89-003368RP Gte Telephone Operations vs. Department Of Transportation
 Status: Closed
DOAH Final Order on Thursday, March 8, 1990.


View Dockets  
Summary: Proposed rule requiring utility to defend DOT from delay claims not invalid; proposal that utility pay for negligence of DOT is invalid; Estimate of Economic Impact inaccurate.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8GTE FLORIDA, INC., )

12)

13Petitioner, )

15)

16vs. ) CASE NO. 89-3368RP

21)

22DEPARTMENT OF TRANSPORTATION, )

26)

27Respondent. )

29_________________________________)

30FLORIDA POWER AND LIGHT COMPANY, )

36)

37Petitioner, )

39)

40vs. ) CASE NO. 89-3567RP

45)

46DEPARTMENT OF TRANSPORTATION, )

50)

51Respondent. )

53_________________________________)

54SOUTHERN BELL TELEPHONE AND )

59TELEGRAPH COMPANY, )

62)

63Petitioner, )

65)

66vs. ) CASE NO. 89-3570RP

71)

72DEPARTMENT OF TRANSPORTATION, )

76)

77Respondent. )

79_________________________________)

80UNITED TELEPHONE COMPANY, )

84)

85Petitioner, )

87)

88vs. ) CASE NO. 89-3572RP

93)

94DEPARTMENT OF TRANSPORTATION, )

98)

99Respondent. )

101_________________________________)

102FLORIDA NATURAL GAS ASSOCIATION, )

107)

108)

109Petitioner, )

111)

112vs. ) CASE NO. 89-3577RP

117)

118DEPARTMENT OF TRANSPORTATION, )

122)

123Respondent. )

125_________________________________)

126FINAL ORDER

128Pursuant to notice, the above-styled matter was heard before the Division

139of Administrative Hearings ) by its duly designated Hearing Officer, Daniel M.

151Kilbride, on November 2 and 3, 1989, and by stipulation on January 29, 1990, in

166Tallahassee, Florida. The following appearances were entered:

173APPEARANCES

174For Petitioner Lorin H. Albeck, Esquire

180GTE FLORIDA, General Attorney

184INC., GTE Florida Incorporated

188Post Office Box 110, Mail Code 7

195Tampa, Florida

197For Petitioner Jean G. Howard, Esquire

203Florida Power Law Department

207and Light Co. Florida Power and Light

214Company

215Post Office Box 029100

219Miami, Florida

221For Petitioner Robert G. Beatty, Esquire

227Southern Bell Southern Bell Telephone

232Telephone and Legal Department

236Telegraph Co. Museum Tower, Suite 1910

242150 West Flagler Street

246Miami, Florida

248For Petitioner Kay L. Wolf, Esquire

254United Telephone Assistant Vice President-

259Company Law

261United Telephone Company

264of Florida

266Post Office Box 5000

270Altamonte Springs, Florida

273For Petitioner Richard Brightman, Esquire

278Florida Natural Post Office Box 6526

284Gas Association Tallahassee, Florida

288For Respondent Robert P. Daniti, Esquire

294Senior Litigation Attorney

297Department of Transportation

300605 Suwannee Street

303Tallahassee, Florida

305STATEMENT OF THE ISSUES

309Whether Respondent's proposed Rule 14-46.0011 is an invalid exercise of

319delegated legislative authority.

322Whether paragraph 12 of the revised DOT utility permit, incorporated by

333reference in the proposed amendments to Rule 14- 46.001, Florida Administrative

344Code, is an invalid exercise of delegated legislative authority.

353Whether paragraph 15 of the revised DOT utility permit, incorporated by

364reference in the proposed amendments to Rule 14- 46.001, Florida Administrative

375Code, is an invalid exercise of delegated legislative authority.

384Whether the economic impact statement prepared by DOT was inadequate so as

396to amount to an invalid exercise of delegated legislative authority.

406PRELIMINARY STATEMENT

408By notice in the Florida Administrative Weekly, Volume 15, Number 24, June

42016, 1989, the Florida Department of Transportation (DOT) initiated Section

430120.54 rulemaking proceedings to amend Rule 14-46.001, Florida Administrative

439Code, including a revised Utility Accommodation Guide (UAG) which is

449incorporated by reference. The revised UAG supersedes the 1979 edition which is

461incorporated by reference in Rule 14-15.014, which will be repealed. The notice

473also initiates rulemaking proceedings for proposed Rule 14-46.0011. Rule 14-

48346.001(3) requires utilities to obtain permits for use of DOT's right of way.

496The permit is to be issued in conformance with DOT's UAG. The revised UAG

510contains the revised Utility Permit (Permit) which is the subject of this rule

523challenge. In initiating rulemaking, the DOT filed with the appropriate

533agencies the documentation required by the applicable procedural rules at this

544stage of the rulemaking proceeding. The notice contains a summary of the

556estimated impact of the proposed amendments and provides for a public hearing.

568The subject of the proposed amendments is DOT's policies regulating the

579accommodation of utility facilities on public roads and rights of way under DOT

592jurisdiction, including the location and manner of installing, adjusting or

602relocating these facilities. The revised UAG contains the reVised Utility

612Permit which is the primary subject of this rule challenge proceeding.

623Five petitions to invalidate have been consolidated for hearing by order

634dated July 10, 1989. At the October 24, 1989 motion hearing, the undersigned

647granted the DOT and Florida Power and Light Company (FPL) motions for summary

660final order regarding the validity of proposed Rule 14-46.0011. That rule will

672be addressed in this order.

677At the October 24, 1989 motion hearing, the undersigned also granted DOT's

689motion for partial abeyance of all issues raised by each Petitioner, except as

702stated in the issues section of these findings of fact. At the beginning of the

717final hearing, the undersigned also abated Florida Natural Gas Association's

727(FNGA) issue concerning the sufficiency of DOT's notice of incorporation by

738reference of the revised Utility Accommodation Guide. Jurisdiction over the

748abated issues is relinquished to the DOT to the extent necessary to resolve

761these issues through formally announced and noticed changes to the proposed

772rule.

773Petitioner Southern Bell Telephone and Telegraph Company's (Southern Bell)

782Motion in Limine is denied. See: Buy-Low Save Centers, Inc. v. Glinert, 547

795So.2d 1283 (Fla. 4th DCA 1989).

801On November 2, 1989, the formal hearing commenced. Petitioners GTE Florida,

812Inc. (GTE) and FNGA did not present any evidence. Petitioner FPL presented

824three witnesses: Terry Vogel, a fact witness employed by FPL as a division

837relocation coordinator and permit administrator; Dennis LaBelle, an expert in

847the relocation of electric utilities; and Paul LaPointe, an expert in public

859utility accounting.

861Petitioner FPL introduced 19 exhibits which were received into evidence,

871subject to DOT's objections as to relevancy and materiality as noted in the

884transcript. Petitioner Southern Bell introduced eight exhibits, including the

893Affidavit of an expert economic and financial consultant. These exhibits were

904admitted into evidence, subject to DOT's objections as to relevancy and

915materiality as noted in Southern Bell's stipulation with DOT. Petitioner United

926Telephone Company of Florida (UTF) presented five exhibits which were admitted,

937subject to DOT'S objections as to relevancy and materiality pursuant to UTF's

949stipulation with DOT. Respondent DOT presented the testimony of Robert D.

960Buser, P.E.; DOT Director of Construction; and Robert I. Scanlan, DOT Deputy

972General Counsel; together with Exhibits 1 through 9 and 13, which were admitted

985into evidence. The transcript of the hearing on November 2 and 3 was filed with

1000the Clerk of the Division on December 4, 1989. As a result of stipulations by

1015the parties, the need for a third day of hearing was obviated, and the

1029evidentiary record as defined by Section 120.57(1)(a)6., Florida Statutes, was

1039closed on January 29, 1990. By the amended order dated February 2, 1990, the

1053parties were afforded an opportunity to present written proposed findings of

1064fact, conclusions of law and argument of counsel by February 20, 1990, in which

1078Petitioners GTE, FPL and Southern Bell and Respondent have submitted proposals.

1089UTC joined in the proposals submitted by Petitioners. Each have been carefully

1101considered and are addressed in the Appendix.

1108Based upon all of the evidence, the following findings of fact are

1120determined:

1121FINDINGS OF FACT

11241. Respondent, Florida Department of Transportation (DOT), an agency of

1134the State of Florida, was created. and defined pursuant to Section 20.23,

1146Florida Statutes, for the purposes delineated in that section, including the

1157building and maintaining of public transportation facilities.

11642. Petitioner, GTE Florida, Inc. (GTE), is a foreign corporation

1174authorized to do business and doing business in the State of Florida. The

1187company operates a telephone system in this State and, therefore, is regulated

1199by the Florida Public Service Commission, pursuant to Chapter 364, Florida

1210Statutes.

12113. Petitioner, Florida Power and Light Company (FPL) is a Florida

1222corporation and operates an electrical generating, transmission and distribution

1231system in this State and, therefore, is regulated by the Florida Public Service

1244Commission pursuant to Chapter 366, Florida Statutes.

12514. Petitioner, Southern Bell Telephone and Telegraph Company (Southern

1260Bell) is a foreign corporation authorized to do business and doing business in

1273the State of Florida. The company operates a telephone system in this State

1286and, therefore, is regulated by the Florida Public Service Commission pursuant

1297to Chapter 364, Florida Statutes.

13025. Petitioner, United Telephone Company of Florida (UTC) is a Florida

1313corporation. The company operates a telephone system in this State and,

1324therefore, is regulated by the Florida Public Service Commission pursuant to

1335Chapter 364, Florida Statutes.

13396. Petitioner Florida Natural Gas Association (FNGA) is a Florida

1349corporation. FNGA is a trade association whose members are in the business of

1362providing natural gas utility services in Florida.

13697. All Petitioners are substantially affected persons who have standing to

1380initiate this rule challenge proceeding.

13858. By notice in the Florida Administrative Weekly, Volume 15, Number 24,

1397June 16, 1989, DOT initiated Section 120.54 rulemaking proceedings to amend Rule

140914-46.001, including a revised Utility Accommodation Guide (UAG). The revised

1419UAG supersedes the 1979 edition which DOT had incorporated by reference in Rule

143214-15.014, which will be repealed. The notice also initiates rulemaking

1442proceedings for proposed Rule 14- 46.0011.

14489. In initiating rulemaking, the DOT filed with the appropriate agencies

1459the documentation required by the applicable procedural rules at this stage of

1471the rulemaking proceeding. The notice contained a summary of the estimated

1482economic impact of the proposed amendments and provides for a public hearing.

149410. The subject of the proposed amendments is DOT's policies regulating

1505the accommodation of utility facilities on public roads and rights of way under

1518DOT's jurisdiction, including the location and manner of installing, adjusting

1528or relocating these facilities.

153211. Proposed Rule 14-46.0011 challenged by FPL provides:

154014-46.0011 Utilities Liaison. Recognizing

1544that all utility owners serving the public

1551have a common obligation to provide their

1558services in cost effective manner, the

1564Department will coordinate its advance

1569planning of highway projects with the

1575affected utilities to facilitate the

1580relocation of the utility in order to

1587eliminate costly construction delays. As

1592part of the project planning and

1598process the Department will consider the cost

1605of utility work necessary for the proposed

1612project. The Department will keep utility

1618agencies informed of future transportation

1623projects and request the utility agencies to

1630advise the Department of the location of

1637existing and proposed structures within

1642proposed project corridors.

164512. This entire section (14-46.0011) is new and is a statement of policy

1658direction. It announces DOT's determination to coordinate the advance planning

1668of highway projects with affected utilities; to consider the cost of utility

1680work necessary for a proposed project; and to keep utilities informed of future

1693transportation projects. As such, DOT is free to refine this policy and to

1706develop procedures to implement this rule on a case by case basis.

171813. All Petitioners challenge paragraphs 12 and 15 of the amended Utility

1730Permit form which appears at pages 36 and 37 of the UAG.

174214. The new paragraph 12 of the Utility Permit provides:

175212. It is agreed that in the event

1760the relocation of said utility facilities

1766are scheduled to be done simultaneously

1772with the Department's construction work,

1777the permittee will coordinate with the

1783Department before proceeding, shall

1787cooperate with the Department's

1791contractor to arrange the sequence of

1797work so as not to unnecessarily delay the

1805work of the Department's contractor,

1810defend any legal claims of the

1816Department's contractor due to delays

1821caused by the permittee's failure

1826comply with the approved schedule, and

1832shall comply with all provisions of the

1839law and Rule 14-46, Florida

1844Administrative Code. The Permittee shall

1849not be responsible for delays beyond its

1856normal control.

185815. The new paragraph 15 of the Utility Permit provides:

186815. Permittee convenants and agrees

1873that it will indemnify and hold harmless

1880Department and all of Department's

1885officers, agents, and employees from any

1891claim, loss damage, cost, charge or

1897expense arising out of any act, action,

1904neglect or omission by Permittee during

1910the performance of the contract, whether

1916direct or indirect, and whether to

1922person or property to which Department or

1929said parties may be subject, except that

1936neither Permittee nor any of its

1942subcontractors will be liable under this

1948section for damages arising out of

1954or damage to persons or property directly

1961caused or resulting from the sole

1967negligence of Department or any of its

1974officers, agents or employees.

197816. Public utilities are on DOT right-of-way by permit and statutory

1989invitation. Frequently such utilities increase the cost to DOT for

1999accomplishing its mission. These costs include expanded liability for DOT.

200917. DOT has a separate utilities section that reports to the director of

2022construction who is responsible for coordinating, in an orderly manner, the

2033permitting of utilities on the right of way. This includes adjustments

2044necessary because of new construction or improvements to existing roads.

205418. Prior to 1987, the DOT was criticized by the Legislature and the

2067public for delays in completing road construction projects.

207519. The DOT formed a DOT Quality Improvement Team to study utility delays.

2088The DOT team identified the root causes of DOT's problems with utility

2100relocation delays and the DOT practices and procedures. Time delays caused by

2112utilities constituted more than 17% of the total time extensions the DOT granted

2125on road work. However, approximately one-half of utility-caused time delays

2135were due to water and sewer utilities.

214220. The DOT team further determined that the majority of the utility delay

2155claims were located in one area. Of 425 delay claims statewide, only 27 were

2169utility related. Of the 27 utility related claims, 14 were in DOT District I,

2183and 11 of the claims came out of one office within that District. Twelve of the

219914 claims involved city or county utilities. After study and analysis of these

2212facts, the DOT Team came up with solutions to help reduce utility delays. These

2226solutions did not include the provisions of paragraphs 12 and 15 of the Utility

2240Permit.

224121. The DOT sends the utility a set of plans at the 60% and 90% completion

2257stage. Usually the utility would submit a relocation schedule to DOT after it

2270receives the 90% plans. In the DOT's District NO. 1, where most of the problems

2285are, DOT sends the 60% and 90% plans together, so the utility is submitting a

2300relocation schedule based on DOT plans, the utility gives DOT its "approved

2312schedule," the estimate of the number of days that the utility will need in the

2327field to relocate the utility facilities. The estimate is usually tied to the

2340start of the DOT construction, e.g., the utility estimates that it will need 60

2354days in the field after starting of construction to relocate its facilities.

236622. In DOT District 1, there is an average of four utilities involved on

2380all road projects. Each utility files its own schedule with the DOT, and that

2394schedule becomes part of the contract which the DOT signs with the contractor.

2407DOT construction plans can change before construction starts. There can be a

2419delay of as much as two or three years after the utility submits its relocation

2434schedule and the start of the DOT construction.

244223. Prior to the study, each individual utility would submit its own

2454relocation schedule months, sometimes years, before the construction actually

2463begins. An average of four different utilities are involved in a DOT relocation

2476project at the same time. The project schedule did not coordinate the work of

2490the utilities with that of the DOT contractor, resulting in delays to the

2503project.

250424. As a consequence of delays (other than for weather), including delays

2516attributable to utilities, contractors file delay claims. Frequently delay

2525claims are approved which increase the cost of road construction projects for

2537DOT.

253825. The increased costs stem from the amount of time the DOT contractor is

2552forced by the delays, such as delays attributable to utilities, to exceed the

2565contract time. These costs are the cost of labor, equipment, other resources

2577and overhead which the contractor experiences when it does not finish the

2589project on time.

259226. Any delay in road construction work, including time delays caused by a

2605utility's failure to comply with its DOT approved relocation schedule, presents

2616significant disks to the safety of the traveling public and construction workers

2628on the extended job since the construction zone is a hazard6us area. By

2641reducing delays, DOT reduces the exposure of the public and the workers, thereby

2654limiting safety risks. These risks include drop-offs, barricades, lane changes,

2664and other road abnormalities that motorists endure when they drive through a

2676road construction project.

267927. As a result of its study of utility-related time delays to its road

2693construction projects, DOT implemented the several recommendations it had made

2703in its study of time delays.

270928. One recommendation was to require any utilities affected by a road

2721construction project to submit to DOT a detailed schedule of the utility's part

2734of that project. DOT implemented this recommendation in September 1987, and

2745this is now an ongoing DOT policy and practice.

275429. Under the new procedures, where utilities are involved in a DOT road

2767construction project, DOT requires the utilities to develop a schedule for

2778relocating or installing their facilities. The DOT now involves the utilities

2789at every stage of its road construction. Not only does DOT involve utilities at

2803an early stage in the planning of the project, but it also gets the contractor

2818and the utility to confer to reconcile their schedules at a preconstruction

2830conference so that the road construction can proceed in an orderly fashion with

2843utilities being relocated in a manner least disruptive to the job.

285430. The relocation or installation schedule developed by utilities is

2864incorporated by the road contractor in its master schedule for the road

2876construction and is approved by the district construction engineer, resident

2886engineer or project engineer when the job is let for bidding.

289731. The utilities agreement forms the basis for DOT's contract with its

2909road contractor so that the contractor knows what effect the utility will have

2922on the project, with the aim that all parties work together in a coordinated

2936fashion to get the road built.

294232. Since utility time delays were one factor contributing to time delays

2954in DOT road construction, DOT rationally chose to address all facets of the time

2968delay problem, including utility-caused time delays. However, the claims

2977tracking reports upon which DOT relied in determining the need for proposed rule

2990changes do not reflect any reduction in delay claims from the new liaison

3003procedure since it was not implemented at the time of DOT's claims reports.

301633. As a further outgrowth of its study of road construction time delays,

3029DOT determined that the addition of a defense to delay claim provision in the

3043utility permit would increase utilities' compliance with their relocation or

3053installation schedule.

305534. DOT relied upon its claims tracking report as a source of data about

3069the cost to DOT for utility-caused delay claims to support this new permit

3082provision.

308335. While the dollar amounts attributable to settled road contractor delay

3094claims caused by utility time delays are often less than the initial amounts

3107claimed by the contractors, the cost to DOT is a significant total.

311936. The DOT has a policy and procedure for the direct review, processing

3132and resolution of all categories of road contractor claims against DOT and has a

3146specific procedure for processing contractor delay claims attributable to

3155utility delays.

315737. Proposed Paragraph 12 of the Utility Permit will have limited impact

3169with respect to the utility schedules and there is limited connection between

3181paragraph 12 of the permit and reducing contractor delay claims.

319138. The requirement that the utility defend any legal claims of DOT's

3203contractor due to delays caused by the utility's failure to comply with the

3216approved schedule is likely to result in increased litigation and expense for

3228DOT and the Utility.

323239. The DOT utilizes the phrase in paragraph 12 of the Utility Permit:

"3245The permittee shall not be responsible for delays beyond its normal control" in

3258the same way it grants its road contractors extensions of time for circumstances

3271beyond the control of the contractor. This determination is an issue of fact

3284which can be made by the DOT district construction engineer on a case by case

3299basis, following general guidelines developed by the DOT.

330740. The DOT's intent in including the defense requirement in paragraph 12

3319of the Permit is to give DOT "extra clout" with which to threaten the utility

3334with revocation of the Permit if the utility refuses to defend DOT or fails to

3349comply with the schedule.

335341. DOT's recently adopted practice and procedure for processing delay

3363claims and for determining whether a utility should defend DOT from a delay

3376claim attributable to utility delays, provides written notice to the utility and

3388contains extensive levels of review by the DOT professionals involved in the

3400particular road project. If the road contractor's claim of utility delay is not

3413deemed valid, DOT will not require the utility to defend against the claim.

342642. The majority of Petitioner FPL's facilities are not covered by the

3438Permit, in that the facilities are not installed on DOT right-of-way or were

3451installed on DOT right-of- way under the old permit which did not have this

3465provision.

346643. Petitioner Utilities cooperate with DOT in utility relocations, and

3476the utility relocation is a complex process in which there will be projects on

3490which there are problems.

349444. The DOT intends that both paragraphs 12 and 15 of the revised utility

3508permit also become part of its standard form contract for utility installation

3520or relocation, so that the contract mirrors these permit provisions.

353045. The DOT's utility contract or agreement is a separate document,

3541distinct from the DOT utility permit.

354746. The purpose of the permit process is the grant or denial of utility

3561access to DOT's right-of-way and to ensure utility compliance with DOT rules.

357347. The purpose of the DOT utility agreement is to negotiate the time

3586within which a utility must complete its relocation or installation on the DOT

3599right-of-way and provide specific provisions relating to the particular job

3609embraced by the agreement.

361348. The DOT currently requires any utility which seeks to be accommodated

3625on DOT right-of-way to indemnify DOT as follows:

3633a) The existing Utility Permit provides:

363915. It is understood and agreed that the

3647rights and privileges herein set out are

3654granted only to the extent of thin State's

3662right, title and interest in the land to be

3671entered upon and used by the holder, and the

3680holder will, at all times, assume all risk of

3689and indemnify, defend, and save harmless the

3696State of Florida and the Department from and

3704against any and all loss, damage, cost or

3712expense arising in any manner on account of

3720the exercise or attempted exercises by said

3727holder for the aforesaid rights and

3733privileges.

3734b) Master Agreements and project specific agreements with DOT contain

3744provisions resembling the existing paragraph 15 of the utility permit.

3754c) The Master Agreement states:

37592. The COMPANY further agrees that said

3766adjustment, changes or relocation of

3771facilities will be made by the COMPANY with

3779sufficient promptness so as to cause no delay

3787to the DEPARTMENT or its contractor in the

3795prosecution of such construction or

3800reconstruction work; provided, however, that

3805the COMPANY shall not be responsible for

3812delay beyond its control; and that such

"3819Relocation Work" will be done under the

3826direction of the DEPARTMENT'S engineer; and

3832the COMPANY further agrees that in the event

3840the changes, adjustments or relocation of

3846such facilities or utilities are bone

3852simultaneously with the construction project,

3857that it will be directly responsible for the

3865handling of any legal claims that the

3872contractor may initiate due to delays caused

3879by the COMPANY'S negligence; and that the

3886COMPANY will not either proceed with the

"3893Relocation Work" with its own forces or

3900advertise or let a contract for such Work

3908until it has received the DEPARTMENT'S

3914written authority to proceed.

391849. Only a small percentage (6%) of Petitioner FPL utility facilities are

3930on DOT right-of-way, and this percentage will remain constant in the future

3942because of FPL's design philosophy.

394750. Since DOT's utility permit is not required for utility facilities

3958unless the facilities are on the right-of-way, nor for existing facilities not

3970being relocated, the challenged paragraphs of the revised utility permit will

3981not impact a vast majority (94%) of Petitioner FPL facilities.

399151. Utility relocation within DOT right-of-way is at the utility's

4001expense; but if the relocation is from private property to the right-of-way it

4014is at DOT's expense.

401852. For both types of relocations, DOT requires the utility to indemnify

4030and to defend DOT for the utility's own negligence.

403953. The utility is not a party to the contract between the DOT and the

4054road contractor. The control of the DOT contract, contractor and relocation

4065procedures is with the DOT.

407054. Utility relocation schedules do not require work to commence on a

4082calendar date, but rather references definable markers in the progress of the

4094road work.

409655. The DOT did not intend paragraph 12 to require a utility to defend a

4111vehicle owner against claims of the DOT road contractor.

412056. DOT's utility coordinator alerts the utility as to the commencement of

4132the utility's deadline for completing its schedule, and the preconstruction

4142conference also provides the utility with information and guidance.

415157. The DOT road construction plans show all utilities on the project and

4164the location of their facilities.

416958. Proposed paragraph 15 requires a utility, as a condition of its

4181permit, to indemnify the DOT for any act or omission of the utility under its

4196contract (with DOT) to install or relocate utility facilities in the right-of-

4208way, except where the DOT is the sole negligent party.

421859. Since 1984, the DOT has required its construction contractors to

4229indemnify DOT for everything, except for DOT's sole negligence, through a

4240supplemental specification practically identical with proposed paragraph 15.

424860. The indemnification provision of paragraph 15 of the Permit requires

4259as a condition of use of DOT right-of-way that the utility pay for the DOT's

4274joint negligence. This will lessen DOT's exposure to liability and free up more

4287dollars for DOT to spend on roads.

429461. As an example, under paragraph 15 of the Permit, if there were a

4308judgment that DOT was 99% negligent and the utility was 1% negligent, the

4321utility would have to pay the entire judgment under the proposed indemnification

4333clause.

433462. The control of road design and maintenance is with DOT.

434563. DOT intends proposed paragraph 15 to pertain only to tort liability,

4357and the utility must indemnify DOT for DOT's joint liability and not the joint

4371liability of any other person or entity.

437864. Utility installations on DOT right-of-way raise land use issues

4388relating to adequate and efficient use of land which include: (a) reduced

4400overall cost of DOT road improvements; (b) the private landowner's property is

4412not encumbered by utility facilities, which are installed in the DOT right-of-

4424way; (c) less clearing of trees or other vegetation is needed if facilities are

4438installed on the DOT right-of-way; and (d) efficiency of land use is maximized.

4451The utility in some instances has no choice but to put its facilities on public

4466right-of-way. In cases involving building setbacks or road crossings, the

4476utility must obtain a permit and put its facilities in DOT or other public

4490right-of-way. The DOT did not consider these important public policy and land

4502use considerations in proposing the defense and indemnification provisions of

4512paragraphs 12 and 15.

451665. The requirement that the utility defend any legal claims of DOT's

4528contractor due to delays caused by tube utility's failure to comply with the

4541approved schedule and the requirement that the utility indemnify DOT for DOT's

4553joint negligence will shift DOT expenses to the utility and cause the utility to

4567incur additional costs and expenses for use of DOT right-of-way.

457766. Utilities do not pass all of their operating costs on to the

4590ratepaying customers; shareholders bear the increase until, and unless, the

4600increase is favorably accepted by the Public Service Commission for inclusion as

4612a factor in the utility's rate structure.

461967. The utilities, in some instances, have no choice but to install their

4632facilities on the DOT right-of-way.

463768. Having utility facilities on DOT right-of-way is an efficient use of

4649land.

465069. The DOT is attempting to force provisions on the utilities through

4662rulemaking because the utilities will not voluntarily sign contracts which

4672contain the indemnification and defense provisions.

467870. The EIS prepared by DOT and incorporated in the June 16, 1989 edition

4692of the Florida Administrative Weekly states in pertinent part:

4701* * *

4704The following specific statements of economic

4710impact are provided as required by 120.54(2),

4717Florida Statutes:

4719* * *

4722(2) An estimate of the costs on the economic

4731benefit to all persons directly affected by

4738the proposed action:

4741Provisions presumed to have cost impact

4747on utilities include:

4750Utilities Liaison: Favorable cost impact

4755is anticipated from advance coordination

4760provisions of the rule chapter as amended.

4767Current reports indicate approximately 22

4772construction claims for $3.7 million relate

4778to utilities problems. A significant number

4784of these will be reduced or eliminated by

4792consistent liaison during the design process.

4798Maintenance of Traffic: Specific new

4803requirements for training of onsite

4808supervisors of Utilities Work Zones may

4814impact certain utilities who do not conduct

4821required training at present. This overhead

4827should be of such limited nature that it will

4836be offset by benefits such as improved

4843safety, reduced hazards, and lower costs of

4850accidents attributable to improperly

4854supervised traffic control in utility work

4860zones.

4861The Florida Utilities Coordinating

4865Committee has been materially involved in the

4872development process for these matters and has

4879provided continuous input to this revision of

4886the Utility Accommodation Guide.

489071. As stated in the EIS, the Florida Utilities Coordinating Committee

4901provided continuous input to the revision of the Utility Accommodation Guide; it

4913did not consider whether the "delay claims" provision should be added to

4925paragraph 12 or whether the "indemnification" provision should be added to

4936paragraph 15 of the new Utility Permit.

494372. The EIS prepared by DOT and incorporated in the June 16 edition of the

4958Florida Administrative Weekly is inaccurate and misleading in claiming

4967construction delays of $3.7 million are attributable to utilities.

497673. The DOT did not consider in the EIS the costs to the utilities of

4991defending "delay claims" filed by the road contractor.

499974. The DOT did not consider in the EIS that in shifting the cost of DOT's

5015joint negligence to the utility, DOT is imposing substantial costs on the

5027utility.

502875. The DOT did not consider that the indemnification amounts which the

5040utility would have to pay DOT for DOT's joint negligence could be in excess of

5055the $100,000-$200,000 allowed under the waiver of sovereign immunity statute,

5067Section 786.28, Florida Statutes (1989).

5072CONCLUSIONS OF LAW

507576. The Division of Administrative Hearings has jurisdiction over the

5085subject matter of this proceeding, and the parties thereto, pursuant to Sections

5097120.54(4) and 120.57(1), Florida Statutes.

510277. Each Petitioner in this proceeding has the burden to demonstrate that

5114it is a substantially affected person in order to have standing to seek an

5128administrative determination of the invalidity of any proposed rule on the

5139ground that the proposed rule is an invalid exercise of delegated legislative

5151authority. Section 120.54(4)(a), Florida Statutes (1989).

515778. A trade or professional association has standing to institute a rule

5169challenge proceeding even though it is acting solely as the representative of

5181its members. Florida Homebuilders Association v. Department of Labor and

5191Security, 412 So.2d 351 (Fla. 1982). The elements of associational standing

5202recognized by the Supreme Court in Florida Homebuilders are elements of proof,

5214which a trade or professional association must prove up at hearing in order to

5228demonstrate that the association has standing to institute a rule challenge

5239proceeding. At hearing, all parties stipulated that FNGA is substantially

5249affected by the challenged rule.

525479. Each of the Petitioners in this consolidated rule challenge matter has

5266met its burden and has standing to seek an administrative determination of the

5279invalidity of the proposed rules.

528480. Petitioners have the burden to demonstrate by the preponderance of the

5296evidence that the proposed rule constitutes an invalid exercise of delegated

5307legislative authority, as that phrase is defined in Section 120.52(8), Florida

5318Statutes (1989). Adam Smith Enterprises, Inc. v. Florida Department of

5328Environmental Regulation, 553 So.2d 1260, 1274, 14 FLW 2722, at footnote 23,

5340(Fla. 1st DCA 1989).

534481. The phrase "invalid exercise of delegated legislative authority" is

5354statutorily defined in Section 120.52(8), Florida Statutes, as follows:

5363(8) "Invalid exercise of delegated

5368legislative authority" means action which

5373goes beyond the powers, functions, and

5379duties delegated by the Legislature. A

5385proposed or existing rule is an invalid

5392exercise of delegated legislative authority

5397if any one or more of the following apply:

5406(a) The agency has materially failed

5412to follow the applicable rulemaking

5417procedures set forth in S. 120.54;

5423(b) The agency has exceeded its grant

5430of rulemaking authority, citation to

5435which is required by S. 120.54(7);

5441(c) The rule enlarges, modifies, or

5447contravenes the specific provisions

5451of law implemented, citation to which

5457is required by S. 120.54(7);

5462The rule is vague, fails to

5468establish adequate standards for

5472agency decisions, or vests unbridled

5477discretion in the agency; or

5482The rule is arbitrary or

5487capricious.

5488This subsection was added to the definitions section of Section 120.52 by

5500legislative act in 1988, and essentially codified judicial interpretation of the

5511term "invalid exercise of delegated legislative authority." See: Grove Isle,

5521Ltd. v. Department of Environmental Regulation, 454 So.2d 571, 573, 575 (Fla.

55331st DCA 1984); Department of Business Regulation v. Salvation Limited, Inc., 452

5545So.2d 65 (Fla. 1st DCA 1984).

555182. The Petitioners, by asserting the affirmative of the issues, have the

5563burden of proof which includes the ultimate burden of persuasion. Florida

5574Department of Transportation v. J.W.C. Co., Inc., 396 So.2d 778 (Fla. 1st DCA

55871981).

558883. In Department of Professional Regulation, Board of Medical Examiners

5598v. Durrani, 455 So.2d 515 at 517 (Fla. 1st DCA 1984), the court stated:

5612The well recognized general rule is that

5619agencies are to be accorded wide discretion

5626in the exercise of their lawful rulemaking

5633authority, clearly conferred or fairly

5638implied and consistent with the agencies'

5644general statutory duties . . . An

5651construction of the statute it administers

5657is entitled to great weight and is not to be

5667overturned unless clearly erroneous .

5672Moreover, the agency's interpretation of a

5678statute need not be the sole possible

5685interpretation or even the most desirable

5691one; it need only be within the range of

5700possible interpretations . .

5704It is not this tribunal's function to say if the Department's interpretation is

5717preferable; this tribunal is concerned only if the proposed rule is within the

5730range of permissible construction that comports with and effectuates discerned

5740legislative intent. Florida League of Cities v. Department of Insurance, 540

5751So.2d 850, 857-858 (Fla. 1st DCA 1989); Department of Administration v. Nelson,

5763424 So.2d 852 (Fla. 1st DCA 1982)

577084. Petitioners' attack on the propriety and constitutionality of the

5780rules on grounds that they are an impairment of contract under Section 10, of

5794the Florida Constitution, are more appropriately dealt with by another forum,

5805since they are not invalid on their face. Department of Administration,

5816Division of Personnel v. Department of Administration, Division of

5825Administrative Hearing, 326 So.2d 187 (Fla. 1st DCA 1976); Department of Revenue

5837v. Young American Builders, 330 So.2d 864 (Fla. 1st DCA 1976); Smith v. Willis,

5851415 So.2d 1331 (Fla. 1st DCA 1982).

585885. The DOT has followed the rulemaking procedure, as set forth in Section

5871120.54, Florida Statutes, in every material way. DOT gave proper notice, and

5883followed the correct procedure for incorporating by reference the permit

5893provisions in the proposed amendments to Rule 14-46.01, Florida Administrative

5903Code. Section 120.52(8)(a), Florida Statutes (1989)

590986. The DOT cites as specific authority in support of the proposed rules

5922Sections 120.53(l) and 334.044(2), Florida Statutes, and, as the law

5932implemented, cites Sections 337.401, 337.403, 337.404 and 339.05, Florida

5941Statutes. These provisions provide in pertinent part:

5948334.044 Powers and duties of department.--

5954The Department shall have the following

5960general powers and duties:

5964(2) To adopt rules, procedures, and

5970standards for the conduct of its business

5977operations and the implementation of any

5983provision of law for which the department is

5991responsible.

5992* * *

5995337.401 Use of right-of-way for utilities

6001subject to regulation; permit; fees.--

6006(1) The department and local governmental

6012entities, referred to in ss. 337.401-337.404

6018as the "authority," that have jurisdiction

6024and control of public roads are authorized to

6032prescribe and enforce reasonable rules or

6038regulations with reference to the placing and

6045maintaining along, across, or on any road

6052under their respective jurisdictions any

6057electric transmission, telephone, or

6061telegraph lines; pole lines; poles; railways;

6067ditches; sewers; water, heat, or gas mains;

6074pipelines; fences; gasoline tanks and pumps;

6080or other structures hereinafter referred to

6086as the "utility."

6089(2) The authority may grant to any person

6097who is a resident of this state,. or to any

6108corporation which is organized under the laws

6115of this state or licensed to do business

6123within this state, the use of a right-of-way

6131for the utility in accordance with such rules

6139or regulations as the authority may adopt.

6146No utility shall be installed, located, or

6153relocated unless authorized by a written

6159permit issued by the authority. The permit

6166shall require the permitholder to be

6172responsible for any damage resulting from the

6179issuance of such permit. The authority may

6186initiate injunctive proceedings as provided

6191in S. 120.69 to enforce provisions of this

6199subsection or any rule or order issued or

6207entered into pursuant thereto.

6211337.403 Relocation of utility; expenses.--

6216(1) Any utility heretofore or hereafter

6222placed upon, under, over, or alone any public

6230road that is found by the authority to be

6239unreasonably interfering in any way with the

6246convenient, safe, or continuous use, or the

6253maintenance, improvement, extension, or

6257expansion, of such public road shall, upon 30

6265days written notice to the utility or its

6273agent by the authority, be removed or

6280relocated by such utility at its own expense

6288except as provided in paragraphs (a) and (b).

6296(a) If the relocation of utility facilities,

6303as referred to in S. 111 of the Federal-Aid

6312Highway Act of 1956, Pub.L.No. 627 of the

6320Eighty-Fourth Congress, is necessitated by

6325the construction of a project on the federal-

6333aid interstate system, including extensions

6338thereof within urban areas, and the cost of

6346such project is eligible and approved for

6353reimbursement by the Federal Government to

6359the extent of 90 percent or more under the

6368Federal Aid Highway Act, or any amendment

6375thereof, then in that event the utility

6382owning or operating such facilities shall

6388relocate such facilities upon order of the

6395department, and the state shall pay the

6402entire expense properly attributable to such

6408relocation after deducting therefrom any

6413increase in the value of the new facility and

6422any salvage value derived from the old

6429facility.

6430(b) When a joint agreement between the

6437department and the utility is executed for

6444utility improvement, relocation, or removal

6449work to be accomplished as part of a contract

6458for construction of a

6462facility, the department may participate in

6468those utility improvement, relocation, or

6473removal costs that exceed the departments

6479official estimate of the cost of such work by

6488more than 10 percent. The amount of such

6496participation shall be limited to the

6502difference between the official estimate of

6508all the work in the joint agreement plus 10

6517percent and the amount awarded for this work

6525in the construction contract for such work.

6532The department may not participate in any

6539utility improvement, relocation, or removal

6544costs that occur as a result of changes or

6553additions during the course of the contract.

6560(2) If such removal or relocation is

6567incidental to work to be done on such road,

6576the notice shall be given at the same time

6585the contract for the work is advertised for

6593bids, or 30 days prior to the commencement of

6602such work by the authority.

6607(3) Whenever an order of the authority

6614requires such removal or change in the

6621location of any utility from the right-of-way

6628of a public road, and the owner thereof fails

6637to remove or change the same at; his own

6646expense to conform to the order within the

6654time stated in the notice, the authority

6661shall proceed to cause the utility to be

6669removed. The expense thereby incurred shall

6675be paid out of any money available therefore,

6683and such expense shall, except as provided in

6691subsection (1), be charged against the owner

6698and levied and collected and paid into the

6706fund from which the expense of such

6713relocation as paid.

6716337.404 Removal or relocation of utility

6722facilities; notice and order; court review--

6728(1) Whenever it shall become necessary for

6735the authority to remove or relocate any

6742utility as provided in the preceding section,

6749the owner of the utility, or his chief agent,

6758shall be given notice of such removal or

6766relocation and an order requiring the payment

6773of the cost thereof, and shall be given

6781reasonable time, which shall not be less than

678920 or more than 30 days, in which to appear

6799before the authority to contest the

6805reasonableness of the order. Should the

6811owner or his representative not appear, the

6818determination of the cost to the owner shall

6826be final. Authorities considered

6830for the purposes of chapter 120 shall

6837adjudicate removal or relocation of utilities

6843pursuant to chapter 120.

6847(2) A final order of the authority shall

6855constitute a lien on any property of the

6863owner and may be enforced by filing an

6871authenticated copy of the order in the office

6879of the clerk of the circuit court of the

6888county wherein the owner's property is

6894located.

6895(3) The owner may obtain judicial review of

6903the final order of the authority within the

6911time and in the manner provided by the

6919Florida Rules of Appellate Procedure by

6925filing in the circuit court of the county in

6934which the utility was relocated a petition

6941for a writ of certiorari in the manner

6949prescribed by said rules or in the manner

6957provided by chapter 120 when the respondent

6964is an agency for purposes of chapter 120.

6972339.05 Assent to federal aid given.--The

6978state hereby assents to the provisions of the

6986Act of Congress approved July 11, 1916, known

6994as the Federal Aid Law, which Act of

7002is entitled "An act to provide that the

7010United States shall aid the states in the

7018construction of rural post roads and for

7025other purposes," and assents to all

7031subsequent amendments to such Act of Congress

7038and any other act heretofore passed or that

7046may be hereafter passed providing for federal

7053aid to the states for the construction of

7061highways and other related projects. The

7067department is authorized to make application

7073for the advancement of federal funds and to

7081make all contracts and do all things

7088necessary to cooperate with the United States

7095Government in the construction of roads under

7102the provisions of such Acts of Congress and

7110all amendments thereto.

7113A. Rule 14-46.0011

711687. The DOT's proposed Rule 14-46.0011 concerning DOT's liaison with

7126utilities is a statement of general policy, and is a reasonable rule authorized

7139by Sections 334.044(2), 337.401, 337.403, 337.404 and 337.405, Florida Statutes

7149These statutes are correctly cited by DOT in support of this proposed rule. On

7163its face, this proposed rule does not offend any of the provisions of Sections

7177120.52(8) or 120.54(4), Florida Statutes, and, therefore, does not constitute an

7188invalid exercise of delegated legislative authority. As a statement of general

7199policy it is not vague. Since no decisions affecting substantial interest are

7211intended under this proposed rule, the rule need not specify any standards for

7224agency decisions. Since the rule directs DOT to coordinate with utilities in

7236planning its highway projects, the rule does not vest unbridled discretion in

7248DOT.

7249B. Rule 14-46.001 - Utility Permit, Paragraph 12

725788. Proposed paragraph 12 of the Utility Permit provides:

726612. It is agreed that in the event the

7275relocation of said utility facilities are

7281scheduled to be done simultaneously with the

7288Department's construction work, the permitee

7293will coordinate with the Department before

7299proceeding, shall cooperate with the

7304Department's contractor to arrange the

7309sequence of work so as not to unnecessarily

7317delay the work of the Department's

7323contractor, defend any legal claims of the

7330Department's contractor due to delays caused

7336by the permittee's failure to comply with the

7344approved schedule, and shall comply with all

7351provisions of the law and Rule 14-46, Florida

7359Administrative Code. The Permittee shall not

7365be responsible for delays beyond its normal

7372control.

737389. The DOT cites in support of the proposed rule, in particular, Sections

7386334.044(2), 337.401, 337.403, 337.404 and 339.05, Florida Statutes. This

7395statutory scheme authorizes DOT to make and enforce reasonable rules with which

7407utilities must comply before receiving a permit to be accommodated on the DOT

7420right-of-way. The DOT's mission under the State Transportation Code is to plan,

7432construct and maintain transportation facilities. Section 334.404(13), Florida

7440Statutes (1989). The accommodation of utilities by permit is subject to

7451compliance by utilities with reasonable DOT rules. Section 337.401(1), Florida

7461Statutes (1989), authorizes DOT to "prescribe and enforce reasonable rules or

7472regulations" with reference to the accommodation of utilities on roads within

7483DOT's jurisdiction. While Section 337.401(2), Florida Statutes, states, in

7492pertinent part:

7494(2) . . . No utility shall be installed,

7503located or relocated unless authorized by a

7510written permit issued by the authority. The

7517permit shall require the permitholder to be

7524responsible for any damage resulting from

7530the issuance of such permit.

753590. It is clear that a statutory condition of the permit requires that the

7549utility shall be responsible for any damage resulting from the issuance of a

7562permit [Section 337.401(2)], and also, the utility must, at its own expense,

7574restore any public road which it damages or impairs in any way because of the

7589installation, inspection or repair of its facilities located on the road. The

7601DOT may charge the cost of such restoration to the utility if the utility fails

7616to act. Section 337.402, Florida Statutes.

762291. Under this statutory scheme, the right of utilities, including

7632whatever rights are provided telephone companies under Section 362.01, Florida

7642Statutes (1987), are subordinate to DOT and the rights of the traveling public

7655to the use of the public roads of this state.

766592. The DOT argues that it is requiring the utility to bear the burden of

7680defense only for claims which DOT would not have had but for the utility's

7694failure to follow its schedule, and only if the failure was within the utility's

7708control. This is a reasonable interpretation of the statutory requirement that

7719a permitholder shall be responsible for "any damage resulting from the issuance

7731of such permit." Section 337.401(2), Florida Statutes.

773893. The DOT has a problem with the mechanics of implementing paragraph 12.

7751The DOT cannot explain which utility would defend the DOT if more than one

7765utility is involved, a frequent occurrence. The DOT testified that the

7776utilities' duty to defend did not extend to "delays beyond its normal control,"

7789and that "normal control" is construed to mean a precondition of the defense

7802duty. "Normal control" could be interpreted in different ways even if

7813guidelines were established. The DOT admitted that there could be litigation

7824over the term "normal control." However, the sentence is not so vague that a

7838person of common intelligence cannot say with certainty from the terms of such

7851rule or statute what is required. See: D'Alemberte v. Anderson, 349 So.2d 164

7864(Fla. 1977).

786694. The DOT put the defense provision in the Permit to force such

7879provisions upon the utility without its consent, because they would not

7890voluntarily consent to the provision during contract negotiations.

789895. The DOT wants this provision: (l) to enforce the provision that

7910utilities will do what they are supposed to do to keep a contractor from being

7925delayed in relocation work; and (2) to give the DOT an additional remedy, a

"7939clout of enforcement," with respect to relocations whereby the DOT could revoke

7951the utility permit in the event of noncompliance. The DOT's intent is to force

7965the provisions through rulemaking into the Permit; then, by the fact the

7977provisions are in the Permit, to require the same type of language be included

7991in a relocation contract.

799596. The utility permit is issued when the utility installs its facilities

8007on the DOT right-of-way; a separate agreement controls relocations. A DOT

8018permit )S only to a utility's facilities that are located on the DOT right-of-

8032way and not to those facilities located in public right-of-way owned by other

8045government agencies, platted utility easements or private easements. Any of

8055these facilities -- to which the Permit does not apply -- could be relocated as

8070the result of a DOT construction project.

807797. The DOT Quality Improvement Team, after studying delay claims,

8087determined the primary root cause of the problems were outdated and inadequate

8099DOT procedures. The recommended solutions to help reduce utility delays did not

8111include the defense and indemnification provisions contained in proposed

8120paragraphs 12 and 15 of the Permit.

812798. The DOT did not consider all relevant facts. The DOT looked at only

8141three things in considering the impact of the proposed rule. The conclusion

8153that the proposed rule would result in a $2 million saving due to reduction in

8168utility delays is an estimate only. The DOT did not consider settlement amounts

8181or the fact that the majority of delay claims were associated with water and

8195sewer relocation. The DOT made no effort to break the claims down into type of

8210utilities and, even though it is not surprised that the majority of claims

8223involved water and sewer facilities, doesn't know why that should be so.

823599. It is the DOT and the DOT's contractor who are responsible for

8248coordinating the various utility schedules and the construction work into one

8259project schedule. The DOT contractor submits this project schedule to the DOT

8271and the DOT project engineer and the district construction engineer review that

8283schedule and have authority to disapprove that schedule. It is not this project

8296schedule, however, but the "approved" utility schedule of the individual utility

8307which gives rise to the utility's duty to defend the DOT against the claims of

8322the DOT's contractor in paragraph 12 of the Permit This approved schedule is

8335prepared at the time that the utility has no knowledge of how the contractor

8349wants to proceed on the job --. the contractor may have a different approach to

8364constructing the job which could result in the utility changing their plane as

8377to where they planned to start work.

8384100. The requirement of a pre-construction conference and a project

8394schedule was implemented by the DOT only toward the end of 1987, when DOT's

8408standard form contract was amended to include scheduling requirements on the

8419part of the contractor. It is too early, and there is no data yet available, to

8435tell whether this new procedure will be effective, as it is anticipated to be,

8449in helping to reduce delays caused by utility relocations.

8458101. Further, the DOT in proposing paragraph 12 did not reasonably

8469consider the fact that the utility is not a party to the construction contract

8483between DOT and the DOT contractor. The utility has no control over the terms

8497and conditions of that contract, including the ability of the DOT contractor to

8510sue the DOT for delay claims. When the DOT contractor sues because of a utility

8525delay, it sues the DOT based on its construction contract with the DOT and may

8540allege the DOT's failure to coordinate the relocation efforts of the utility

8552owners constituted a breach of the Contract. DOT may then join the utility as a

8567third party.

8569102. Although it may not be wise or efficient, it is not arbitrary to

8583force a utility as a condition of right-of-way use to defend the DOT against

8597DOT's own contractors, when the delay claim is allegedly due to delays caused by

8611the utility's failure to comply with the approved schedule.

8620103. The preponderance of evidence is that the phrase

"8629. . . defend any legal claims of the Department's contractor due to delays

8643caused by the permittee's failure to comply with the approved schedule . . . "

8657within DOT's proposed paragraph 12 of the new Utility Permit is not an invalid

8671exercise of delegated legislative authority, as defined in Section 120.52(8),

8681Florida Statutes.

8683C. Paragraph 15 of the Utility Permit Indemnification of DOT's Joint

8694Negligence

8695104. The proposed paragraph 15 of the Utility Permit, which is a part of

8709the Utility Accommodations Guide (UAG), is incorporated by reference into Rule

872014-46.001. By its terms, the "except [for the] . . . sole negligence"

8733provision requires the utility to pay for the joint negligence of the DOT as a

8748condition of use of the DOT right-of-way.

8755105. Under the provisions of Section 337.401, Florida Statutes, DOT can

8766require the utility to be responsible for any damage resulting from the issuance

8779of a permit. Under the existing provisions of paragraph 15 of the Utility

8792Permit, utilities are required to indemnify, defend, and save harmless the DOT

8804from all loss, damage, cost or expense arising from the permit. The proposed

8817new paragraph 15 provision which requires indemnification, except for DOT's sole

8828negligence is an extension of that provision. Paragraph 12 of the existing

8840standard form Master Agreements, previously executed by Petitioners, requires

8849utilities to defend against contractor delay claims due to delays caused by the

8862utilities' negligence that were not beyond its control. The new permit requires

8874the utility to defend DOT from any delay claims caused by the utility's failure

8888to comply with its approved work schedule other than for delays beyond the

8901utility's normal control, and indemnify DOT for any claim, loss, damage, cost,

8913charge or expense except for damages resulting from the sole negligence of the

8926DOT.

8927106. Under proposed paragraph 15, if there was a judgment finding that the

8940DOT was 99% negligent and the utility was 1% negligent, the utility would have

8954to pay the entire judgment. Under the general law relating to comparative fault

8967and contribution among tort-feasors, the utility would have a judgment entered

8978against it and, therefore, have to pay for only 1% of that liability -- the part

8994directly attributed to the utility's own fault. Paragraph 15 of the Utility

9006Permit modifies Florida negligence law, Section 768.81, Florida Statutes, and

9016enlarges, modifies or contravenes the specific provisions of Section 337.401(2),

9026Florida Statutes, permitting the DOT to hold the utility responsible for any

9038damage that the utility causes. State Board of Optometry v. Florida Society of

9051Ophthalmology, 539 So.2d 878. As the court stated at p. 885

9062We recognize that in [Department of

9068Professional Regulation, Board of Medicine v.

9074Durrani, 455 So.2d 515 (Fla. 1st DCA 1984] we

9083indicated that the court must approve the

9090agency's selection of any possible

9095interpretation of the enabling statute. But

9101in so stating, we did not mean that any

9110conceivable construction of a statute must be

9117approved irrespective of how strained or

9123ingeniously reliant or implied authority is

9129might be; rather, as made clear in the cases

9138cited in Durrani in support of the stated

9146proposition, only a permissible construction

9151by the agency that comports with and

9158effectuates discerned legislative intent will

9163be sustained by the court. (citations

9169omitted)."

9170DOT's interpretation of the statute goes beyond the permissible construction

9180that can be given to the statute and is an invalid exercise of delegated

9194legislative authority.

9196107. The DOT found it necessary to put the indemnification provision in

9208the Permit because the utilities would not sign a contract with that language in

9222the contract. Because Florida law views indemnification of another for that

9233other's own negligence with disfavor, it allows such indemnification only in

9244contracts freely entered into, provided that the indemnification is expressed in

9255clear and unequivocal terms. See: Charles Poe Masonry, Inc. v. Spring

9266Scaffolding Rental Equipment Company,

9270108. The DOT strongly relies on the case of Mitchell Maintenance Systems

9282v. State, Department of Transportation, 442 So.2d 276 (Fla. 4th DCA 1983), in

9295its justification for implementing paragraph 15. The sole issue decided by the

9307court in Mitchell, supra, is that the indemnification language identical to the

9319language which DOT proposes for paragraph 15 of the Permit is clear and

9332unequivocal. However, the Mitchell case is limited by its facts to a contract

9345situation. It is limited to a contract willingly entered into by a private

9358individual who wished to perform maintenance work on DOT utility poles. Mitchell

9370does not involve rulemaking, does not involve public utility use of right-of-way

9382and does not involve the public policy issues of providing economic utility

9394service or land use discussed above.

9400109. Further, unlike the situation in Mitchell where the maintenance work

9411is completely under the control of the party agreeing to indemnify the DOT with

9425respect to any damage arising out of that maintenance work, the control on the

9439right-of-way situation is with the DOT or third persons. The road construction

9451and maintenance of the road is under the control and is the responsibility of

9465DOT. The DOT's use of the Mitchell case, as justification for shifting the cost

9479of the DOT's joint negligence to the utility through rulemaking is not legal

9492authorization for requiring the utility to pay for DOT's joint negligence.

9503110. Prior to the adoption of any rule, Section 120.54(2)(b), Florida

9514Statutes, mandates that an agency prepare an economic impact statement (EIS) to

9526promote agency introspection in administrative rulemaking; to ensure a

9535comprehensive and accurate analysis of economic factors which work with social

9546and legislative goals to facilitate informed decision making and to expose the

9558administrative rulemaking process to public scrutiny. Florida-Texas Freight,

9566Inc. v. Hawkins, 379 So.2d 933, at 946 (Fla. 1979). In Dept. of Health &

9581Rehabilitative Services v. Wright, 439 So.2d 937 (Fla. 1st DCA 1983), the court

9594held that an economic impact statement which insufficiently addressed the

9604potentially substantial economic repercussions of a proposed rule change was

9614invalid and, hence, the rule was an invalid exercise of delegated legislative

9626authority. The court said:

9630. . .materiality of the economic impact

9637statement to the rulemaking process cannot be

9644given short shrift. Preparation of the

9650statement is a sobering task, one designed to

9658arrest agency discretion bordering on the

9664despotic, and to channel it through logic and

9672reason to a rational end. Id. at 641

9680111. The EIS prepared by DOT and incorporated in the June 16 edition of

9694the Florida Administrative Weekly is inaccurate and misleading in claiming that

9705construction delays of $3.7 million are attributable to utilities. The costs of

9717claims for delays related to utilities' problems are insignificant overall and

9728cannot serve as a reasonable basis for adoption of the proposed rules.

9740112. A public utility has a general requirement under Section 366.03,

9751Florida Statutes (1989), to provide the public with adequate and economical

9762utility installations and services. The DOT did not consider the fact in the EIS

9776that in shifting the cost of DOT's joint negligence to the utility, DOT is

9790imposing substantial costs on the utility and is, in fact., increasing those

9802costs by an unquantifiable amount. These additional costs can have a negative

9814impact on the utility's ability to provide economical service.

9823113. The DOT did not consider that the indemnification amounts which the

9835utility would have to pay DOT foil DOT's joint negligence could be in excess of

9850the $100,000 - $200,000 allowed under the waiver of sovereign immunity statute,

9864Section 786.28, Florida Statutes (1989).

9869114. The EIS discussing the costs and benefits of the proposed rule

9881change, completely ignores the cost of requiring utilities to assume all of

9893DOT's tort and contract liability, except where the Department is solely

9904negligent.

9905Section 120.54(2), Florida Statutes (1989), provides that an agency's

9914failure to include within its rule an "adequate" statement of economic impact is

9927grounds for invalidation of the rule. The Florida Supreme Court has observed

9939that the procedure envisioned by this section does not "command adherence to

9951form over substance," Florida-Texas Freight, supra, and that provision does not

9962require perfection but only "substantial compliance" with Section 120.57(2)(b),

9971Florida Statutes (1989). In the matter before this tribunal, DOT gave no

9983consideration at all to the economic impact of shifting liability from the

9995Department to the utility and ultimately the utility's ratepayers. This section

10006of the rule could be devastating economically to the utility permitholder and,

10018therefore, the Department's reasoning for its adoption is not supported by law

10030or logic and is invalid. Department of Health and Rehabilitative Services v.

10042Wright, 439 So.2d 937 (Fla. 1st DCA 1983).

10050115. Paragraph 15 of the Utility Permit enlarges, modifies or contravenes

10061the law implemented, and the EIS is not adequate as pertains to this section and

10076is, therefore, an invalid exercise of delegated legislative authority under

10086Sections 120.52(8)(c) and 120.54(2)(b), Florida Statutes (1989). Therefore,

10094based on the foregoing findings of fact and conclusions of law it is

10107ORDERED, as follows:

101101. Proposed Rule 14-46.0011 is not an invalid exercise of delegated

10121legislative authority;

101232. Proposed Rule 14-46.001 and the Utility Accommodation Guide, adopted by

10134reference therein, Which includes a new form Utility Permit, are not an invalid

10147exercise of delegated legislative authority, except for Paragraph 15 of the

10158Utility Permit, contained within the UAG and adopted by reference in proposed

10170Rule 14-46.001, which is held to be invalid. Section 120.52(8)(c) and

10181120.54(2)(b), Florida Statutes (198).

101853. Except for the issues abated (see: Preliminary Statement), all other

10196issues are dismissed, and the Department of Transportation is free to conclude

10208its rule promulgation of the rules and Utility Accommodation Guide.

10218Jurisdiction of the abated issues are remanded to the Department of

10229Transportation for resolution through formally announced and noticed changes to

10239the proposed rules.

10242DONE and ORDERED this 8th day of March, 1990, in Tallahassee, Leon County,

10255Florida.

10256__________________________

10257DANIEL M. KILBRIDE

10260Hearing Officer

10262Division of Administrative Hearings

10266The DeSoto Building

102691230 Apalachee Parkway

10272Tallahassee, Florida 32399-1550

10275(904) 488-9675

10277Filed with the Clerk of the

10283Division of Administrative Hearings

10287this 9th day of March, 1990.

10293APPENDIX

10294The following constitutes my specific rulings, in accordance with section

10304120.59, Florida Statutes, on findings of fact submitted by the parties.

10315Proposed Findings of Fact - GTE Florida Inc.

10323Accepted: Paragraphs 1, 2, 4, 5 (impart) , 6, 7, 8 (in substance) 9, 10, 13,

1033814, 15

10340Rejected: Against weight: 3, 5 (in part) Argument: 11, 12

10350Proposed Findings of Fact-Florida Power and Light Co.

10358Accepted 1, 2 (in substance), 3, 6, 7, 8, 9, 10, 11, 12, 13, 15, 16, 17, 18, 19,

1037720, 21, 23, 24, 25 (in substance), 26, 27, 28 (in substance), 29, 31

10391Rejected: - Against greater weight of the evidence: 4, 5

10401- Subservient: 14

10404- conclusions of law: 22, 30, 32

10411Proposed Findings of Fact - Southern Bell Telephone and Telegraph Co.

10422Accepted: 1, 2, 4, 5, 6, 7, 10 (in substance), 12 (in substance) Rejected:

10436Resolved in the Preliminary Statement: 3

10442- conclusion of law: 8, 9, 13, 14, 17

10451- not supported by the greater weight of the

10460evidence: 11, 15, 16

10464Proposed Findings of Fact - Department of Transportation

10472Accepted: (as stated or in substance): 10, 11, 12, 13, 15, 16, 17, 18, 19, 20,

1048821 (in part), 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35 36, (in

10507part), 42, 46, 47, 48, 49, 50, 51, 55(in part), 57, 60, 62, 63, 64, 65, 68, 69,

1052570, 71, 72, 75, 77, 82, 84, 87, 88

10534Rejected as resolved in the Preliminary Statement: 1, 2, 3, 4, 5, 6, 7, 8, 9,

1055014

10551Rejected as irrelevant or subservient: 58, 79, 80, 81, 85, 94

10562Rejected as argument: 44, 45, 54, 56, 61, 66, 67, 73, 74, 78, 83, 90, 91, 95,

1057996, 91

10581Rejected as not supported by the greater weight of the evidence: 21 ( in part),

1059637, 38, 39, 40, 41, 43, 52, 53, 55 (in part), 59, 76, 85, 86, 87

10612COPIES FURNISHED:

10614Robert P. Daniti, Esquire Ben G. Watts, Esquire

10622Senior Litigation Attorney Secretary

10626Department of Transportation Department of Transportation

10632605 Suwannee Street 605 Suwannee Street

10638Tallahassee, FL 32399-0458 Tallahassee, Fl 32399-0458

10644Attn: Eleanor Turner, MS 58

10649Lorin H. Albeck, Esquire

10653General Attorney Thomas H. Bateman, III

10659GTE Florida Incorporated General Counsel

10664Post Office Box 110, Mail Code 7 Department of Transportation

10674Tampa, FL 33601-0110 562 Haydon Burns Building

10681Tallahassee, FL 32399-0458

10684Jean G. Howard, Esquire

10688Law Department

10690Florida Power and Light Company

10695Post Office Box 029100

10699Miami, FL 33102

10702Robert G. Beatty, Esquire

10706Southern Bell Telephone

10709Legal Department

10711Museum Tower, Suite 1910

10715150 West Flagler Street

10719Miami, FL 33130

10722Kay L. Wolf, Esquire

10726Assistant Vice President-

10729Law

10730United Telephone Company

10733of Florida

10735Post Office Box 5000

10739Altamonte Springs, FL 32716-5000

10743Richard Brightman, Esquire

10746Post Office Box 6526

10750Tallahassee, FL 32314

10753NOTICE OF RIGHT TO JUDICIAL REVIEW

10759A PARTY WHO IS ADVERSELY AFFECTED BY THIS FINAL ORDER IS ENTITLED TO JUDICIAL

10773REVIEW PURSUANT TO SECTION 102.68, FLORIDA STATUTES. REVIEW PROCEEDINGS ARE

10783GOVERNED BY THE FLORIDA RULES OF APPELLATE PROCEDURE. SUCH PROCEEDINGS ARE

10794COMMENCED BY FILING ONE COPY OF A NOTICE OF APPEAL WITH THE AGENCY CLERK OF THE

10810DIVISION OF ADMINISTRATIVE HEARINGS AND A SECOND COPY, ACCOMPANIED BY FILING

10821FEES PRESCRIBED BY LAW, WITH THE DISTRICT COURT OF APPEAL, FIRST DISTRICT, OR

10834WITH THE DISTRICT COURT OF APPEAL IN THE APPELLATE DISTRICT WHERE THE PARTY

10847RESIDES. THE NOTICE OF APPEAL MUST BE FILED WITHIN 30 DAYS OF RENDITION OF THE

10862ORDER TO BE REVIEWED.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 03/08/1990
Proceedings: DOAH Final Order
PDF:
Date: 03/08/1990
Proceedings: Final Order (hearing held , 2013). CASE CLOSED.

Case Information

Judge:
DANIEL M. KILBRIDE
Date Filed:
06/26/1989
Date Assignment:
07/24/1989
Last Docket Entry:
03/08/1990
Location:
Tallahassee, Florida
District:
Northern
Agency:
Department of Transportation
Suffix:
RP
 

Related DOAH Cases(s) (5):

Related Florida Statute(s) (16):

Related Florida Rule(s) (1):