87-003338BID Lido Lines, Inc. vs. Lee County School Board
 Status: Closed
Recommended Order on Friday, September 25, 1987.


View Dockets  
Summary: Apparent low bidder non-responsive since its qualifying agent's contractor license was inactive for failure to complete licensure process at bid time.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8LEDO LINES, INC., )

12)

13Petitioner, )

15)

16vs. ) CASE NO. 87-3338B1D

21)

22SCHOOL BOARD OF LEE COUNTY, )

28)

29Respondent. )

31_________________________________)

32RECOMMENDED ORDER

34Pursuant to notice, this cause was heard by Linda M. Rigot, the assigned

47Hearing Officer of the Division of Administrative Hearings, on August 25, 1987,

59in Fort Myers, Florida.

63Petitioner Ledo Lines, Inc., was represented by E. G. Couse, Esquire, Fort

75Myers, Florida; and Respondent School Board of Lee County was represented by

87Harry A. Blair, Esquire, Fort Myers, Florida.

94Respondent invited bids on a project involving grading and drainage

104improvements. After Respondent announced its intention to award the bid to the

116other bidder, Petitioner timely filed this protest pursuant to Section

126120.53(5), Florida Statutes. Accordingly, the issue for determination herein is

136whether Petitioner is the lowest responsible bidder.

143Petitioner presented the testimony of Herbert L. Martin and Warren Hunt.

154Respondent presented the testimony of Herbert L. Martin, Steve Cook, and James

166Paul Elliott. Additionally, Joint Exhibits numbered 1-9 were admitted in

176evidence.

177Although both parties requested leave to submit post hearing Proposed

187findings of fact in the form of proposed recommended orders, only the Petitioner

200did so. Petitioner's Proposed findings of fact numbered 1-3, 6-9, and 11 have

213been adopted in this Recommended Order either verbatim or in substance.

224Petitioner's proposed findings of fact numbered 4, 5, and 10 have been rejected

237as not constituting findings of fact but rather as constituting conclusions of

249law or argument of counsel.

254FINDINGS OF FACT

2571. In June 1987 The School Board of Lee County, Florida invited the

270submission of sealed bids for grading and drainage improvements at the new

282Multipurpose Building at Fort Myers High School. In addition to requiring

293grading, the project involves the erection or placement of structures in the

305nature of a drainage system consisting of culverts, pipes, and concrete inlets

317with grates, to be tied into the existing drainage system off School Board

330property across a county right-of-way into a culvert for discharge across the

342street, and which on School Board property attaches to and becomes a part of an

357existing building.

3592. Sealed bids were submitted by Systems Technologies Co. of Ft. Myers,

371Inc. (hereinafter "Systems Technologies") and by Ledo Lines, Inc. Respondent

382determined Systems Technologies to be the lowest responsible bidder and advised

393Ledo Lines, Inc., that it would be awarding the contract to Systems

405Technologies.

4063. Warren W. Hunt is the president and the qualifying agent of Systems

419Technologies. Hunt has an underground utilities contractor's license which has

429been inactive since it was obtained by him in March, 1986, being inactive

442therefore both at the time that Hunt submitted the bid on behalf of Systems

456Technologies and at the time of the final hearing in this cause. The inactive

470status results from Hunt's failure to complete the license process with the

482State of Florida. Since Hunt's license was inactive due to being incomplete at

495the times material to this cause, neither Hunt nor Systems Technologies was a

508licensed contractor and Systems Technologies was not a responsible bidder at the

520time that the bid was submitted.

5264. The contract specifications set forth the method by which the bids

538would be evaluated. Paragraph numbered 2.9 on page PD-4 provides as follows:

550Comparison of Proposals - Proposals will

556be compared on the basis of total

563computed price for each division of work.

570Total computed price equals the sum of

577the prices for the lump sum Contract

584Item, plus the sum of the total prices

592for the unit price Contract Items for

599each Division of work. The total price

606for each unit price Contract Item will be

614obtained by multiplying the estimated

619quantity of each item by the correspond-

626ing unit price set forth in the Proposal

634form[.]

635That provision, accordingly, requires that the bids be evaluated based upon the

647sum of all line items rather than based only upon their total or "bottom line"

662figure. Respondent's Director of Facilities Planning admitted that he failed to

673comply with this provision of the contract specifications in evaluating the two

685bids submitted to him and in determining that the bid should be awarded to

699Systems Technologies.

7015. In Systems Technologies' bid, the sum of the prices for the lump sum

715contract items plus the sum of the total prices for the unit price contract

729items amounts to $30,109.60. However, in submitting its bid Systems

740Technologies incorrectly added its column of figures and incorrectly computed

750its Total Contract Price (Estimated) to be $29,768. Since the contract

762specifications envision a unit price bid rather than a lump sum bid, the amount

776of the bid of Systems Technologies is in fact the amount of $30,109.60. The bid

792of Ledo Lines, Inc., is for $29,913.84. Ledo Lines, Inc., is, therefore, the

806low bidder on this project.

8116. The contract specifications when read in their entirety clearly require

822that the low bid be determined by adding the unit price and lump sum components

837rather than relying on the lump sum "bottom line" figure shown for Total

850Contract Price (Estimated). Employees of the consultant who Prepared the

860specifications testified that they expect to be able to hold the bidders to the

874unit prices but not to the Total Contract Price (Estimated) because the

886estimated quantities may change. Thus, the evidence is uncontroverted that the

897determination of low bidder pursuant to the contract specifications is based

908upon the total of the unit price provisions and not by the single figure at the

924bottom of the page which adds those individual prices and which was added

937erroneously in this case by Systems Technologies.

9447. In their Prehearing Stipulation, the parties stipulated that the School

955Board is subject to mandatory competitive bidding for this project. They

966further stipulated that where there is mandatory competitive bidding, the

976contract must be awarded to the lowest qualified, responsive bidder. Since

987Systems Technologies is neither a qualified, responsive bidder nor the lowest

998bidder, it is clear that Ledo Lines, Inc., is the lowest responsive bidder for

1012the project in question.

1016CONCLUSIONS OF LAW

10198. The Division of Administrative Hearings has jurisdiction over the

1029subject matter hereof and the parties hereto. Section 120.57(1), Florida

1039Statutes.

10409. It is uncontroverted that the grading and drainage improvements

1050involved in the project under consideration herein require licensure as a

1061contractor by the State of Florida. Section 489.105(3), Florida Statutes. That

1072section further requires that the licensure requirements as a contractor apply

1083not just at the time that the work is performed but also requires that proper

1098licensure exist at the time that the contractor submits a bid. Since neither

1111the corporation nor its qualifying agent possessed appropriate licensure at the

1122time its bid was submitted, Systems Technologies is not a qualified responsive

1134bidder for this project. Although Respondent's Director of Facilities Planning

1144testified that he was willing to waive any licensure requirements so that the

1157bid could be awarded to Systems Technologies, it is doubtful that he has the

1171authority to naive state licensure requirements; even if he could, the contract

1183specifications cannot be amended after the opening of sealed bids.

119310. Respondent argues that Systems Technologies will "use" the license of

1204another contractor. Even if such an arrangement were legal pursuant to Chapter

1216489, Florida Statutes, no provision was made in Systems Technologies' bid for

1228work on, or supervision of, the project by any entity other than Systems

1241Technologies, and its bid cannot be amended after the sealed bids have been

1254opened.

125511. Respondent's argument that it is not required to follow the contract

1267provision which establishes how the bids will be evaluated and that the

1279determination of the winner of the bid is totally discretionary, i.e., that

1291Respondent can award the bid to any one it pleases, is without merit, and is

1306contrary to the applicable law stipulated to by the parties in their Prehearing

1319Stipulation, i.e., that where there is mandatory competitive bidding a contract

1330must be awarded to the lowest qualified, responsive bidder. In this case, not

1343only is Ledo Lines, Inc., the lowest bidder , it is also the only qualified,

1357responsive bidder on this project.

1362RECOMMENDATION

1363Based upon the foregoing Findings of Fact and Conclusions of Law, it is,

1376RECOMMENDED that a Final Order be entered determining Ledo Lines, Inc., to

1388be the lowest responsive bidder and awarding the contract for grading and

1400drainage improvements to the Multi- purpose Building at Fort Myers High School

1412to Ledo Lines, Inc.

1416DONE and RECOMMENDED this 25th day of September, 1987, at Tallahassee,

1427Florida.

1428_________________________________

1429LINDA M. RIGOT, Hearing Officer

1434Division of Administrative Hearings

1438The Oakland Building

14412009 Apalachee Parkway

1444Tallahassee, Florida 32399-1550

1447(904) 488-9675

1449Filed with the Clerk of the

1455Division of Administrative Hearings

1459this 25th day of September, 1987.

1465COPIES FURNISHED:

1467James E. Melvin, Superintendent

1471School Board of Lee County

14762055 Central Avenue

1479Fort Myers, Florida 33901

1483E. G. Couse, Esquire

1487Post office Drawer 1647

1491Fort Myers, Florida 33902

1495Harry A. Blair, Esquire

1499Post Office Box 1467

1503Fort Myers, Florida 33902

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 10/20/1987
Proceedings: Agency Final Order
PDF:
Date: 10/20/1987
Proceedings: Recommended Order
PDF:
Date: 09/25/1987
Proceedings: Recommended Order (hearing held , 2013). CASE CLOSED.

Case Information

Judge:
LINDA M. RIGOT
Date Filed:
08/10/1987
Date Assignment:
08/10/1987
Last Docket Entry:
09/25/1987
Location:
Fort Myers, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
Suffix:
BID
 

Related Florida Statute(s) (3):