89-005053 Mary Anne Hoffert, Barbara D. Winn, Inez Stanton, Dorothy S. Holland, Ed And Lala Connell, Denver R. And Natalie H. Bennett vs. St. Joe Paper Company And Department Of Environmental Regulation
 Status: Closed
Recommended Order on Friday, October 26, 1990.


View Dockets  
Summary: Application showed preponderance evidence of reasonble assurance that marina project would not violation class III water quality standards public interest standards adequate.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8FOR PETITIONERS: Mary Cornwell, pro se

14(Mary and Irv 2652 State Road 13

21Cornwell) Switzerland, FL 32259

25FOR RESPONDENT: T. R. Hainline, Jr., Esq.

32and conclusions of law, on August 22, 1990. The Department filed a post-hearing

45pleading indicating that it joined in the proposed recommended order submitted

56by the applicant and would not be submitting its own proposed recommended order.

69Barbara Davis Winn, representing Hoffert, timely filed a letter to the Hearing

81Officer, in lieu of a proposed recommended order, indicating that Hoffert would

93not be filing a proposed recommended order, but requesting the Hearing Officer,

105in rendering his Recommended Order, to take into account a number of

117considerations involving environmental and recreational concerns held by those

126Petitioners, and upon which they had presented evidence at hearing, in arriving

138at conditions for any grant of the permit recommended in the Recommended Order.

151Cornwell submitted a pleading entitled "Notice of Filing Petitioners'

160Recommended Findings and Clarifications of Respondents' Proposed Findings". This

170pleading was filed on September 7, 1990, over two weeks late. Additionally, the

183pleading seeks to clarify or respond to the proposed findings of fact and

196conclusions of law timely submitted by the Respondents. As explained by the

208Hearing Officer at the conclusion of the hearing, proposed recommended orders

219are not responsive pleadings, but must be simultaneously submitted by the

230deadline which was set and agreed upon by all of the parties. Further, much of

245Cornwell's "proposed findings" really involve a discussion and recitation of

255testimony or evidence, chiefly that submitted through Dr. Carol DeMort's

265deposition, instead of proposing specific findings of fact, which can be ruled

277upon in a coherent fashion by the Hearing Officer. Consequently, specific

288rulings on proposed findings of fact submitted by Cornwell cannot be made since

301none were actually submitted as such. However, in spite of this, and in spite

315of the non-timely filing of this pleading and its impermissible nature as a

328responsive pleading, the relevant issues and discussions raised in it have been

340considered and addressed by the Hearing Officer in this Recommended Order.

351In consideration of the evidence and testimony adduced

359and admitted into evidence and the post-hearing pleadings and

368arguments of the parties, the following findings of fact are

378entered.

379FINDINGS OF FACT

3821. The applicant, St. Joe, seeks to construct and

391operate a recreational boat marina, consisting of a single, main

401pier, 12 feet wide and extending some 850 feet waterward in a

413westerly direction from the shoreline of the east bank of the St.

425Johns River in St. Johns County, Florida. The main pier will

436join a terminal pier extending approximately 575 feet in a

446general north/south direction parallel to the shoreline of the

455St. Johns River, perpendicular to and abutting the longer main

465pier. Extended in a landward or easterly direction from the

475terminal pier structure will be four (4) individual "finger

484piers" ranging from 119 to 305 feet in length. Located along the

496individual piers and along a portion of the main pier near the

508waterward end of it will be 84 slips for recreational-type boats.

519Additionally, a breakwater system will be suspended along the

528outer perimeter of the terminal pier and northernmost and

537southernmost individual piers in order to reduce wave action and

547its effect on boats in the interior of the marina. Additional

558details concerning the marina design and operation are contained

567in the findings of fact below.

573The Site

5752. The site of the proposed marina is on the eastern

586shore of the St. Johns River in St. Johns County, Florida. At

598that point, the St. Johns River is almost two miles wide, being

610approximately 10,000 feet from shoreline to shoreline. The

619proposed marina site encompasses approximately 1,100 linear feet

628of river bank frontage. All of the adjacent upland property is

639owned by St. Joe, and St. Joe owns extensive additional river

650frontage to the north and south of the marina site. The nearest

662properties not owned by St. Joe are located 3,500 feet to the

675north of the site and 1,500 feet to the south of the site. The

690site is located approximately two miles north of Hallowes Cove, a

701relatively pristine, diverse and productive marine habitat.

7083. The site is characterized, landward of the

716terminal end of the pier and waterward of the upland, by an

728unvegetated "near shore area or tidal zone" which extends

737approximately 50 feet from the mean high-water line of the river

748to the mean low-water line. Waterward of this zone and extending

759to a depth of approximately two feet is a system of grass beds,

772(vallisnerida), commonly known as "tape grass". The grass beds

782extend approximately 200 to 250 feet from the shoreline.

791Waterward of the grass beds is an unvegetated area with a gradual

803slope to a depth of approximately six feet. From the six-foot

814contour of the river bottom, a relatively precipitous slope

823begins, extending to depths which exceed 19 feet. In this zone, there are no

837grass beds. Further waterward and extending beyond

844the most waterward extent of the the marina site, the river bottom rises

857somewhat to depths of 13 feet, 12 feet and 11 feet, in the direction of the

873center of the river.

8774. The river bottom substrate in the area of the

887marina is composed primarily of sand. This includes some shell

897and other coarse materials, with minor amounts of silt. In fact,

908organic silt is a very small portion of the bottom sediments,

919consisting, at a depth of four and one-half feet, of less than 1%

932silt and at a depth of 15 feet of less than 6% silt content. The

947present water quality prevailing at the marina site is good, and

958the benthic habitat in the general area is healthy and diverse.

9695. The most landward boat slips proposed at the

978marina will be located at a distance of approximately 275 feet

989from the most waterward extent of the grass beds. These most

1000landward slips will be located in depths of approximately eight

1010feet.

10116. Access to the marina will be from the north and

1022south in defined channels marked on the west by the end of the

1035individual piers and on the east by channel markers located at

1046the depth contour of minus six feet. That is, the six-foot depth

1058will be the most shallow portion of the channel marked by the

1070channel markers, so that boats will not be permitted to navigate

1081the shallower portion landward of the channel markers insofar as

1091the marina's enforcement program can insure that. The

1099approximate width of the northern channel is 75 feet, and the

1110width of the southern channel is 50 feet. Due to the precipitous

1122drop in depth beyond the contour of minus six feet, the average

1134depth of the channels is 10 to 12 feet.

11437. The majority of the boat slips, as well as the

1154basin of the marina, will be located in depths of between 10 and

116718 feet. The consultant and expert witness who designed the

1177marina, Erik Olsen, established that the length of the main pier

1188and the location of the most landward of the boat slips and the

1201location of the channel markers are all part of a design and plan

1214intended to insure that marina and boat activity within the

1224marina occur well beyond the extant grass beds and waterward of

1235depths of six feet, to insure that no damage to the grass bed

1248habitat area is occasioned by propeller scouring, "prop-wash", or

1257grounding of boats.

12608. Other design measures are also intended to

1268preclude boaters from entering the shallow depths and grass bed

1278areas. Two tiers of signs will be located between the marina

1289basin and the most waterward extent of the grass beds. First,

1300regulatory buoys and signs are proposed to be located at the

1311contour of minus four feet and will establish a "manatee

1321protection zone" landward of that contour. The evidence reveals,

1330however, that a safer contour for the manatee protection zone

1340boundary to be established by the applicant would dictate placing

1350the regulatory warning signs concerning the manatee protection

1358zone at the same contour, minus six feet of water, where the

1370channel markers will be located. This is because the marina will

1381serve boats of up to 4.5 feet in draught. Secondly, a tier of

1394signs will be located approximately ten feet waterward of the

1404most waterward extent of the grass beds warning boaters that

1414aquatic grass beds exist landward of the signs and that prop dredging and boat

1428operation is prohibited. Such warnings at the locations found above should be

1440mandatory conditions to any grant

1445of the permit. A specific, agreed-upon condition is already in

1455the draft permit issued by the Department prescribing the size

1465and lettering of these signs and other design details. A railing

1476will extend, as proposed by the applicant, along the main pier

1487between the slips and the shoreline to discourage boaters from

1497mooring along the main pier, landward of the slips. The evidence

1508establishes that in order to more adequately insure protection of

1518the manatee habitat area and the grass beds, a mandatory

1528condition in boat-slip rental leases should be inserted to

1537absolutely prohibit boaters from mooring along the main pier,

1546landward of the boat slips.

15519. Because of the currents and significant water

1559depth prevailing at the marina site, the marina construction will

1569require no dredging nor will operation and maintenance of the

1579marina require any dredging on a continuing basis. Additionally,

1588in the interest of protecting water quality, no fueling

1597facilities or boat fueling will be permitted at the marina at

1608all; and the grant of a permit should be mandatorily conditioned

1619on this basis.

162210. Neither will any boat maintenance or repair be

1631permitted at the marina, including no hauling of boats or

1641scraping or painting of boat bottoms. This condition should be

1651clearly pointed out to users of the marina by appropriate warning

1662signs regarding the prohibition against boat maintenance and

1670repair, including warnings concerning the proper methods of

1678disposal of used oil and other petroleum products.

168611. The marina will feature pump-out facilities for

1694boat heads and bilges. The pump-out facilities will consist of a

1705central pumping system in which waste is removed from the boats,

1716transported by pipeline to an upland, central waste water

1725collection and treatment system. No holding tanks or other

1734storage of wastes will be located at the piers. The pump-out

1745facility will serve not only the boat heads but also boat bilges

1757in order to prevent contaminants, such as oil and boat fuel from

1769entering the State waters involved.

177412. The piers will feature trash collection

1781containers of appropriate number, size and location on the piers

1791so as to provide convenient trash disposal for each boat slip.

1802The piers will also feature plastic modular dock boxes to

1812preclude boaters from randomly storing materials and equipment on

1821the piers. No fish cleaning will be permitted on the piers at

1833all, but rather must be accomplished on the uplands, with

1843disposal of related wastes in the upland collection system.

185213. A "no wake" zone will be established in an area

1863extending 500 feet north and 500 feet south of the marina. The

"1875no wake" zone will be marked pursuant to requirements of the

1886Florida Marine Patrol. The marked "no wake" zone should also

1896extend waterward of the farthest waterward extent of the marina,

1906as well as 500 feet north and south of it.

191614. Only private, recreational boats will be moored

1924at the marina. All commercial boats will be prohibited. The

1934marina will serve a Yacht Club to be developed by St. Joe in

1947conjunction with the marina. Only members of the Yacht Club and their guests

1960will be permitted to use the marina. This will

1969assist with enforcement of the various conditions on marina

1978operation and maintenance by the owners as to the boat-slip

1988lessees and their guests. This and all other conditions should

1998be enforced by mandatory restrictions in the boat-slip leases.

2007Likewise, the applicant has agreed to permit no "liveaboard"

2016boats at the marina in order to avoid the possibility of sewage

2028or other contaminants entering the State waters from liveaboard

2037boats. The upland facilities will include restrooms, and signs

2046should be appropriately placed on the piers to advise boaters and

2057boat owners and operators of the availability of restroom

2066facilities. The marina will not feature fueling facilities;

2074however, St. Joe will maintain pollution containment supplies and

2083equipment at the marina sufficient to contain any potential fuel

2093or other petroleum spills from catastrophic events, such as the

2103rupture of a boat fuel tank. Expert witnesses for St. Joe

2114established that a "management and operational plan" designed to

2123enforce the provisions enumerated above will be enacted by the

2133applicant. The management and operational plan includes three

2141mechanisms of enforcement:

2144A. Warning signs.

2147B. Boat-slip lease agreements which must incorporate

2154all restrictions found to be necessary herein. These will

2163contain an enforcement provision providing for mandatory eviction

2171from use and lease of the marina facilities for any breach of

2183those conditions by lessees or their guests.

2190C. Management personnel will be employed on the

2198marina property to enforce all restrictions and conditions

2206designed to insure environmentally-safe operation and maintenance

2213of the marina, and such personnel should be employed during all

2224operating hours of the marina, not just during daylight hours, as

2235proposed by the applicant.

223915. Signs will be posted at conspicuous locations at

2248the marina and at the upland facilities of the Yacht Club

2259informing boaters of the marina rules and prohibitions. The

2268signage will be visible to Yacht Club members and their guests

2279using the marina, and members' guests will be required, upon

2289mooring at the marina, to register and to review the rules and

2301prohibitions. Boat-slip lease agreements at the marina will

2309incorporate these marina rules and prohibitions. Under the lease

2318agreements, a violation of the marina rules or prohibitions by a

2329member or guest will be considered a breach of the lease and will

2342result in revocation of the lease and removal of the member's

2353boat from the marina.

235716. A dock master will be employed at the marina to

2368supervise the operation and maintenance of the marina and will be

2379assisted by dock hands and other personnel in order to see that

2391the conditions and restrictions referenced herein are enforced.

2399The applicant has proposed such personnel being employed during

2408daylight hours. However, in order to insure that the standards

2418for operation and maintenance of the marina and boats using it

2429will be enforced so as to avoid water-quality violations and

2439violations of the public interest parameters delineated below, the permit grant

2450should be conditioned upon such personnel being

2457employed during all operating hours of the marina, whether

2466daylight hours or not. If this is accomplished, the enforcement

2476mechanisms outlined in the management and operational plan will

2485reasonably insure enforcement of the marina's rules, prohibitions

2493and conditions on any grant of the permit and likewise reasonably

2504insure that water-quality and public interest standards are not

2513violated.

2514Upland Facilities

251617. The upland and Yacht Club facilities to be

2525developed in conjunction with the marina will be located on

2535approximately seven acres adjacent to the marina site. The Yacht

2545Club and related facilities will include a clubhouse, parking,

2554and a storm water treatment system which will serve the upland

2565facilities. St. Joe has obtained a conceptual permit for the

2575management and storage of surface waters for the proposed upland

2585improvements, including the Yacht Club. It will also seek a

2595permit for the storm water treatment system, itself. St. Joe,

2605through its consultants, has investigated and opined that the

2614installation of the proposed upland facilities are feasible and

2623can comply with applicable regulatory criteria and is pursuing

2632the necessary permits and approvals from local governments and

2641state agencies. It will insure that all such is accomplished

2651prior to initiation of construction of the Yacht Club facilities.

2661The precise configuration and design of all upland facilities

2670will be dictated by applicable local ordinances and the

2679requirements of State regulatory agencies.

2684Marina Impacts

268618. The applicant/Respondent and the Petitioners are

2693in essential agreement, through the testimony of their witnesses,

2702regarding the general potential impacts which may be posed by

2712marinas in a general sense, when located in proximity to

2722environmentally-sensitive areas. Concerning anticipated impacts

2727of this marina at the subject site, however, St. Joe presented

2738the testimony of three expert witnesses, as well as a hydrographic study. It

2751was thus established that violations of

2757the pertinent water-quality statute and rules and the public

2766interest standards contained in the statute referenced herein

2774will not be violated. The Petitioners, although presenting both

2783lay and expert testimony regarding the water quality and habitat

2793type and quality in the general area of the site and the general

2806impacts that can be caused by marinas in such areas, presented no

2818expert testimony or studies regarding the anticipated impacts of

2827this particular marina, as designed and configured by the

2836applicant, on the subject site and aquatic habitat.

2844Water Quality Considerations

284719. Marinas are potential sources of pollutants which

2855may adversely impact water quality. Different sources at a

2864marina may generate different pollutants; and in this case,

2873testimony addressed these potential pollutant impacts. The

2880totality of the expert testimony taken at hearing establishes

2889that the marina will not likely cause a violation of applicable

2900water-quality standards. One witness for the Petitioners, Bill

2908Watkins, was accepted as an expert in water quality. In

2918describing potential impacts of the marina, however, he only

2927opined that there "could be some effect on water quality";

2937however, he did not specifically establish adverse effects on

2946water quality which could be anticipated or reasonably expected

2955regarding violations of applicable standards. Mr. Watkins

2962acknowledged: "As to whether or not that degree of pollution,

2972and that's what we're talking about, degree of impact, would be

2983something that would be, have a significant degradation effect, I

2993could not answer without further site specific studies." Mr.

3002Watkins further described the type of site specific information

3011which would be required for him to make a proper assessment of

3023water-quality impacts, including hydrographics and the nature of

3031the sediments existing at the site. Other witnesses for the

3041Petitioners similarly declined to opine regarding violations of

3049the water-quality standards because site specific information was

3057not available to them. Dr. DeMort, for example, explicitly

3066declined to offer an opinion regarding water-quality violations.

307420. The opinions and testimony of the expert

3082witnesses on water quality presented on behalf of St. Joe, as

3093well as by the Department, are accepted in establishing that no

3104water-quality violations by the construction and operation of the

3113marina are anticipated.

311621. The reasonable assurance that water-quality

3122violations will not occur through the construction and operation

3131of the marina is illustrated by the unrefuted evidence concerning

3141the hydrographics by which the site is characterized. A

3150knowledge of site hydrographics is necessary to accurately determine potential

3160water-quality impacts. A hydrographic study

3165was prepared by St. Joe through the auspices of its consultant,

3176Olsen Associates Incorporated. The experts who prepared that

3184study testified on behalf of St. Joe at hearing, and a Department

3196witness who reviewed the study testified by deposition. None of

3206the Petitioners' expert witnesses addressed the subject of site

3215hydrographics other than to note that they were an important

3225consideration.

322622. Mr. Buckingham was accepted as an expert witness

3235in the area of marine engineering with emphasis on hydrographics.

3245He testified regarding the hydrographic study prepared and

3253submitted by St. Joe. The study involved the collection of data

3264at the site, including the gauging of water surface elevations

3274over a two-day period in December of 1988; the comparison of

3285those elevations to predicted elevations based upon historical

3293data; a measurement of current velocities at the site; a dye

3304study to assess the flow regime at the site; and the gathering of

3317depth soundings and sediment samples to confirm the bathymetry

3326and nature of bottom sediments at the site. The hydrographic

3336study also involved the analysis of the data collected at the

3347site.

334823. Hydrographics at the site are composed of two

3357components, the transport of a pollutant by advective currents

3366and the dispersion or diffusion of a pollutant within the water

3377column. The physical transport by advective currents dominates

3385the hydrographic circumstance prevailing at the marina site. A

3394pollutant introduced at the site is more likely to be physically transported

3406away from the site, in addition to being merely

3415dispersed through the water column at the site. This is because

3426of the relatively high current velocities prevailing. Both the

3435transport and dispersion components were analyzed in the study to

3445determine the time and distance necessary to reduce an initial

3455concentration of a hypothetical pollutant to 10% of its initial

3465concentration. A pollutant introduced at the site would be

3474reduced to 10% of its initial concentration in less than seven

3485minutes and within 400 feet of the site on the ebb tide and

3498within 300 feet of the site on the flood tide. Moreover, the

"3510plume" of this hypothetical pollutant would occur in a longshore

3520direction parallel to the shore, as opposed to a direction toward

3531the shore and would be of comparatively narrow width

3540(approximately 30 feet). The hydrographics of this site are such

3550that a complete water exchange will occur in 20 to 30 minutes at

3563any point during the tidal cycle. The evidence thus demonstrated

3573that the site is extremely well flushed by tidal currents.

358324. In his deposition, Ken Echternacht, of the

3591Department, testified that data in the hydrographic study was

3600realistic in his experience and that he had no questions or

3611concerns regarding the data and methodology used to confirm that

3621data. In addition to Mr. Buckingham's testimony and the study,

3631itself, the testimony of Dr. Echternacht established that

3639flushing is of no concern and is thoroughly adequate at the site.

3651Dr. Echternacht is the Department's hydrographic engineer, whose

3659function is to review all dredge and fill permit applications

3669which may have impacts upon the hydraulics of surface water systems. He has

3682reviewed approximately 1,500 dredge and fill

3689permit applications. His testimony and that of Mr. Buckingham is

3699accepted, as is that of other Department expert witnesses in

3709establishing the excellent flushing characteristics of the site

3717and that the construction and operation of the marina will not

3728adversely affect the present hydrographic situation at the site,

3737as that relates to establishing that no water quality violations

3747will occur.

374925. All marinas are potential sources of pollutants.

3757The first to be addressed involves the installation of the

3767pilings themselves during the construction of the marina. This

3776is a potential source of turbidity. Turbidity involves the

3785suspension of bottom sediments and substrate material in the

3794water column, which can pose, among other problems, the

3803retardation of light penetration through the water column which

3812can have an adverse impact on photosynthesis in marine grass

3822beds. In extreme cases, it can cause the destruction of grass

3833beds through killing of the grass by lack of adequate light

3844penetration, as well as the smothering effect of sediments being

3854deposited upon grasses. The method to be used by St. Joe in

3866installing the pilings will be by "jetting" them into the bottom

3877of the river initially and then driving the pilings into the

3888river bottom to the required depth to support the piers.

3898Witnesses for St. Joe and the Department established that this

3908method will constitute an adequate safeguard to be employed

3917during construction to minimize any turbidity. Any temporary or

3926local turbidity caused by the installation of the pilings will be transitory and

3939will pose no significant water-quality violation;

3945however, turbidity curtains will, be employed, if necessary, by

3954the applicant to control any such turbidity during construction.

396326. Another potential source of turbidity at a marina

3972involves the dredging, washing or disturbance of the river bottom

3982caused by boat propellers or boat keels. The evidence

3991demonstrated that the risk of such "prop dredging" or wash at

4002this marina will be negligible due to the design features and

4013conditions at the site, including the channels and channel

4022markers, and particularly by the depth of waters prevailing at

4032the site.

403427. The marina basin and boat slips are located in

4044water of sufficient depth to prevent prop dredging or wash. The

4055=average depth of the entrance channels is between 10 and 12 feet. Maneuvering

4068within the marina basin will occur in depths of 10 feet or greater. Although

4082the most landward boat slips are located in depths of approximately eight feet,

4095the average depth within most slips is approximately 10 to 12 feet. These

4108depths are based upon the bathymetric survey of the site and confirmed by random

4122soundings performed during the course of the hydrographic study in evidence.

4133Further, these depths are "mean low water" depths. Mean low water reflects the

"4146lowest expected

4148level" within a 29-day tidal epic. The "mean lower low" level is

4160the lowest expected level over the course of a year. That level

4172prevailing at the site, according to the study, is 0.1 feet lower

4184than mean low water. The maximum draught of boats expected to be

4196moored at the marina is 4.5 feet. Thus, the depths in the marina will allow

4211ample clearance between propellers and keels and the

4219river bottom. The required clearance between boat bottoms and

4228propellers and the river bottom can further be assured by proper

4239placement of boats in the boat slips in the leasing process and

4251in the assignment of boat slips to casual, temporary users of the

4263marina. In other words, the larger boats will be assigned to the

4275deeper, more waterward slips. Other measures include warning

4283signs, which should be placed along the six-foot depth contour,

4293along the landward edge of the entrance channels and beyond the

4304waterward extent of the grass beds. This will insure that

4314boaters do not stray into shallow-water, aquatic habitat areas.

432328. A second factor in determining the potential for prop dredging at the

4336marina is the nature of the sediments

4343themselves. Four witnesses, including those testifying for the

4351Department and for the Petitioners, established that the

4359sediments at the site are primarily sand-based, with minimal

4368organic silt content. The sandy nature of the sediments

4377minimizes the potential for turbidity caused by prop dredging or

4387prop washing (hydraulic currents created by propeller operation)

4395because sand, by its density, mass and weight, tends to settle

4406out to the bottom much quicker if it is suspended in the water

4419column. Even if prop dredging did occur at the marina,

4429generating turbidity, the high flushing characteristic of the

4437site would quickly transport and disperse any such turbidity and

4447render it undetectable and likely prevent its deposition on the

4457grass beds.

445929. A potential source of pollutants at a marina is

4469boat fuel. Expert witnesses for the Department and the applicant

4479established that the design and operational features of the

4488marina, primarily the absence of any fueling facilities, will

4497minimize or eliminate the potential for pollutants generated by

4506fueling operations.

450830. Another potential source of pollutants at a

4516marina is waste from boat heads and bilges generated by flushing

4527boat heads or pumping out of bilges with bilge pumps. Expert

4538witnesses for St. Joe, as well as the Department, established

4548that the design and operational features with which this marina

4558will be characterized will minimize or eliminate the potential

4567for such pollutants to be generated because liveaboard boats will

4577be prohibited, and the pumping out of heads and bilges will also

4589be prohibited because of the conditions agreed to by the

4599applicant for a grant of this permit.

460631. Another potential source of pollutants at a

4614marina is the use of anti-fouling paint used on the bottoms of

4626boats and the periodic scraping and repainting of boats. Expert

4636witnesses for the Department and the applicant established that

4645the operational features and design of this marina will minimize

4655the potential for pollutants from this source because boat

4664painting, sanding, and scraping and other operations attendant to

4673boat painting will be absolutely prohibited at the marina.

468232. Finally, another potential source of pollutants

4689would be trash and garbage materials. The potential for

4698pollution from this source will be minimized by the use of trash containers and

4712dock boxes located at frequent intervals around

4719the piers and boat slips, as well as the instructional signs to

4731be placed on the piers and slips by the applicant and the

4743publication of marina rules in order to inform boat operators and

4754guests of the necessity to dispose of trash in the proper

4765containers.

476633. It has thus been established that the design and

4776operational characteristics of the marina and conditions to be

4785imposed thereon will minimize or eliminate the potential for

4794pollutants to be generated and placed in the surface waters at

4805the site. The marina will not occasion violations of applicable

4815water-quality standards. Any pollutants which might be deposited

4823in the surface waters at the site will be quickly transported and

4835dispersed so as to be undetectable at the marina or in the

4847vicinity of the marina because of the critical role played by the

4859hydrographics prevailing at the site.

4864Public Interest Impacts

486734. Much of the testimony at hearing regarding impacts upon the various

4879public interest standards, including wildlife and habitats, focused upon the

4889grass beds, and the benthic communities prevailing in deeper water at the site,

4902as well as the fact that the site is used by manatees. Dr. Quinton White was

4918accepted as an expert in biology and biological impacts of marina construction

4930and operation. He testified on behalf of the applicant. His testimony and that

4943of other expert witnesses offered by St. Joe and the Department established that

4956there would be no adverse impact on benthic communities and organisms, including

4968manatees, caused by the construction and operation of the marina. The

4979Petitioners called expert witnesses on the issue of impacts on wildlife. Mike

4991Allen, a Florida Game and Fresh Water Fish Commission staff member, testified

5003that he was not really qualified as an expert in fisheries or benthic

5016communities but, rather, in terms of terrestrial species which are not involved

5028in this proceeding. Lawson Snyder, another Florida Game and Fresh Water Fish

5040Commission staff member, was accepted as an expert in fisheries biology on

5052behalf of Petitioner but testified that the marina's impacts upon fish and

5064wildlife would not be detectable. Jim Valade, a Florida Department of Natural

5076Resources staff member, was also accepted as an expert in marine biology,

5088including fish and manatees, but testified that the permit applicant has taken

5100steps to protect manatees in virtually all aspects and that his department's

5112concerns regarding the safety of manatees have been adequately addressed by the

5124design and proposed operation of the marina. Bill Watkins, a St. Johns River

5137Water Management District staff member, was accepted as an expert in biology,

5149but testified that the design of the marina provides the grass beds "a fair

5163degree of protection" and declined to opine that the marina would have any

5176adverse impacts upon wildlife or fish. Finally, Dr. Carol DeMort, in her

5188deposition, specifically declined to render any opinion regarding adverse

5197impacts upon wildlife or fish. Thus, the evidence adduced by the Petitioners at

5210hearing did not rebut the evidence introduced by the applicant that the marina

5223will have no detectable impacts upon wildlife or habitats involved in the

5235vicinity of the site

523935. St. Joe introduced evidence concerning impacts from shading upon

5249grass beds by the marina structures themselves and from turbidity "washed" onto,

5261the grass beds by motorized boats maneuvering in the marina basin. Expert

5273testimony was adduced that established that shading caused by the widest pier,

5285that is, the main pier with a width of 12 feet, would have no adverse impact on

5302the grass beds due to shading. That testimony was unrebutted and is accepted.

5315Two expert witnesses for St. Joe, a marine engineer and a biologist, as well as

5330a Department witness, established that, even assuming that turbidity was

5340generated by propeller action in the marina basin, the turbidity resulting from

5352prop wash would not be transported 275 feet from the marina basin offshore to

5366the :grass beds at the inshore area. They attributed those opinions to the

5379nature of the sediments involved which are not readily suspended, the flushing

5391at the site, the distance between the basin and the grass beds, and the typical

5406extent of prop wash from boats expected to be used at the marina. The

5420Petitioners presented two witnesses, who testified regarding the impacts of prop

5431wash. Mr. Allen, an expert in upland terrestrial species, testified regarding

5442the potential for deposition of sediments on grass beds but also acknowledged

5454that the hydrographics at the site, the distance between the marina basin and

5467the grass beds and other protective measures would minimize this potential. One

5479lay witness for the Petitioners testified to the effect that if a "handful" of

5493boat owners in the marina violated the "no wake" restrictions and accelerated

5505their boats in violation of those restrictions, they would cause turbidity to be

5518placed upon the grass beds. His testimony was contradicted, however, by a

5530marine engineer, who testified that prop wash is a function of many parameters

5543(e.g., the RPM of the engine, the horsepower of the engine, the draught of the

5558boat, and configuration of the propellers, etc.). He established that it would

5570not be reasonable to expect prop wash extending twice the length of a boat.

558436. Regarding impacts upon benthic communities at the site, the applicant

5595introduced expert testimony which established that the benthic communities in

5605that vicinity of the marina, including the grass beds, fin fish, shellfish, and

5618other organisms, will not be adversely impacted by the construction and

5629operation of the marina in light of the safeguards which would be imposed upon

5643the permit, as delineated herein. This is primarily due to the absence of

5656significant concentrations of pollutants to be expected and the hydrographics

5666prevailing at the site as that relates to the unlikelihood of boat grounding,

5679prop dredging, and prop wash suspending pollutants and turbidity and depositing

5690them on benthic community habitat areas. Only one of Petitioners' witnesses,

5701Dr. DeMort, testified in her deposition concerning potential impacts upon

5711benthic communities. Dr. DeMort made it clear, however, that she had conducted

5723no investigations and studies necessary to enable her to render an expert

5735opinion on the impacts upon the benthic communities prevailing at the site which

5748might be caused by the marina's construction and operation. Her testimony in

5760this regard only related to marina installation and operation in general and was

5773not related to the specific design characteristics and proposed operational

5783parameters of the subject marina.

578837. Manatees are an endangered species. There is much concern about their

5800welfare with regard to the proposed project because all parties acknowledge that

5812the site and the shoreward grass bed areas, particularly, are frequented by

5824manatees, particularly for summer foraging. Manatees tend to forage in shallow

5835waters and associated grass beds. Boats pose definite hazards to manatees and

5847cause significant manatee deaths each year due to impact from boats, as much as

586115% to 30% of the known population. In response to this hazard, the U.S. Marine

5876Mammal Commission has recommended that grass beds be protected and that

5887establishment of protective or "no wake" zones in manatee foraging areas be

5899accomplished. In light of such restrictions voluntarily agreed to by St. Joe

5911and its expert testimony in this regard and in light of the manatee education

5925and awareness measures proposed by the applicant, it has been demonstrated that

5937the marina will not have any negative impact on the manatee population in the

5951area. The Petitioners' only expert witness concerning manatees, Jim Valade,

5961indeed, opined that the marina had taken steps to protect manatees "in virtually

5974all aspects".

597738. In this connection, the design features in the management and

5988operational plan discussed herein and proposed by the applicant embodies

5998measures to address potential impacts upon manatees which frequent the marina

6009site. These include manatee awareness signs to be posted at the marina; and an

6023additional specific condition has been agreed upon by the Department and the

6035applicant which specifies the size, lettering and other details of the warning

6047signs, and the location of them within the marina, all of which will be included

6062in a plan to be submitted to, reviewed, and approved by the Florida Department

6076of Natural Resources. Additionally, a permanent educational display will be

6086located at the Yacht Club informing boaters who frequent the facility of the

6099presence of manatees in the area and the need to minimize the impact of boats

6114upon manatees. During construction, if a manatee is sited within 100 yards of

6127the marina site, construction activities will cease and not resume until

6138manatees have left the area. A handbook will be prepared concerning manatees

6150and the effect on them of boat operation, which will be distributed to employees

6164of the facility and to Yacht Club members and guests. This requirement and the

6178review of it by Yacht Club members and guests will be an integral requirement in

6193the terms of the slip leases. Additionally, no docking facilities, pilings or

6205cleats will be located along the portions of the piers not containing boat slips

6219in order to discourage boaters from attempting to moor at those locations, which

6232will reduce the number of boats frequenting the marina, as that relates to

6245manatee safety.

624739. This portion of the St. Johns River functions as a highly productive

6260juvenile fish nursery and sports fishing area. Therefore, an examination of the

6272marina's potential impacts upon marine productivity, fishing and recreation in

6282the area is an important consideration in this proceeding. The discussion of

6294this potential impact involves the same issues discussed in connection with

6305impacts upon water quality and wildlife habitat; namely, the generation of

6316pollutants and the impacts upon the grass beds and benthic communities directly

6328by boat operation itself. Unrefuted testimony adduced by the applicant and the

6340Department has established that impacts upon the fish population and upon marine

6352productivity, fishing and recreational values will not be adverse. No

6362deliterious effect is likely to be occasioned the fisheries and fish habitat and

6375the habitat of other aquatic organisms in terms of juveniles or adults or to the

6390sport fishing values of the area in which the marina will be located. Indeed,

6404the marina structures and the shade and concealment offered by moored boats will

6417provide additional habitat for juvenile fish, as well as provide an additional

6429source of food because of the "fouling communities" of life forms which will be

6443expected to grow on the pilings. These will serve as food for juvenile fish and

6458some species of adult fish which, in turn, will enhance the food supply of

6472predatory fish operating at an upper level in the food web. The boats and

6486structures themselves also will operate as a source of protection for certain

6498fish populations from predators. The Petitioners produced a fisheries biologist

6508as an expert witness, who testified in this regard; but he acknowledged that he

6522did not know whether noticeable impacts on conservation of fish, marine

6533productivity and recreational values will be caused by the installation and

6544operation of the marina. He testified in a general sense that he feared some

6558negative impacts might result but did not feel that any such impacts would be

6572detectable based upon testimony he heard and deferred to, including testimony

6583that the littoral zone would not be impacted by the marina to any significant

6597degree. He ultimately opined that the marina would likely have little impact on

6610sports fishing. The other witness produced by the Petitioners concerning

6620impacts upon fishing and recreational values was unable to render any expert

6632opinion, by her own admission, because she had conducted no studies or otherwise

6645been provided information regarding the design and proposed operation of the

6656marina. Consequently, the testimony adduced by the applicant as to these

6667parameters is accepted; and it has been established that the marina will not

6680adversely impact fisheries, fish conservation, aquatic habitat, sport fishing,

6689recreational values and marine productivity in the area involved at the project

6701site.

670240. Regarding potential impacts upon the public

6709health, safety and welfare and property of others, the applicant

6719and the Department adduced expert testimony that no adverse impact regarding

6730these interests will occur. The testimony of

6737Petitioners' experts similarly establishes that the marina would

6745not pose safety hazards or would otherwise give rise to any

6756noticeable impacts upon the public health, safety, welfare and

6765property of others.

676841. Regarding potential impacts upon navigation or

6775the flow of water, St. Joe and the Department introduced expert

6786testimony to establish that the marina would not adversely impact

6796navigation or the flow of water, and it is so found. The

6808Petitioners' introduced no evidence regarding this subject.

681542. Regarding potential impacts upon significant

6821historical and archaeological resources, the applicant and the

6829Department introduced evidence that no adverse impact as regards

6838these resource parameters will occur. Although one of the

6847Petitioners, in her testimony, speculated that the marina could

"6856detract" from the William Bartram scenic highway, she was unable

6866to specify how the marina would impact the highway or to what

6878extent the highway was a significant, historical or

6886archaeological resource. It is found that no such adverse impact

6896on the William Bartram scenic highway will occur.

6904Cumulative Impact

690643. Regarding cumulative impacts, the applicant and

6913the Department introduced evidence that the marina would not give

6923rise to impacts which, cumulative with the impacts of other

6933marina facilities, would be significant. The evidence

6940establishes that there are six marinas within four miles of this

6951marina site; two upriver, and four downriver. Due to the

6961hydrographic circumstances in the area and the distance of the

6971other marinas from this site, it has been demonstrated that the

6982addition of this marina to the area will not result in any

6994adverse cumulative impacts. Mr. Mike Allen, the expert in upland

7004terrestrial species (not involved in this proceeding), referenced

7012in his testimony the cumulative impacts he feared on sports and

7023commercial fishing. Mr. Allen made it clear, however, that his

7033reference was not to cumulative impacts caused by the marina and

7044existing marinas but, rather, to impacts which could be brought

7054about by many such future facilities located in this particular area. The

7066evidence does not reflect, however, that any other

7074marinas are conceptually contemplated or are the subject of other

7084permit applications for this area for the future. It is thus

7095found that no significant adverse cumulative impacts will be

7104occasioned by the installation and operation of the subject

7113facility.

7114CONCLUSIONS OF LAW

711744. The Division of Administrative Hearings has

7124jurisdiction of the subject matter of and the parties to this proceeding.

7136Section 120.57(1), Florida Statutes (1989).

714145. This proceeding arises under the purview of Section

7150403.918(1)(2), Florida Statutes (1989), which provides that an

7158applicant for such a permit, as involved herein, must provide

7168reasonable assurances that water-quality standards will not be

7176violated and that the project will not be contrary to the public

7188interest. Also at issue are the water-quality standards for

7197State Class III surface waters, which are involved at the project

7208site.

720946. The permit applicant bears the burden of demonstrating

7218entitlement to the dredge and fill permit being sought and must

7229present evidence demonstrating that entitlement. The applicant

7236must bear the burden of making a preliminary presentation of

7246evidence showing entitlement which "depends to a large extent on

7256the nature of the objection raised by the Petitioners requesting

7266a hearing". If the applicant makes a preliminary showing of

7277entitlement, the permit must be issued unless the Petitioners

7286present "contrary evidence of equivalent quality" and prove the truth of the

7298facts alleged in their petitions. See, Florida

7305Department of Transportation v. J.W.C. Company, Inc., 396 So.2d

7314778 (Fla. 1st DCA 1981). Assuming a preliminary showing of

7324entitlement, the Petitioners in opposition to such a permit

7333application cannot carry their burden of presenting contrary

7341evidence by mere presentation of speculation concerning what

"7349might" occur. Chipola Basin Protective Group, Inc. v. Florida

7358Chapter Sierra Club, 11 FALR 467, 480-81 (December 29, 1988).

736847. Section 403.918(1), Florida Statutes, requires an

7375applicant to provide reasonable assurances that water-quality

7382standards will not be violated; and Section 403.918(2), Florida

7391Statutes, requires such an applicant to prove reasonable

7399assurances that a project is not contrary to the public interest

7410in regard to projects, such as this one, which are not proposed

7422to be placed in outstanding Florida waters. The subject project

7432is proposed to be installed in Class III surface waters of the

7444State so that the applicant's burden involves a demonstration

7453that the project "is not contrary to the public interest".

7464Section 403.918(2)(a), Florida Statutes, sets forth seven (7)

7472criteria, which are employed by the Department in determining

7481whether a project is "not contrary to the public interest".

7492Additionally, reasonable assurances must be provided that the

7500cumulative impacts of the project and similar projects, existing,

7509under construction, or reasonably expected in the future, will

7518not adversely impact the water-quality considerations of Section

7526403.918(1), Florida Statutes, and the public-interest parameters

7533associated with subsection (2) of that statutory section.

754148. The applicant's burden "is one of reasonable

7549assurance, not absolute guarantees". Manasota 88, Inc. v. Agrico

7559Chemical Company and Florida Department of Environmental

7566Regulation, 12 FALR 1319, 1325 (February 19, 1990). The burden

7576does not require that the applicant "eliminate all contrary

7585possibilities" or address impacts which are "only theoretical

7593and...could not be detected or measured in real life". Florida

7604Keys Citizens Coalition v. 1800 Atlantic Developers and Florida

7613Department of Environmental Regulation, 8 FALR 5564, 5577

7621(October 17, 1986), reversed on other grounds, 552 So.2d 946

7631(Fla. 1st DCA 1989). Rather, an applicant must provide

7640reasonable assurances which take into account contingencies which

7648might reasonably be expected.

765249. The preponderant evidence of record culminating in the

7661above Findings of Fact clearly demonstrates that St. Joe has met

7672the test set forth in Section 403.918(1), Florida Statutes, and

7682has provided reasonable assurances that the marina will not

7691result in the violation of applicable Class III water-quality

7700standards embodied in Chapter 17- 3, Florida Administrative Code.

7709The evidence also demonstrates that the applicant has met the

7719test set forth in Section 403.918(2), Florida Statutes, and has

7729provided reasonable assurances that the marina is not contrary to

7739the public interest. St. Joe presented expert testimony, studies

7748admitted into evidence, and other evidence establishing that the

7757proposed design and operational measures and conditions to be

7766imposed on operation and construction regarding the project and

7775the project site will render all potential impacts to be of a non-violative

7788nature. The evidence adduced by Petitioners may be

7796categorized in several ways. First, some of the evidence

7805actually supported the applicant's case, such as the ultimate

7814opinions rendered by Jim Valade and Lawson Snyder. Secondly,

7823some of the evidence consisted of general concerns, as

7832distinguished from specific expert opinions, expressed as to the

7841impacts of marinas in general in a generic sense but not as

7853applied to any specific scientific information concerning the

7861characteristics of this marina site and the design, construction

7870and operation of the proposed marina as it might actually impact

7881the waters, benthic communities, etc. at the site. Witnesses,

7890including expert witnesses for the Petitioners, expressing these

7898more generic concerns, were Dana Morton, Mike Allen, and Dr.

7908Carol DeMort. They admitted to have little or no familiarity

7918with design, construction and operational features of the marina

7927at issue and no specific familiarity with the physical and

7937biological characteristics of the site. Finally, other testimony

7945consisted of speculation or fears of impacts caused by the marina

7956without a specific description of the source or extent of such

7967impacts. For example, none of the Petitioners' witnesses

7975testified regarding levels or concentrations of pollutants which

7983they contended would be generated at the marina or to what extent

7995the various resources enumerated as considerations in the above

8004statutory provision, would actually be exposed to or impacted by

8014those unspecified levels of pollutants or physical operation of

8023boats or the marina facilities itself. Thus, the Petitioners

8032failed to rebut the showing of entitlement by the applicant to

8043the permit with any evidence of "equivalent value". JWC, supra.

805450. The Petitioners raised an issue concerning the

8062likelihood of effective enforcement or implementation of some of

8071the design and operational measures and conditions proposed by

8080the Department and accepted by St. Joe. These issues were

8090primarily raised in the testimony of Tom Beale, who testified as

8101to his experience as a boat operator with lax marina operators

8112and unruly or unlawful boaters. The enforcement measures

8120proposed by the applicant, including the warning signs, mandatory

8129provisions for slip-leasing agreements, and the provision of dock

8138personnel for all operating hours of the marina, have been

8148acknowledged in other administrative proceedings as being

8155adequate mechanisms of enforcement. City of Parker v. Bravo and

8165Florida Department of Environmental Regulation, 9 FALR 5014,

81735021-24 (August 24, 1987); MacMillan v. Dax and Trin Development

8183Corporation and Florida Department of Environmental Regulation, 7

8191FALR 3780, 3792-96 (July 29, 1985). In evaluating the reasonable

8201assurances provided by an applicant in this regard, it must be

8212remembered that the applicant is charged with the burden of

8222active and vigorous enforcement of the conditions imposed upon

8231the grant of its permit but that the applicant cannot be expected

8243to provide an absolute insurance policy, in effect, that persons

8253using its facility will never violate the law prevailing or the

8264restrictive conditions imposed upon the grant of its permit and

8274the operation of its facility which it is charged in that permit

8286with enforcing. Rather, there is a threshold presumption that

"8295people will observe and abide by the law". MacMillan, 7 FALR at

83083796. The burden of the applicant is to provide reasonable

8318assurances, not absolute assurances. In this particular, the

8326applicant has done so by proposing an extensive program designed

8336to enforce the provisions and prohibitions incorporated in the

8345design and operation of the marina. This Recommended Order, in

8355the above Findings of Fact, indicates other conditions

8363established by the preponderant evidence of record concerning

8371additional conditions or, in several instances, more restrictive

8379conditions, which should be imposed in order for the permit to be

8391granted. If those conditions are imposed upon a grant of the

8402permit, as delineated in this Recommended Order, the reasonable

8411assurances delineated above will be adequately addressed and

8419enforced. It is not the applicant's burden to automatically

8428assume that the marina patrons will ignore signs, warnings, lease

8438agreements, the enforcement measures of the dock master's

8446personnel, or operate their crafts so as to place themselves,

8456their guests, and the benthic communities involved in jeopardy

8465and violate the clearly enunciated and posted rules of the

8475marina. Under the pertinent rules and statutes bearing upon this

8485and similar proceedings, applicants are not required to bear such a heavy

8497burden.

849851. The Petitioners have also raised an issue involving

8507the applicant's undisputed need to obtain permits for certain

8516upland facilities necessarily associated with the proper

8523operation of the marina in terms of the reasonable assurances

8533provided by the applicant being effective. For example, the

8542sewage and bilge water pump-out facilities at the marina will

8552transport waste to an upland waste water collection and treatment system, which,

8564ultimately, must be reviewed and permitted by the

8572Department. Also the Yacht Club storm water treatment facilities

8581must be permitted by the Water Management District, which has

8591jurisdiction thereof. St. Joe has acknowledged the need to

8600obtain these additional permits and already has determined

8608through its experts that the construction and operation of these

8618upland facilities are feasible in terms of their operational

8627characteristics and relevant environmental standards. The

8633Petitioners introduced no evidence regarding any impacts of these

8642upland facilities concerning the environmental standards

8648prevailing and enforceable in this proceeding, referenced above,

8656or which would indicate that the facilities are not feasible as

8667that might relate to the proper operation of the subject marina

8678facility in terms of the reasonable assurances required for the

8688grant of its permit. As held in Caloosa Property Owners

8698Association, Inc. v. Department of Environmental Regulation, 462

8706So.2d 523 (Fla. 1st DCA 1985), the mere fact that an applicant

8718seeking a dredge and fill permit will need other permits for

8729associated development does not require the Department to

8737consider simultaneously all those other permits. In Caloosa, the

8746First District Court of Appeal rejected the argument that permits

8756not yet acquired for an associated development must be considered

8766in the context of a dredge and fill permit application. Id. at

8778525-27. The court specifically noted "that only one permit for

8788dredge and fill was at issue, and that other needed permits would

8800be processed separately at future dates". Id. at 527N.4.

8810Similarly, in J.T. McCormick v. City of Jacksonville and Department of

8821Environmental Regulation, 12 FALR 960, 988 (January

882822, 1990), an applicant for a landfill construction permit

8837demonstrated that leachate from the landfill would be transported

8846to a treatment plant. In that order, the Department rejected the

8857argument that the applicant must demonstrate that the treatment

8866plant will always comply with all applicable standards.

"8874Compliance with those standards is more properly addressed in

8883the treatment facility's permit." Id. at 988. Similarly, in The

8893Conservancy, Inc. v. A. Vernon Allen Builder, Inc. and Department

8903of Environmental Regulation, 12 FALR 2582, 2586 (January 22,

89121990), it was held that:

8917Large projects often may have a variety of

8925activities that are potential sources of

8931pollution requiring more than one department

8937permit. In some cases, more than one permit

8945may be considered at a consolidated hearing.

8952However, there is no requirement, either

8958expressed or implied, in any of the governing

8966legislation of the department that would

8972require an applicant to submit, or the

8979department to consider, all permit

8984applications at one time.

898851. Thus, although the applicant may require additional

8996permits in the future for related upland facilities, it need not

9007seek them or show entitlement to them in this dredge and fill

9019permit proceeding regarding the marina; and those questions

9027raised by the Petitioners concerning the upland facilities and

9036related permitting are not appropriately at issue in this

9045proceeding.

904652. In addressing impacts upon water quality, other

9054decisions have acknowledged the importance of hydrographic

9061assessment of a project site, such as this, and the installation of the proposed

9075facility in the State waters at that site. In

9084one such decision, a Hearing Officer noted "The chief means of

9095providing this assurance [that water quality standards will not

9104be violated] in marina permitting rests upon an accurate

9113assessment of the system's hydrographics." Turnberry Isle

9120Associates v. Florida Department of Environmental Regulation, In

9128FALR 124, 143 (November 10, 1988); Old Port Cove Property Owners

9139Association, Inc. v. Florida Department of Environmental

9146Regulation, 9 FALR 3821, 3858 (July 1, 1987). The testimony of

9157the applicant's experts in this regard, as well as Dr.

9167Echternacht of the Department, and the hydrographic study in

9176evidence itself, established the excellent flushing

9182characteristics in the area of the marina. Conversely, the

9191Petitioners adduced no evidence regarding the specific

9198hydrographics of the site; and their witnesses generally

9206expressed ignorance of the site's hydrographics.

921253. The Petitioners also contended that pollutants

9219generated by the marina, regardless of their relationship to the

9229applicable Class III water-quality standards, may give rise to

9238adverse impacts under Section 403.918(2) (a), Florida Statutes.

9246Therefore, the importance of the hydrographic circumstances of

9254the site and the project extends beyond the issue of mere

9265compliance with water-quality standards and relates to the public

9274interest analysis under this section. Certainly, the operation

9282of this or any marina can be expected to generate some level of

9295pollutants. The fact that marinas generically may generate some

9304pollutants does not mandate permit denial, however. See, Old Port Cove, 9 FALR

9317at 3852, 3857-59, 3863. Where design and

9324operational measures and hydrographic circumstances minimize the

9331pollutants generated and render their impact negligible, the

9339statutory criteria prevailing herein and the Class III water-

9348quality standards embodied in Chapter 17-3, Florida

9355Administrative Code, present no impediment to permit issuance

9363where it has been demonstrated, as it has herein, that those

9374criteria and standards will not be violated by any pollutants

9384which might be generated by marina construction and operation.

9393The Petitioners presented no evidence that the pollutants

9401generated at the marina would violate water-quality standards or

9410adversely impact the various interests set forth in Section

9419403.918(2)(a), Florida Statutes, in response to the demonstration

9427by the applicant of reasonable assurances that those parameters

9436will not be violated.

944054. Regarding impacts upon fish, wildlife, and their

9448habitats, the applicant demonstrated that the marina will not

9457have adverse impacts upon the grass beds, the other benthic

9467communities, or the manatees themselves. Although manatee

9474mortality rates are high and, in large part, directly

9483attributable to boat operation, the witnesses in this proceeding

9492were virtually unanimous in their agreement that, indeed, St. Joe

"9502has taken steps to protect manatees in virtually all aspects".

9513Although, assuming arguendo, that were no marina placed in the

9523immediate geographical site involved, manatees might be safer or

9532better protected, the present state of the law, as referenced

9542herein by the above decisions and interpretation of the relevant statutory

9553authority, does not impose such a burden on an

9562applicant and does not render the mere use by manatees of a

9574certain habitat area, such as that involved at the subject marina

9585site, an absolute impediment to any demonstration of reasonable

9594assurances that the relevant statutory and regulatory standards

9602will not be violated. Where various protective measures will be

9612instituted designed to assure the welfare of manatees using the

9622littoral habitat, such as involved at this site, such as the

9633conditions recommended to be imposed in the above Findings of

9643Fact, reasonable assurances have been determined to be provided.

9652See, Coscan Florida, Inc. v. Florida Department of Environmental

9661Regulation, 12 FALR 1359, 1369, 1387-88 (March 4, 1990).

967055. Marine productivity, fishing, and recreational values

9677must also be considered in this proceeding. The experts

9686testifying for both the applicant and the Petitioners

9694established, by the totality of their testimony, that the marina

9704proposed, with its operation restricted as proposed by the above-

9714found conditions on a grant of the permit, will not adversely

9725affect those interests. Indeed, on the positive side of the

9735scale, concerning consideration of marine productivity, fishing,

9742and recreational values, it was shown that the marina structure

9752and the moored boats may provide additional feeding grounds and

9762protective habitat for juvenile fish occurring in the area which

9772can enhance their population and ultimately the population of the

9782species which prey upon them. Finally, St. Joe demonstrated that

9792as to the remaining interests required to be addressed by Section

9803403.918(2) (a), Florida Statutes, that there will be an absence of any adverse

9816impacts.

981756. Evidence was adduced by the parties concerning

9825cumulative impacts, as noted in the above Findings of Fact. That

9836evidence demonstrates, by preponderance, that even considering

9843the existence of other marinas in the area, no adverse impacts

9854upon water quality or upon the public interest criteria embodied

9864in the above statutory section will be detectable, especially in

9874view of the lack of evidence of any new marinas proposed

9885conceptually, or by permit applications, for the area of the St.

9896Johns River involved in this proceeding.

990257. In summary, the relevant standards embodied in Section

9911403.918(1), Florida Statutes, involving water quality as related

9919to the specific water-quality pollutant standards contained in

9927Chapter 17-3, Florida Administrative Code, have been reasonably

9935assured to be complied with. The standards concerning the public

9945interest criteria contained in Section 403.918(2) (a), Florida

9953Statutes, have also been reasonably assured to be complied with

9963by the preponderant evidence adduced by the applicant and the

9973Department and which was not refuted by evidence of equivalent

9983quality adduced by the Petitioners.

9988RECOMMENDATION

9989Having considered the foregoing Findings of Fact,

9996Conclusions of Law, the evidence of record, the candor and

10006demeanor of the witnesses, and the pleadings and arguments of the

10017parties, it is therefore,

10021RECOMMENDED that the application of St. Joe Paper

10029Company for the dredge and fill permit at issue be granted,

10040provided that the terms and conditions enumerated in the Department's Intent to

10052Issue, in evidence as St. Joe Exhibit 9,

10060and accepted by the applicant, as well as those conditions found

10071in this Recommended Order to be necessary and supported by the

10082evidence, are incorporated in the permit as mandatory conditions.

10091DONE AND ENTERED this __26__ day of October, 1990, in

10101Tallahassee, Leon County, Florida.

10105__________________________________

10106P. MICHAEL RUFF

10109Hearing Officer

10111Division of Administrative Hearings

10115The DeSoto Building

101181230 Apalachee Parkway

10121Tallahassee, FL 32399-1550

10124(904) 488-9675

10126Filed with the Clerk of the

10132Division of Administrative Hearings

10136this __29__ day of October, 1990.

10142APPENDIX TO RECOMMENDED ORDER

10146IN CASE NO. 89-5053

10150Applicant's/Respondent's Proposed Findings of Fact

101551-53. Accepted, but are subordinate to the Hearing

10163Officer's Findings of Fact on the same subject matter,

10172particularly in those several instances where conditions on the

10181grant of the permit have been recommended to be modified somewhat

10192by the Hearing Officer in light of the totality of the

10203preponderant evidence presented.

1020654. Rejected, as unnecessary.

1021055. Accepted.

10212Respondent DER's Proposed Findings of Fact

10218The Department submitted no proposed findings of fact

10226but, rather, adopted those submitted by the applicant/Respondent.

10234Petitioners' Proposed Findings of Fact

10239Petitioners, Hoffert, presented no proposed findings of

10246fact but, rather, a letter in the nature of final argument which

10258has been referenced and discussed in the above Preliminary

10267Statement to this Recommended Order. Petitioners, Cornwell,

10274submitted a post-hearing pleading; but it contained no specific,

10283separately-stated proposed findings of fact, which can be

10291separated from their mere recitation and discussion of testimony

10300in evidence and arguments such that coherent, specific rulings

10309could be made. Petitioners, Cornwell's post-hearing pleading did

10317not conform to the instructions given to them by the Hearing

10328Officer at the conclusion of the hearing concerning the

10337appropriate manner for submission of proposed findings of fact,

10346and they were submitted late. They have been considered in the

10357rendition of this Recommended Order, however, in spite of the

10367fact that they were filed in a tardy fashion.

10376COPIES FURNISHED:

10378Dale H. Twachtmann, Secretary

10382Department of Environmental

10385Regulation

10386Twin Towers Office Building

103902600 Blair Stone Road

10394Tallahassee, FL 32399-2400

10397Daniel H. Thompson, Esq.

10401General Counsel

10403Department of Environmental

10406Regulation

10407Twin Towers Office Building

104112600 Blair Stone Road

10415Tallahassee, FL 32399-2400

10418T. R. Hainline, Jr., Esq.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 12/06/1990
Proceedings: Agency Final Order
PDF:
Date: 12/06/1990
Proceedings: Recommended Order
PDF:
Date: 10/26/1990
Proceedings: Recommended Order (hearing held , 2013). CASE CLOSED.

Case Information

Judge:
P. MICHAEL RUFF
Date Filed:
09/15/1989
Date Assignment:
09/25/1989
Last Docket Entry:
10/26/1990
Location:
Jacksonville, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (1):