19-005130
Network Engineering Services, Inc., D/B/A Bolton Perez And Associates vs.
Department Of Transportation
Status: Closed
Recommended Order on Friday, April 17, 2020.
Recommended Order on Friday, April 17, 2020.
1S TATE OF F LORIDA
6D IVISION OF A DMINISTRATIVE H EARINGS
13N ETWORK E NGINEERING S ERVICES , I NC .,
22D/B/A B OLTON P EREZ A ND A SSOCIATES ,
31Petitioner ,
32Case No. 19 - 5130
37vs.
38D EPARTMENT OF T RANSPORTATION ,
43Respondent .
45/
46R ECOMMENDED O RDER
50Pursuant to notice, a formal administrative hearing was conducted before
60Administrative Law Judge ( " ALJ " ) Mary Li Creasy in Tallahassee, Florida,
72on February 13, 14, and 17, 2020.
79A PPEARANCES
81For Petit ioner: George Richard Truitt, Esquire
88Anthony Lopez, Esquire
91Cole, Scott & Kissane, PA
969150 South Dadeland Boulevard, Suite 1400
102Miami, Florida 33156
105For Respondent: George Spears Reynolds, IV, Esquire
112John Ashley Peacock, Esquire
116Florida Department of Transportation
120605 Suwannee Street, Mail Stop 58
126Tallahassee, Florida 32399 - 0450
131S TATEMENT OF T HE I SSUE
138The issue in this administrative proceeding is whether the Florida
148Department of TransportationÔs ( " DO T " or " the Department " ) denial of
160PetitionerÔs, Network Engineering Services, Inc. d/b/a Bolton Perez &
169Associates ( " BPA " ) , 2019 application for qualification pursuant to section
180337.105, Florida Statutes, and Florida Administrative Code Chapter 14 - 75,
191was for good cause due to PetitionerÔs participation in the construction of the
204Florida International University ( " FIU " ) City Prosperity Project ( " FIU Bridge
216p roject " ).
219P RELIMINARY S TATEMENT
223On July 11, 2019, DOT issued a Notice of Intent to Deny Request for
237Qualification ( " NOID " ) to BPA. The NOID removed BPA from consideration
249for award of professional service contracts with DOT. DOT issued the NOID
261based upon BPAÔs failure to appropriately exercise independent professional
270judgment required of a constructio n engineering and inspection firm ( " CEI " ) ,
283as evidenced by the reports issued by the Occupational Safety and Health
295Administration ( " OSHA " ) and the investigation of the National
305Transportation Safety Board ( " NTSB " ) concerning the collapse of the FIU
317Bridge p roject on March 15, 2018.
324On August 1, 2019, BPA filed a Petition for Formal Administrative
335Hearing. On September 24, 2019, the petition and accompanying documents
345were filed with DOAH.
349A formal hearing was held as scheduled on February 13, 14, and 17, 2020,
363in Tallahassee, Florida. At the final hearing, BPA presented the testimony of
375Joaquin " Jake " Perez, BPAÔs President and Director of Engineering ; Jose
385Morales, BPAÔs CEI Services Manager ; and Gustavo Quesada, BPAÔs expert
395witness. BPAÔs Exhibi ts 5, 7, 9, 11 through 18 , 29 through 32, 39, and 40
411were admitted into evidence.
415DOT presented the testimony of William Watts, P.E., Chief Engineer for
426the Departmen t ; Robert V. Robertson, Jr., P.E., State Structures Design
437Engineer for the Departmen t ; and Carlos Chapman, BPAÔs S enior I nspector.
450DOTÔs Exhibits 1, 6, 9 through 16(c), 18 through 29, 33, and 34 were admitted
465into evidence. DOT's deposition designations of BPAÔs corporate
473representatives, Mr. Perez and Mr. Morales were also admitted and acce pted
485into evidence.
487DOT marked the OSHA report as Exhibit 2 for identification. BPA
498objected to the admissibility of the OSHA and NTSB reports as unreliable
510hearsay expert testimony and objected to the admissibility of the statements
521within the report a s hearsay within hearsay. Prior to the final hearing, by
535O rder dated January 24, 2020, the undersigned ALJ , upon motion filed by
548Petitioner, took official recognition of both the OSHA and the NTSB reports.
560However, despite multiple references to it, the OS HA report was neither
572moved nor admitted into evidence.
577The six - volume final hearing Transcript was filed on February 26, 2020.
590The parties requested and were granted several extensions of time within
601which to file proposed recommended orders. Both partie s submitted proposed
612recommended orders which were considered in the drafting of this
622Recommended Order. All references to statutes refer to the 2019 version ,
633unless otherwise specified.
636F INDINGS OF F ACT
641T HE P ARTIES
6451. DOT is the state agency responsible for coordinating the planning,
656construction, and maintenance of a safe, viable, and balanced state
666transportation system. DOT relies on qualified contractors and professional
675consultants to provide services for FloridaÔs transportation needs.
6832. Section 28 7.055(3), Florida Statues, requires that any firm or individual
695desiring to provide professional serv ic es to a governmental agency must first
708be certified by the agency as qualified , pursuant to law and the regulations of
722the agency. The agency must find t hat the firm or individual to be employed
737is fully qualified to render the required service. Among the factors to be
750considered in making this finding are the capabilities, adequacy of personnel,
761past record, and experience of the firm or individual. Each agency is also
774required to evaluate professional services, including capabilities, adequacy of
783personnel, past record, and experience of the firm or individual.
7933. Section 337.105 and Florida Administrative Code Chapter 14 - 75 also
805govern s the qualification s of professional consultants and other contractual
816services providers to DOT. Section 337.105 authorizes DOT to deny or
827suspend an application for qualification based upon a determination of " good
838cause , " which includes, but is not limited to, nine illust rative examples
850specified in s ection 337.105(1)(a) Ï (i) . DOT may, for good cause, deny or
865suspend for a specified period of time a person or firm from consideration for
879award of a professional service contract for a particular type of work.
8914. BPA is a mult idiscipline engineering firm specializing primarily in
902transportation related engineering services, including bridge design, roadway
910design, civil works, construction engineering inspection ( " CEI " ), and program
921and construction management. At the time of t he hearing, BPA had
933approximately 38 employees. BPA was formed by Joaquin " Jake " Perez, P.E. ,
944and John Bolton, P.E. , in 1997 to provide transportation - related engineering
956services.
9575. BPAÔs CEI qualifications are independent from, and do not necessarily
968m irror, BPAÔs design qualifications. In some instances, BPA was qualified to
980serve as a CEI for categories of structures that the firm was not qualified to
995design. This is because BPA was internally divided into two core groups:
1007design and CEI. Since incept ion, BPAÔs design group was and continues to be
1021headed by Mr. Perez, and the CEI group headed by Mr. Bolton.
10336. The operations of BPAÔs CEI and design groups were completely
1044segregated within the firm. CEI personnel did not work on design projects,
1056and des ign personnel did not work on CEI projects. As President, Mr. Perez
1070was involved in pursuing contracts for CEI services, but CEI services were
1082provided only by CEI personnel.
10877. In or about 1999 or 2000, BPA first became qualified to respond to
1101DOTÔs requ est for qualifications to provide professional services to DOT.
1112Mr. Bolton qualified the firm to provide CEI services, and Mr. Perez qualified
1125it to provide design services. BPA remained qualified with the Department on
1137an annual basis for both CEI and des ign work for nearly 20 years until
1152July 2019. At that time, DOT issued a NOID removing BPA from
1164consideration for award of professional service contracts with DOT for 2019 -
11762020. DOT issued the NOID based solely upon a report issued by OSHA and
1190the investig ation of NTSB regarding the collapse of the FIU Bridge p roject on
1205March 15, 2018.
1208T HE F IU P EDESTRIAN B RIDGE P ROJECT
12188. In 2014, DOT entered into a Local Agency Program ( " LAP " ) Agreement
1232with FIU for its pedestrian bridge project, a Category II, complex bri dge, that
1246would be constructed along Southwest 109 th Avenue and Southwest 8 th
1258Street in the City of Sweetwater, Florida (the " project " ). As the supervising
1271agency of the LAP program, DOT was responsible for supervising and
1282authorizing work by the local age ncy.
12899. The design of a Category II structure required an independent peer
1301review by a firm with no other involvement in the project, which was
1314prequalified with DOT. In September 2016, FIGG Bridge Engineers, Inc.
1324( " FIGG " ), the Engineer of Record ( " EOR " ) f or the project, hired Louis Berger
1341to review FIGGÔs plans for bridge foundation, substructure (end bents and
1352center tower), and superstructure. Those plans included construction
1360sequencing (including construction sequence drawings), the covered main
1368span p re - casting, transport of main span, and placement of the main span
1383between end bent 1 (south pier) and the pylon pier. The plans also included
1397the post - tensioning stressing and destressing sequences.
140510. As the Local Agency, FIU was in responsible charge o f the day - to - day
1423activities, including project safety issues. Alfredo Reyna, P.E. , was the
1433DepartmentÔs LAP Coordinator for the project. Mr. Reyna is a licensed
1444professional engineer, although he is not a structural engineer.
14531 1. In January 2016, FIU ente red into a design - build contract 1 with
1469Munilla Construction Management, LLC ( " MCM " ) , to design the bridge and
1481to perform all work and furnish all materials, equipment, supplies, and labor
1493necessary to construct the project. The bridge was designed by FIGG, a
1505member of the MCM design - build team and the EOR. FIGG is a reputable
1520designer who has been recognized internationally for its work. FIGG has
1531experience in designing complex bridges, such as the Sunshine Skyway
1541Bridge near Tampa, Florida.
154512. On Septembe r 23, 2016, FIU entered into a Standard Professional
1557Services Agreement with BPA for CEI services (the " CEI Contract " ). At the
15701 The interaction of the local agency, contractor, designer, EOR , DOT, and the CEI is
1585different between a " conventional " and a " design build " bridge project. In a conventional
1598project, the designer is hired by DOT or owner to cr eate a new bridge. The design goes
1616through a review process at DOT and a final set of plans goes to bid for a contractor. By the
1636time the contractor is selected, the EOR has completed the plans. The EOR is essentially " on
1652call " for the construction phase o f the project because the design work is complete. The CEI
1669begins its work when the contractor begins construction. If there is a question in the field,
1685the CEI makes a request for information from the EOR. DOT supplies design and
1699construction managers thr oughout the process.
1705In contrast, for a " design build " project, the owner has a conceptual plan for the project.
1721The designer and contractor bid for the job based on the preliminary conceptual plan. The
1736Designer/EOR and contractor work hand in hand from the beginning of the project and are in
1752constant communication. The CEI begins work when the contractor starts work on the
1765project. The CEI facilitates the resolution of any issues between the EOR/designer and the
1779contractor who continue to plan thro ughout the duration of the project. Like a conventional
1794build project, DOT has construction managers and design project managers involved from
1806the beginning of the project.
1811If concrete cracking occurs , it is the CEI's obligation to document the crack ing and speak
1827to people in the process who can assess and address the cracking. For a conventional build
1843bridge, if cracking is observed, the CEI documents it, copies DOT , and sends it to the EOR
1860for assessment. The EOR provides an assessment by conducting a site visit. The EOR then
1875prepares an Engineering Assessment Report (EAR) for the project team. In a design build
1889bridge job, if cracks are observed, they are documented by the CEI who notifies the EOR. The
1906EOR, who is already on the job site, assesses t he cracks and works with the contractor to
1924devise a solution.
1927time, John Bolton was the CEI qualifier for BPA. As CEI, BPA was to act as
1943the liaison between the project owner (FIU) and the co ntractor (MCM). The
1956CEI handles quality control, materials, schedules, payments, documents the
1965entire process, and monitors the project.
197113. Jose Morales, P.E. , worked under John Bolton as the Senior Project
1983Engineer for the project. Mr. Morales first obta ined his professional
1994engineerÔs license in 2006. He had approximately 12 years of CEI experience
2006at the time of the collapse. Although he was the Senior Project Engineer for
2020the project, Mr. Morales had little - to - no design experience.
203214. Mr. Morales was first involved in the early stages of pursuing the CEI
2046Contract for the project. After the project was awarded, BPA was not involved
2059in the design phase, but was later brought back into the fold beginning in
2073October 2016, when BPA received the Notice to Pr occed and fully staffed its
2087CEI scope of services when construction was scheduled to begin in or about
2100March of 2017.
210315. The " Scope of Services " section (Exhibit B) to the CEI Contract
2115required BPA to be prequalified with the Department in the following w ork
2128categories: Work Type 10.1 -- Roadway CEI ; Work Type 10.4 -- Minor Bridge
2141and Miscellaneous Structures CEI ; and Work Type 10.5.1 -- Major Bridge CEI -
2154- Concrete. For the FIU bridge project, Categories 10.1 and 10.4 were
2166considered to be the " major " type of wor k while 10.5.1 was considered to be
2181the " minor " type of work. As expressly permitted by the Standard
2192Professional Services Agreement, BPA satisfied the 10.5.1 prequalification
2200requirement through its sub - consultant, The Corradino Group, Inc.
2210( " Corradino " ).
221316. BPAÔs scope of services for the project did not include any design
2226responsibilities. BPA performed constructability review of the plans as part of
2237its CEI scope of work, but it did not review the plans or drawings on a
2253technical level.
225517. The FIU bri dge was a Complex Category II structure as defined by the
2270DepartmentÔs Design Manual. The structure had a unique, complex design
2280that was meant to be a signature, architectural feature for the area.
229218. The relevant construction sequence for the main span (Span 1) of the
2305FIU bridge consisted of:
2309a. c asting the main span superstructure in the casting yard;
2320b. i nstalling post - tension bars in the diagonal and vertical members of
2334the structure;
2336c. s tressing of the main - span post - tensioning while the main span i s in
2354the casting yard;
2357d. r emoving the temporary formwork and supports;
2365e. t ransporting the main span from the casting yard using a self -
2379propelled modular transporter and placing the structure in a " simply
2389supported " condition on the south pier and pylon p ier; and
2400f. d e - tensioning truss members 2 and 11 .
241119. Generally, cracks in concrete are common and are not, in and of
2424themselves, a cause for concern. On a design - build job, when cracks manifest
2438themselves in a concrete element, the CEI must document the c racking and
2451report it to the design - build team, which includes the EOR. Depending on the
2466nature of the cracks, the CEI may request an EAR from the EOR. This
2480process is set out in s ection 400, subsection 400 - 21, of DOTÔs Standard
2495Specifications for Road and Bridge Construction (the " Standard
2503Specifications " ).
250520. DOT's Construction Project Administration Manual ( " CPAM " ) includes
2515the procedures to be followed by a CEI in addressing cracks in concrete. The
2529CPAM requires that the CEI identify and document its o bservations and
2541convey the information to the EOR for a final disposition as to the potential
2555danger of the crack or the need for further evaluation.
2565The FIU Bridge Cracking and Inspections by BPA
257321. On or about February 6, 2018, while Span 1 of the brid ge was still in
2590the casting yard, BPA became aware of certain cracks that had developed in
2603the structure. Mr. Morales personally inspected the structure after the
2613tendons on truss members 2 and 11 were stressed, and he noted that cracks
2627had developed in ot her locations on the bridge. The cracks observed were very
2641small, approximately 0.004 of an inch wide.
264822. On February 13, 2018, BPA submitted Crack Report # 1 to MCM, FIU,
2662and Corradino, documenting the cracks that had developed in the concrete
2673truss membe rs after completing the post - tensioning operations in the casting
2686yard. Despite the small size of the cracks, BPA requested that the EOR
2699provide an assessment of the cracks.
270523. FIGG, the EOR, responded to BPAÔs request by stating that the
2717current conditio n observed was temporary in nature and that the cracks were
2730not an issue.
273324. BPA exercised independent professional judgment when it exceeded
2742the requirements of s ection 400 of the Standard Specifications and the CPAM
2755by documenting and reporting these in itial cracks.
276325. In late February 2018, before the placement of the main bridge span
2776on the permanent pylon and south pier supports, cracks were observed in
2788certain truss members. BPA prepared and submitted Crack Report # 2 to FIU
2801and MCM on February 28, 2 018, documenting the size and location of these
2815cracks and requested that FIGG evaluate the cracks and provide a
2826disposition.
282726. In its report, BPA called attention to certain cracks that were
2839significant in size. As CEI, BPA was not qualified to determin e whether these
2853larger cracks posed an imminent danger of collapse. Further, BPAÔs design
2864team was not involved in the design of the bridge and was not qualified to
2879evaluate these cracks from a design engineering perspective due to the
2890category and complex ity of the bridge.
289727. At this point, the cracks were not " structural " as defined by
2909Section 400 of the Standard Specifications. Cracks more than one - half inch in
2923depth are deemed " structural " and trigger the obligation of the CEI to notify
2936the EOR. Nevert heless, BPA, again, exercised its independent professional
2946judgment above and beyond the requirements of the Standard Specifications
2956and CPAM by requesting that the report be forwarded to the EOR and
2969requesting that the EOR provide a response and dispositi on of the cracks.
298228. On March 7, 2018, FIGG replied to Crack Report # 2, stating, in part,
2997that the cracks appeared small, that they were not concerned about these
3009types of cracks in the particular region shown in the report, and that MCM
3023would need to sea l the cracks in accordance with the DepartmentÔs
3035specifications. As the EOR, FIGG did not have any structural concerns
3046regarding the cracks in Crack Report #2.
305329. On March 7, 2018, FIGG representatives were on site and observed
3065the cracks referenced in Cr ack Report #2. After observing the cracks, FIGG
3078did not delay the bridge movement that was scheduled to take place three
3091days late r on March 10th.
309730. As of March 8, 2018, BPA had no concerns regarding the integrity of
3111the structure or public safety becaus e the EOR had looked at the cracks in -
3127person and assured the project team that the cracks were not a safety issue
3141or structurally significant. These assurances came two to three days prior to
3153the bridge being moved over Southwest 8 th S treet and placed on t he
3168permanent pylon and pier supports. The bridge movement was not delayed
3179due to the cracks observed by the EOR.
318731. On March 10, 2018, Span 1 was moved from the casting yard and
3201placed on the permanent pylon and south pier supports. After the placement
3213an d de - tensioning of diagonal members 2 and 11, cracks began to appear at
3229the construction joint of diagonal 11, the deck, and at the top of diaphragm II.
324432. At approximately 11 :00 a.m. on March 13, 2018, two days before the
3258collapse, BPA circulated a draft of Crack Report #3 to MCM, recommending
3270further monitoring and documenting of the cracks to determine whether they
3281were active or dormant, and requesting that BPA be informed of the outcome
3294of the EORÔs EAR and course of action. At 5:18 p . m . on March 13, 2018, the
3313EOR responded to MCM with additional recommendations and stated
" 3322[a]gain, we have evaluated this further and confirmed that this is not a
3335safety issue. "
333733. Because BPAÔs design team was not involved in the project, no BPA
3350design personnel were a ware of the documented cracking on the structure
3362until sometime after Crack Report #3 was generated. At that time,
3373Mr. Morales provided Mr. Perez with a copy of a draft of Crack Report #3.
3388Mr. Perez briefly reviewed the draft report and confirmed with Mr. Morales
3400that the CEI team had elevated the issue to the EOR.
341134. At all times in the documented communication relating to the cracks,
3423the EOR and members of the FIGG design team represented to BPA that the
3437cracks were not a safety concern, without reservat ion.
344635. Starting on March 13, 2018, FIGG directed MCM to implement an
3458initial, temporary measure to address observed cracking in the member 11/12
3469nodal region. At that time, BPA was not aware of this communication
3481between the EOR and the c ontractor. To re store the temporary support
3494conditions when the structure was in the casting yard, MCM placed shims
3506between diaphragm II and the pylon on March 13, 2018.
351636. FIGG also directed re - tensioning the post - tensioning rods in truss
3530member 11 to begin on March 15, 2018. The re - tensioning operation was
3544made as a " rushed request " to the post - tensioning subcontractor by MCM on
3558March 14, 2018. " FIGG recommends to stress these PT bars as soon as
3571possible but again, this is not a safety concern. "
3580M ARCH 15, 2018 , A ND T HE B RIDGE C OLLAPSE
359237. Rather than waiting for the EAR, BPA once again exercised its
3604independent , professional judgment and went above and beyond the
3613requirements of the Standard Specifications, CPAM, and Contract
3621Documents when it further escalated the issu e of the cracks by calling for a
3636meeting with the EOR. On the morning of March 15, 2018, a meeting
3649requested by BPA and coordinated by MCM, was held in Miami, Florida.
3661Representatives of FIGG, MCM, DOT, FIU, and BPA were present.
367138. At the March 15 th meet ing, BPA first became aware of the EORÔs
3686instruction to MCM to proceed with a second temporary measure. This
3697subsequent temporary measure was to reinstate the post - tensioning
3707compression force back in member 11 as per the previous construction phase.
3719As ex plained by the EOR, both temporary measures (shims and re -
3732tensioning) were intended to restore the temporary support conditions when
3742the structure was in the casting yard.
374939. Prior to the start of the meeting, the EOR, other FIGG engineers, and
3763DOTÔs LAP Coordinator inspected the bridge and the cracks in the nodal
3775region of members 11/12.
377940. Only FIGG had structural engineers at the meeting. No other
3790engineers present at the meeting had a background in structural
3800engineering, including those in attendance on behalf of BPA. The meeting
3811was called for purposes of discussing the concrete cracking on Span 1, and
3824specifically the concrete cracking in nodal connection between truss members
383411 and 12 and the bridge deck. At this meeting, BPA informed FIGG that th e
3850cracks in the bridge were lengthening and growing daily. Though not
3861formally invited, Mr. Reyna attended this meeting in his capacity as DOTÔs
3873consultant/Assistant LAP Coordinator.
387641. At the March 15 th meeting, the EOR presented FIGG's assessment of
3889the cracking after having reviewed the three BPA crack reports and having
3901personally inspected the cracks on at least the following two occasions:
3912( 1) prior to the bridge being moved from the casting yard over Southwest 8th
3927S treet; and ( 2) on the morning of t he March 15 th meeting. The EORÔs
3944presentation consisted of a lengthy and comprehensive PowerPoint slide
3953presentation on the conditions of the bridge, structural analysis by
3963calculation s and 3D modeling of the loads and forces the area of member
397711/12 nodal region cracks, and an evaluation of the safety of the span over
3991Southwest 8 th Street for workers and the public.
400042. Throughout the March 15 th meeting, BPA exercised its independent
4011professional judgment by actively participating in the EORÔs presentation ,
4020questioning and challenging the EOR. For example, BPA:
4028a. inquired as to whether temporary shoring was needed;
4037b. sought clarification regarding the mechanism being used to
4046capture the load from the node and whether it would have to be
4059integrated with th e pylon diaphragm;
4065c. requested clarification on the amount of transferred post -
4075tensioning assumed for the nodal shear stability analysis;
4083d. inquired as to whether there were any restrictions on load;
4094e. inquired as to whether there would be a crack mon itoring plan;
4107f. requested a copy of the EORÔs presentation;
4115g. inquired as to whether it had been peer reviewed and commented
4127that it wanted more eyes on the presentation calculations; and
4137h . BPA requested a copy of the stressing procedure that was bei ng
4151recommended by the EOR.
415543. Throughout the presentation, and during the question and answer
4165phase of the meeting, the EOR assured BPA and the other attendees that the
4179structure was safe. These assurances were based on statements made by the
4191EOR as well as its calculations and modeling, which were part of its slide
4205presentation at the meeting.
420944. In the presentation on the slide entitled " Safety, " FIGG stated that
" 4221È[it] had conducted sufficient supplemental/independent computations to
4228conclude that ther e is not any concern with safety of the span suspended over
4243the road. " At the end of the presentation, the EOR concluded the meeting
4256with " [b]ased on conservative calculations, it is concluded that the design
4267meets LRFD strength requirements for this tempo rary condition and
4277therefore there is no safety concern relative to the observed cracks and minor
4290spalls. "
429145. During the meeting, the EOR stated that some cracking similar to the
4304ones on the structure , were expected. The EOR further stated during the
4316meet ing that the top deck spalls could not be replicated, but that the spalled
4331areas were minor and they should be repaired during the next phase of work
4345when the pylon concrete was to be placed.
435346. No engineer at the meeting, including DOT's representative,
4362Mr. Reyna, requested or recommended a complete road closure to protect the
4374public safety or that the bridge be shut down. BPA had no reason to request a
4390full road closure of Southwest 8 th S treet. There was no preplanned complete
4404road closure, there was no maintenance of traffic ( " MOT " ) deficiency, and,
4417based on the EORÔs presentation, BPA was reasonably satisfied that no
4428safety issues required a road closure.
443447. Towards the end of the meeting on March 15 th , MCM informed BPA
4448that a specialty contractor, Str uctural Technologies ( " VSL " ), was already
4460onsite to conduct the re - tensioning operation. Without BPAÔs knowledge, VSL
4472had already mobilized on site to perform the remedial re - tensioning. BPA was
4486not involved in pre - coordination for the re - tensioning operat ion. Therefore,
4500BPAÔs sub - consultant, Corradino, was not onsite to participate in monitoring
4512of the re - tensioning procedure.
451848. CorradinoÔs role, as BPA's sub - contractor, was that of a 10.5.1 CEI
4532(Major Bridge CEI -- Concrete). Corradino was responsible for monitoring and
4543documenting the post - tensioning operations. The post - tensioning operation
4554after placement of the span had already occurred and therefore, Corradino
4565was not on - site on March 15 , 2018 .
457549. Based on the safety assurances and conservative calc ulations
4585presented by the FIGG EOR that the structure was safe, BPA , and the other
4599professional engineers present at the meeting, including those representing
4608FIU and DOT, followed the recommendations of the FIGG EOR to bring the
4621main span condition back t o its pre - existing state when the span was in the
4638casting yard.
464050. BPA did not have the expertise or the contractual duty to perform its
4654own analysis of th e cracking o n this complex bridge and override, or even call
4670into question, FIGGÔs unequivocal asses sment that the bridge was safe.
468151. During the restressing operation of member 11, the roadway below the
4693bridge had two westbound lanes closed as per the blanket, two - lane, closure
4707permit issued by DOT. This blanket, two - lane, closure permit was obtained
4720b y MCM to provide workspace underneath the bridge to conduct the remedial
4733action. MCM obtained the blanket, two - lane , closure permit from the
4745Department the morning of March 15, 2018, before conducting the remedial
4756action.
475752. A CEIÔs authority to request a partial or complete road closure is
4770defined by the contract plans and roadway closure permits, which is
4781implemented using the procedures outlined by the CPAM and the CEI Scope
4793of Services of the CEI Contract. A CEI is authorized to request the contractor
4807to either partially or fully close a road if there is an MOT deficiency, as
4822contemplated by CPAM Section 9.1.8 -- " Recommended Action to Shut Down a
4834Project Due to MOT Deficiencies. " Lastly, a CEI has authority to request a
4847partial or full road closure if it is aware of a safety issue .
486153. None of these conditions existed on the project in the days leading up
4875to the collapse in light of the EORÔs comprehensive presentation regarding
4886the cracking conditions of the bridge, strength in the area of member 11/12
4899n odal region, safety of the span over Southwest 8th Street, and repeated,
4912unequivocal reassurances that the structure did not pose a safety concern.
492354. Ultimately, BPAÔs authority to request a partial or complete road
4934closure on the project was a collectiv e effort with the Department and FIU.
4948BPA did not have the authority or ability to act on its own to close the road.
496555. The FIU Pedestrian Bridge collapsed during the re - tensioning of the
4978truss member 11 post - tensioning rods on the afternoon of March 15, 2018.
4992Six people died as a result of the FIU bridge collapse, including one bridge
5006worker and five vehicle occupants. Ten people were critically injured as a
5018result of the FIU bridge collapse, including two BPA employees, Mr. Morales
5030and Carlos Chapman.
503356 . Mr. Chapman was on the canopy of the bridge during the re -
5048tensioning operation, observing the work being performed by VSL and
5058communicating the progress to Mr. Morales who was on the deck of the
5071bridge. Because of the representations made by the EOR, nei ther
5082Mr. Chapman nor Mr. M orales was concerned for his own safety or well - being
5098when they went on the bridge on the day it collapsed.
510957. BPAÔs role, responsibilities, and scope of work on the FIU Bridge
5121project as the CEI was that of a contract administra tor, not as a structural
5136engineer with the capability to analyze the structural behavior of the bridge
5148sufficient to determine if the cracks posed any danger of collapse. BPA had no
5162basis, ability, or contractual obligation, to perform its own analysis of this
5174complex structure sufficient to override the FIGG EORÔs unequivocal safety
5184assessment and recommendations. BPA performed its CEI duties and utilized
5194its independent professional judgement when it documented and monitored
5203the cracks and requested an im mediate structural evaluation by the FIGG
5215EOR.
521658. Ultimately, the bridge collapse was caused by a fundamental design
5227error.
5228T HE OSHA A ND NTSB I NVESTIGATIONS
523659. Shortly after the collapse, both OSHA and NTSB began investigating
5247the causes of the collapse. OHSA completed its investigation and released a
5259written report of its findings in June 2019. 2 The June 2019 OSHA report was
52742 DOT failed to enter into evidence the OSHA report on which it relies. However, prior to the
5292final hearing, DOT filed a Motion for Judicial Notice of Reports Issued by Federal Agencies
5307Concerni ng the FIU Bridge Collapse ( " Motion " ). The Motion was opposed by BPA on the
5324basis that the first OSHA report was not final because a second report was issued, and is
5341hearsay. By Order dated January 24, 2020, the undersigned officially recognized both the
5354issued without prior review or comments from all party members who
5365willingly cooperated with and were involved in the investigation , including
5375NTSB and BPA. OSHA released an amended report on the collapse of the
5388FIU Bridge p roject in July 2019; however, none of the amendments in the
5402report pertained to the ac tions of BPA on the FIU Bridge p roject. NTSB
5417completed its investigation and issued its report in October 2019.
542760. Significantly, no evidence was presented at the final hearing regarding
5438from whom either agency conducted the investigations or drafted the reports,
5449the qualifications or expertise of the investigators, the methodolog y used in
5461the investigations, or the ability of any of the participants in the
5473investigation to rebut the findings or conclusions.
548061. BPA willingly participated in both the OSHA and NTSB
5490investigations, working with investigators and providing them with
5498i nformation, photographs, and details on the FIU Bridge p roject. Both OSHA
5511and NTSB also conducted interviews of BPA personne l involved with the FIU
5524Bridge p roject as part of their investigations.
553262. In its report, OSHA found that BPA failed to classify t he concrete
5546cracks, which were structural in nature, in accordance with DOT
5556requirements. OSHA determined that BPA, as CEI, was expected to exercise
5567its own independent professional judgment in accordance with their contract
5577with FIU and DOT requirements. With intimate knowledge of extensive
5587i nitial OSHA report and the NTSB report. Accordingly, references to the report in this
5602Recommended Order are based upon the official recognition.
5610As noted in the O rder on the Motion, official recognition of the OSHA and NTSB reports,
5627however, does no t make the statements contained therein automatically admissible. " The
5639distinction between noticing the contents of a record and noticing the truth of the contents
5654resembles the distinction in the hearsay doctrine between offering an out - of - court statement
5670simply to show it was said, and offering it for the truth of the matter asserted. " C. Ehrhardt,
5688Florida Evidence § 201.1 (2011 Edition)(quoting Wright & Graham, Federal Practice and
5700Procedure: Evidence § 6337). Although the existence of the report and its findings were
5714officially recognized, the greater weight of the evidence supports that the contents were not
5728accurate as to the exercise of independent judgment of BPA.
5738cracking on the bridge, BPA failed to recognize the bridge was in danger of
5752collapsing, and did not recommend to FIU, MCM, or others to close the street
5766and shore the bridge, regardless of the opinion held by the EOR. As a result,
5781OSHA imposed a monetary fine on BPA for its conduct and failure to take
5795appropriate action in the days leading up to the collapse of the main bridge
5809span.
581063. In its October 2019 report (issued after the NOID to BPA in this case) ,
5825NTSB found t hat beginning with the cracking identified on February 24,
58372018, the distress in the main bridge span was active, continued to grow, and
5851was well documented by all parties involved in the design, construction, and
5863oversight of the bridge. Neither FIU, MCM, FIGG, nor BPA took
5874responsibility for declaring that the cracks were beyond any level of
5885acceptability and did not meet DOT standards. Further, NTSB concluded
5895that under the terms and conditions of the CEI Contract, BPA had the
5908authority to direct or auth orize partial or complete road closures as
5920necessary, acting in concert with DOT and FIU; however, none acted to close
5933the road under the bridge, contributing to the severity of the impact of the
5947bridge collapse.
5949BPA P OST - C OLLAPSE A CTIVITIES A ND 2018 A PPLI CATION F OR Q UALIFICATION
596764. On May 3, 2018, BPA submitted its Request for Qualification for the
5980July 1, 2018, through June 30, 2019, fiscal year ( " 2018 Application " ). BPAÔs
59942018 Application was for the same Work Groups that would eventually be
6006included in the 2019 Request for Qualification.
601365. Each work category is tied to a distinct job function. There is no
6027relationship or similarity between CEI services (Work Group 10) and the
6038other work groups.
604166. On June 27, 2018, DOT accepted BPAÔs Request for Qual ification in all
6055work categories. In processing the application, the Department did not ask
6066BPA any questions regarding its involvement in the project, offer any
6077criticisms of BPA in response to the application, request to interview any
6089BPA employees, or r aise any concerns at all regarding BPAÔs participation in
6102the project.
610467. From the date of the collapse on March 15, 2018, to December 2018,
6118DOT awarded two contracts to BPA directly for CEI and design services,
6130respectively. During the same period, DOT a llowed BPA to participate as a
6143qualified sub - consultant on one CEI contract, three design contracts, and one
6156traffic task work order contract. During the 2018 - 2019 fiscal year, before
6169DOT attempted to suspend BPAÔs qualifications, BPA was able to win sever al
6182jobs in both the prime and sub - consultant role, including projects in which
6196BPA would be providing CEI services.
620268. In October 2018, approximately seven months after the collapse, BPA
6213applied to change its CEI qualifier from John Bolton to Jose Morale s because
6227John Bolton wanted to retire. DOT approved the request and did not object or
6241raise any concerns with respect to Jose Morales serving as BPAÔs qualifier for
6254CEI services.
625669. On December 19, 2018, nine months after the collapse, DOT expressed
6268conc ern for the first time about BPAÔs role in the bridge project, staffing of
6283current DOT projects, quality assurance/quality control ( " QA/QC " ) plans, and
6294professional liability insurance. DOT sent BPA a " Qualifications Letter of
6304Concern, " stating that it had " serious concerns regarding [BPA]Ôs
6313involvement as the Construction Engineering Inspection consultant on the
6322Florida International University (FIU) pedestrian bridge project[.] " DOT
6330requested in its letter, among other things, " a detailed explanation of t he
6343firmÔs actions on the FIU pedestrian bridge project andÈ any controls or
6355changes in personnel, policies or practices that [BPA] has implemented
6365subsequent to the collapse. "
636970. On December 21, 2018, BPA responded to the Letter of Concern
6381addressing each concern raised by the Department, in detail, including
6391providing a copy of its Certificate of Liability Insurance demonstrating that
6402there was no lapse in professional liability insurance coverage.
641171. On February 12, 2019, DOT responded to BPAÔs correspo ndence dated
6423December 21, 2018, requesting additional detail from BPA relative to its
6434revised QA/QC plan and punctuated the correspondence by stating that DOT
6445would refuse to process any further qualification requests from BPA,
6455including ministerial prequa lification name changes, until the matter was
6465addressed to the DepartmentÔs satisfaction.
647072. Around this time, BPA submitted a request to change its name with
6483DOT to reflect its business name with the Division of Corporations. BPA
6495requested that DOT updat e this information on its website, but DOT refused
6508to process the request due to its concerns with BPAÔs qualifications.
651973. On February 20, 2019, BPA provided further detail regarding the
6530specific policies and procedures that have been implemented to its CEI
6541services. Specifically, BPA provided extensive detail regarding its revised
6550QA/QC plan, which included a section dedicated to Category II type bridge
6562structures and included a copy of the revised QA/QC program for DOT
6574review. DOT never responded or req uested any additional information in this
6586regard.
658774. On March 15, 2019, one year to the day after the collapse, DOT issued
6602a Notice of Intent to Suspend BPAÔs existing certificate of qualifications. DOT
6614attempted to suspend BPAÔs qualifications in all Wor k Groups and declare
6626BPA non - responsible for a period of one year for good cause. DOT further
6641claimed that BPA " failed to adequately address the DepartmentÔs concerns
6651regarding the firmÔs performance of the contract, and the [BPA] staff directly
6663involved w ith the FIU project who continue to work on other Department
6676structural contracts. " No further explanation was provided as to how BPA
6687failed to address these concerns.
669275. BPA timely responded to the Notice of Intent to Suspend by way of a
6707Notice of Contes t, requesting an administrative hearing on the issues raised
6719therein. Despite the Notice of Contest, DOT suspended BPAÔs qualification,
6729and sent written notice to its various offices stating, among other things, that
6742BPA had been removed from DOTÔs prequal ification list. Ultimately, DOT
6753reinstated BPAÔs qualifications, but never formally withdrew the Notice of
6763Intent to Suspend.
676676. However, in reinstating BPAÔs qualifications, DOT neglected to
6775reinstate BPAÔs Small Business Enterprise ( " SBE " ) designation, which
6785negatively affected BPAÔs ability to obtain points for SBE participation. The
6796points add value in scoring competing responses to Requests for Proposals for
6808DOT contracts. BPA repeatedly requested that this be corrected. BPAÔs
6818requests went largely ig nored for nearly two months.
682777. On April 2, 2019, after BPA had an in - person meeting with
6841Courtney Drummond , DOT's Assistant Secretary of Engineering and
6849Operations, BPA submitted a qualifications modifications package to replace
6858Jose Morales, P.E. , with John Bolton, P.E., as the qualifier for the CEI Work
6872Group to address Mr. Drummond's and DOTÔs concerns about BPA staff
6883involved on the FIU project working on other DOT contracts.
689378. On April 5, 2019, in response to the Notice of Intent to Suspend, BPA
6908pr ovided specific facts in support of BPAÔs proper performance of the CEI
6921Contract. As an accommodation to DOT, BPA further proposed a solution to
6933DOT's concern about the staff involved in the FIU project. BPA stated that it
6947was " willing to immediately remov e the BPA staf f directly involved in the
6961FIU B ridge project from working on any Department contracts or qualifying
6973the company for CEI services " and resubmitted its qualifications application
6983with those changes.
69862019 B PA R EQUEST FOR Q UALIFICATION R EJECTION
699679. On May 7, 2019, BPA submitted its 2019 Request for Qualification to
7009the Department early due to the lack of response from DOT on BPA's April 5,
70242019 , correspondence. BPA sought qualifications for design work and CEI
7034services in the same work categorie s it was qualified in for the prior fiscal
7049year.
705080. On June 10, 2019, BPAÔs counsel met with DOT representatives in
7062Tallahassee to discuss several outstanding issues relative to BPAÔs current
7072qualification, the upcoming renewal, and DOTÔs failure to reins tate BPAÔs
7083SBE designation. DOT responded by promising to correct the " mistake " that
7094same day. Inexplicably, it took another two weeks and several reminders
7105from BPA for DOT to finally correct the SBE designation.
711581. BPAÔs 2018 - 2019 qualifications expired on June 30, 2019. The next
7128day, on July 1, 2019, DOT untimely responded to BPAÔs Request for
7140Qualification with a letter titled " Incomplete Renewal Applications for Pre -
7151Qualification. " DOT's letter raised the same concerns regarding BPAÔs
7160involvement in t he bridge project and, again, requested " a detailed
7171explanation of BPAÔs actions on the FIU pedestrian bridge project andÈany
7182controls or changes in personnel, policies or practices that BPA has
7193implemented subsequent to the collapse. " This is the same req uest that had
7206been previously made by DOT in its December 19, 2018, Qualifications Letter
7218of Concern, February 12, 2019, Qualifications Letter of Concern, March 15,
72292019 , Notice of Intent to Suspend, and April 26, 2019 , denial of BPAÔs
7242Submittal for Modifi cation.
724682. BPA had already provided the information requested several months
7256prior to DOT's July 1, 2019, correspondence.
726383. On July 11, 2019, DOT issued its Notice of Intent to Deny Request for
7278Qualification directed to BPAÔs 2019 Request for Qualificat ion. In issuing its
7290denial of BPAÔs Request for Qualification, DOT relied solely on the findings
7302and conclusions of the June 2019 OSHA Report as they relate to the CEI
7316services provided by BPA on the project and referenced the pending NTSB
7328investigation.
73298 4. The DepartmentÔs Notice of Intent to Deny was executed by
7341William Watts, the DepartmentÔs Chief Engineer. Mr. Watts admitted at
7351final hearing that he does not have the training or experience necessary to
7364evaluate a CEIÔs performance on a CEI contract. M oreover, neither Mr. Watts
7377nor DOT retained or consulted with any individuals with CEI expertise prior
7389to issuing the Notice of Intent to Deny. When he issued the Notice of Intent to
7405Deny, Mr. Watts was completely unfamiliar with the following: the terms o f
7418BPAÔs CEI Contract; BPAÔs Request for Qualification; BPAÔs past
7427performance on CEI or any other Department contract; and BPAÔs
7437professional reputation.
743985. Mr. Watts did not evaluate BPA under the criteria required by Florida
7452Statute s and the Florida Adm inistrative Code prior to denying BPAÔs
7464Request for Qualification for good cause. Mr. Watts did not receive any
7476analysis from the DepartmentÔs prequalification staff regarding their
7484evaluation of BPAÔs application under the statutory criteria.
749286. Mr. Watt s admitted that he was aware that BPA documented the
7505cracking on the bridge, reported the cracking to the design - build firm, and
7519requested an EAR from the EOR -- actions which were all in accordance with
7533BPA's obligations as CEI pursuant to the CPAM and its contractual
7544obligations with FIU.
754787. Mr. WattsÔ only reason for issuing the Notice of Intent to Deny, as
7561Chief Engineer for DOT, was because BPA was under investigation by OSHA
7573and the NTSB, and OSHAÔs release of its June 2019 Report. However,
7585Mr. Watts d id not know the author of the June 2019 OSHA Report, whether
7600the author of the report was qualified to evaluate the performance of a CEI
7614under Florida Statutes and the Florida Administrative Code, or whether the
7625author of the OSHA report did anything to ev aluate BPAÔs performance
7637relative to any other CEI, at the same time, and/or in the same community.
765188. DOT did not investigate the structure or organization of BPA to
7663determine whether the issues raised in the OSHA report, regarding BPAÔs
7674performance of t he CEI Contract, would reflect negatively on other groups or
7687divisions within BPA that provided services exclusively under other non - CEI
7699work categories (design services).
770389. Prior to issuance of the NOID, M r . Watts did not undertake a review
7719of BPA Ô s pas t performance or professional reputation -- both of which were
7734beyond reproach.
773690. DOT evaluates its consultantsÔ performance on all projects
7745approximately every six to eight months. These evaluations produce a score
7756that ranges from one to five, five being the highest possible score. A perfect
7770score of five is uncommon and a score of four is outstanding. In the five years
7786prior to the final hearing, DOT evaluated BPAÔs performance on projects
7797involving both design and CEI services. Specifically, DOT scored BPAÔs
7807performance in Work Groups 3.1, 3.2 (Highway Design), 4.12 (Bridge Design),
78185.1 (Bridge Inspection), 7.2 (Traffic Operations Design), and 10.1 and 10.3
7829(CEI). During that period, BPA averaged a score of outstanding to nearly -
7842outstanding on all projec ts, including outstanding and nearly - outstanding
7853scores for inspection services on bridge rehabilitation projects, which involved
7863cracking concrete elements.
786691. In May of 2019, prior to denying BPAÔs request for qualifications for
7879the fiscal year July 1, 2019 , through June 20, 2020, Mr. Drummond
7891personally presented BPA with an award from the American Council of
7902Engineering Companies ( " ACEC " ) , for excellence in major urban
7912reconstruction. Specifically, the award was for CEI services on the State
7923Road 7 pro ject, and the ACEC recognized two - and - a - half - years of excellence
7942in CEI services from late - 2016/early - 2017 through 2019. DOT's District
7955Construction Engineer, District 6 Secretary, and Headquarters were
7963intimately involved in the selection and vetting proc ess that, ultimately,
7974resulted in BPA receiving the award.
798092. In September 2019, after denying its request and three months after
7992the release of the June 2019 OSHA Report, DOT voted that BPA receive
8005another award for excellence in CEI services. As a membe r of the selection
8019committee, DOT chose BPA to receive an award from the Florida
8030Transportation Builders Association ( " FTBA " ) , for excellence on the BakerÔs
8041Haulover Bridge rehabilitation project. By this award, FTBA and DOT
8051recognized BPAÔs excellence in CEI services, which spanned from one year
8062before the collapse to one year after the collapse.
8071The Experts 3
8074a. Gustavo Quesada, P.E.
807893. At the Final Hearing, BPA presented the expert testimony of Gustavo
8090Quesada, P.E., a CEI with over 30 years of experience. The ALJ finds that
8104Mr. Quesada is a qualified expert on the standard of care for a CEI and his
8120opinions in that regard are based on competent substantial evidence.
813094. As explained by Mr. Quesada, the role of a CEI with respect to cracks
8145in concrete is to identify the cracks and make sure they do not go unseen or
8161undetected and that an EOR is engaged for purposes of addressing the
8173cracking. Pursuant to the CPAM, when a CEI encounters cracks in concrete,
8185a CEI is required to document the obser vation and make a disposition on the
8200cracks based on Section 400 of the Standard Specifications. Moving forward,
8211the CEI is also required to monitor any changes in the cracks. A CEI is not
8227responsible for making a determination as to whether a crack is pot entially
8240dangerous. This is a determination for the EOR , who has an understanding of
8253the structure, its design, and how the structure is expected to behave. A CEI
8267is not charged with making judgment calls on the design of a structure or
8281whether its integri ty has been jeopardized.
828895. BPA documented, monitored, and reported the cracks on the project in
8300compliance with the industry standards for CEIs working on Complex
8310Category II Bridges, as well as the relevant sections of the CPAM and
8323Section 400 of the St andard Specifications. BPAÔs Senior Project Engineer,
8334Mr. Morales, exercised his independent professional judgment in elevating
83433 DOT intended to offer Mr. Watts at hearing as an expert to testify to the " good cause " DOT
8362had when issuing the NOID to BPA. BPA filed a Motion in Limine to exclude or limit the
8380testimony of both Mr. Watts and Mr. Robertson. The motion was argued at the outset of the
8397final hearing. The undersigned precluded Mr. Watts from testifying as an expert in the field
8412of CEI. Mr. Watts was allowed to testify as to DOT's qualification process and did so as a fact
8431witness, rather than an expert.
8436the issue of the cracks to the EOR even before he was required to do so under
8453the CPAM and Section 400 of the Standard Specifica tions.
846396. At the meeting called by BPA on the morning of March 15, 2018, BPA
8478exercised its independent professional judgment and complied with the
8487applicable standard of care when Mr. Morales asked the EOR a series of
8500questions in response to the EORÔs pr esentation and evaluation of the cracks
8513on the bridge.
851697. According to Mr. Quesada, professional engineers are expected to rely
8527on other engineers with superior or specialized knowledge when exercising
8537their independent professional judgment. BPAÔs role, responsibilities, and
8545scope of work on the project as the CEI was largely that of a contract
8560administrator, and a liaison between FIU and MCM -- not as a structural
8573engineer with the capability to analyze the structural behavior of the bridge
8585sufficient to d etermine if the cracks posed any danger of collapse.
8597b. Robert V. Robertson, P.E.
860298. DOT presented the testimony of Robert V. Roberson as an expert on
8615the standard of care for CEIs. Mr. Robertson has served as DOT's State
8628StructureÔs Design Enginee r for 13 years. Mr. Robertson has been a
8640professional engineer for 35 years.
864599. Although preliminarily accepted by the undersigned as an expert in
8656this field, it became apparent through cross - examination that Mr. Robertson
8668has no significant CEI experie nce. Mr. Robertson has not worked in the CEI
8682industry in the last 26 years, nor has he ever graded a CEIÔs performance.
8696Mr. Robertson was not involved in the DepartmentÔs evaluation of BPAÔs
8707performance of the CEI Contract. Accordingly, Mr. Robertson's tes timony was
8718of limited value.
8721100. Mr. Robertson acknowledged that the FIU bridge was a complex
8732concrete bridge structure that required a separate design qualification and
8742that BPA did have such qualification. Mr. Robertson admitted that BPAÔs
8753contract with FIU did not require BPA to be qualified to inspect complex
8766concrete bridges because BPA was allowed to satisfy that particular
8776qualification requirement of the contract through a sub - consultant
8786(Corradino).
8787101. Mr. Robertson testified that any licensed e ngineer with a college
8799degree in engineering should have known, based on the photographs in Crack
8811Report #3, that the cracks were dangerous and should have acted to stop
8824work on the project and close the road. However, DOT's LAP representative
8836at the March 15, 2018, meeting held prior to the bridge collapse, Mr. Reyna, a
8851licensed professional engineer with a college degree in engineering, failed to
8862raise any concerns at the March 15 th meeting or act to cease bridge work,
8877shore the bridge, or close Southwest 8 th Street under the bridge.
8889102. Mr. Robertson opined that the re - tensioning operation of the bridge
8902should have been peer reviewed. In his opinion, BPA failed to use sufficient
8915independent judgment. BPA, as the CEI, should have recognized the bridge
8926was in danger and known to stop traffic and shut down the road. However,
8940Mr. Roberston admitted that he did only a cursory review of the PowerPoint
8953presentation provided on the morning of March 15, 2018, in which FIGG, as
8966the EOR, stated it had no safety conc erns.
8975103. Mr. Robertson stated that he performed no analysis on anything
8986other than BPA ' s CEI work relative to the FIU bridge. He had no information
9002about BPA ' s design group or its qualification in any work category. However,
9016he suggested the denial of BP A ' s application for qualification across the
9030board, in all work categories because he questioned " the culture at BPA. "
9042Significantly, concerns regarding " the culture " of BPA was not cited by DOT
9054as a basis for the NOID.
9060104. Most significantly, Mr. Robert son testified that six months prior to
9072the issuance of the NOID, he had a conversation with Mr. Drummond during
9085which Mr. Drummond recommended that the qualification of all parties
9095involved with the FIU Pedestrian Bridge project should be suspended.
9105Import antly, this was prior to the issuance of either the OSHA or NTSB
9119reports and seemingly with no analysis of the role of any party to the possible
9134prevention of the bridge collapse, injuries, or loss of life.
9144Ultimate Findings of Fact
9148105. DOT failed to demo nstrate that BPA, as the CEI, fell below the
9162standard of care by failing to exercise its independent professional judgment
9173by not acting to cease bridge work, shore the bridge, or close Southwest 8 th
9188Street under the bridge in light of the documented crack ing on the structure
9202in the days leading up to the collapse.
9210106. The evidence shows that BPA documented, monitored, and reported
9220the cracks pursuant to the CPAM, Section 400 of the Standard Specifications,
9232and industry standards. BPA involved the EOR in evaluating the cracks even
9244before it was required by the CPAM, Section 400 of the Standard
9256Specifications, and industry standards. BPA was assured time and again by
9267the EOR that the bridge did not pose a danger to the travelling public and
9282that the structu re was safe. At the meeting on the morning of March 15,
92972018, BPA inquired as to whether temporary shoring was needed , and the
9309suggestion was rejected by the EOR who had inspected the cracks on the
9322structure just moments before the meeting. There is no evi dence that BPA
9335deviated from the standard of care for CEIs on design - build projects or that
9350BPA failed to exercise its independent professional judgment. To the
9360contrary, BPA met all of its obligations pursuant to contract and state
9372regulation.
9373107. DOT fa iled to demonstrate that BPA, as the CEI, fell below the
9387standard of care by failing to exercise independent professional judgment by
9398not acting to cease bridge work, shore the bridge, and close Southwest 8th
9411Street under the bridge pending a peer review o f the re - tensioning plan
9426proposed by the EOR at the March 15 th meeting.
9436108. At the March 15 th meeting, BPA was reasonably convinced by the
9449EOR that the structure was safe and that the re - tensioning plan was a
9464temporary measure that should be implemented a s soon as possible. BPA had
9477already engaged the EOR to prepare an EAR to address the cracking
9489observed on the bridge, which would have included signed and sealed
9500calculations and a repair protocol that would have been implemented in a
9512later phase of constr uction. On March 15, 2018, the cracks were not a safety
9527concern such that BPA should have overridden the EORÔs directive to MCM
9539and required that the re - tensioning operation be postponed pending a peer -
9553review of the re - tensioning plan. There is no evidence in the record that BPA
9569deviated from the standard of care for CEIs on design - build projects or
9583allegedly failed to exercise its independent professional judgment by allowing
9593the re - tensioning procedure to proceed as directed by the EOR. Conversely,
9606the ev idence supports a finding that BPA acted appropriately in relying on
9619the recommendations of the EOR who was uniquely qualified to evaluate the
9631safety of the structure and who had specialized knowledge of its design.
9643109. DOT failed to demonstrate that BPA, as the CEI, fell below the
9656standard of care by failing to exercise independent professional judgment by
9667not acting to cease bridge work, shore the bridge, and close Southwest 8th
9680Street under the bridge until the Corradino Group could arrive on the projec t
9694site to observe the re - tensioning operation proposed by the EOR during the
9708meeting on March 15, 2018. CorradinoÔs role on the project was to monitor
9721and document post - tensioning operations. By the time the meeting was over,
9734MCMÔs specialty contractor, VS L , was mobilized and prepared to proceed
9745with the re - tensioning operation. BPA was not involved in the pre -
9759coordination of this work. Ultimately, the bridge collapsed due to an inherent
9771design error in the plans and not due to CorradinoÔs absence from the re -
9786tensioning operations.
9788110. The findings of the OSHA report and the pendency of the NTSB
9801investigation , standing alone , were insufficient " good cause " for DOT to deny
9812BPAÔs 2019 Request for Qualification.
9817C ONCLUSIONS OF L AW
9822111. DOAH has jurisdiction over the parties to and the subject matter of
9835this proceeding. §§ 120.569 and 120.57, Fla. Stat.
9843112. A hearing involving disputed issues of material fact under
9853section 120.57(1) is a de novo proceeding, and the agencyÔs initial action
9865carries no presumpti on of correctness. See § 120.57(1)(k) , Fla. Stat . ; Moore v.
9879State, Dep Ô t. of HRS , 596 So. 2d 759 (Fla. 1st DCA 1992); Fla . Dep Ô t. of
9899Trans p . v. J. W. C. Co ., 396 So. 2d 778 (Fla. 1st DCA 1981).
9916113. " The general rule is that a party asserting the affirmati ve of an issue
9931has the burden of presenting evidence as to that issue. " DepÔt of Banking &
9945Fin., Div. of Sec. & Inv'r Prot. v. Osborne Stern & Co. , 670 So. 2d 932, 934
9962(Fla. 1996)(quoting Osborne Stern & Co. v. DepÔt of Banking and Fin ., 647 So.
99772d 425 (Fl a. 1 st DCA 1994)(Booth, J. concurring and dissenting)); Fla . Dep Ô t
9994of Transp . v. J.W.C. Co . , 396 So. 2d 778 (Fla. 1st DCA 1981).
10009114. " [W]here [an] agency proposes to deny the license because the
10020applicant is unfit, it has the burden to prove the applicant Ôs unfitness. " Fla.
10034DepÔt of Child . and Fams . v. Davis Fa m. Day Care Home , 160 So. 3d 854, 857
10053(Fla. 2015)(citing Osborne Stern , 670 So.2d at 934 ( " [T]he Department had
10065the burden of presenting evidence that appellants had violated certain
10075statutes and wer e thus unfit for registration. " ).
10084115 . In this case, the Department is asserting the affirmative, namely,
10096that it had good cause to deny BPAÔs Request for Qualification due to the
10110findings in the June 2019 OSHA Report as they relate to BPAÔs CEI services.
10124116. To the extent that denial of PetitionerÔs application for qualification
10135is akin to denial of a renewal of a license, the Department bears the burden of
10151proving good cause for denying renewal by " clear and convincing evidence. "
10162See Coke v. DepÔt of Chi ld . & Fam . Servs. , 704 So. 2d 726, 726 (Fla. 5th DCA
101821998)(Department " had the burden of proving [ p etitionerÔs] lack of
10193entitlement to a renewal of her license and that the evidence needed to be
10207clear and convincing. " )(citing Osborne Stern , 670 So. 2d at 9 33; Dubin v.
10221Dep Ô t. of Bus . Reg ., 262 So. 2d 273 (Fla. 1st DCA 1972)). 4 Otherwise, the
10240Department bears the burden of proving good cause by a " preponderance of
10252the evidence. " See § 120.57(1)(j), Fla. Stat. ( " Findings of fact shall be based
10266upon a preponder ance of the evidence, except in penal or licensure
10278disciplinary proceedings or except as otherwise provided by statute, and shall
10289be based exclusively on the evidence in the record and on matters officially
10302recognized. " ).
10304117. In Florida Department of Chil dren and Families v. Davis Family Day
10317Care Home , 160 So. 3d 854 (Fla. 2015), the Florida Supreme Court recognized
10330that the preponderance of the evidence burden of proof, not the clear and
10343convincing burden, is applicable to initial license application proc eedings.
10353Id. at 857. The Court explained that although it had not previously addressed
10366the situation where an agency erroneously references its disciplinary
10375authority in the context of noticing its intent to deny an initial license
10388application, " it is the nature of the agency's action and the underlying rights
10401implicated by the action that govern the applicable evidentiary standard[.] "
10411Id. In reaching its conclusion, the Davis Family court reaffirmed its holding
10423in Department of Banking and Finance v. Osbor ne Stern and Company ,
10435where the court distinguished cases involving denials of initial applications
10445(in which the Department must prove good cause for the denial by a
" 10458preponderance of the evidence " ) from cases involving revocations or denials
10469of renewal a pplications (which the Department must prove good cause for the
10482denial by " clear and convincing evidence " ). See Davis Family , 160 So. 3d at
10496856 (citing Dep't of Banking & Fin., Div. of Sec. & Inv'r Prot. v. Osborne
10511Stern & Co ., 670 So. 2d 932, 933 (Fla. 19 96) ) .
105254 At the Final Hearing, counsel stipulated that the burden of proof was a preponderance of
10541the evidence. (T. 129) However, " [i]t is well settled that a court is not bound to accept as
10559controlling stipulations as to questions of law[.] " Alvarez v. Smith , 714 So. 2d 652, 653
10574(Fla. 5 th DCA 1998)( quoting Clark v. Munroe , 407 So. 2d 1036, 1037 (Fla. 1st DCA 1981)
10592( " T he parties cannot by stipulation control questions of law. " )). The DepartmentÔs burden of
10608proving that it had good cause to deny BPAÔs Request for Qualification is by clear and
10624convincing evidence.
10626118. This is a renewal case (like Ferris and Coke ) -- not an initial
10641application case (like Davis Family and Osborne Stern ). Here, BPA had been
10654prequalified with the Department for the last 20 years. In May 2019, BPA
10667attempted to renew its qualificatio ns for the same Work Groups as the
10680previous fiscal year. DOT relied on the disciplinary section of the Florida
10692licensing statute as grounds to support its denial of BPAÔs renewal. DOTÔs
10704action is disciplinary in nature and subject to the clear and convinci ng
10717standard.
10718119. In denying BPAÔs Request for Qualification, DOT relied on
10728s ection 287.055 and Florida Administrative Code Chapter 14 - 75 . DOT cited
10742no other authority in its Notice of Intent to Deny.
10752120. As described above, section 287.055(3) requires th at any firm or
10764individual desiring to provide professional services to a governmental agency
10774must first be certified by the agency as qualified pursuant to law and the
10788regulations of the agency.
10792121. Rule 14 - 75.0022(4), entitled " Consultant Qualification P rocess , "
10802provides, in pertinent part, as follows:
10808(b) Upon receipt of a complete application the
10816Department shall make such inquiries and
10822investigations as deemed necessary to verify and
10829evaluate the applicant's statements and determine
10835competency for qual ification.
10839(c) Information which the Department shall
10845consider in determining whether a consultant is
10852qualified to perform the types of work shall include:
108611. Current license or registration as regulated by
10869the State of Florida or national organizations, as
10877appropriate.
108782. Personnel with appropriate experience and
10884training as detailed in the type of work
10892qualifications.
108933. Registration with the Florida Department of
10900State, if the applicant is a corporation or limited
10909partnership.
109104. Past performance on Department contracts.
109165. Integrity and responsibility, which shall include
10923history of debarment or suspension from
10929consideration for work with any other
10935governmental entity.
10937122. Rule 14 - 75.0051(1), entitled " Revocation, Denial, or Suspension of
10948Qualifi cation, " provides in part that " the Department will, for good cause,
10960deny or suspend the qualification of any professional consultant, or other
10971provider of service, to render services to the Department. " " Good cause "
10982includes instances where the consultant 's work performance in one of the
10994work types is not satisfactory. Unsatisfactory performance shall result in
" 11004revocation, denial, or suspension of qualifications for that type of work for a
11017period not to exceed one year. "
11023123. Rule 14 - 75.0051(1)(c), furthe r provides that good cause also includes
" 11036any other good cause, as defined in Section 337.105(1), F.S., established by
11048the factual circumstances. "
11051124. Section 471.033, Florida Statutes , and Florida Administrative Code
11060C hapter 61G15 - 19 establish es the grou nds for disciplinary proceedings
11073against licensed professional engineers in Florida. Under section 471.033,
11082engaging in negligence or misconduct in the practice of engineering, or
11093otherwise violation of chapter 455 , Florida Statutes, are grounds for
11103discip linary action against the status of a professional engineerÔs license with
11115the State of Florida. Under section 455.227(1)(o), performing professional
11124responsibilities the licensee knows, or has reason to know, they are not
11136competent to perform constitutes grounds for disciplinary action against the
11146status of a professional engineerÔs license with the State of Florida. 5
11158125. There is no evidence that BPA deviated from the standard of care for
11172CEIs on design - build projects or that BPA failed to exercise its i ndependent
11187professional judgment regarding the FIU Bridge project.
11194126. The record is devoid of any evidence that DOT examined any of the
11208criteria listed in r ule 14 - 75.0022(4) to determine if BPA met qualification
11222standards for 2019.
11225127. For " good cause , " DOT relies entirely on the OSHA Report . The
11238statements and opinions contained in the OSHA report are hearsay, and the
11250author of the report was not called to testify as an expert and was not subject
11266to cross - examination.
11270128. Absent from the OSHA report was any reference to BPA's design
11282services because BPA had no design responsibility for the project. Yet it is
11295this very document DOT relies on to deny BPA's request for qualification in
11308all work groups, including those exclusively related to design, rathe r than
11320CEI, work.
11322129. It is undisputable that the bridge collapse was a horrific tragedy with
11335long term consequences to the community, the victims, and those involved
11346with the project , including BPA and DOT. Understandably, it was politically
11357expedient fo r DOT to disqualify those entities that worked on the FIU Bridge
11371p roject. However, the plain language of the applicable statutes and
11382regulations required DOT to engage in an analysis of BPA's 2019 Request for
11395Qualification application. That analysis simply did not occur.
114035 Florida Administrative Code Rule 61G15 - 19.001(6), define s the term " misconduct " as used
11418in section 471.003 in part, as " [p]erforming an engineering assignment when not qualified by
11432training or experience in the practice area involved. " Although the Department cited
11444r ule 61G15 - 19.001(6) in its Pre - Hearing Statem ent, none of the three instances of BPAÔs
11463alleged failure to exercise its independent professional judgment include an allegation that
11475BPA undertook activities or services outside of its training or experience. This issue was not
11490plead or framed by the Dep artmentÔs Pre - Hearing Statement. At the Final Hearing, BPA
11506contemporaneously objected to the presentation of evidence on this unpled theory that BPA
11519allegedly performed services it was not prequalified to perform.
11528130. Under either a preponderance of the evidence, or by a clear and
11541convincing evidentiary standard, DOT did not meet its burden with respect to
11553the issues framed by its Pre - Hearing Statement and Notice of Intent to Deny.
11568R ECOMMENDATION
11570Based on the foregoing Findings of Fact and Conclusions of Law, it is
11583R ECOMMENDED that a Final Order be entered by the Department of
11595Transportation finding that good cause does not exist to deny BPAÔs 2019
11607Request for Qualification.
11610D ONE A ND E NTERED this 17th day of April , 2020 , in Tallahassee, Leon
11625County, Florida.
11627S
11628M ARY L I C REASY
11634Administrative Law Judge
11637Division of Administrative Hearings
11641The DeSoto Building
116441230 Apalachee Parkway
11647Tallahassee, Florida 32399 - 3060
11652(850) 488 - 9675
11656Fax Filing (850) 921 - 6 847
11663www.doah.state.fl.us
11664Filed with the Clerk of the
11670Division of Administrative Hearings
11674this 17th day of April , 2020 .
11681C OPIES F URNISHED :
11686George Spears Reynolds, IV, Esquire
11691Florida Department of Transportation
11695605 Suwannee Street , Mail Stop 58
11701Tallaha ssee, Florida 32399 - 0450
11707(eServed)
11708Scott Kirschbaum, Esquire
11711Cole, Scott & Kissane, P.A.
117169150 South Dadeland Boulevard , Suite 1400
11722Miami, Florida 33156
11725Anthony Lopez, Esquire
11728Cole, Scott & Kissane, P.A.
117339150 South Dadeland Boulevard , Suite 1400
11739Miami, Florida 33156
11742George Richard Truitt, Esquire
11746Cole, Scott & Kissane, PA
117519150 South Dadeland Boulevard , Suite 1400
11757Miami, Florida 33156
11760(eServed)
11761John Ashley Peacock, Esquire
11765Department of Transportation
1176860 5 Suwannee Street , Mail Stop 58
11775Tallahassee, Flo rida 32399 - 045 0
11782(eServed)
11783Andrea Shulthiess, Clerk of
11787Agency Proceedings
11789D epartment of T ransportation
11794Haydon Burns Building
11797605 Suwannee Street, M ail S top 58
11805Tallahassee, Florida 32399 - 0450
11810(eServed)
11811Erik Fenniman, General Counsel
11815D epartment of T rans portation
11821Haydon Burns Building
11824605 Suwannee Street, M ail S top 58
11832Tallahassee, Florida 32399 - 0450
11837(eServed)
11838Kevin J. Thibault, P.E., Secretary
11843D epartment of T ransporation
11848Haydon Burns Building
11851605 Suwannee Street, M ail S top 57
11859Tallahassee, Florida 32399 - 0 450
11865(eServed)
11866N OTICE OF R IGHT T O S UBMIT E XCEPTIONS
11877All parties have the right to submit written exceptions within 15 days from
11890the date of this Recommended Order. Any exceptions to this Recommended
11901Order should be filed with the agency that will issue th e Final Order in this
11917case.
- Date
- Proceedings
- PDF:
- Date: 04/17/2020
- Proceedings: Recommended Order cover letter identifying the hearing record referred to the Agency.
- PDF:
- Date: 04/17/2020
- Proceedings: Recommended Order (hearing held February 13, 14, and 17, 2020). CASE CLOSED.
- PDF:
- Date: 03/13/2020
- Proceedings: Respondent Florida Department of Transportation's Proposed Recommended Order filed.
- PDF:
- Date: 03/12/2020
- Proceedings: Amended Unopposed Motion to Extend Time Period to File Proposed Recommended Orders filed.
- PDF:
- Date: 03/11/2020
- Proceedings: Unopposed Motion to Extend Time Period for Petitioner to File Its Proposed Recommended Order filed.
- PDF:
- Date: 02/27/2020
- Proceedings: Joint Motion to Extend Time Period for Parties to File Proposed Recommended Orders filed.
- Date: 02/26/2020
- Proceedings: Transcript of Proceedings (not available for viewing) filed.
- Date: 02/13/2020
- Proceedings: CASE STATUS: Hearing Held.
- PDF:
- Date: 02/12/2020
- Proceedings: Network Engineering Services, Inc. d/b/a Bolton Perez and Associates Objections to Florida Department of Transportation's Notice of Filing Deposition Designations for Final Hearing filed.
- PDF:
- Date: 02/12/2020
- Proceedings: Motion in Limine to Exclude or, in the Alternative, Limit Expert Testimony filed.
- PDF:
- Date: 02/12/2020
- Proceedings: Petitioner's Motion for Leave to Have Witness Testify Out-of-Order and Through Video Teleconference at Final Hearing filed.
- PDF:
- Date: 02/12/2020
- Proceedings: Response in Opposition to Respondent's Motion in Limine to Exclude Petitioner's Expert Witness filed.
- PDF:
- Date: 02/11/2020
- Proceedings: Department's Motion in Limine to Exclude Petitioner's Expert Witness filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 10) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 9) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 8) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 7) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 6) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 5) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 4) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 3) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: FDOT Notice of Filing Deposition Designations for Final Hearing (Part 2) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: Florida Department of Transportation's Notice of Filing Deposition Designations for Final Hearing (Part 1) filed.
- PDF:
- Date: 02/11/2020
- Proceedings: Department's Motion in Limine to Exclude Petitioner's Expert Witness filed. (FILED IN ERROR)
- PDF:
- Date: 02/11/2020
- Proceedings: Florida Department of Transportation's Objections to Bolton Perez and Associates' Amended Exhibit List for Final Hearing filed.
- PDF:
- Date: 02/10/2020
- Proceedings: Bolton Perez and Associates' Objections/Stipulations to Respondent's Exhibit List for Final Hearing filed.
- PDF:
- Date: 02/10/2020
- Proceedings: Bolton Perez and Associates' Amended Exhibit List for Final Hearing filed.
- PDF:
- Date: 02/07/2020
- Proceedings: Petitioner's Exhibit A to Pre-Hearing Stipulation (Exhibit List) filed.
- PDF:
- Date: 02/05/2020
- Proceedings: Department's Responses to Petitioner's First Request for Production filed.
- PDF:
- Date: 02/05/2020
- Proceedings: Florida Department of Transportation's Notice of Serving Answers to Petitioner's First Set of Interrogatories filed.
- PDF:
- Date: 02/03/2020
- Proceedings: Unopposed Motion for Extension of Time to File Joint Pre-Hearing Stipulation filed.
- PDF:
- Date: 02/03/2020
- Proceedings: Bolton Perez and Associates' Notice of Serving Verified Answers to Florida Department of Transportation's Expert Interrogatories filed.
- PDF:
- Date: 01/23/2020
- Proceedings: Bolton Perez and Associates' Notice of Serving Unverified Answers to Florida Department of Transportation's Expert Witness Interrogatories filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 7) filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 6) filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses filed (Part 5).
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 4) filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 3) filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 2) filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Florida Department of Transportation's Notice of Filing Affidavit and Discovery Responses filed.
- PDF:
- Date: 01/21/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part 2) filed.
- PDF:
- Date: 01/17/2020
- Proceedings: Department of Transportation's Notice of Filing Affidavit and Discovery Responses (Part1) filed.
- PDF:
- Date: 01/17/2020
- Proceedings: Department's Reply to Petitioner's Response to the Department's Motion for Judicial Notice filed.
- PDF:
- Date: 01/17/2020
- Proceedings: Notice of Taking Deposition Duces Tecum (Gustavo "Gus" Quesada) filed.
- PDF:
- Date: 01/14/2020
- Proceedings: Bolton Perez and Associates' Amended Response to Florida Department of Transportation's First Requests for Admission filed.
- PDF:
- Date: 01/14/2020
- Proceedings: Bolton Perez and Associates' Amended Response to Florida Department of Transportation's First Request for Production filed.
- PDF:
- Date: 01/13/2020
- Proceedings: Bolton Perez and Associates' Response to Florida Department of Transportation's First Requests for Admission filed.
- PDF:
- Date: 01/13/2020
- Proceedings: Bolton Perez and Associates' Notice of Serving Answers to Florida Department of Transportation's First Set of Interrogatories filed.
- PDF:
- Date: 01/13/2020
- Proceedings: Bolton Perez and Associates' Response to Florida Department of Transportation's First Request for Production filed.
- PDF:
- Date: 01/10/2020
- Proceedings: Order Granting Respondent's Motion for Leave to File a Reply to Petitioner's Response to the Department's Motion for Judicial Notice.
- PDF:
- Date: 01/09/2020
- Proceedings: Motion for Leave to File a Reply to Petitioner's Response to the Department's Motion for Judicial Notice filed.
- PDF:
- Date: 01/07/2020
- Proceedings: Bolton Perez and Associates' First Request for Production to Department of Transportation filed.
- PDF:
- Date: 01/07/2020
- Proceedings: Notice of Serving First Set of Interrogatories on Respondent filed.
- PDF:
- Date: 01/07/2020
- Proceedings: Response to Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse filed.
- PDF:
- Date: 12/20/2019
- Proceedings: Florida Department of Transportation's Notice of Serving Expert Witness Interrogatories on Petitioner filed.
- PDF:
- Date: 12/06/2019
- Proceedings: Order Granting Continuance and Rescheduling Hearing (hearing set for February 13, 14, 17, and 18, 2020; 9:00 a.m.; Tallahassee).
- PDF:
- Date: 12/04/2019
- Proceedings: Department's Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse (Part 3) filed.
- PDF:
- Date: 12/04/2019
- Proceedings: Department's Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse (Part 2) filed.
- PDF:
- Date: 12/04/2019
- Proceedings: Department's Motion for Judicial Notice of Reports Issued by Federal Agencies Concerning the FIU Bridge Collapse (Part 1) filed.
- PDF:
- Date: 12/04/2019
- Proceedings: Florida Department of Transportation's Notice of Serving First Set of Interrogatories on Petitioner filed.
- PDF:
- Date: 11/22/2019
- Proceedings: Florida Department of Transportation's Motion for Leave to Have Witness Testify Out-of-Order and Through Video Teleconference at Final Hearing filed.
Case Information
- Judge:
- MARY LI CREASY
- Date Filed:
- 09/24/2019
- Date Assignment:
- 09/25/2019
- Last Docket Entry:
- 10/09/2020
- Location:
- Tallahassee, Florida
- District:
- Northern
- Agency:
- ADOPTED IN PART OR MODIFIED
Counsels
-
Thomas L. Hunker, Esquire
Address of Record -
Scott Kirschbaum, Esquire
Address of Record -
Anthony Lopez, Esquire
Address of Record -
Virginia A. Paxton, Esquire
Address of Record -
John Ashley Peacock, Esquire
Address of Record -
George Spears Reynolds, Esquire
Address of Record -
George Richard Truitt, Esquire
Address of Record -
Scott D Kirschbaum, Esquire
Address of Record