89-003259
Florida Public Service Commission vs.
St. Johns North Utilities Corporation
Status: Closed
Recommended Order on Wednesday, June 13, 1990.
Recommended Order on Wednesday, June 13, 1990.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8FLORIDA PUBLIC SERVICE COMMISSION, )
13)
14Petitioner, )
16)
17vs. ) CASE NO. 89-
223259
23)
24ST. JOHNS NORTH UTILITY CORP., )
30)
31Respondent. )
33___________________________________)
34RECOMMENDED ORDER
36Pursuant to notice, this cause came on for formal
45hearing before P. Michael Ruff, duly-designated Hearing
52Officer, on February 12, 1990, in St. Augustine, Florida.
61APPEARANCES
62FOR PETITIONER: David C. Schwartz, Esq.
68Florida Public Service Commission
72Legal Division
74101 E. Gaines Street
78Tallahassee, FL 32399-0850
81FOR RESPONDENT: Joseph E. Warren, Esq.
871930 San Marco Boulevard
91Suite 200
93Jacksonville, FL 32207
96STATEMENT OF THE ISSUES
100The issues in this cause concern whether the
108Respondent, St. Johns North Utility Corp. ("St. Johns"),
118knowingly or willfully failed to comply with Public Service
127Commission Order No. 20409, requiring that entity to
135respond to certain requests for information adopted in that
144Order and to file a request for approval of the charging of
156its customers for the income tax implication of
164contributions-in-aid-of- construction ("CIAC"). That is,
171the Commission takes the position that by that Order, the
181utility was informed of the requirement to file a request
191for permission from the Commission to charge customers so-
200called CIAC "gross-up" charges and failed to do so. The
210other issue to be considered, conjunctively, concerns
217whether a penalty should be imposed against the Respondent
226and, if warranted, in what amount.
232PRELIMINARY STATEMENT
234This cause arose upon the issuance of Public Service
243Commission Order No. 20762, issued on February 17, 1989.
252That Order required the Respondent, St. Johns North Utility
261Corp. ("St. Johns, Utility"), to show cause in writing why
273it should not be fined up to $5,000.00 per day for failure
286to comply with the provisions of Order No. 20409. Order
296No. 20409 had required a written response to certain
305questions posed to the Utility by the Commission concerning
314the existence and specifics of certain "developer
321agreements" regarding the provision of utility services.
328It also required that the Utility submit a written request
338to implement so-called "CIAC gross-up charges". The
346Utility responded to Order No. 20762 with a Motion for
356Rehearing, Reconsideration and for Leave to Amend. That
364Motion was denied by Order No. 21195. However, in
373rendering that Order, the Commission also permitted the
381Utility a Section 120..57, Florida Statutes, formal
388proceeding in order to resolve the issues raised in the
398show cause proceeding initiated by Order No. 20762,
406concerning whether the Utility had willfully failed to
414comply with Order No. 20409 and whether further penalties
423should be assessed and imposed.
428This cause came on for hearing as noticed. At the
438hearing, the Commission presented the testimony of Jerrold
446E. Chapdelaine. The Respondent presented the testimony of
454C.E. Bohannon and Joseph E. Warren. The Petitioner adduced
463five exhibits. Petitioner's Exhibits 1 through 4 were
471admitted into evidence. Respondent's Exhibit 1 was admitted
479into evidence.
481At the conclusion of the proceeding, the parties
489elected to order a transcript thereof and requested an
498extended briefing schedule, which was approved. The
505Commission submitted its proposed findings of fact and
513conclusions of law on a timely basis, and those have been
524specifically ruled upon in the Appendix attached hereto and
533incorporated by reference herein, as well as in the
542Recommended Order itself.
545FINDINGS OF FACT
5481. Pursuant to its authority to regulate water and
557sewer rates, charges and rate structures embodied in
565Chapters 367, Florida Statutes, and 25-30, Florida
572Administrative Code, the Public Service Commission entered
579Orders numbered 16971 and 17058, which adopted specific
587guidelines and conditions for utilities to implement
594certain income tax impact charges for contributions-in-aid-
601of-construction ("CIAC gross-up charges"). (See Orders
609numbered 20409, p.3; 16971, p.2-4; and 17058). One of
618these conditions requires that utilities submit appropriate
625tariff sheets (rates and charges sheets) for the
633Commission's approval prior to implementation of the CIAC
641gross-up charge.
6432. CIAC is the payment or contribution of cash or
653property to a utility from a customer or entity seeking
663service from that utility in order to secure the provision
673of such services or to reserve it for a future time. The
685Internal Revenue Code of 1986 changed the treatment of CIAC
695from being non-taxable to being taxable as income. A CIAC
705gross-up charge is a method by which a utility can recover
716that tax expense, represented by the income tax assessed
725against collected CIAC, through approved rates and charges
733to customers. The amount of CIAC tax impact funds
742collected by a utility is not itself treated as CIAC for
753rate-making purposes.
7553. The Respondent, St. Johns North Utility Corp.,
763collected gross-up charges which were not authorized by its
772filed and approved tariff schedules (rate schedules), and
780without securing the requisite approval from the
787Commission. (See Orders numbered 20409 and 20762). The
795Commission was made aware of the charging of unauthorized
804CIAC gross-up charges by the Utility Respondent when a
813developer, Fruit Cove Limited, communicated with the
820Commission concerning its doubts about utility service
827being available for one of its subdivisions, when required,
836from the Respondent. Fruit Cove Limited had paid CIAC
845gross-up charges to St. Johns. On June 3, 1988, the
855Commission, through its staff, contacted Mr. Joseph E.
863Warren, the General Manager for the Respondent, and
871explained the Commission's requirements regarding the
877requisite pre-approval of the charging of CIAC gross-up
885charges. Mr. Warren agreed to file a written request for
895authorization to implement such charges. No request was
903filed, despite repeated admonitions and solicitations by
910the Commission and its staff and a lengthy opportunity to
920comply.
9214. Finally, Order No. 20409 was issued by the
930Commission on December 5, 1988, requiring the Utility to
939file a written request for authorization to implement CIAC
948gross-up charges within thirty (30) days of that Order. A
958written request was not timely filed, however. The
966Utility finally filed its written request for approval of
975these charges on September 5, 1989. The accompanying
983tariff sheets representing such charges were ultimately
990filed in response to Orders numbered 16971 and 20409, and
1000Show Cause Order No. 20762. They became effective on
1009September 15, 1989.
10125. The Commission, through its staff, also made
1020repeated inquiries to the Utility regarding certain service
1028availability charges and practices, initially by letter of
1036July 29, 1988. The Utility was allowed until August 19,
10461988 to make the requested responses. The letter was
1055addressed to Mr. Joseph Warren at the Utility's mailing
1064address of record. The Utility, however, did not provide
1073written responses to the comments and questions by the
1082Commission, despite repeated assurances that it would do
1090so. Order No. 20409, issued on December 5, 1988, required
1100the Utility to provide the full written responses to the
1110July 29, 1988 letter within thirty (30) days of the date of
1122that Order. The responses were not timely made.
11306. Order No. 20762 was issued on February 17, 1989,
1140requiring the Utility to show cause in writing on or before
1151March 13, 1989 why it should not be fined up to $5,000.00
1164per day, in accordance with the Commission's penalty
1172authority, for failure to comply with the provisions of
1181Order No. 20409, regarding the necessity for written
1189responses to the Commission's specified questions and the
1197submission of a written request to implement the CIAC
1206gross-up charges referenced above.
12107. The first item in the Commission's July 29, 1988
1220letter to the Utility had requested the Utility to seek
1230approval, including submission of proposed rate tariff
1237sheets for authorization to implement the CIAC tax impact
1246charge referenced above. That item was responded to on
1255September 5, 1989, more than eight months after the
1264deadline set by Order No. 20409.
12708. The second item in the Commission's July 29, 1988
1280letter to the Utility had requested the Utility to provide
1290the names and addresses of financial institutions in which
1299gross-up charge funds were being retained. That item was
1308responded to as requested.
13129. The third item in the Commission's July 29, 1988
1322letter to the Utility had requested the Utility to provide
1332a listing of all gross-up monies received from each
1341contributor. No response was ever provided by the
1349Respondent. The significance of the information requested
1356by the Commission is that it would provide identity of the
1367individuals who were entitled to a refund of the
1376unauthorized CIAC gross-up charges collected by the
1383Utility, as provided in Order No. 20762.
139010. The fourth item in the Commission's July 29, 1988
1400letter to the Utility had requested the Utility to provide
1410a copy of all current developer agreements. That item was
1420responded to within the deadline set by Order No. 20409.
143011. The fifth item in the Commission's July 29, 1988
1440letter to the Utility had requested the Utility to file
1450revised tariff sheets indicating the actual legal
1457description of the Utility's certificated service
1463territory. No response was ever provided.
146912. Order No. 20762 was ultimately issued on February
147817, 1989 imposing a $5,000.00 fine on the Utility for
1489serving outside of its authorized service area.
149613. Order No. 20409 requested the Utility to indicate
1505to the Commission whether, with regard to the developer
1514agreement between the Respondent and Fruit Cove Limited,
1522the charges listed in the various paragraphs of that
1531agreement would, upon completion of the real estate
1539development involved, be adjusted to reflect actual utility
1547service costs incurred. No response to that request was
1556ever provided by the Utility. Additionally, in that
1564Order, the Commission requested information concerning a
1571so- called "step tank", which was referenced in paragraphs
158012C and 13D of the developer agreement with Fruit Cove
1590Limited. That request, in Order No. 20409, was never
1599responded to. A certain fee was charged for installation
1608of the step tank by the Utility to Fruit Cove Limited, and
1620no response was given to the Commission's inquiry as to why
1631that fee was omitted from the Utility's approved tariff on
1641file with the Commission. The significance of the
1649requested information was that the omission of the step
1658tank installation fee from the Utility's tariff of rates
1667and charges could cause the developer agreement to
1675constitute a "special service availability agreement",
1681which can only be approved in advance by the Commission.
1691It is not a matter, approval of which has been delegated by
1703the Commission to its staff members.
170914. The Order referenced last above also requested an
1718explanation for why a meter installation fee, referred to
1727in that same developer agreement, does not include a "curb
1737stop" or a meter box. This information is significant
1746because it is necessary in order for the Commission to
1756determine whether the charge involved is reasonable. A
1764cost breakdown for the meter installation, including the
1772various hardware components and other charges, was
1779necessary and was not provided by the Utility.
178715. Additional information concerning the area of
1794service availability, required to be provided to the
1802commission by Order No. 20409, included the requirement
1810that approval be obtained from the Commission for the CIAC
1820gross-up charge in the developer agreement with Fruit Cove
1829Limited. As stated above, that approval was not requested
1838in writing, as required by the Order, for more than eight
1849months after the deadline set by that Order.
185716. By Order No. 20762, St. Johns was fined $5,000.00
1868for three separate violations of the statutes and rules,
1877and the Orders enumerating them, for a total of $15,000.00.
1888The Utility was fined for serving outside of its authorized
1898service territory, for collecting unauthorized CIAC gross-
1905up charges, and for failing to file its developer
1914agreements with the Commission as required by law. The
1923developer agreements were only submitted after repeated
1930efforts by the Commission's staff which culminated in Order
1939No. 20409 and which were either unresponded to or not
1949properly responded to by the Utility. Additionally, by
1957Order No. 21559, issued on July 17, 1989, St. Johns was
1968fined $5,000.00 for failure to file an application for an
1979extension of its territory as required by Order No. 20409.
198917. In the meantime, by Order No. 22342, issued on
1999December 26, 1989, the Commission approved a transfer of
2008the Utility's assets from St. Johns to Jacksonville
2016Suburban Utilities Corporation ("Jacksonville Suburban").
2023That Order did not authorize transfer of the liabilities of
2033the Respondent to Jacksonville Suburban. The Order
2040specifies that St. Johns, and not Jacksonville Suburban,
2048will remain liable for the previously imposed refund
2056obligations and fines. Only in the event that there
2065remained sales proceeds in excess of the certain debt of
2075St. Johns owed to its institutional lender would funds from
2085the Jacksonville Suburban sale be applied toward payment of
2094the refund and fines found to be due and owing by the
2106above-cited Orders, by way of escrow or otherwise. Any
2115excess proceeds, absent Order No. 22342, were to be paid to
2126St. Johns. Order No. 22342 does not make Jacksonville
2135Suburban liable for the refund and fines at issue. It is
2146speculative whether there will be any sales proceeds
2154available from the sale, after payment of the debt, to be
2165applied toward the refund and fines. The sales price was
2175made dependent upon establishment of the Utility's "rate
2183base" amount, to be established in that transfer proceeding
2192at a point in time after entry of Order No. 22342. That
2204Order, however, specifically preserves the liability of St.
2212Johns for the refund and fines and does not provide for the
2224extinguishment of such liability in the event that the
2233sales proceeds prove to be insufficient to pay them.
2242CONCLUSIONS OF LAW
224518. The Division of Administrative Hearings has
2252jurisdiction over the subject matter of and the parties to
2262this proceeding, by the authority of subsection 120.57(1),
2270Florida Statutes (1989).
227319. Contributions-in-aid-of-construction ("CIAC")
2278mean any amount or item of money, services or property
2288received by the Utility, from any person, governmental
2296agency, or other entity, any portion of which is provided
2306at no cost to the Utility and which is utilized to offset
2318the acquisition, improvement or construction costs of the
2326Utility's property, facilities or equipment used to provide
2334service to the public. The term includes system capacity
2343charges, main extension charges, and customer connection
2350charges. See, Rule 25-30.515(3), Florida Administrative
2356Code.
235720. On or after January 1, 1987, in accordance with
2367Commission Order Nos. 16971 and 17058, the Utility was
2376authorized to collect from developers and others who
2384transfer cash or property to a utility as CIAC, a "gross-up
2395charge", in an amount equal to the income tax impact
2405related to the CIAC contribution. Correspondingly, a
2412utility must submit appropriate tariff charge sheets for
2420Commission approval prior to implementation of the
2427assessment of CIAC gross-up charges, pursuant to Order No.
243617058.
243721. Pursuant to Rule 25-30.135(2), Florida
2443Administrative Code, no utility may modify or revise its
2452schedule of rates and charges ("tariff") until it files and
2464receives approval from the Commission for any such
2472modification or revision. Rule 25- 30.550(2), Florida
2479Administrative Code, in turn, requires that any special
2487service availability contract with real estate developer
2494entities, or other persons, shall be approved by the
2503Commission prior to becoming effective.
250822. The evidence adduced by the Petitioner was
2516unrebutted in showing that St. Johns violated Order No.
252520409 by not filing a request for authorization to
2534implement CIAC gross-up charges within the time set forth
2543in that Order. The Utility violated that Order by not
2553filing written responses to the questions and comments
2561incorporated in that Order within the time set forth by the
2572Order. The Utility's response to two out of eleven items
2582within the time limit set in that Order is not deemed to
2594constitute "substantial compliance" with Order No. 20409.
2601Indeed, there has been no showing that "substantial
2609compliance" is a doctrine relevant to this case. The Order
2619specified the particular responses required, and the
2626subject matter thereof, and set a time certain for such
2636responses, which were to be in writing. The Utility simply
2646failed to comply.
264923. Likewise, there is no doubt that, in view of
2659repeated informal notification by the Commission through
2666letters from its staff, and by multiple orders by the
2676Commission as a part of its continuing efforts to procure
2686compliance by the Utility, the Utility was fully aware of
2696the requirements imposed upon it by the Commission through
2705its statutes and rules, enunciated in the above-cited
2713Orders, and was aware of the deadlines for submittal of the
2724required information. Thus, the violations of the statutes
2732and rules embodied in the above-cited Orders constitute
2740knowing and willful violations of those statutes. See,
2748Section 367.161(1), Florida Statutes (1987).
275324. In light of the Respondent's actual knowledge of
2762the Commission's mandate in Order No. 20409, coupled with
2771its history of violations and lack of cooperation, even
2780after it knew of the specifics of what was required of it
2792by the Commission in the above factual regards; it must be
2803concluded that the Utility's failure to comply with Order
2812No. 20409 was knowing and willful even though it is
2822understood by the Hearing Officer that that willfulness
2830might have been tempered by financial impossibility.
283725. Section 367.161(1), Florida Statutes (1987),
2843provides, in effect, that if any utility, by any authorized
2853officer, agent or employee knowingly refuses to comply
2861with, or willfully violates, any provision of Chapter 367,
2870Florida Statutes, which sets forth the Commission's
2877regulatory authority over water and sewer utilities, or
2885knowingly violates or refuses to comply with any lawful
2894rule or order of the Commission, the utility shall be
2904subject to a penalty for each such offense of not more than
2916$5,000.00. The Commission is authorized in those statutory
2925provisions to fix, impose and collect such a penalty.
2934Each day of such refusal or violation constitutes a
2943separate offense. It is further provided in that
2951subsection that each penalty constitutes a lien upon any
2960real and personal property held by the utility, enforceable
2969as a statutory lien pursuant to the provisions of Chapter
297985, Florida Statutes.
298226. The case of Deltona Corporation v. Florida Public
2991Service Commission, 220 So.2d 905, 908 (Fla. 1969), made it
3001clear that the Commission has authority to impose penalties
3010within the statutory limits authorized it, which are
3018sufficiently weighty as to insure compliance with its
3026orders. Commission Orders numbered 20137, 20781 and 20884
3034indicate that the Commission follows a policy of
3042considering a utility's compliance history in determining
3049to assess penalties and the amount thereof. A utility's
3058financial difficulties, particularly those which are
3064largely self-imposed, are not deemed to be grounds for
3073leniency in assessing penalties against a utility for
3081serious and repeated violations of statutes, rules or
3089orders the Commission has been charged with enforcing.
3097See, Order No. 20781 (p. 2).
310327. Order No. 22342 provides that the Commission has
3112interpreted the provisions of Section 367.171, Florida
3119Statutes, generally to the effect that where assets of a
3129utility are transferred, as opposed to a transfer of stock
3139of the entity, that the transferor remains liable for
3148violations occurring before approval of the transfer by the
3157Commission.
315828. Finally, when a utility becomes subject to
3166regulation by a county, all cases in which it was a party,
3178pending before the Commission, or in any court of appeal
3188from any order of the Commission, remain within the
3197jurisdiction of the Commission or the court until disposed
3206of in accordance with the law in effect on the day the case
3219was filed. See, Section 367.171(5), Florida Statutes
3226(1989).
322729. Accordingly, there is no question concerning the
3235authority of the Commission to impose the fine sought in
3245this case; and the evidence establishes the knowing,
3253repeated and willful nature of the violations, albeit they
3262may have resulted in large part from the extreme financial
3272difficulty which the Utility experienced at times pertinent
3280hereto. There is no question that the evidence of the
3290Utility's repeated and knowing violations, coupled with the
3298Commission's repeated formal and informal efforts to obtain
3306compliance with its directives, justifies a significant
3313penalty in this instance.
3317RECOMMENDATION
3318Having considered the foregoing Findings of Fact,
3325Conclusions of Law, the evidence of record, the candor and
3335demeanor of the witnesses, and the pleadings and arguments
3344of the parties, it is therefore,
3350RECOMMENDED that St. Johns be assessed a penalty of
3359$5,000.00 for knowingly and willfully failing to comply
3368with Order No. 20409.
3372DONE AND ENTERED this __13th__ day of June, 1990, in
3382Tallahassee, Leon County, Florida.
3386_________________________
3387P. MICHAEL RUFF
3390Hearing Officer
3392Division of Administrative
3395Hearings
3396The DeSoto Building
33991230 Apalachee Parkway
3402Tallahassee, FL 32399-1550
3405(904) 488-9675
3407Filed with the Clerk of the
3413Division of Administrative
3416Hearings
3417this __14th__ day of June,
34221990.
3423APPENDIX TO RECOMMENDED ORDER
3427Petitioner's Proposed Findings of Fact 1.-24. Accepted.
3434Respondent's Proposed Findings of Fact.
3439(Respondent filed no proposed Findings of Fact)
3446Copies furnished to:
3449David Schwartz, Esq.
3452Florida Public Service Commission
3456Legal Division
3458101 E. Gaines Street
3462Tallahassee, FL 32399-0850
3465Joseph E. Warren, Esq.
34691930 San Marco Boulevard
3473Suite 200
3475Jacksonville, FL 32207
3478Mr. Steve Tribble
3481Director of Records and Recording
3486Florida Public Service Commission
3490101 E. Gaines Street
3494Tallahassee, FL 32399-0850
3497Mr. David Swafford
3500Executive Director
3502Florida Public Service Commission
3506101 E. Gaines Street, Room 116
3512Tallahassee, FL 32399-0850
3515Susan Clark, Esq.
3518General Counsel
3520Florida Public Service Commission
3524101 E. Gaines Street, Room 212
3530Tallahassee, FL 32399-0850
Case Information
- Judge:
- P. MICHAEL RUFF
- Date Filed:
- 06/19/1989
- Date Assignment:
- 06/22/1989
- Last Docket Entry:
- 06/13/1990
- Location:
- St. Augustine, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO