsite to participate in monitoring

4512of the re - tensioning procedure.

451848. CorradinoÔs role, as BPA's sub - contractor, was that of a 10.5.1 CEI

4532(Major Bridge CEI -- Concrete). Corradino was responsible for monitoring and

4543documenting the post - tensioning operations. The post - tensioning operation

4554after placement of the span had already occurred and therefore, Corradino

4565was not on - site on March 15 , 2018 .

457549. Based on the safety assurances and conservative calc ulations

4585presented by the FIGG EOR that the structure was safe, BPA , and the other

4599professional engineers present at the meeting, including those representing

4608FIU and DOT, followed the recommendations of the FIGG EOR to bring the

4621main span condition back t o its pre - existing state when the span was in the

4638casting yard.

464050. BPA did not have the expertise or the contractual duty to perform its

4654own analysis of th e cracking o n this complex bridge and override, or even call

4670into question, FIGGÔs unequivocal asses sment that the bridge was safe.

468151. During the restressing operation of member 11, the roadway below the

4693bridge had two westbound lanes closed as per the blanket, two - lane, closure

4707permit issued by DOT. This blanket, two - lane, closure permit was obtained

4720b y MCM to provide workspace underneath the bridge to conduct the remedial

4733action. MCM obtained the blanket, two - lane , closure permit from the

4745Department the morning of March 15, 2018, before conducting the remedial

4756action.

475752. A CEIÔs authority to request a partial or complete road closure is

4770defined by the contract plans and roadway closure permits, which is

4781implemented using the procedures outlined by the CPAM and the CEI Scope

4793of Services of the CEI Contract. A CEI is authorized to request the contractor

4807to either partially or fully close a road if there is an MOT deficiency, as

4822contemplated by CPAM Section 9.1.8 -- " Recommended Action to Shut Down a

4834Project Due to MOT Deficiencies. " Lastly, a CEI has authority to request a

4847partial or full road closure if it is aware of a safety issue .

486153. None of these conditions existed on the project in the days leading up

4875to the collapse in light of the EORÔs comprehensive presentation regarding

4886the cracking conditions of the bridge, strength in the area of member 11/12

4899n odal region, safety of the span over Southwest 8th Street, and repeated,

4912unequivocal reassurances that the structure did not pose a safety concern.

492354. Ultimately, BPAÔs authority to request a partial or complete road

4934closure on the project was a collectiv e effort with the Department and FIU.

4948BPA did not have the authority or ability to act on its own to close the road.

496555. The FIU Pedestrian Bridge collapsed during the re - tensioning of the

4978truss member 11 post - tensioning rods on the afternoon of March 15, 2018.

4992Six people died as a result of the FIU bridge collapse, including one bridge

5006worker and five vehicle occupants. Ten people were critically injured as a

5018result of the FIU bridge collapse, including two BPA employees, Mr. Morales

5030and Carlos Chapman.

503356 . Mr. Chapman was on the canopy of the bridge during the re -

5048tensioning operation, observing the work being performed by VSL and

5058communicating the progress to Mr. Morales who was on the deck of the

5071bridge. Because of the representations made by the EOR, nei ther

5082Mr. Chapman nor Mr. M orales was concerned for his own safety or well - being

5098when they went on the bridge on the day it collapsed.

510957. BPAÔs role, responsibilities, and scope of work on the FIU Bridge

5121project as the CEI was that of a contract administra tor, not as a structural

5136engineer with the capability to analyze the structural behavior of the bridge

5148sufficient to determine if the cracks posed any danger of collapse. BPA had no

5162basis, ability, or contractual obligation, to perform its own analysis of this

5174complex structure sufficient to override the FIGG EORÔs unequivocal safety

5184assessment and recommendations. BPA performed its CEI duties and utilized

5194its independent professional judgement when it documented and monitored

5203the cracks and requested an im mediate structural evaluation by the FIGG

5215EOR.

521658. Ultimately, the bridge collapse was caused by a fundamental design

5227error.

5228T HE OSHA A ND NTSB I NVESTIGATIONS

523659. Shortly after the collapse, both OSHA and NTSB began investigating

5247the causes of the collapse. OHSA completed its investigation and released a

5259written report of its findings in June 2019. 2 The June 2019 OSHA report was

52742 DOT failed to enter into evidence the OSHA report on which it relies. However, prior to the

5292final hearing, DOT filed a Motion for Judicial Notice of Reports Issued by Federal Agencies

5307Concerni ng the FIU Bridge Collapse ( " Motion " ). The Motion was opposed by BPA on the

5324basis that the first OSHA report was not final because a second report was issued, and is

5341hearsay. By Order dated January 24, 2020, the undersigned officially recognized both the

5354issued without prior review or comments from all party members who

5365willingly cooperated with and were involved in the investigation , including

5375NTSB and BPA. OSHA released an amended report on the collapse of the

5388FIU Bridge p roject in July 2019; however, none of the amendments in the

5402report pertained to the ac tions of BPA on the FIU Bridge p roject. NTSB

5417completed its investigation and issued its report in October 2019.

542760. Significantly, no evidence was presented at the final hearing regarding

5438from whom either agency conducted the investigations or drafted the reports,

5449the qualifications or expertise of the investigators, the methodolog y used in

5461the investigations, or the ability of any of the participants in the

5473investigation to rebut the findings or conclusions.

548061. BPA willingly participated in both the OSHA and NTSB

5490investigations, working with investigators and providing them with

5498i nformation, photographs, and details on the FIU Bridge p roject. Both OSHA

5511and NTSB also conducted interviews of BPA personne l involved with the FIU

5524Bridge p roject as part of their investigations.

553262. In its report, OSHA found that BPA failed to classify t he concrete

5546cracks, which were structural in nature, in accordance with DOT

5556requirements. OSHA determined that BPA, as CEI, was expected to exercise

5567its own independent professional judgment in accordance with their contract

5577with FIU and DOT requirements. With intimate knowledge of extensive

5587i nitial OSHA report and the NTSB report. Accordingly, references to the report in this

5602Recommended Order are based upon the official recognition.

5610As noted in the O rder on the Motion, official recognition of the OSHA and NTSB reports,

5627however, does no t make the statements contained therein automatically admissible. " The

5639distinction between noticing the contents of a record and noticing the truth of the contents

5654resembles the distinction in the hearsay doctrine between offering an out - of - court statement

5670simply to show it was said, and offering it for the truth of the matter asserted. " C. Ehrhardt,

5688Florida Evidence § 201.1 (2011 Edition)(quoting Wright & Graham, Federal Practice and

5700Procedure: Evidence § 6337). Although the existence of the report and its findings were

5714officially recognized, the greater weight of the evidence supports that the contents were not

5728accurate as to the exercise of independent judgment of BPA.

5738cracking on the bridge, BPA failed to recognize the bridge was in danger of

5752collapsing, and did not recommend to FIU, MCM, or others to close the street

5766and shore the bridge, regardless of the opinion held by the EOR. As a result,

5781OSHA imposed a monetary fine on BPA for its conduct and failure to take

5795appropriate action in the days leading up to the collapse of the main bridge

5809span.

581063. In its October 2019 report (issued after the NOID to BPA in this case) ,

5825NTSB found t hat beginning with the cracking identified on February 24,

58372018, the distress in the main bridge span was active, continued to grow, and

5851was well documented by all parties involved in the design, construction, and

5863oversight of the bridge. Neither FIU, MCM, FIGG, nor BPA took

5874responsibility for declaring that the cracks were beyond any level of

5885acceptability and did not meet DOT standards. Further, NTSB concluded

5895that under the terms and conditions of the CEI Contract, BPA had the

5908authority to direct or auth orize partial or complete road closures as

5920necessary, acting in concert with DOT and FIU; however, none acted to close

5933the road under the bridge, contributing to the severity of the impact of the

5947bridge collapse.

5949BPA P OST - C OLLAPSE A CTIVITIES A ND 2018 A PPLI CATION F OR Q UALIFICATION

596764. On May 3, 2018, BPA submitted its Request for Qualification for the

5980July 1, 2018, through June 30, 2019, fiscal year ( " 2018 Application " ). BPAÔs

59942018 Application was for the same Work Groups that would eventually be

6006included in the 2019 Request for Qualification.

601365. Each work category is tied to a distinct job function. There is no

6027relationship or similarity between CEI services (Work Group 10) and the

6038other work groups.

604166. On June 27, 2018, DOT accepted BPAÔs Request for Qual ification in all

6055work categories. In processing the application, the Department did not ask

6066BPA any questions regarding its involvement in the project, offer any

6077criticisms of BPA in response to the application, request to interview any

6089BPA employees, or r aise any concerns at all regarding BPAÔs participation in

6102the project.

610467. From the date of the collapse on March 15, 2018, to December 2018,

6118DOT awarded two contracts to BPA directly for CEI and design services,

6130respectively. During the same period, DOT a llowed BPA to participate as a

6143qualified sub - consultant on one CEI contract, three design contracts, and one

6156traffic task work order contract. During the 2018 - 2019 fiscal year, before

6169DOT attempted to suspend BPAÔs qualifications, BPA was able to win sever al

6182jobs in both the prime and sub - consultant role, including projects in which

6196BPA would be providing CEI services.

620268. In October 2018, approximately seven months after the collapse, BPA

6213applied to change its CEI qualifier from John Bolton to Jose Morale s because

6227John Bolton wanted to retire. DOT approved the request and did not object or

6241raise any concerns with respect to Jose Morales serving as BPAÔs qualifier for

6254CEI services.

625669. On December 19, 2018, nine months after the collapse, DOT expressed

6268conc ern for the first time about BPAÔs role in the bridge project, staffing of

6283current DOT projects, quality assurance/quality control ( " QA/QC " ) plans, and

6294professional liability insurance. DOT sent BPA a " Qualifications Letter of

6304Concern, " stating that it had " serious concerns regarding [BPA]Ôs

6313involvement as the Construction Engineering Inspection consultant on the

6322Florida International University (FIU) pedestrian bridge project[.] " DOT

6330requested in its letter, among other things, " a detailed explanation of t he

6343firmÔs actions on the FIU pedestrian bridge project andÈ any controls or

6355changes in personnel, policies or practices that [BPA] has implemented

6365subsequent to the collapse. "

636970. On December 21, 2018, BPA responded to the Letter of Concern

6381addressing each concern raised by the Department, in detail, including

6391providing a copy of its Certificate of Liability Insurance demonstrating that

6402there was no lapse in professional liability insurance coverage.

641171. On February 12, 2019, DOT responded to BPAÔs correspo ndence dated

6423December 21, 2018, requesting additional detail from BPA relative to its

6434revised QA/QC plan and punctuated the correspondence by stating that DOT

6445would refuse to process any further qualification requests from BPA,

6455including ministerial prequa lification name changes, until the matter was

6465addressed to the DepartmentÔs satisfaction.

647072. Around this time, BPA submitted a request to change its name with

6483DOT to reflect its business name with the Division of Corporations. BPA

6495requested that DOT updat e this information on its website, but DOT refused

6508to process the request due to its concerns with BPAÔs qualifications.

651973. On February 20, 2019, BPA provided further detail regarding the

6530specific policies and procedures that have been implemented to its CEI

6541services. Specifically, BPA provided extensive detail regarding its revised

6550QA/QC plan, which included a section dedicated to Category II type bridge

6562structures and included a copy of the revised QA/QC program for DOT

6574review. DOT never responded or req uested any additional information in this

6586regard.

658774. On March 15, 2019, one year to the day after the collapse, DOT issued

6602a Notice of Intent to Suspend BPAÔs existing certificate of qualifications. DOT

6614attempted to suspend BPAÔs qualifications in all Wor k Groups and declare

6626BPA non - responsible for a period of one year for good cause. DOT further

6641claimed that BPA " failed to adequately address the DepartmentÔs concerns

6651regarding the firmÔs performance of the contract, and the [BPA] staff directly

6663involved w ith the FIU project who continue to work on other Department

6676structural contracts. " No further explanation was provided as to how BPA

6687failed to address these concerns.

669275. BPA timely responded to the Notice of Intent to Suspend by way of a

6707Notice of Contes t, requesting an administrative hearing on the issues raised

6719therein. Despite the Notice of Contest, DOT suspended BPAÔs qualification,

6729and sent written notice to its various offices stating, among other things, that

6742BPA had been removed from DOTÔs prequal ification list. Ultimately, DOT

6753reinstated BPAÔs qualifications, but never formally withdrew the Notice of

6763Intent to Suspend.

676676. However, in reinstating BPAÔs qualifications, DOT neglected to

6775reinstate BPAÔs Small Business Enterprise ( " SBE " ) designation, which

6785negatively affected BPAÔs ability to obtain points for SBE participation. The

6796points add value in scoring competing responses to Requests for Proposals for

6808DOT contracts. BPA repeatedly requested that this be corrected. BPAÔs

6818requests went largely ig nored for nearly two months.

682777. On April 2, 2019, after BPA had an in - person meeting with

6841Courtney Drummond , DOT's Assistant Secretary of Engineering and

6849Operations, BPA submitted a qualifications modifications package to replace

6858Jose Morales, P.E. , with John Bolton, P.E., as the qualifier for the CEI Work

6872Group to address Mr. Drummond's and DOTÔs concerns about BPA staff

6883involved on the FIU project working on other DOT contracts.

689378. On April 5, 2019, in response to the Notice of Intent to Suspend, BPA

6908pr ovided specific facts in support of BPAÔs proper performance of the CEI

6921Contract. As an accommodation to DOT, BPA further proposed a solution to

6933DOT's concern about the staff involved in the FIU project. BPA stated that it

6947was " willing to immediately remov e the BPA staf f directly involved in the

6961FIU B ridge project from working on any Department contracts or qualifying

6973the company for CEI services " and resubmitted its qualifications application

6983with those changes.

69862019 B PA R EQUEST FOR Q UALIFICATION R EJECTION

699679. On May 7, 2019, BPA submitted its 2019 Request for Qualification to

7009the Department early due to the lack of response from DOT on BPA's April 5,

70242019 , correspondence. BPA sought qualifications for design work and CEI

7034services in the same work categorie s it was qualified in for the prior fiscal

7049year.

705080. On June 10, 2019, BPAÔs counsel met with DOT representatives in

7062Tallahassee to discuss several outstanding issues relative to BPAÔs current

7072qualification, the upcoming renewal, and DOTÔs failure to reins tate BPAÔs

7083SBE designation. DOT responded by promising to correct the " mistake " that

7094same day. Inexplicably, it took another two weeks and several reminders

7105from BPA for DOT to finally correct the SBE designation.

711581. BPAÔs 2018 - 2019 qualifications expired on June 30, 2019. The next

7128day, on July 1, 2019, DOT untimely responded to BPAÔs Request for

7140Qualification with a letter titled " Incomplete Renewal Applications for Pre -

7151Qualification. " DOT's letter raised the same concerns regarding BPAÔs

7160involvement in t he bridge project and, again, requested " a detailed

7171explanation of BPAÔs actions on the FIU pedestrian bridge project andÈany

7182controls or changes in personnel, policies or practices that BPA has

7193implemented subsequent to the collapse. " This is the same req uest that had

7206been previously made by DOT in its December 19, 2018, Qualifications Letter

7218of Concern, February 12, 2019, Qualifications Letter of Concern, March 15,

72292019 , Notice of Intent to Suspend, and April 26, 2019 , denial of BPAÔs

7242Submittal for Modifi cation.

724682. BPA had already provided the information requested several months

7256prior to DOT's July 1, 2019, correspondence.

726383. On July 11, 2019, DOT issued its Notice of Intent to Deny Request for

7278Qualification directed to BPAÔs 2019 Request for Qualificat ion. In issuing its

7290denial of BPAÔs Request for Qualification, DOT relied solely on the findings

7302and conclusions of the June 2019 OSHA Report as they relate to the CEI

7316services provided by BPA on the project and referenced the pending NTSB

7328investigation.

73298 4. The DepartmentÔs Notice of Intent to Deny was executed by

7341William Watts, the DepartmentÔs Chief Engineer. Mr. Watts admitted at

7351final hearing that he does not have the training or experience necessary to

7364evaluate a CEIÔs performance on a CEI contract. M oreover, neither Mr. Watts

7377nor DOT retained or consulted with any individuals with CEI expertise prior

7389to issuing the Notice of Intent to Deny. When he issued the Notice of Intent to

7405Deny, Mr. Watts was completely unfamiliar with the following: the terms o f

7418BPAÔs CEI Contract; BPAÔs Request for Qualification; BPAÔs past

7427performance on CEI or any other Department contract; and BPAÔs

7437professional reputation.

743985. Mr. Watts did not evaluate BPA under the criteria required by Florida

7452Statute s and the Florida Adm inistrative Code prior to denying BPAÔs

7464Request for Qualification for good cause. Mr. Watts did not receive any

7476analysis from the DepartmentÔs prequalification staff regarding their

7484evaluation of BPAÔs application under the statutory criteria.

749286. Mr. Watt s admitted that he was aware that BPA documented the

7505cracking on the bridge, reported the cracking to the design - build firm, and

7519requested an EAR from the EOR -- actions which were all in accordance with

7533BPA's obligations as CEI pursuant to the CPAM and its contractual

7544obligations with FIU.

754787. Mr. WattsÔ only reason for issuing the Notice of Intent to Deny, as

7561Chief Engineer for DOT, was because BPA was under investigation by OSHA

7573and the NTSB, and OSHAÔs release of its June 2019 Report. However,

7585Mr. Watts d id not know the author of the June 2019 OSHA Report, whether

7600the author of the report was qualified to evaluate the performance of a CEI

7614under Florida Statutes and the Florida Administrative Code, or whether the

7625author of the OSHA report did anything to ev aluate BPAÔs performance

7637relative to any other CEI, at the same time, and/or in the same community.

765188. DOT did not investigate the structure or organization of BPA to

7663determine whether the issues raised in the OSHA report, regarding BPAÔs

7674performance of t he CEI Contract, would reflect negatively on other groups or

7687divisions within BPA that provided services exclusively under other non - CEI

7699work categories (design services).

770389. Prior to issuance of the NOID, M r . Watts did not undertake a review

7719of BPA Ô s pas t performance or professional reputation -- both of which were

7734beyond reproach.

773690. DOT evaluates its consultantsÔ performance on all projects

7745approximately every six to eight months. These evaluations produce a score

7756that ranges from one to five, five being the highest possible score. A perfect

7770score of five is uncommon and a score of four is outstanding. In the five years

7786prior to the final hearing, DOT evaluated BPAÔs performance on projects

7797involving both design and CEI services. Specifically, DOT scored BPAÔs

7807performance in Work Groups 3.1, 3.2 (Highway Design), 4.12 (Bridge Design),

78185.1 (Bridge Inspection), 7.2 (Traffic Operations Design), and 10.1 and 10.3

7829(CEI). During that period, BPA averaged a score of outstanding to nearly -

7842outstanding on all projec ts, including outstanding and nearly - outstanding

7853scores for inspection services on bridge rehabilitation projects, which involved

7863cracking concrete elements.

786691. In May of 2019, prior to denying BPAÔs request for qualifications for

7879the fiscal year July 1, 2019 , through June 20, 2020, Mr. Drummond

7891personally presented BPA with an award from the American Council of

7902Engineering Companies ( " ACEC " ) , for excellence in major urban

7912reconstruction. Specifically, the award was for CEI services on the State

7923Road 7 pro ject, and the ACEC recognized two - and - a - half - years of excellence

7942in CEI services from late - 2016/early - 2017 through 2019. DOT's District

7955Construction Engineer, District 6 Secretary, and Headquarters were

7963intimately involved in the selection and vetting proc ess that, ultimately,

7974resulted in BPA receiving the award.

798092. In September 2019, after denying its request and three months after

7992the release of the June 2019 OSHA Report, DOT voted that BPA receive

8005another award for excellence in CEI services. As a membe r of the selection

8019committee, DOT chose BPA to receive an award from the Florida

8030Transportation Builders Association ( " FTBA " ) , for excellence on the BakerÔs

8041Haulover Bridge rehabilitation project. By this award, FTBA and DOT

8051recognized BPAÔs excellence in CEI services, which spanned from one year

8062before the collapse to one year after the collapse.

8071The Experts 3

8074a. Gustavo Quesada, P.E.

807893. At the Final Hearing, BPA presented the expert testimony of Gustavo

8090Quesada, P.E., a CEI with over 30 years of experience. The ALJ finds that

8104Mr. Quesada is a qualified expert on the standard of care for a CEI and his

8120opinions in that regard are based on competent substantial evidence.

813094. As explained by Mr. Quesada, the role of a CEI with respect to cracks

8145in concrete is to identify the cracks and make sure they do not go unseen or

8161undetected and that an EOR is engaged for purposes of addressing the

8173cracking. Pursuant to the CPAM, when a CEI encounters cracks in concrete,

8185a CEI is required to document the obser vation and make a disposition on the

8200cracks based on Section 400 of the Standard Specifications. Moving forward,

8211the CEI is also required to monitor any changes in the cracks. A CEI is not

8227responsible for making a determination as to whether a crack is pot entially

8240dangerous. This is a determination for the EOR , who has an understanding of

8253the structure, its design, and how the structure is expected to behave. A CEI

8267is not charged with making judgment calls on the design of a structure or

8281whether its integri ty has been jeopardized.

828895. BPA documented, monitored, and reported the cracks on the project in

8300compliance with the industry standards for CEIs working on Complex

8310Category II Bridges, as well as the relevant sections of the CPAM and

8323Section 400 of the St andard Specifications. BPAÔs Senior Project Engineer,

8334Mr. Morales, exercised his independent professional judgment in elevating

83433 DOT intended to offer Mr. Watts at hearing as an expert to testify to the " good cause " DOT

8362had when issuing the NOID to BPA. BPA filed a Motion in Limine to exclude or limit the

8380testimony of both Mr. Watts and Mr. Robertson. The motion was argued at the outset of the

8397final hearing. The undersigned precluded Mr. Watts from testifying as an expert in the field

8412of CEI. Mr. Watts was allowed to testify as to DOT's qualification process and did so as a fact

8431witness, rather than an expert.

8436the issue of the cracks to the EOR even before he was required to do so under

8453the CPAM and Section 400 of the Standard Specifica tions.

846396. At the meeting called by BPA on the morning of March 15, 2018, BPA

8478exercised its independent professional judgment and complied with the

8487applicable standard of care when Mr. Morales asked the EOR a series of

8500questions in response to the EORÔs pr esentation and evaluation of the cracks

8513on the bridge.

851697. According to Mr. Quesada, professional engineers are expected to rely

8527on other engineers with superior or specialized knowledge when exercising

8537their independent professional judgment. BPAÔs role, responsibilities, and

8545scope of work on the project as the CEI was largely that of a contract

8560administrator, and a liaison between FIU and MCM -- not as a structural

8573engineer with the capability to analyze the structural behavior of the bridge

8585sufficient to d etermine if the cracks posed any danger of collapse.

8597b. Robert V. Robertson, P.E.

860298. DOT presented the testimony of Robert V. Roberson as an expert on

8615the standard of care for CEIs. Mr. Robertson has served as DOT's State

8628StructureÔs Design Enginee r for 13 years. Mr. Robertson has been a

8640professional engineer for 35 years.

864599. Although preliminarily accepted by the undersigned as an expert in

8656this field, it became apparent through cross - examination that Mr. Robertson

8668has no significant CEI experie nce. Mr. Robertson has not worked in the CEI

8682industry in the last 26 years, nor has he ever graded a CEIÔs performance.

8696Mr. Robertson was not involved in the DepartmentÔs evaluation of BPAÔs

8707performance of the CEI Contract. Accordingly, Mr. Robertson's tes timony was

8718of limited value.

8721100. Mr. Robertson acknowledged that the FIU bridge was a complex

8732concrete bridge structure that required a separate design qualification and

8742that BPA did have such qualification. Mr. Robertson admitted that BPAÔs

8753contract with FIU did not require BPA to be qualified to inspect complex

8766concrete bridges because BPA was allowed to satisfy that particular

8776qualification requirement of the contract through a sub - consultant

8786(Corradino).

8787101. Mr. Robertson testified that any licensed e ngineer with a college

8799degree in engineering should have known, based on the photographs in Crack

8811Report #3, that the cracks were dangerous and should have acted to stop

8824work on the project and close the road. However, DOT's LAP representative

8836at the March 15, 2018, meeting held prior to the bridge collapse, Mr. Reyna, a

8851licensed professional engineer with a college degree in engineering, failed to

8862raise any concerns at the March 15 th meeting or act to cease bridge work,

8877shore the bridge, or close Southwest 8 th Street under the bridge.

8889102. Mr. Robertson opined that the re - tensioning operation of the bridge

8902should have been peer reviewed. In his opinion, BPA failed to use sufficient

8915independent judgment. BPA, as the CEI, should have recognized the bridge

8926was in danger and known to stop traffic and shut down the road. However,

8940Mr. Roberston admitted that he did only a cursory review of the PowerPoint

8953presentation provided on the morning of March 15, 2018, in which FIGG, as

8966the EOR, stated it had no safety conc erns.

8975103. Mr. Robertson stated that he performed no analysis on anything

8986other than BPA ' s CEI work relative to the FIU bridge. He had no information

9002about BPA ' s design group or its qualification in any work category. However,

9016he suggested the denial of BP A ' s application for qualification across the

9030board, in all work categories because he questioned " the culture at BPA. "

9042Significantly, concerns regarding " the culture " of BPA was not cited by DOT

9054as a basis for the NOID.

9060104. Most significantly, Mr. Robert son testified that six months prior to

9072the issuance of the NOID, he had a conversation with Mr. Drummond during

9085which Mr. Drummond recommended that the qualification of all parties

9095involved with the FIU Pedestrian Bridge project should be suspended.

9105Import antly, this was prior to the issuance of either the OSHA or NTSB

9119reports and seemingly with no analysis of the role of any party to the possible

9134prevention of the bridge collapse, injuries, or loss of life.

9144Ultimate Findings of Fact

9148105. DOT failed to demo nstrate that BPA, as the CEI, fell below the

9162standard of care by failing to exercise its independent professional judgment

9173by not acting to cease bridge work, shore the bridge, or close Southwest 8 th

9188Street under the bridge in light of the documented crack ing on the structure

9202in the days leading up to the collapse.

9210106. The evidence shows that BPA documented, monitored, and reported

9220the cracks pursuant to the CPAM, Section 400 of the Standard Specifications,

9232and industry standards. BPA involved the EOR in evaluating the cracks even

9244before it was required by the CPAM, Section 400 of the Standard

9256Specifications, and industry standards. BPA was assured time and again by

9267the EOR that the bridge did not pose a danger to the travelling public and

9282that the structu re was safe. At the meeting on the morning of March 15,

92972018, BPA inquired as to whether temporary shoring was needed , and the

9309suggestion was rejected by the EOR who had inspected the cracks on the

9322structure just moments before the meeting. There is no evi dence that BPA

9335deviated from the standard of care for CEIs on design - build projects or that

9350BPA failed to exercise its independent professional judgment. To the

9360contrary, BPA met all of its obligations pursuant to contract and state

9372regulation.

9373107. DOT fa iled to demonstrate that BPA, as the CEI, fell below the

9387standard of care by failing to exercise independent professional judgment by

9398not acting to cease bridge work, shore the bridge, and close Southwest 8th

9411Street under the bridge pending a peer review o f the re - tensioning plan

9426proposed by the EOR at the March 15 th meeting.

9436108. At the March 15 th meeting, BPA was reasonably convinced by the

9449EOR that the structure was safe and that the re - tensioning plan was a

9464temporary measure that should be implemented a s soon as possible. BPA had

9477already engaged the EOR to prepare an EAR to address the cracking

9489observed on the bridge, which would have included signed and sealed

9500calculations and a repair protocol that would have been implemented in a

9512later phase of constr uction. On March 15, 2018, the cracks were not a safety

9527concern such that BPA should have overridden the EORÔs directive to MCM

9539and required that the re - tensioning operation be postponed pending a peer -

9553review of the re - tensioning plan. There is no evidence in the record that BPA

9569deviated from the standard of care for CEIs on design - build projects or

9583allegedly failed to exercise its independent professional judgment by allowing

9593the re - tensioning procedure to proceed as directed by the EOR. Conversely,

9606the ev idence supports a finding that BPA acted appropriately in relying on

9619the recommendations of the EOR who was uniquely qualified to evaluate the

9631safety of the structure and who had specialized knowledge of its design.

9643109. DOT failed to demonstrate that BPA, as the CEI, fell below the

9656standard of care by failing to exercise independent professional judgment by

9667not acting to cease bridge work, shore the bridge, and close Southwest 8th

9680Street under the bridge until the Corradino Group could arrive on the projec t

9694site to observe the re - tensioning operation proposed by the EOR during the

9708meeting on March 15, 2018. CorradinoÔs role on the project was to monitor

9721and document post - tensioning operations. By the time the meeting was over,

9734MCMÔs specialty contractor, VS L , was mobilized and prepared to proceed

9745with the re - tensioning operation. BPA was not involved in the pre -

9759coordination of this work. Ultimately, the bridge collapsed due to an inherent

9771design error in the plans and not due to CorradinoÔs absence from the re -

9786tensioning operations.

9788110. The findings of the OSHA report and the pendency of the NTSB

9801investigation , standing alone , were insufficient " good cause " for DOT to deny

9812BPAÔs 2019 Request for Qualification.

9817C ONCLUSIONS OF L AW

9822111. DOAH has jurisdiction over the parties to and the subject matter of

9835this proceeding. §§ 120.569 and 120.57, Fla. Stat.

9843112. A hearing involving disputed issues of material fact under

9853section 120.57(1) is a de novo proceeding, and the agencyÔs initial action

9865carries no presumpti on of correctness. See § 120.57(1)(k) , Fla. Stat . ; Moore v.

9879State, Dep Ô t. of HRS , 596 So. 2d 759 (Fla. 1st DCA 1992); Fla . Dep Ô t. of

9899Trans p . v. J. W. C. Co ., 396 So. 2d 778 (Fla. 1st DCA 1981).

9916113. " The general rule is that a party asserting the affirmati ve of an issue

9931has the burden of presenting evidence as to that issue. " DepÔt of Banking &

9945Fin., Div. of Sec. & Inv'r Prot. v. Osborne Stern & Co. , 670 So. 2d 932, 934

9962(Fla. 1996)(quoting Osborne Stern & Co. v. DepÔt of Banking and Fin ., 647 So.

99772d 425 (Fl a. 1 st DCA 1994)(Booth, J. concurring and dissenting)); Fla . Dep Ô t

9994of Transp . v. J.W.C. Co . , 396 So. 2d 778 (Fla. 1st DCA 1981).

10009114. " [W]here [an] agency proposes to deny the license because the

10020applicant is unfit, it has the burden to prove the applicant Ôs unfitness. " Fla.

10034DepÔt of Child . and Fams . v. Davis Fa m. Day Care Home , 160 So. 3d 854, 857

10053(Fla. 2015)(citing Osborne Stern , 670 So.2d at 934 ( " [T]he Department had

10065the burden of presenting evidence that appellants had violated certain

10075statutes and wer e thus unfit for registration. " ).

10084115 . In this case, the Department is asserting the affirmative, namely,

10096that it had good cause to deny BPAÔs Request for Qualification due to the

10110findings in the June 2019 OSHA Report as they relate to BPAÔs CEI services.

10124116. To the extent that denial of PetitionerÔs application for qualification

10135is akin to denial of a renewal of a license, the Department bears the burden of

10151proving good cause for denying renewal by " clear and convincing evidence. "

10162See Coke v. DepÔt of Chi ld . & Fam . Servs. , 704 So. 2d 726, 726 (Fla. 5th DCA

101821998)(Department " had the burden of proving [ p etitionerÔs] lack of

10193entitlement to a renewal of her license and that the evidence needed to be

10207clear and convincing. " )(citing Osborne Stern , 670 So. 2d at 9 33; Dubin v.

10221Dep Ô t. of Bus . Reg ., 262 So. 2d 273 (Fla. 1st DCA 1972)). 4 Otherwise, the

10240Department bears the burden of proving good cause by a " preponderance of

10252the evidence. " See § 120.57(1)(j), Fla. Stat. ( " Findings of fact shall be based

10266upon a preponder ance of the evidence, except in penal or licensure

10278disciplinary proceedings or except as otherwise provided by statute, and shall

10289be based exclusively on the evidence in the record and on matters officially

10302recognized. " ).

10304117. In Florida Department of Chil dren and Families v. Davis Family Day

10317Care Home , 160 So. 3d 854 (Fla. 2015), the Florida Supreme Court recognized

10330that the preponderance of the evidence burden of proof, not the clear and

10343convincing burden, is applicable to initial license application proc eedings.

10353Id. at 857. The Court explained that although it had not previously addressed

10366the situation where an agency erroneously references its disciplinary

10375authority in the context of noticing its intent to deny an initial license

10388application, " it is the nature of the agency's action and the underlying rights

10401implicated by the action that govern the applicable evidentiary standard[.] "

10411Id. In reaching its conclusion, the Davis Family court reaffirmed its holding

10423in Department of Banking and Finance v. Osbor ne Stern and Company ,

10435where the court distinguished cases involving denials of initial applications

10445(in which the Department must prove good cause for the denial by a

" 10458preponderance of the evidence " ) from cases involving revocations or denials

10469of renewal a pplications (which the Department must prove good cause for the

10482denial by " clear and convincing evidence " ). See Davis Family , 160 So. 3d at

10496856 (citing Dep't of Banking & Fin., Div. of Sec. & Inv'r Prot. v. Osborne

10511Stern & Co ., 670 So. 2d 932, 933 (Fla. 19 96) ) .

105254 At the Final Hearing, counsel stipulated that the burden of proof was a preponderance of

10541the evidence. (T. 129) However, " [i]t is well settled that a court is not bound to accept as

10559controlling stipulations as to questions of law[.] " Alvarez v. Smith , 714 So. 2d 652, 653

10574(Fla. 5 th DCA 1998)( quoting Clark v. Munroe , 407 So. 2d 1036, 1037 (Fla. 1st DCA 1981)

10592( " T he parties cannot by stipulation control questions of law. " )). The DepartmentÔs burden of

10608proving that it had good cause to deny BPAÔs Request for Qualification is by clear and

10624convincing evidence.

10626118. This is a renewal case (like Ferris and Coke ) -- not an initial

10641application case (like Davis Family and Osborne Stern ). Here, BPA had been

10654prequalified with the Department for the last 20 years. In May 2019, BPA

10667attempted to renew its qualificatio ns for the same Work Groups as the

10680previous fiscal year. DOT relied on the disciplinary section of the Florida

10692licensing statute as grounds to support its denial of BPAÔs renewal. DOTÔs

10704action is disciplinary in nature and subject to the clear and convinci ng

10717standard.

10718119. In denying BPAÔs Request for Qualification, DOT relied on

10728s ection 287.055 and Florida Administrative Code Chapter 14 - 75 . DOT cited

10742no other authority in its Notice of Intent to Deny.

10752120. As described above, section 287.055(3) requires th at any firm or

10764individual desiring to provide professional services to a governmental agency

10774must first be certified by the agency as qualified pursuant to law and the

10788regulations of the agency.

10792121. Rule 14 - 75.0022(4), entitled " Consultant Qualification P rocess , "

10802provides, in pertinent part, as follows:

10808(b) Upon receipt of a complete application the

10816Department shall make such inquiries and

10822investigations as deemed necessary to verify and

10829evaluate the applicant's statements and determine

10835competency for qual ification.

10839(c) Information which the Department shall

10845consider in determining whether a consultant is

10852qualified to perform the types of work shall include:

108611. Current license or registration as regulated by

10869the State of Florida or national organizations, as

10877appropriate.

108782. Personnel with appropriate experience and

10884training as detailed in the type of work

10892qualifications.

108933. Registration with the Florida Department of

10900State, if the applicant is a corporation or limited

10909partnership.

109104. Past performance on Department contracts.

109165. Integrity and responsibility, which shall include

10923history of debarment or suspension from

10929consideration for work with any other

10935governmental entity.

10937122. Rule 14 - 75.0051(1), entitled " Revocation, Denial, or Suspension of

10948Qualifi cation, " provides in part that " the Department will, for good cause,

10960deny or suspend the qualification of any professional consultant, or other

10971provider of service, to render services to the Department. " " Good cause "

10982includes instances where the consultant 's work performance in one of the

10994work types is not satisfactory. Unsatisfactory performance shall result in

" 11004revocation, denial, or suspension of qualifications for that type of work for a

11017period not to exceed one year. "

11023123. Rule 14 - 75.0051(1)(c), furthe r provides that good cause also includes

" 11036any other good cause, as defined in Section 337.105(1), F.S., established by

11048the factual circumstances. "

11051124. Section 471.033, Florida Statutes , and Florida Administrative Code

11060C hapter 61G15 - 19 establish es the grou nds for disciplinary proceedings

11073against licensed professional engineers in Florida. Under section 471.033,

11082engaging in negligence or misconduct in the practice of engineering, or

11093otherwise violation of chapter 455 , Florida Statutes, are grounds for

11103discip linary action against the status of a professional engineerÔs license with

11115the State of Florida. Under section 455.227(1)(o), performing professional

11124responsibilities the licensee knows, or has reason to know, they are not

11136competent to perform constitutes grounds for disciplinary action against the

11146status of a professional engineerÔs license with the State of Florida. 5

11158125. There is no evidence that BPA deviated from the standard of care for

11172CEIs on design - build projects or that BPA failed to exercise its i ndependent

11187professional judgment regarding the FIU Bridge project.

11194126. The record is devoid of any evidence that DOT examined any of the

11208criteria listed in r ule 14 - 75.0022(4) to determine if BPA met qualification

11222standards for 2019.

11225127. For " good cause , " DOT relies entirely on the OSHA Report . The

11238statements and opinions contained in the OSHA report are hearsay, and the

11250author of the report was not called to testify as an expert and was not subject

11266to cross - examination.

11270128. Absent from the OSHA report was any reference to BPA's design

11282services because BPA had no design responsibility for the project. Yet it is

11295this very document DOT relies on to deny BPA's request for qualification in

11308all work groups, including those exclusively related to design, rathe r than

11320CEI, work.

11322129. It is undisputable that the bridge collapse was a horrific tragedy with

11335long term consequences to the community, the victims, and those involved

11346with the project , including BPA and DOT. Understandably, it was politically

11357expedient fo r DOT to disqualify those entities that worked on the FIU Bridge

11371p roject. However, the plain language of the applicable statutes and

11382regulations required DOT to engage in an analysis of BPA's 2019 Request for

11395Qualification application. That analysis simply did not occur.

114035 Florida Administrative Code Rule 61G15 - 19.001(6), define s the term " misconduct " as used

11418in section 471.003 in part, as " [p]erforming an engineering assignment when not qualified by

11432training or experience in the practice area involved. " Although the Department cited

11444r ule 61G15 - 19.001(6) in its Pre - Hearing Statem ent, none of the three instances of BPAÔs

11463alleged failure to exercise its independent professional judgment include an allegation that

11475BPA undertook activities or services outside of its training or experience. This issue was not

11490plead or framed by the Dep artmentÔs Pre - Hearing Statement. At the Final Hearing, BPA

11506contemporaneously objected to the presentation of evidence on this unpled theory that BPA

11519allegedly performed services it was not prequalified to perform.

11528130. Under either a preponderance of the evidence, or by a clear and

11541convincing evidentiary standard, DOT did not meet its burden with respect to

11553the issues framed by its Pre - Hearing Statement and Notice of Intent to Deny.

11568R ECOMMENDATION

11570Based on the foregoing Findings of Fact and Conclusions of Law, it is

11583R ECOMMENDED that a Final Order be entered by the Department of

11595Transportation finding that good cause does not exist to deny BPAÔs 2019

11607Request for Qualification.

11610D ONE A ND E NTERED this 17th day of April , 2020 , in Tallahassee, Leon

11625County, Florida.

11627S

11628M ARY L I C REASY

11634Administrative Law Judge

11637Division of Administrative Hearings

11641The DeSoto Building

116441230 Apalachee Parkway

11647Tallahassee, Florida 32399 - 3060

11652(850) 488 - 9675

11656Fax Filing (850) 921 - 6 847

11663www.doah.state.fl.us

11664Filed with the Clerk of the

11670Division of Administrative Hearings

11674this 17th day of April , 2020 .

11681C OPIES F URNISHED :

11686George Spears Reynolds, IV, Esquire

11691Florida Department of Transportation

11695605 Suwannee Street , Mail Stop 58

11701Tallaha ssee, Florida 32399 - 0450

11707(eServed)

11708Scott Kirschbaum, Esquire

11711Cole, Scott & Kissane, P.A.

117169150 South Dadeland Boulevard , Suite 1400

11722Miami, Florida 33156

11725Anthony Lopez, Esquire

11728Cole, Scott & Kissane, P.A.

117339150 South Dadeland Boulevard , Suite 1400

11739Miami, Florida 33156

11742George Richard Truitt, Esquire

11746Cole, Scott & Kissane, PA

117519150 South Dadeland Boulevard , Suite 1400

11757Miami, Florida 33156

11760(eServed)

11761John Ashley Peacock, Esquire

11765Department of Transportation

1176860 5 Suwannee Street , Mail Stop 58

11775Tallahassee, Flo rida 32399 - 045 0

11782(eServed)

11783Andrea Shulthiess, Clerk of

11787Agency Proceedings

11789D epartment of T ransportation

11794Haydon Burns Building

11797605 Suwannee Street, M ail S top 58

11805Tallahassee, Florida 32399 - 0450

11810(eServed)

11811Erik Fenniman, General Counsel

11815D epartment of T rans portation

11821Haydon Burns Building

11824605 Suwannee Street, M ail S top 58

11832Tallahassee, Florida 32399 - 0450

11837(eServed)

11838Kevin J. Thibault, P.E., Secretary

11843D epartment of T ransporation

11848Haydon Burns Building

11851605 Suwannee Street, M ail S top 57

11859Tallahassee, Florida 32399 - 0 450

11865(eServed)

11866N OTICE OF R IGHT T O S UBMIT E XCEPTIONS

11877All parties have the right to submit written exceptions within 15 days from

11890the date of this Recommended Order. Any exceptions to this Recommended

11901Order should be filed with the agency that will issue th e Final Order in this

11917case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 10/09/2020
Proceedings: Notice of Appearance (Virginia Paxton) filed.
PDF:
Date: 10/08/2020
Proceedings: Notice of Appearance (Thomas Hunter) filed.
PDF:
Date: 08/20/2020
Proceedings: Directions to Clerk filed.
PDF:
Date: 08/17/2020
Proceedings: Petitioner's Notice of Appeal filed.
PDF:
Date: 07/28/2020
Proceedings: Agency Final Order filed.
PDF:
Date: 07/20/2020
Proceedings: Agency Final Order filed.
PDF:
Date: 07/16/2020
Proceedings: Agency Final Order
PDF:
Date: 07/16/2020
Proceedings: Agency Final Order
PDF:
Date: 04/17/2020
Proceedings: Recommended Order
PDF:
Date: 04/17/2020
Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
PDF:
Date: 04/17/2020
Proceedings: Recommended Order (hearing held February 13, 14, and 17, 2020). CASE CLOSED.
PDF:
Date: 03/13/2020
Proceedings: Petitioner's Proposed Recommended Order filed.
PDF:
Date: 03/13/2020
Proceedings: Respondent Florida Department of Transportation's Proposed Recommended Order filed.
PDF:
Date: 03/12/2020
Proceedings: Order Granting Extension of Time.
PDF:
Date: 03/12/2020
Proceedings: Amended Unopposed Motion to Extend Time Period to File Proposed Recommended Orders filed.
PDF:
Date: 03/11/2020
Proceedings: Unopposed Motion to Extend Time Period for Petitioner to File Its Proposed Recommended Order filed.
PDF:
Date: 02/27/2020
Proceedings: Order Granting Extension of Time.
PDF:
Date: 02/27/2020
Proceedings: Joint Motion to Extend Time Period for Parties to File Proposed Recommended Orders filed.
PDF:
Date: 02/26/2020
Proceedings: Notice of Filing Transcript.
Date: 02/26/2020
Proceedings: Transcript of Proceedings (not available for viewing) filed.
Date: 02/13/2020
Proceedings: CASE STATUS: Hearing Held.
PDF:
Date: 02/12/2020
Proceedings: Network Engineering Services, Inc. d/b/a Bolton Perez and Associates Objections to Florida Department of Transportation's Notice of Filing Deposition Designations for Final Hearing filed.
PDF:
Date: 02/12/2020
Proceedings: Motion in Limine to Exclude or, in the Alternative, Limit Expert Testimony filed.
PDF:
Date: 02/12/2020
Proceedings: Petitioner's Motion for Leave to Have Witness Testify Out-of-Order and Through Video Teleconference at Final Hearing filed.
PDF:
Date: 02/12/2020
Proceedings: Response in Opposition to Respondent's Motion in Limine to Exclude Petitioner's Expert Witness filed.
PDF:
Date: 02/11/2020
Proceedings: Department's Motion in Limine to Exclude Petitioner's Expert Witness filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 10) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 9) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 8) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 7) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 6) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 5) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 4) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 3) filed.
PDF:
Date: 02/11/2020
Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 2) filed.
PDF:
Date: 02/11/2020
Proceedings: Florida Department of Transportation's Notice of Filing Deposition Designations for Final Hearing (Part 1) filed.
PDF:
Date: 02/11/2020
Proceedings: Department's Motion in Limine to Exclude Petitioner's Expert Witness filed. (FILED IN ERROR)
PDF:
Date: 02/11/2020
Proceedings: Florida Department of Transportation's Objections to Bolton Perez and Associates' Amended Exhibit List for Final Hearing filed.
PDF:
Date: 02/10/2020
Proceedings: Bolton Perez and Associates' Objections/Stipulations to Respondent's Exhibit List for Final Hearing filed.
PDF:
Date: 02/10/2020
Proceedings: Bolton Perez and Associates' Amended Exhibit List for Final Hearing filed.
PDF:
Date: 02/07/2020
Proceedings: Petitioner's Exhibit A to Pre-Hearing Stipulation (Exhibit List) filed.
PDF:
Date: 02/07/2020
Proceedings: Petitioner's Pre-hearing Stipulation filed.
PDF:
Date: 02/06/2020
Proceedings: Respondent's Pre-Hearing Statement filed.
PDF:
Date: 02/05/2020
Proceedings: Department's Responses to Petitioner's First Request for Production filed.
PDF:
Date: 02/05/2020
Proceedings: Florida Department of Transportation's Notice of Serving Answers to Petitioner's First Set of Interrogatories filed.
PDF:
Date: 02/04/2020
Proceedings: Order Granting Extension of Time.
PDF:
Date: 02/03/2020
Proceedings: Unopposed Motion for Extension of Time to File Joint Pre-Hearing Stipulation filed.
PDF:
Date: 02/03/2020
Proceedings: Bolton Perez and Associates' Notice of Serving Verified Answers to Florida Department of Transportation's Expert Interrogatories filed.
PDF:
Date: 01/24/2020
Proceedings: Order on Department's Motion for Judicial Notice.
PDF:
Date: 01/23/2020
Proceedings: Bolton Perez and Associates' Notice of Serving Unverified Answers to Florida Department of Transportation's Expert Witness Interrogatories filed.
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 7) filed.
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 6) filed.
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses filed (Part 5).
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 4) filed.
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 3) filed.
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 2) filed.
PDF:
Date: 01/21/2020
Proceedings: Florida Department of Transportation's Notice of Filing Affidavit and Discovery Responses filed.
PDF:
Date: 01/21/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 2) filed.
PDF:
Date: 01/17/2020
Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part1) filed.
PDF:
Date: 01/17/2020
Proceedings: Department's Reply to Petitioner's Response to the Department's Motion for Judicial Notice filed.
PDF:
Date: 01/17/2020
Proceedings: Notice of Taking Deposition Duces Tecum (Gustavo "Gus" Quesada) filed.
PDF:
Date: 01/14/2020
Proceedings: Bolton Perez and Associates' Amended Response to Florida Department of Transportation's First Requests for Admission filed.
PDF:
Date: 01/14/2020
Proceedings: Bolton Perez and Associates' Amended Response to Florida Department of Transportation's First Request for Production filed.
PDF:
Date: 01/14/2020
Proceedings: Order Allowing Video Testimony.
PDF:
Date: 01/13/2020
Proceedings: Bolton Perez and Associates' Response to Florida Department of Transportation's First Requests for Admission filed.
PDF:
Date: 01/13/2020
Proceedings: Bolton Perez and Associates' Notice of Serving Answers to Florida Department of Transportation's First Set of Interrogatories filed.
PDF:
Date: 01/13/2020
Proceedings: Bolton Perez and Associates' Response to Florida Department of Transportation's First Request for Production filed.
PDF:
Date: 01/10/2020
Proceedings: Order Granting Respondent's Motion for Leave to File a Reply to Petitioner's Response to the Department's Motion for Judicial Notice.
PDF:
Date: 01/09/2020
Proceedings: Motion for Leave to File a Reply to Petitioner's Response to the Department's Motion for Judicial Notice filed.
PDF:
Date: 01/08/2020
Proceedings: Notice of Taking Video Deposition filed.
PDF:
Date: 01/07/2020
Proceedings: Bolton Perez and Associates' First Request for Production to Department of Transportation filed.
PDF:
Date: 01/07/2020
Proceedings: Notice of Serving First Set of Interrogatories on Respondent filed.
PDF:
Date: 01/07/2020
Proceedings: Response to Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse filed.
PDF:
Date: 01/06/2020
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 01/06/2020
Proceedings: Notice of Taking Deposition filed.
PDF:
Date: 12/20/2019
Proceedings: Florida Department of Transportation's Notice of Serving Expert Witness Interrogatories on Petitioner filed.
PDF:
Date: 12/06/2019
Proceedings: Order Granting Continuance and Rescheduling Hearing (hearing set for February 13, 14, 17, and 18, 2020; 9:00 a.m.; Tallahassee).
PDF:
Date: 12/05/2019
Proceedings: Petitioner's Unopposed Motion to Continue Final Hearing filed.
PDF:
Date: 12/04/2019
Proceedings: Department's Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse (Part 3) filed.
PDF:
Date: 12/04/2019
Proceedings: Department's Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse (Part 2) filed.
PDF:
Date: 12/04/2019
Proceedings: Department's Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse (Part 1) filed.
PDF:
Date: 12/04/2019
Proceedings: Florida Department of Transportation's Notice of Serving First Set of Interrogatories on Petitioner filed.
PDF:
Date: 11/22/2019
Proceedings: Florida Department of Transportation's Motion for Leave to Have Witness Testify Out-of-Order and Through Video Teleconference at Final Hearing filed.
PDF:
Date: 11/19/2019
Proceedings: Notice of Appearance (John Peacock) filed.
PDF:
Date: 10/07/2019
Proceedings: Order of Pre-hearing Instructions.
PDF:
Date: 10/07/2019
Proceedings: Notice of Hearing (hearing set for December 11 through 13, 2019; 9:00 a.m.; Miami, FL).
PDF:
Date: 10/02/2019
Proceedings: Joint Reponse to Initial Order filed.
PDF:
Date: 09/25/2019
Proceedings: Initial Order.
PDF:
Date: 09/24/2019
Proceedings: Notice of Appearance (George Reynolds).
PDF:
Date: 09/24/2019
Proceedings: Agency action letter filed.
PDF:
Date: 09/24/2019
Proceedings: Petition for Formal Administrative Hearing filed.
PDF:
Date: 09/24/2019
Proceedings: Agency referral filed.

Case Information

Judge:
MARY LI CREASY
Date Filed:
09/24/2019
Date Assignment:
09/25/2019
Last Docket Entry:
10/09/2020
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
 

Counsels

Related Florida Statute(s) (7):