93-001499 Helen C. Sutton vs. Tana Hubbard And Department Of Environmental Regulation
 Status: Closed
Recommended Order on Wednesday, May 31, 1995.


View Dockets  
Summary: Single family dock in waters of the State and sovereign submerged lands is entitled to dredge and fill permit and consent of use.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8HELEN C. SUTTON, )

12)

13Petitioner, )

15)

16vs. ) CASE NOS. 93-1499

21) 93-6507

23TANA HUBBARD and STATE OF FLORIDA )

30DEPARTMENT OF ENVIRONMENTAL )

34PROTECTION, )

36)

37Respondent. )

39__________________________________)

40RECOMMENDED ORDER

42A formal hearing was conducted in this proceeding before Daniel Manry, a

54duly designated Hearing Officer of the Division of Administrative Hearings, on

65March 8 and 9, 1994, in Crystal River, Florida and on March 27, 1995, in

80Tallahassee, Florida.

82APPEARANCES

83For Petitioner: John H. Rains, III, Esquire

90Ammis, Mitchell, Cockey,

93Edwards & Roehn, P.A.

97One Tampa City Center Building, Suite 2100

104Tampa, Florida 33601

107For Respondent, Keith Hetrick, Esquire

112Department of Evelyn Davis Golden, Esquire

118Environmental M.B. Adelson, Esquire

122Protection: Douglas MacLaughlin, Esquire

126Department of Environmental Protection

1302600 Blair Stone Road

134Tallahassee, Florida 32399-2400

137For Respondent, Emily G. Pierce, Esquire

143Tana Hubbard: Marcia Penman Parker, Esquire

149Roger, Towers, Bailey, Jones & Gay

1551301 Riverplace Boulevard, Suite 1500

160Jacksonville, Florida 32207

163STATEMENT OF THE ISSUES

167The issues for determination in this proceeding are whether Respondent,

177Department of Environmental Protection (the "Department"), should issue a permit

188for an existing retaining wall and dock located at the residence of Respondent,

201Tana Hubbard ("Hubbard"), in waters of the state; and whether the Department

215should issue an after-the-fact consent of use for the dock.

225PRELIMINARY STATEMENT

227The Department issued a Notice of Intent to Issue a dredge and fill permit

241for construction of the Hubbard dock on November 4, 1992. On December 10, 1992,

255the Department issued a dredge and fill permit for the dock.

266Petitioner filed a Petition challenging the permit on December 7, 1992. On

278February 19, 1993, the Department dismissed the Petition. On March 4, 1993,

290Petitioner filed an Amended Petition. In the interim between the Petition and

302Amended Petition, Hubbard constructed the dock.

308The dock Hubbard constructed did not comply with the permitted plans.

319Hubbard notified the Department that the dock was not in compliance with the

332permitted plans.

334On July 30, 1993, Hubbard and the Department entered into a Consent Order

347approving the dock constructed by Hubbard. On October 5, 1993, Petitioner filed

359a petition challenging the Consent Order.

365Matters relevant to the project as constructed, the dredge and fill permit,

377and the Consent Order were addressed by the parties in the formal hearing

390conducted on March 8-9, 1994. The formal hearing was continued to address

402Petitioner's allegation that the dock was constructed on sovereign submerged

412lands without a consent of use.

418On September 2, 1994, the Department issued a Notice of Agency Statement

430that the Board of Trustees of the Internal Improvement Trust Fund (the "Board")

444claimed ownership of the submerged lands on which the dock was constructed.

456Hubbard applied for a consent of use and, on September 20, 1994, the Department

470issued an after-the-fact consent of use for the Hubbard dock.

480Petitioner challenged the consent of use and requested a formal hearing.

491Petitioner's challenge to the consent of use was heard on March 27, 1995.

504Pursuant to the agreement of the parties, the matters were consolidated.

515At the formal hearing on March 8-9, 1994, and March 27, 1995, Petitioner

528presented the testimony of three witnesses and submitted 13 exhibits for

539admission in evidence. Respondents presented the testimony of nine witnesses

549and submitted 35 exhibits for admission in evidence. The identity of the

561witnesses and exhibits and the evidentiary rulings regarding each are set forth

573in the transcripts of the formal hearings filed with the undersigned on March

58617, 1994, March 27 and 29, 1995, and on April 6, 1995.

598The parties timely filed proposed recommended orders ("PROs") on April 27,

6111995. Proposed findings of fact in Respondents' PRO are accepted in this

623Recommended Order. Proposed findings of fact in Petitioner's PRO are addressed

634in the Appendix to this Recommended Order.

641FINDINGS OF FACT

6441. Dredge And Fill Permit And Consent Order

6521.01 Background

6541. On December 10, 1992, the Department issued a dredge and fill permit

667pursuant to Florida Administrative Code Rule 17-312. 1/ The permit was issued

679to Hubbard in care of Dock Masters of Homosassa, Inc. ("Dock Masters"). Dock

694Masters is the entity responsible for the project.

7022. The project is located in a lagoon off Kings Bay, in the Crystal River

717in Citrus County, Florida. It is in a man-altered Class III waterbody in

730Section 28, Township 18 South, Range 17 West, on Lot 15, West Baywater Court.

7443. The permit authorized construction of an 883 square foot single family

756dock and 70 foot retaining wall. The permit required Hubbard to create 346

769square feet of wetlands as mitigation and to dedicate all remaining wetlands on

782the site as a conservation easement to the Department.

7914. The dock is constructed several feet east of the permitted location and

804is built in a slightly different configuration. The permitted square footage

815over the water is

819reduced in the dock actually constructed by approximately 20 feet. About 10

831feet of fill is added to wetlands.

8385. Hubbard notified the Department of the discrepancy between the

848permitted dock and the dock actually constructed. In July, 1993, the Department

860inspected the site and determined that the dock was not constructed in

872accordance with the permit.

8766. The Department determined that there was a violation of the permit.

888The location and configuration of the dock actually constructed did not comply

900with the permitted plans. However, the Department determined that the dock

911actually constructed was permittable.

9157. The Department entered into a Consent Order with Dock Masters approving

927the dock actually constructed. The Consent Order imposed civil penalties of

938$932 and costs of $150 but required no corrective action.

9488. During the formal hearing conducted on March 8-9, 1994, Hubbard

959requested that the dock actually constructed be shortened 3.5 feet and that a

972four foot section of the west side of the dock be removed (the "as-built dock").

988Modifications included in the as-built dock are minor. They merely reduce the

1000size of the dock and do not create additional adverse impacts.

10119. Petitioner is an adjacent land owner to the as-built dock.

1022Petitioner's dock is configured, more or less, parallel to the shore line. The

1035as-built dock on Hubbard's property is configured, more or less, perpendicular

1046to the shore line.

105010. The as-built dock extends farther into the lagoon than does

1061Petitioner's dock. In addition, the as-built dock is situated between

1071Petitioner's dock and the confluence of the lagoon and King's Bay.

10821.02 Navigation

108411. The as-built dock does not adversely impact navigation. The as-built

1095dock extends approximately 37 feet into the lagoon. The lagoon is approximately

1107197 feet wide at the project site. There is 160 feet of open water in which to

1124navigate past the as- built dock.

113012. Depths in the open water beyond the end of the as-built dock are

1144adequate for navigation. During low tide, depths in the lagoon at the project

1157site are: 3.5 feet at the end of the as- built dock; 5.0 feet, 40 feet from the

1175end of the dock; 4.4 feet, 80 feet from the end of the dock; and 3.0 feet, 120

1193feet from the dock.

119713. The as-built dock does not adversely affect boaters' ingress and egress

1209into and out of the lagoon. The center of the navigational channel in the

1223lagoon is approximately 40 feet from the edge of the as-built dock. In

1236extremely low tides, areas around the as-built dock will go dry before the

1249center of the navigational channel goes dry.

125614. Boat traffic in the lagoon is sparse at the project site. Boats using

1270the lagoon are required to travel at idle speed. The speed limit is posted on

1285signs in the lagoon.

128915. The as-built dock does not present a navigational hazard. The dock is

1302easily seen and is lighted at night.

13091.03 Manatees

131116. The as-built dock will not adversely impact manatees. The area around

1323the project site is not a core area for manatees. The as-built dock is a single

1339family dock with a berth for one boat.

134717. The U.S. Fish and Wildlife Service and the Department's Threatened and

1359Endangered Species Section have responsibility for protecting manatees. Both

1368agencies were contacted regarding the Hubbard dock. Neither agency objects to

1379the as-built dock.

138218. Manatees congregate around large springs. There are no large springs

1393near the project site. The two nearest manatee sanctuaries are approximately

14042,000 feet from the as-built dock.

141119. No boating or snorkeling is allowed in the manatee sanctuaries during

1423manatee season. Boat traffic in the lagoon where the as-built dock is located

1436is limited to idle speed.

144120. Manatees feed on hydrilla. Hydrilla is the predominant submerged plant

1452around the project site.

145621. The as-built dock has no significant adverse impact on hydrilla in the

1469area. Even if the as-built dock had an adverse impact on hydrilla, the as-built

1483dock will not significantly reduce the amount of hydrilla available for manatee

1495feeding.

149622. Hydrilla is an exotic plant that crowds out native plants. Hydrilla is

1509harvested or treated with herbicides by

1515Citrus County to try to control the growth of hydrilla. Citrus County attempted

1528to control the growth of hydrilla by harvesting or treating approximately 666

1540acres of hydrilla in 1992 and approximately 580 acres in 1993.

15511.04 Other Potential Impacts

155523. The as-built dock will not cause any other adverse impacts to the

1568public interest. The as-built dock does not adversely affect the property of

1580others living on the lagoon and does not prevent reasonable access to any other

1594property on the lagoon.

159824. The as-built dock does not adversely affect public safety. The dock is

1611highly visible and is lighted at night. The project is located in an area in

1626which boat traffic is limited to idle speed.

163425. The as-built dock does not adversely affect the conservation of fish

1646and wildlife species, including threatened or endangered species, or the

1656habitats of such fish and wildlife species. Aquatic habitat around the as-built

1668dock is functioning normally.

167226. Shoreline vegetation is relatively natural and includes sawgrass,

1681arrowhead, cedars, and red bay trees. The mitigation area has been correctly

1693initiated and is now tending toward success as plantings mature. Use of the as-

1707built dock avoids damage to shoreline and submerged vegetation that otherwise

1718may occur if a boat were brought to shore in the absence of the dock.

173327. Various species of fish use the area, but the primary species is

1746mullet. The retaining wall will benefit fish and wildlife habitat by preventing

1758fertilizer and other yard chemicals from draining directly into the lagoon and

1770causing water quality problems.

177428. Fish and wildlife habitat is further protected from adverse impacts by

1786permit conditions. Permit conditions prohibit live-aboard boats, fueling

1794facilities, and fish cleaning facilities at the dock.

18021.05 Cumulative Impacts

180529. The as-built dock and similar facilities in the area will not have a

1819cumulative adverse impact on fish and wildlife habitat, endangered species, or

1830navigation. Hubbard conveyed a conservation easement to the Department covering

1840the remaining 400 feet of her shoreline.

184730. No future permitted or permit exempt docks can be built on Hubbard's

1860shoreline. Remaining wetlands on-site will be preserved in perpetuity.

186931. Few docks and seawalls can be constructed in the area in the future.

1883Substantially all of the residential lots in the area along the lagoon have:

1896already been built out; already have water dependent facilities such as docks

1908and slips; and already are sea-walled or rip-rapped.

191632. The state's land acquisition program (the "P-2000 Program") is seeking

1928to acquire major tracts along the Crystal

1935River in nearby areas. Those acquisitions will prevent similar future

1945development in areas farther from the as-built dock.

19531.06 Benefits To The Public Interest

195933. The as-built dock has resulted in benefits to the public interest

1971including the conservation easement over 400 feet of shoreline and wetlands.

1982The conservation easement will benefit the public interest by permanently

1992preserving fish and wildlife habitat.

199734. The as-built dock helps prevent prop dredging that may otherwise occur

2009if a boat were kept on the shoreline in the absence of a dock. The retaining

2025wall will reduce fertilizer and yard chemical runoff into the lagoon.

20362. Consent Of Use

20402.01 Background

204235. The Department notified Hubbard on September 2, 1994, that the as-built

2054dock and retaining wall are located on sovereign submerged lands. Hubbard

2065applied for an after-the-fact consent of use pursuant to Florida Administrative

2076Code Chapter 18-21. On September 20, 1994, the Department issued an after- the-

2089fact consent of use on Project No. 091923403 to allow Hubbard to maintain and

2103use the dock on sovereign submerged land.

21102.02 Review Of The Dock

211536. The as-built dock was reviewed by Mr. Todd A. Vandeberg, Planning

2127Manager for the Department's Southwest District, Mr. Henry Michaels, and Mr.

2138Matt Clements in accordance with Rule 18- 21 and the Department's guidelines and

2151policies for issuing consents of use for single family docks. See, Submerged

2163Lands Environmental Resources Program Operations and Manual, Volume III (the

"2173Operations Manual"). Mr. Michaels and Mr. Clements performed an on-site

2184compliance check with respect to the as- built dock in accordance with Rule 18-

219821 and the Operations Manual.

220337. The as-built dock is not contrary to the public interest. The dock

2216preempts less than 1,000 square feet of sovereign land for each 100 linear feet

2231of shoreline owned by Hubbard. The dock meets the 25 foot setback requirements

2244of the Board. The dock extends only to a depth of three feet rather than the

2260four foot depth allowed. The dock extends across only 19 percent of the width

2274of the lagoon.

22772.03 Intent And Purpose Of The Board

228438. The as-built dock insures maximum benefit and use of sovereign

2295submerged lands for all citizens of Florida. The dock does not prevent the

2308continued enjoyment of traditional uses of the lagoon by the public including

2320navigation, fishing, and swimming.

232439. The as-built dock extends into the lagoon only as far as necessary. 2/

2338The as-built dock does not constitute a navigational hazard.

234740. The as-built dock provides maximum protection for the management and

2358use of sovereign submerged lands including public recreation and fish and

2369wildlife propagation and management. Hubbard provided a conservation easement

2378along the majority of her shoreline. The easement is being well maintained.

239041. Issuance of the consent of use was coordinated with the Department's

2402regulatory staff. The as-built dock minimized or eliminated the cutting,

2412removal, and destruction of wetland vegetation. The as-built dock will not

2423adversely impact manatees or their habitat.

242942. The as-built dock aids in the implementation of the State Lands

2441Management Plan. It is consistent with the state's overall management plan for

2453the management of all sovereign lands. The as-built dock is consistent with the

2466Board's specific standards and criteria for siting docking facilities. 3/

247643. The consent of use contains terms, conditions, and restrictions

2486sufficient to protect and manage sovereign lands. The consent of use contains

2498general conditions established by the Department pursuant to Chapter 253,

2508Florida Statutes, 4/ and Rule 18-21.

251444. The as-built dock is a water dependent facility. It is not enclosed or

2528climatized for human habitation. The primary purpose of the dock is to moor a

2542vessel. Secondary uses include fishing and recreational activities such as

2552swimming and sun bathing. 5/

255745. The primary purpose and secondary uses for the as-built dock are

2569consistent with the Board's stated goal that all sovereign lands are single use

2582lands which should be managed for traditional recreational uses such as fishing,

2594boating, and swimming. The dock provides ingress and egress to the lagoon and

2607provides a safe place to moor a boat.

261546. No significant adverse impacts will result from Hubbard's use of

2626sovereign lands and associated resources, including fish and wildlife habitat

2636and endangered and threatened species. A conservation easement along a majority

2647of the Hubbard shoreline protects existing resources beyond the area of the

2659dock.

266047. The as-built dock was designed and constructed to minimize or eliminate

2672cutting, removal, and destruction of wetland vegetation. 6/ No dredging of

2683sovereign lands was required to construct the as-built dock.

269248. The as-built dock protects the riparian rights of adjacent property

2703owners. The as-built dock meets applicable setback requirements.

2711CONCLUSIONS OF LAW

271449. The Division of Administrative Hearings has jurisdiction over the

2724subject matter of this proceeding and the parties thereto. The parties were

2736duly noticed for the formal hearing.

27423. Burden Of Proof

274650. The applicant carries the ultimate burden of proof throughout this

2757proceeding. Hubbard must show by a preponderance of the evidence that she is

2770entitled to the permit and consent of use. Department of Transportation v.

2782J.W.C. Co., Inc., 396 So. 2d 778, 787 (Fla. 1st DCA 1981).

279451. For the permit, Hubbard must make a prima facie showing which provides

2807reasonable assurances that the as-built dock: (a) will not adversely affect

2818water quality; (b) is clearly in the public interest; and (c) will not cause

2832adverse cumulative or secondary impacts. Sections 403.918(1) and (2). If the

2843applicant makes a prima facie showing of reasonable assurances, the burden

2854shifts to Petitioner to go forward with contrary evidence that proves the

2866allegations in the petition for formal hearing. J.W.C., 396 So.2d at 789. The

2879permit can not be denied unless Petitioner presents contrary evidence of

2890equivalent value. Id.

289352. For the consent of use, the applicant has the ultimate burden of proof.

2907The applicant must show by a preponderance of the evidence that she is entitled

2921to the consent of use. Id.

29274. The Permit

293053. The parties stipulated that the as-built dock will not adversely affect

2942water quality within the meaning of Section 403.918(1). In determining whether

2953the as-built dock is clearly in the public interest, Section 403.918(2)(a)

2964requires the following seven criteria to be balanced:

29721. Whether the project will adversely affect

2979the public health, safety, or welfare, or

2986the property of others;

29902. Whether the project will adversely affect

2997the conservation of fish and wildlife,

3003including endangered species, or their

3008habitat;

30093. Whether the project will adversely affect

3016navigation or the flow of water or cause

3024harmful erosion or shoaling;

30284. Whether the project will adversely affect

3035the fishing or recreational value or marine

3042productivity in the vicinity of the project;

30495. Whether the project will be of temporary or

3058permanent nature;

30606. Whether the project will adversely affect or

3068will enhance significant historical and

3073archaeological resources under the provisions

3078of Section 267.061, F.S.; and

30837. The current condition and relative value of

3091functions being performed by areas affected

3097by the proposed activity.

310154. The parties stipulated: that the as-built dock is of a permanent

3113nature, within the meaning of Section 403.918(2)(a) 5.; and that it will not

3126violate the criteria in Section 403.918(2)(a) 6. The parties further stipulated

3137that the as- built dock will not adversely affect the flow of water or cause

3152harmful erosion or shoaling within the meaning of Section 403.918(2)(a) 3.

316355. The as-built dock does not adversely affect either navigation or the

3175public health, safety, or welfare within the meaning of Sections 403.918(2)(a)

31863. and 1., respectively. Boaters are required to travel at idle speed in the

3200lagoon. There is approximately 160 feet of open water, from the edge of the

3214dock across the lagoon, in which to navigate. The center of the navigation

3227channel is 40 feet from the edge of the dock.

323756. Boaters traveling between Hubbard's shoreline and the edge of the dock

3249are able to see the dock in sufficient time to steer around it. The applicant

3264has installed devices that make the dock visible at night.

327457. The as-built dock does not adversely affect the property of others. It

3287does not diminish ingress or egress to and from the property of adjacent

3300property owners and does not diminish the full use and enjoyment of their

3313property.

331458. The as-built dock will not adversely affect the conservation of fish

3326and wildlife, including endangered or threatened species within the meaning of

3337Section 403.918(2)(a) 2. Fish and wildlife in the area other than manatees are

3350primarily transitory.

335259. The closest manatee sanctuaries are 2,000 feet from the project. The

3365project does not cause concern for manatees.

337260. The as-built dock does not adversely affect fishing, recreational

3382value, or marine productivity in the area within the meaning of Section

3394403.918(2)(a) 4. The primary affect of the dock is shading. Shading from the

3407dock is minimal and will not adversely affect sea grass beds in the area.

3421Shading is beneficial to some types of fish in the area.

343261. The as-built dock will not adversely affect the current condition and

3444relative value of functions being performed in the area within the meaning of

3457Section 403.918(2)(a) 7. Any lost wetland functions are replaced through the

3468mitigation plan. Water quality benefits are provided by the retaining wall.

3479Permit conditions are adequate to prevent potential adverse impacts.

348862. The as-built dock does not create any adverse secondary impacts.

3499Permit conditions are adequate to prohibit secondary impacts including "live-

3509aboards", fueling facilities, and fish cleaning facilities.

351663. The as-built dock does not create any adverse cumulative impacts. The

3528remainder of the applicant's shoreline and wetlands are located within a

3539permanent conservation easement which precludes the construction of additional

3548docks on the applicant's property.

355364. Any impacts that have occurred from the dock are minimal and are

3566compensated for in the mitigation plan. The project creates a permanent

3577conservation easement over 400 feet of shoreline and wetlands, thereby

3587preserving fish and wildlife habitat. Docking a boat in water that is deeper

3600than water at the shoreline prevents prop damage to shoreline areas. The

3612retaining wall provides some water quality benefit.

361965. The as-built dock, existing docks, and reasonably anticipated future

3629docks do not create any adverse cumulative impacts. Major portions of the area

3642are being preserved through public acquisition. Some docks in the area are

3654being removed from use.

365866. Petitioner alleged that the as-built dock violates the Citrus County

3669Manatee Protection Plan. As a matter of law, however, the Department has no

3682authority to deny a permit application on the basis of local restrictions. The

3695denial or issuance of a permit must be based upon the Department's standards and

3709criteria. Taylor v. Cedar Key Special Water & Sewerage District, 590 So.2d 481

3722(Fla. 1st DCA 1991); Council of the Lower Keys v. Charley Toppino & Sons, Inc.,

3737429 So.2d 67, 68 (Fla. 3d DCA 1983). No finding is made regarding Petitioner's

3751allegation that the as-built dock violates local restrictions.

37595. The Consent Of Use

376467. The as-built dock is constructed on sovereign submerged lands. Use of

3776sovereign submerged lands requires approval from the Department. Section

3785253.77(1).

378668. The type of approval required for use of sovereign submerged land is

3799prescribed in Rule 18-21.005. The as-built dock requires a consent of use.

3811Rule 18-21.005(1)(a).

381369. The criteria for issuing a consent of use are set forth in Rule 18-

382821.004. The only disputed criteria are: whether the as-built dock is a water

3841dependent activity, within the meaning of Rule 18-21.004(1)(d); whether the

3851activity has an adverse impact on the natural resources of the state, within the

3865meaning of Rule 18-21.004(2); and whether the activity interferes with the

3876riparian rights of adjacent land owners within the meaning of Rule 18-21.004(3).

388870. The as-built dock does not adversely affect the natural resources of

3900the state within the meaning of Rule 18-21.004(2). See, paras. 53-66, supra.

3912Nor does the dock interfere with the riparian land owners within the meaning of

3926Rule 18-21.004(3). See, para. 57, supra.

393271. The as-built dock is a water dependent activity within the meaning of

3945Rule 18-21.003(56). The definition of a water dependent activity includes one

3956which requires direct access to sovereign submerged lands for recreation. The

3967purpose of the as- built dock is for recreation.

397672. The Department provided adequate explication for its non-rule policy

3986that distinguishes water dependent activities from other activities. The dock

3996is not enclosed or climatized for human habitation. The primary purpose of the

4009dock is to moor a vessel. Secondary uses include fishing and recreational

4021activities such as swimming and sun bathing.

40286. Attorney Fees

403173. The request in Petitioner's PRO for attorney fees is denied. Hubbard

4043showed by a preponderance of the evidence that she is entitled to a permit and

4058consent of use. That evidence was credible, persuasive, and substantial. The

4069contrary evidence submitted by Petitioner was, at best, minimal.

4078RECOMMENDATION

4079Based upon the foregoing Findings of Fact and Conclusions of Law, it is

4092RECOMMENDED that the Department enter a Final Order granting Hubbard's

4102application for a permit and consent of use, approving the consent order entered

4115into between the Department and Hubbard, and denying Petitioner's request for

4126attorney fees.

4128RECOMMENDED this 31st day of May, 1995, in Tallahassee, Florida.

4138___________________________________

4139DANIEL MANRY

4141Hearing Officer

4143Division of Administrative Hearings

4147The DeSoto Building

41501230 Apalachee Parkway

4153Tallahassee, Florida 32399-1550

4156(904) 488-9675

4158Filed with the Clerk of the

4164Division of Administrative Hearings

4168this 31st day of May, 1995.

4174ENDNOTES

41751/ All references to rules are to rules in the Florida Administrative Code

4188published as of the date of this Recommended Order.

41972/ The as-built dock extends only to a depth of three feet rather than the four

4213foot depth allowed by applicable rules. The dock extends across only 19 percent

4226of the lagoon.

42293/ The dock preempts less than 1,000 square feet of sovereign land area for

4244each 100 linear feet of shoreline owned by Hubbard. The dock meets the 25 foot

4259setback requirement. The dock extends only to a depth of three feet, and it

4273extends across only 19 percent of the width of the lagoon. The primary purpose

4287of the dock is to moor a vessel.

42954/ All chapter and section references are to Florida Statutes (1993) unless

4307otherwise stated.

43095/ A non-water dependent dock is one for which the vertical area between the

4323framing of the roof and the upper surface of the walkway of the dock is enclosed

4339on all four sides and/or is climatized for human habitation.

43496/ Hydrilla is the predominant submerged plant in the area. It is an exotic,

4363non-native species. The as-built dock will have no significant adverse impact

4374on the growth of hydrilla.

4379APPENDIX TO RECOMMENDED ORDER, CASE NO. 93-1499

4386Petitioner's Proposed Findings Of Fact.

43911.-5. Accepted in substance

43956. Rejected as conclusion of law and legal argument

44047. Rejected as not supported by credible and persuasive

4413evidence

44148.-9. Rejected as recited testimony and as not supported by a

4425preponderance of evidence

442810.-12. Rejected as not supported by credible and persuasive

4437evidence

443813. Rejected as recited testimony

444314.-15. Rejected as irrelevant and immaterial

444916.-18. Rejected as not supported by credible and persuasive

4458evidence or as irrelevant and immaterial

446419. Rejected as recited testimony

446920. Accepted in substance

447321.-22. Rejected as immaterial

447723.-28. Findings concerning activities other than water

4484dependent activities are rejected as not supported by

4492credible and persuasive evidence. Findings concerning

4498the Citrus County Manatee Plan are rejected as

4506irrelevant and immaterial. See para. 57 supra. Other

4514findings are rejected as conclusions of law and as

4523irrelevant and immaterial.

452629. Rejected as conclusion of law

453230.-32. Accepted in substance

453633.-38. Rejected as not supported by credible and persuasive

4545evidence and as a conclusions of law

455239.-41. Rejected as an issue of fact that is not disputed by

4564the parties

456642. Rejected as recited testimony

457142. Rejected as an issue of fact that is not disputed by

4583the parties

4585Respondents' Proposed Findings Of Fact.

4590Respondents' proposed findings of fact are accepted in this Recommended Order.

4601COPIES FURNISHED:

4603Virginia B. Wetherell, Secretary

4607Department of Environmental Protection

4611Twin Towers Office Building

46152600 Blair Stone Road

4619Tallahassee, Florida 32399-2400

4622Kenneth Plante, Esquire

4625General Counsel

4627Department of Environmental Protection

4631Twin Towers Office Building

46352600 Blair Stone Road

4639Tallahassee, Florida 32399-2400

4642John H. Rains, III, Esquire

4647Ammis, Mitchell, Cockey, Edwards

4651& Roehn, P.A.

4654Suite 2100

4656One Tampa City Center Building

4661Tampa, Florida 33601

4664Keith Hetrick, Esquire

4667Evelyn Davis Golden, Esquire

4671M.B. Adelson, Esquire

4674Douglas MacLaughlin, Esquire

4677Department of Environmental Protection

46812600 Blair Stone Road

4685Tallahassee, Florida 32399-2400

4688Emily G. Pierce, Esquire

4692Marcia Penman Parker, Esquire

4696Roger, Towers, Bailey, Jones & Gay

47021301 Riverplace Boulevard, Suite 1500

4707Jacksonville, Florida 32207

4710NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

4716All parties have the right to submit written exceptions to this Recommended

4728Order. All agencies allow each party at least 10 days in which to submit

4742written exceptions. Some agencies allow a larger period within which to submit

4754written exceptions. You should contact the agency that will issue the final

4766order in this case concerning agency rules on the deadline for filing exceptions

4779to this Recommended Order. Any exceptions to this Recommended Order should be

4791filed with the agency that will issue the final order in this case.

4804STATE OF FLORIDA

4807DIVISION OF ADMINISTRATIVE HEARINGS

4811HELEN C. SUTTON, )

4815)

4816Petitioner, )

4818)

4819vs. ) CASE NOS. 93-1499

4824) 93-6507

4826TANA HUBBARD and STATE OF FLORIDA ) 94-6501

4834DEPARTMENT OF ENVIRONMENTAL )

4838PROTECTION, )

4840)

4841Respondent. )

4843__________________________________)

4844CORRECTED ORDER

4846The Recommended Order entered on May 31, 1995, is corrected nunc pro tunc

4859to include all three cases that were consolidated prusuant to the agreement of

4872the parties.

4874DONE and ORDERED this 1st day of June, 1995.

4883___________________________________

4884DANIEL S. MANRY

4887Hearing Officer

4889Division of Administrative Hearings

4893The DeSoto Building

48961230 Apalachee Parkway

4899Tallahassee, Florida 32399-1550

4902(904) 488-9675

4904Filed with the Clerk of the

4910Division of Administrative Hearings

4914this 1st day of June, 1995.

4920COPIES FURNISHED:

4922Virginia B. Wetherell, Secretary

4926Department of Environmental Protection

4930Twin Towers Office Building

49342600 Blair Stone Road

4938Tallahassee, Florida 32399-2400

4941Kenneth Plante, Esquire

4944General Counsel

4946Department of Environmental Protection

4950Twin Towers Office Building

49542600 Blair Stone Road

4958Tallahassee, Florida 32399-2400

4961John H. Rains, III, Esquire

4966Ammis, Mitchell, Cockey, Edwards

4970& Roehn, P.A.

4973Suite 2100

4975One Tampa City Center Building

4980Tampa, Florida 33601

4983Keith Hetrick, Esquire

4986Evelyn Davis Golden, Esquire

4990M.B. Adelson, Esquire

4993Douglas MacLaughlin, Esquire

4996Department of Environmental Protection

50002600 Blair Stone Road

5004Tallahassee, Florida 32399-2400

5007Emily G. Pierce, Esquire

5011Marcia Penman Parker, Esquire

5015Roger, Towers, Bailey, Jones & Gay

50211301 Riverplace Boulevard, Suite 1500

5026Jacksonville, Florida 32207

5029=================================================================

5030AGENCY FINAL ORDER

5033=================================================================

5034STATE OF FLORIDA

5037DEPARTMENT OF ENVIRONMENTAL PROTECTION

5041HELEN C. SUTTON,

5044Petitioner, OGC Case Nos. 92-2226

504993-2807

5050vs. 94-3663

5052TANA HUBBARD and DOAH Case Nos. 93-1499

5059DEPARTMENT OF ENVIRONMENTAL 93-6507

5063PROTECTION, 94-6501

5065Respondents.

5066_____________________________/

5067FINAL ORDER

5069On May 31, 1995, a Hearing Officer with the Division of Administrative

5081Hearings (hereafter "DOAH"), submitted his Recommended Order to the Respondent,

5092Department of Environmental Protection (hereafter "Department") 1/ Copies of

5102the Recommended Order were simultaneously served on the Petitioner, Helen C.

5113Sutton (hereafter "Petitioner"), and on the Co-Respondent, Tana Hubbard

5123(hereafter "Hubbard"). A copy of the Recommended Order is attached hereto as

5136Exhibit A.

5138On June 12, 1995, Petitioner filed with the Department her Exceptions to

5150the Recommended Order, Objection to Ex Parte communication with Agency Head and

5162Request for Oral Argument. The Department filed its Response to Petitioner's

5173Exceptions to Recommended Order and Request for Oral Argument on June 15, 1995.

5186No response was filed on behalf of Hubbard. The matter is now before the

5200Secretary of the Department for final agency action.

5208Background

5209Hubbard filed an application with the Department for a permit to construct

5221a single family dock and related retaining wall in Citrus County, Florida. The

5234project site is located adjacent to and in the waters of a lagoon off the King's

5250Bay portion of Crystal River. King's Bay is classified as a man-altered Class

5263III water body /2 and is designated an Outstanding Florida Water. /3

5275The Department issued a preliminary Notice of Intent to Issue the requested

5287permit on November 4, 1992. Petitioner filed a challenge to the permit on

5300December 7, 1992, which was dismissed as untimely by the Department on February

531319, 1993, with leave to amend. On December 10, 1992, the Department issued

5326permit number 091923403 authorizing Hubbard to construct the dock and retaining

5337wall project, subject to various restrictions and conditions set forth in the

5349permit. Petitioner filed an amended petition challenging the project on March

53604, 1993, but Hubbard had constructed the dock and retaining wall between the

5373time that the permit was issued and the time of Petitioner's filing of the

5387amended petition.

5389Hubbard subsequently notified the Department that the dock had not been

5400constructed in compliance with the plans and specifications submitted to and

5411approved by the Department. On September 14, 1993, /4 the Department entered

5423into a Consent Order in OGC Case No. 93-2807 approving Hubbard's as-built dock

5436structure. Petitioner then filed a petition challenging the propriety of the

5447Consent Order.

5449During this period of time, the issue of Hubbard's use of sovereign

5461submerged lands was also raised. On September 2, 1994, the Department issued a

5474Notice of Agency Statement that the Board of Trustees of the Internal

5486Improvement Trust Fund of the State of Florida ("Board of Trustees") claimed

5500ownership of the submerged lands on which Hubbard's dock had been constructed.

5512Hubbard then applied for a consent of use for the submerged lands underlying the

5526dock facility, and the Department issued an after-the-fact consent of use on

5538September 20, 1993. Petitioner subsequently filed a timely challenge to the

5549consent of use and requested a formal administrative hearing.

5558Pursuant to agreement of the parties, Petitioner's three administrative

5567challenges to Hubbard's dock structure were consolidated by DOAH. A two part

5579formal administrative hearing was held in these consolidated cases before DOAH

5590Hearing Officer Daniel Manry ("Hearing Officer"). The first part of the hearing

5604was held on March 8-9, 1994, in Crystal River, Florida. The second part of the

5619hearing was held in Tallahassee, Florida, on March 27, 1995. Proposed

5630recommended orders were timely filed by the parties after the completion of the

5643formal hearing and the Hearing Officer's Recommended Order was entered on May

565531, 1995.

5657The Hearing Officer rejected all of Petitioner's claims and ruled that

5668Hubbard's as-built dock structure complied with the applicable water quality

5678standards for permitting and consent of use criteria. The Hearing Officer

5689recommended that the Department enter a Final Order "granting Hubbard's

5699application for a permit and consent of use, approving the consent order entered

5712into between the Department and Hubbard, and denying Petitioner's request for

5723attorney fees." (Rec. Order, p. 20)

5729Ruling on Petitioner's Reguest for Oral Argument

5736Petitioner's exceptions were accompanied by a Request for Oral Argument

5746pursuant to Rule 62-103.200(3), Florida Administrative Code. These rule

5755provisions state that the Secretary, in her discretion, may grant oral argument

5767in support of a party's exceptions to a Recommended Order submitted by a DOAH

5781hearing officer. The matters before the Secretary of the Department for

5792consideration are adequately set forth in Petitioner's written exceptions and

5802the Department's written response thereto and oral argument is not necessary to

5814clarify the issues. Accordingly, Petitioner's Request for Oral Argument is

5824denied.

5825Rulings on Petitioner's Exceptions Preface

5830Petitioner filed several exceptions taking issue with certain evidentiary

5839rulings at the final hearing and the Hearing Officer's rulings in the Appendix

5852to Recommended Order rejecting portions of her Proposed Findings of Fact.

5863Petitioner also takes exception to the Hearing Officer's conclusion of law

5874rejecting her request for award of attorney's fees. As a preface to the rulings

5888on the Petitioner's exceptions, it is appropriate to comment on the standard of

5901review imposed by law on an agency in reviewing recommended orders submitted by

5914DOAH hearing officers.

5917Under Section 120.57(1)(b)10, Florida Statutes, a reviewing agency may

5926reject or modify the conclusions of law and interpretations of administrative

5937rules contained in the recommended order of an administrative hearing officer.

5948However, these statutory provisions mandate that an agency may not reject or

5960modify findings of fact made by a hearing officer, unless a review of the

5974complete record demonstrates that such findings were not based on competent

5985substantial evidence or that the proceedings on which the findings were based do

5998not comply with the essential requirements of law. See Freeze v. Dept. of

6011Business Regulation, 556 So.2d 1204 (Fla. 5th DCA 1990); Florida Department of

6023Corrections v. Bradley, 510 So.2d 1122 (Fla. 1st DCA 1987).

6033The agency reviewing a recommended order may not reweigh the evidence,

6044resolve conflicts therein or judge the credibility of witnesses, as those are

6056evidentiary matters within the province of the hearing officer as the trier of

6069the facts. Heifetz v. Dept. of Business Reu1ation, 475 So.2d 1277 (Fla. 1st DCA

60831985). Consequently, if the record of the DOAH proceedings discloses any

6094competent, substantial evidence to support a finding of fact made by the hearing

6107officer, the reviewing agency is bound by such finding. Bradley, supra, 1123.

6119Exceptions 2A and 2B

6123These two exceptions deal with Petitioner's unsuccessful attempt to

6132introduce evidence at the DOAH final hearing relating to her claim that

6144Hubbard's dock failed to comply with the Citrus County Manatee Protection Plan.

61565/ The Hearing Officer sustained objections to this evidence at the final

6168hearing and rejected Petitioner's Proposed Findings of Fact 25-27 dealing with

6179the Citrus County Manatee Protective Plan on grounds of irrelevancy and

6190immateriality. (App. to Rec. Order, p. 22) Factual issues susceptible of

6201ordinary methods of proof that are not infused with agency policy considerations

6213are within the perogative of the Hearing Officer, as the trier of the facts.

6227See Heifetz, sura, 1281. There are no apparent overriding policy considerations

6238presented here relating to these evidentiary rulings of the Hearing Officer that

6250the issue of Hubbard's compliance with the Citrus County Manatee Protective Plan

6262is irrelevant and immaterial in these consolidated cases.

6270The Hearing Officer made a related ruling in Conclusion of Law 66 that the

6284Department has no legal authority to deny a permit application based on local

6297restrictions, such as the Citrus County Manatee Protective Plan. The Hearing

6308Officer cited controlling appellate decisions of Florida holding that permits

6318must be granted or denied by the Department based solely on the permitting

6331criteria set forth in the governing pollution control statutes and the

6342Department's implementing rules. See Taylor v. Cedar Key Sewerage District, 590

6353So.2d 481, 484 (Fla. 1st DCA 1991); Council of the Lower Keys v. Charley Toppino

6368& Sons, Inc., 429 So.2d 67, 68 (Fla. 3d DCA 1983).

6379The Hearing Officer's conclusion that the Department has no authority to

6390deny a permit to construct a dock based on purported noncompliance with elements

6403of Citrus County's Manatee Protection Plan is affirmed. The issues presented in

6415these proceedings are whether Hubbard's existing dock complies with the state's

6426applicable water quality standards and sovereign submerged lands consent of use

6437criteria. The Hearing Officer found that the dock site is not a core area for

6452manatees and that Hubbard's dock structure will not adversely impact manatees.

6463/6 (Rec. Order, para. 16) Paragraph 17 Of the Recommended Order also contains a

6477finding that both the U.S. Fish and Wildlife Service and the Department's

6489Threatened and Endangered Species Section were contacted and that neither entity

6500raised an objection to the as-built dock. These significant findings of the

6512Hearing Officer relating to the absence of any adverse impact on manatees 6/ are

6526amply supported by testimony presented at the DOAH final hearing. (Tr. I, Vol

65391, 105-109; Tr. I Vol. 2, 190-198; Tr. I Vol. 3, 310-311).

6551In view of the above, Petitioner's exceptions 2A and 2B are denied.

6563Exception 2C

6565In this exception, Petitioner contends that the Hearing Officer erred in

6576rejecting her Proposed Findings of Fact 8, 9, and 10 dealing primarily with the

6590claim that Hubbard's existing dock has adversely impacted existing native

6600seagrass (widgeon grass) growing in the immediate vicinity. These proposed

6610factual findings of Petitioner were rejected by the Hearing Officer on the

6622ground of being recited testimony not supported by a preponderance of evidence.

6634(App. to Rec. Order, p. 22)

6640Petitioner's Proposed Findings of Fact 8, 9, and 10 are purportedly based

6652on the expert testimony at the DOAH final hearing of biologist Robin Lewis. Mr.

6666Lewis was called on behalf of Petitioner and testified of his personal

6678observation of seagrass growing at the edge of Hubbard's dock. (Tr. I, Vol. 3,

6692374-376) Petitioner's exceptions, however, fail to cite any transcribed

6701testimony of Mr. Lewis where he renders an expert opinion that Hubbard's

6713existing dock had or would have a significant adverse impact on seagrass or

6726other native aquatic vegetation. Mr. Lewis only testified that "the discovery

6737of seagrass [at the dock site) would be something that would be significant in

6751terms of assessing the potential adverse environmental effects of this type of

6763project." (Tr. I, Vol. 3, 376) Furthermore, Lewis admitted on cross-examination

6774that he did not know the density of the seagrass at the dock site and that he

6791did not have any knowledge of the dominant vegetation of that area as of the

6806date of the final hearing. (Tr. I, Vol. 3, 393-394)

6816The Department's response cites testimony of Hubbard's expert witness,

6825Quinton White, Jr. Mr. White, a biologist, was of the opinion that that the dock

6840has no significant adverse impact on native aquatic vegetation in the area and

6853that any adverse impact would be to hydrilla, an undesirable exotic species.

6865(Tr. I, Vol. 2, 190-195) Hubbard also presented the expert testimony of

6877biologist Michael Czerwinski. Mr. Czerwinski was of the opinion that the

6888existing dock does not adversely affect the biological system of the site or

6901area. (Tr. I, Vol. 3, 312) Mr. Czerwinski also testified that he visited the

6915dock site the day before he appeared at the final hearing and did not observe

6930any seagrass growing there at that time. (Tr. I, Vol. 3, 337)

6942This exception of Petitioner involves the respective weight and credibility

6952given by the Hearing Officer to the testimony of the expert witnesses as

6965summarized above. The decision to accept one expert's testimony over that of

6977another is a matter within the sound discretion of the Hearing Officer and

6990cannot be altered absent a complete lack of competent substantial evidence of

7002record from which the finding could be reasonably inferred. See Collier Medical

7014Center v. State, Dept. of HRS, 446 So.2d 83, 85 (Fla. 1st DCA 1985); Florida

7029Chapter of Sierra Club v. Orlando Utilities Commission, 436 So.2d 383, 389 (Fla.

70425th DCA 1983).

7045Based on the above, the Hearing Officer's ruling rejecting Petitioner's

7055proposed findings relating to the impact of Hubbard's dock on native seagrass is

7068determined to be supported by competent substantial evidence of record and is

7080affirmed.

7081Consequently, Petitioner's exception 2C is denied.

7087Exception 2D

7089Petitioner's Exception 2D challenges the propriety of the Hearing Officer's

7099rejection in the Appendix to the Recommended Order of her proposed findings of

7112fact 33-38 on grounds that they were "not supported by credible and persuasive

7125evidence and as conclusions of law." (Appendix to Rec. Order, p. 22) These

7138proposed factual findings relate to Petitioner's claim that a portion of

7149Hubbard's dock facility consisting of an elevated sun deck/roof located directly

7160over and providing covering for the boat slip was not constructed for "water

7173dependent activities" within the context of Rules 18-21.003(56) and 18-

718321.004(1)(d), Florida Administrative Code. Rule 18-21.004(1)(d) limits approval

7191of activities on sovereignty lands to "water dependent activities." Rule 18-

720221.003(56) defines a water dependent activity as "an activity which can only be

7215conducted on, in, over, or adjacent to water areas because the activity requires

7228direct access to the water body or sovereign submerged lands for transportation,

7240recreation . .

7243The Hearing Officer found in paragraphs 44 of the Recommended Order that

7255Hubbard's as-built dock is a "water dependent facility" in that the primary use

7268of the dock facility is to moor a vessel and secondary uses included

7281recreational activities such as fishing, swimming and sun bathing. The Hearing

7292Officer also found in paragraph 45 that the dock facility provides ingress and

7305egress to the lagoon and that such primary and secondary uses were consistent

7318with the Board of Trustees' goals for use of sovereign submerged lands.

7330At the DOAH final hearing, on March 27, 1995, the Department presented the

7343testimony of Todd VandeBerg, a planning manager for the Department's Southwest

7354District. Mr. VandeBerg, a Department employee for over five years, supervised

7365the review of Hubbard's after-the-fact request for consent of use of the subject

7378sovereignty lands and had personally visited the dock site. (TR II, Vol. 1, 23-

739224, 28) VandeBerg repeatedly testified that it was the position of Department

7404staff 7/ that Hubbard's entire dock facility, including the elevated sun

7415deck/roof portion, was a "water dependent" structure based on Department policy

7426in effect at the time Hubbard's consent of use request was reviewed interpreting

7439Chapter 18-21, Florida Administrative Code. (Tr. II, Vol. 1, 28-29, 55, 82-83;

7451Tr. II, Vol. 2, 237, 242)

7457The Department policy relied upon by Mr. VandeBerg is that dock structures

7469having roofs that are not "completely closed in and/or climatized for human

7481habitation" are deemed to be water dependent structures under Chapter 18-21,

7492Florida Administrative Code. (TR II, Vol.1, 48-49) This policy was codified in

75041992 into a Department document entitled "Bureau of Submerged Lands & Preserves

7516Interim Policy for Single-Family Docks Outside Aquatic Preserves." (Dept.

7525Composite Ex. 21)

7528Petitioner did present expert testimony at the DOAH hearing from Robert

7539Routa, who was involved in a supervisory capacity in the review of requests for

7553approval of activities on sovereign submerged lands in the early 1970's for the

7566former Department of Natural Resources. Mr. Routa was of the opinion that the

7579elevated sun deck/roof portion of Hubbard's dock facility was not a water

7591dependent structure. (Tr. II, Vol. 2, 156) Mr. Routa testified, however, that

7603he had been in the private practice of law since 1978 and admitted that he had

7619no authority to speak for the Department concerning its interpretation in the

76311990's of the rules pertaining to review of requests for consent of use of

7645sovereignty lands. (Tr. II, Vol. 2, 142, 161-162)

7653The Recommended Order rejects Petitioner's challenge to Hubbard's as-built

7662deck facility on the ground that it is not a "water dependent" structure under

7676Chapter 18-21 of the Florida Administrative Code. Thus, the Hearing Officer

7687obviously gave more weight and credence to the testimony of the Department's

7699witness Todd VandeBerg than to the testimony of Petitioner's witness Robert

7710Routa. As noted above, an agency reviewing a recommended order of a DOAH

7723hearing officer may not reweigh the evidence, resolve conflicts therein or judge

7735the credibility of witnesses. Heifetz v. Dept. of Business Regulation supra 475

7747So.2d at 1281. These are evidentiary matters within the sound discretion of the

7760Hearing Officer as the trier of the facts.

7768The Department staff interpretation of the rule definition of "water

7778dependent activities" to include the construction of roofs over docks and boat

7790slips that are not "completely closed in and/or climatized for human habitation"

7802appears to be a reasonable attempt to distinguish between a structure whose

7814primary function is habitation and one whose primary function is water

7825transportation or recreation. The case law of Florida holds that great

7836deference should be accorded to administrative interpretations of statutes and

7846rules that the agency is required to enforce, and such administrative

7857interpretations should not be overturned unless clearly erroneous. See, e. q.,

7868Falk v. Beard, 614 So.2d 1086, 1089 (Fla. 1993); Dept. of Env. Regulation v.

7882Goldring, 477 So.2d 532, 534 (Fla. 1985); Harloff v. City of Sarasota, 575 So.2d

78961324, 1327 (Fla. 2d DCA 1991); Reedy Creek Improvement Dist. v. Dept. of Env.

7910Regulation, 486 So.2d 642, 648 (Fla. 1st DCA 1986).

7919This Department written policy interpreting its rules relating to "water

7929dependent activities" is not clearly erroneous and should not be overturned. In

7941addition, the Hearing Officer's Findings of Fact 44 and 45 related to the "water

7955dependent activity" issue are supported by competent substantial evidence of

7965record and must be affirmed. Consequently, Petitioner's exception 2D is denied.

7976Exception 2E

7978This exception of Petitioner takes issue with the Hearing Officer's

7988Conclusion of Law 73 denying a request for award of attorney's fees as set forth

8003in Petitioner's Proposed Recommended Order. The denial of Petitioner's request

8013for attorney's fees was based on the Hearing Officer's conclusions that "Hubbard

8025showed by a preponderance of the evidence that she is entitled to a permit and

8040consent of use" and that the "evidence was credible, persuasive, and

8051substantial." (Rec. Order, para. 73)

8056The question of whether a party intended to participate in a formal

8068administrative proceeding for an "improper purpose" so as to warrant an award of

8081attorney's fees to an adverse party has been judicially determined to be an

8094issue of fact within the prerogative of a hearing officer, rather than a

8107conclusion of law that may be freely rejected by the reviewing agency. See

8120Burke v. Harbor Estates Associates, Inc., 591 So.2d 1034, 1037 (Fla. 1st DCA

81331991). The court noted in the Burke opinion that the Department's predecessor

8145agency, the Department of Environmental Regulation, claimed no special insight

8155or expertise in determining whether a party participated in a formal

8166administrative proceeding for an "improper purpose." Burke, supra, at 1037. No

8177claim of such special insight or expertise has been made in these proceedings.

8190In addition, the provisions of Section 120.59(6), Florida Statutes, only

8200authorize an award of attorney's fees in a formal administrative proceeding to a

8213nonagency "prevailing party." The Recommended Order of the Hearing Officer

8223rejects all Petitioner's challenges to the construction of Hubbard's dock.

8233Also, the Hearing Officer recommends that the Department approve the Consent

8244Order entered into with Hubbard and grant the after-the-fact applications for a

8256permit and consent of use for Hubbard's existing dock facility. This Final

8268Order affirms all of the Hearing Officer's findings of fact and conclusions of

8281law with one minor clerical correction and adopts the recommendations set forth

8293in the Recommended Order. Thus, Petitioner is obviously not a "prevailing

8304party" in these consolidated administrative proceedings within the purview of

8314the statutory provisions of Section 120.59(6).

8320Based on the above, Petitioner's exception 2E is denied.

8329CONCLUSION

8330The Department shares Petitioner's concerns for the protection of the

8340manatee, which is an endangered species and a precious natural resource of this

8353state. However, as discussed above, the Hearing Officer's findings and related

8364conclusions that Hubbard's dock structure will not adversely affect manatees are

8375supported by competent substantial evidence of record. In addition, even if

8386Petitioner had established that Hubbard's dock structure did not comply with

8397certain specifications of the Citrus County Manatee Protection Plan, the

8407Department does not have the legal authority to deny the dock permit based

8420solely on such a showing. The Florida courts have ruled that "[r]emedies apart

8433from the permitting scheme are available" if Hubbard's dock should violate any

8445mandatory requirements of Citrus County's Comprehensive Plan. Taylor v. Cedar

8455Key Special Water and Sewerage District, supra, at 482.

8464It is therefore ORDERED:

8468A. The date of September 14, 1993, is substituted for the date of July 10,

84831993, as set forth on unnumbered line 13 of the Preliminary Statement on page

8497two of the Recommended Order.

8502B. The Recommended Order of the Hearing Officer, as modified by the

8514clerical correction in paragraph A above, is adopted and incorporated by

8525reference herein.

8527C. Permit number 091923403, proposed for issuance by the Department to

8538Hubbard on November 4, 1992, is hereby ISSUED, subject to the conditions set

8551forth in the permit, the matters set forth in the Consent Order described in

8565paragraph D below, and the modifications described in the Hearing Officer's

8576Finding of Fact No. 8 in the Recommended Order.

8585D. The Consent Order between the Department and Hubbard in OGC Case No.

859893-2807 dated September 14, 1993, is APPROVED.

8605E. Hubbard's after-the-fact application for consent of use for the

8615sovereign submerged lands underlying the dock structure is GRANTED.

8624Any party to this Order has the right to seek judicial review of the Order

8639pursuant to Section 120.68, Florida Statutes, by the filing of a Notice of

8652Appeal pursuant to Rule 9.110, Florida Rules of Appellate Procedure, with the

8664clerk of the Department in the Office of General Counsel, 2600 Blair Stone Road,

8678Tallahassee, Florida 32399-2400; and by filing a copy of the Notice of Appeal

8691accompanied by the applicable filing fees with the appropriate District Court of

8703Appeal. The Notice of Appeal must be filed within 30 days from the date this

8718Order is filed with the clerk of the Department.

8727DONE AND ORDERED this 13th day of July, 1995, in Tallahassee, Florida.

8739STATE OF FLORIDA DEPARTMENT

8743OF ENVIRONMENTAL PROTECTION

8746_________________________________

8747VIRGINIA B. WETHERELL

8750Secretary

8751Marjory Stoneman Douglas Building

87553900 Commonwealth Boulevard

8758Tallahassee, Florida 32399-3000

8761FILING AND ACKNOWLEDGMENT:

8764FILED, on this date, pursuant to

8770Section 120.52, Florida Statutes,

8774with the designated Department

8778Clerk, receipt of which is

8783her acknowledged.

8785_______________________ 07/14/95

8787Kathy C. Carter

8790ENDNOTES

87911/ On June 1, 1995, the Hearing Officer entered a "Corrected Order" wherein the

8805initial Recommended Order was corrected nunc fro tunc to reflect the case

8817numbers of all three consolidated cases.

88232/ The designated uses for Class III surface waters are recreation and the

8836propagation and maintenance of a healthy, well-balanced population of fish and

8847wildlife. Rule 62-302.400(1), Florida Administrative Code. 3. Since the

8856project site is adjacent to an Outstanding Florida Water as designated by

8868Department rule, Hubbard has to provide reasonable assurances that the project

8879will be clearly in the public interest under Section 373.414(1), Florida

8890Statutes. The Hearing Officer found that Hubbard's dock and retaining wall has

8902resulted in benefits to the public, including the 400 foot conservation easement

8914given to the state and reduction of fertilizer and yard chemical runoff into the

8928lagoon. These findings of the Hearing Officer in paragraphs 33 and 34 of the

8942Recommended Order related to the public interest criteria were not discussed or

8954even cited in Petitioner's exceptions and are, therefore, unchallenged on agency

8965review.

89664/ The last paragraph on page two of the Recommended Order erroneously recites

8979July 30, 1993, as the date the Consent Order

89885/ The Citrus County Manatee Protection Plan is a part of the Citrus County

9002Comprehensive Plan.

90046/ One of the statutory criteria to be considered by the Department in

9017reviewing a permit application is whether the "activity will adversely affect

9028the conservation of fish and wildlife, including endangered or threatened

9038species, or their habitats." See Section 373.414(1)(a) 2., Florida Statutes.

90487/ Petitioner has placed considerable emphasis in these proceedings on the fact

9060that one of VandeBerg's subordinates, Harry Michaels, raised some initial

9070concerns in an internal memorandum as to whether the sun deck/roof portion of

9083Hubbard's dock facility was consistent with a water dependent activity under the

9095Department rules. Mr. Michaels testified in deposition that he had only been

"9107involved in submerged lands authorizations for about five months at that time"

9119and wasn't sure whether the flat roof complied with Department policy. (Pet.

9131Ex. 20, p. 16) Mr. Michael's initial concerns were obviously determined to be

9144unfounded by his more experienced supervisor, Todd VandeBerg. In any event, it

9156is a general rule of case law that agencies are not estopped through

9169misstatements of law by agency employees. See, ., Cordes v. Dept. of Env.

9182Regulation, 582 So.2d 652, 655 (Fla. 1st DCA 1991).

9191CERTIFICATE OF SERVICE

9194I CERTIFY that a true copy of the foregoing was sent by U.S. Mail to:

9209John M. Rains, III, Esquire

9214Ammis, Mitchell, Cockey, Edwards & Roehn, P.A.

92211 Tampa City Ctr Ste 2100

9227201 N Franklin St

9231Tampa Florida 33602

9234and

9235Emily G. Pierce, Esquire

9239Marcia Penman Parker, Esquire

9243Roger, Towers, Bailey, Jones & Gay

92491301 Gulf Life Dr. Ste 1500

9255Jacksonville Florida 32207

9258and by hand delivery to:

9263Daniel Manry Ann Cole, Clerk

9268Hearing Officer Division of Administrative

9273Division of Administrative Hearings

9277Hearings The DeSoto Bldg.

9281The DeSoto Bldg. 1230 Apalachee Pkwy

92871230 Apalachee Pkwy Tallahassee Florida 32399-1550

9293Tallahassee Florida 32399-1550

9296Kenneth Plante, Esquire

9299Evelyn Davis Golden, Esquire

9303M.B. Adelson, Esquire

9306Department of Environmental Protection

93103900 Commonwealth Building

9313Tallahassee Florida 32399-3000

9316on this 14th day of July, 1995.

9323STATE OF FLORIDA DEPARTMENT

9327OF ENVIRONMENTAL PROTECTION

9330_________________________________

9331J. TERRELL WILLIAMS

9334Assistant General Counsel

9337Marjory Stoneman Douglas Building

93413900 Commonwealth Boulevard

9344Mail Station 35

9347Tallahassee, Florida 32399-3000

9350Telephone: (904) 488-9314

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 07/14/1995
Proceedings: Final Order filed.
Date: 07/14/1995
Proceedings: Final Order filed.
PDF:
Date: 07/13/1995
Proceedings: Agency Final Order
PDF:
Date: 05/31/1995
Proceedings: Recommended Order
PDF:
Date: 05/31/1995
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held March 8 & 9, 1995.
Date: 05/24/1995
Proceedings: (Petitioner) Notice of Supplemental Authority; Opinion filed May 19, 1995 filed.
Date: 05/23/1995
Proceedings: (Petitioner) Notice of Supplemental Authority filed.
Date: 04/27/1995
Proceedings: Respondent`s Proposed Recommended Order; Petitioner`s Notice of Filing the Proposed Recommended Order filed.
Date: 04/27/1995
Proceedings: Proposed Recommended Order (For HO Signature) filed.
Date: 04/20/1995
Proceedings: Order Granting Extension of Time sent out. (motion granted)
Date: 04/17/1995
Proceedings: (Petitioner) Reply to Motion to Extend Filing Proposed Recommended Order filed.
Date: 04/17/1995
Proceedings: (Petitioner) Reply to Motion to Extend Filing Proposed Recommended Order filed.
Date: 04/13/1995
Proceedings: (DEP) Motion to Extend Filing Proposed Recommended Order filed.
Date: 04/06/1995
Proceedings: Transcript 2 volumes filed.
Date: 03/29/1995
Proceedings: Notice of Filing Respondent Department of Environmental Protection's Composite Exhibit 21 and Original Transcript of March 8 and 9, 1994 Hearing; Certificate of Service; Memo to Environmental Administrators Planning Managers from Michael E. Ashey Re: Si
Date: 03/29/1995
Proceedings: Transcript March 8 and 9, 1994; Volume One; Volume Two; Volume Three filed.
Date: 03/16/1995
Proceedings: Notice of Appearance and Substitution of Counsel and Co-Counsel for Florida Department of Environmental Protection filed.
Date: 03/03/1995
Proceedings: (Petitioner) Amended Re-Notice of Taking Deposition Duces Tecum (change of location only) filed.
Date: 02/27/1995
Proceedings: (Petitioner) Amended Re-Notice of Taking Depositions Duces Tecum (change of time only) filed.
Date: 02/23/1995
Proceedings: RE-Notice of Taking Deposition Duces Tecum (canceling depositions at request of Respondent, Department of Environmental Protection, previously scheduled for 2/27/95) filed.
Date: 02/03/1995
Proceedings: Order Granting Withdrawal sent out. (motion granted)
Date: 01/24/1995
Proceedings: Notice of Appearance of Counsel for Department of Environmental Protection filed.
Date: 01/23/1995
Proceedings: (Petitioner) Response to Motion for Leave to Withdrawal (sic) as Counsel for Respondent Tana Hubbard; Notice of Taking Depositions Duces Tecum filed.
Date: 01/17/1995
Proceedings: Motion for Leve to Withdrawal as Counsel for Respondent Tana Hubbard filed.
Date: 12/30/1994
Proceedings: Notice of Hearing sent out. (hearing set for 3/27/95; 9:30am; Talla)
Date: 12/30/1994
Proceedings: Order Granting Consolidation sent out. (Consolidated cases are: 93-1499, 93-6507, 94-6501)
Date: 12/30/1994
Proceedings: Case No/s 93-1499, 93-6507: unconsolidated.
Date: 11/28/1994
Proceedings: Response to Status Report (Petitioner) filed.
Date: 11/28/1994
Proceedings: Response to Status Report (Petitioner) filed.
Date: 11/21/1994
Proceedings: (DEP) Status Report filed.
Date: 09/23/1994
Proceedings: Letter to DSM from Cathy Gaddis (re: ltr dated 8/15/94) filed.
Date: 09/19/1994
Proceedings: Order of Abeyance sent out. (Parties to file status report by 11/14/94)
Date: 09/09/1994
Proceedings: (Petitioner) Notice of Substitution of Counsel for Department of Environmental Protection filed.
Date: 09/09/1994
Proceedings: (Petitioner) Response to Notice of Agency Statement and Request for Sanctions filed.
Date: 09/09/1994
Proceedings: CC: Letter to DSM from K. Hetrick (RE: Cancellation of hearing scheduled 9/12/94) filed.
Date: 09/08/1994
Proceedings: (Petitioner) Response to Notice of Agency Statement and Request for Sanctions filed.
Date: 09/02/1994
Proceedings: Notice of Agency Statement filed.
Date: 08/26/1994
Proceedings: Motion for Scheduling Order filed. (From John H. Rains, III)
Date: 08/26/1994
Proceedings: (Petitioner) Motion for Scheduling Order filed.
Date: 08/26/1994
Proceedings: (DER) Notice of Appearance filed.
Date: 08/16/1994
Proceedings: Order sent out. (hearing rescheduled for 9/12/94; 9:30am; Talla)
Date: 08/15/1994
Proceedings: Letter to parties of record from DSM (RE: enclosing copy of letter from hearing held in March) sent out.
Date: 08/02/1994
Proceedings: Letter to DSM from J. Hayes (RE: payment of transcript) filed.
Date: 06/29/1994
Proceedings: (Respondent) Memorandum of Law In Response To The Hearing Officer's Order Dated June 7, 1994 filed.
Date: 06/27/1994
Proceedings: (Respondent) Memorandum of Law in Response to the Hearing Officer`s Order Dated June 7, 1994; Memorandum of Law in Support of Division of Administrative Hearings` Jurisdiction of the Department of Environmental Protection filed.
Date: 06/27/1994
Proceedings: Memorandum of Law in Response to the Hearing Officer`s Order Dated June 7, 1994 filed.
Date: 06/07/1994
Proceedings: Order sent out. (re: resolving issues from 4/22/94 Order sent out)
Date: 05/13/1994
Proceedings: (Petitioner) Supplemental Report To Hearing Officer filed.
Date: 05/09/1994
Proceedings: (Petitioner) Motion Showing Good Cause and Report of Efforts to Address Issues in Hearing Officer's Order Continuing Portion of Formal Hearing filed.
Date: 04/22/1994
Proceedings: Order Continuing Portion of Formal Hearing sent out. (hearing date to be rescheduled at a later date)
Date: 03/25/1994
Proceedings: Respondent Tana Hubbard's Memorandum of Law in Opposition to Alternative Motion to Continue a Portion of the Administrative Hearing filed.
Date: 03/23/1994
Proceedings: Respondent Tana Hubbard's Memorandum of Law in Opposition to Alternative Motion to Continue a Portion of the Administrative Hearing filed.
Date: 03/23/1994
Proceedings: (Respondent) Memorandum of Law in Response to and In Opposition to Petitioner's Motion to Continue Portion of Administrative Hearing w/Exhibit-1 filed.
Date: 03/18/1994
Proceedings: Petitioner's Original Photographs w/cover ltr filed.
Date: 03/17/1994
Proceedings: Memorandum of Law in Support of Alternative Motion to Continue Portion of Administrative Hearing w/cover ltr filed. (From John H. Rains, III)
Date: 03/17/1994
Proceedings: (Petitioner) Memorandum of Law in Support of Alternative Motion to Continue Portion of Administrative Hearing w/(2)copy of Transcript & attachment (ALL TAGGED) filed.
Date: 03/16/1994
Proceedings: Petitioner's Exhibit-12 w/cover ltr filed.
Date: 03/16/1994
Proceedings: (Petitioner) Memorandum of Law in Support of Alternative Motion to Continue Portion of Administrative Hearing filed.
Date: 03/07/1994
Proceedings: (Respondent) Notice of Taking Deposition Duces Tecum filed.
Date: 03/07/1994
Proceedings: Parties' Prehearing Stipulation filed.
Date: 03/07/1994
Proceedings: (Petitioner) Motion for Clarification and Alternative Motion to Continue Portion of Administrative Hearing w/Final Order Dismissing Petition for Declaratory Statement filed.
Date: 03/04/1994
Proceedings: (Petitioner) Unilateral Prehearing Stipulation filed.
Date: 03/04/1994
Proceedings: Letter to CCA from John H. Rains, III (re: February 18, 1994 Order) w/CC Petitioner's Supplemental Witness List filed.
Date: 03/01/1994
Proceedings: Order Designating Location of Hearing sent out (hearing set for 3/8/94, 1:00pm; 3/9/94, 9:00am; Crystal River)
Date: 02/18/1994
Proceedings: Order sent out. (Re: Motion in Limine and Memorandum of Law)
Date: 02/16/1994
Proceedings: Petitioner's Supplemental Response to Motion in Limine filed.
Date: 02/14/1994
Proceedings: Notice of Taking Deposition Duces Tecum w/cover ltr filed. (From John H. Rains, II)
Date: 02/08/1994
Proceedings: Petitioner`s Preliminary Response to Motion in Limine and Motion for Additional Time in Which to Respond to Motion in Limine filed.
Date: 02/07/1994
Proceedings: Order sent out. (Re: Motion Denied as to witness Rose; Motion Granted as to witness Patchett)
Date: 02/07/1994
Proceedings: (Respondent) Notice of Taking Deposition Duces Tecum filed.
Date: 02/04/1994
Proceedings: Petitioner's Response to Motion for Protective Order and Notice of Filing of Affidavits of Service of Process w/cover ltr filed.
Date: 02/03/1994
Proceedings: (Petitioner) Amended Notice of Taking Deposition Duces Tecum filed.
Date: 02/03/1994
Proceedings: Petitioner's Response to Motion for Protective Order and Notice of Filing of Affidavits of Service of Process & cover ltr filed.
Date: 02/03/1994
Proceedings: (Respondent) Notice of Hearing filed.
Date: 02/01/1994
Proceedings: Respondent, Tana Hubbard's Motion in Limine And Memorandum of Law in Support filed.
Date: 02/01/1994
Proceedings: (Respondent) Motion for Protective Order w/Exhibits 1-4 filed.
Date: 01/10/1994
Proceedings: (Petitioner) Amended Notice of Taking Deposition Duces Tecum filed.
Date: 01/03/1994
Proceedings: (Petitioner) Notice of Taking Deposition Duces Tecum (4) filed.
Date: 12/06/1993
Proceedings: Amended Third Notice of Hearing sent out. (hearing set for 3/8/94; 1:00pm; Crystal River)
Date: 12/01/1993
Proceedings: Joint Response to Order of November 16, 1993 and Initial Order of November 17, 1993 in Case No. 93-6507 filed.
Date: 12/01/1993
Proceedings: Third Notice of Hearing sent out. (hearing set for April 12-13, 1993; 1:00pm; Crystal River)
Date: 12/01/1993
Proceedings: Joint Response to Order of November 16, 1993 and Initial Order of November 17, 1993 in Case NO. 93-6507 filed.
Date: 11/30/1993
Proceedings: Department of Environmental Protection's Response to Initial Order filed.
Date: 11/16/1993
Proceedings: Order sent out. (Consolidated cases are: 93-1499 & 93-6507)
Date: 11/10/1993
Proceedings: Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection filed.
Date: 09/30/1993
Proceedings: Petitioner's Status Report filed.
Date: 09/23/1993
Proceedings: Notice of Agency Position filed.
Date: 08/11/1993
Proceedings: Order sent out. (Parties to file status report by 9/30/93; hearing cancelled)
Date: 08/10/1993
Proceedings: (Respondent) Second Amended Notice of Taking Deposition Duces Tecum filed.
Date: 08/10/1993
Proceedings: (Petitioner) Notice of Taking Deposition Duces Tecum filed.
Date: 08/10/1993
Proceedings: Respondent, Tana Hubbard's Motion for Continuance filed.
Date: 08/09/1993
Proceedings: (Respondent) Amended Notice of Taking Deposition Duces Tecum filed.
Date: 08/09/1993
Proceedings: (Petitioner) Second Amended Notice of Taking Deposition Duces Tecum filed.
Date: 08/09/1993
Proceedings: Second Amended Notice of Taking Depositions Duces Tecum filed. (From John H. Rains, III)
Date: 08/05/1993
Proceedings: Petitioner's Witness List filed.
Date: 08/04/1993
Proceedings: Respondent, Tana Hubbard`s Notice of Service of Answers to Petitioner, Helen C. Sutton`s First Interrogatories to Respondent filed.
Date: 08/03/1993
Proceedings: Respondent Department of Environmental Protection's Final Witness List filed.
Date: 08/02/1993
Proceedings: (Respondent) Notice of Taking Deposition Duces Tecum (2); Respondent,Tana Hubbard's Response to Petitioner's Request for Production of Documents filed.
Date: 08/02/1993
Proceedings: (Petitioner) Amended Notice of Taking Deposition Duces Tecum filed.
Date: 08/02/1993
Proceedings: Respondent Tana Hubbard's Final Witness List filed.
Date: 07/30/1993
Proceedings: Amended Notice of Taking Deposition Duces Tecum filed. (From John H. Rains, III)
Date: 07/28/1993
Proceedings: (Petitioner) Notice of Taking Deposition Duces Tecum filed.
Date: 07/15/1993
Proceedings: Petitioner`s Supplement Response to Interrogatories filed.
Date: 07/06/1993
Proceedings: Notice of Appearance of Counsel for Department of Environmental Protection filed.
Date: 07/06/1993
Proceedings: Request for Production of Documents filed. (From John H. Rains, III)
Date: 07/06/1993
Proceedings: Petitioner, Helen C. Sutton's First Interrogatories to Respondent, Tana Hubbard filed.
Date: 06/30/1993
Proceedings: Order sent out. (Re: Rulings on Motions)
Date: 06/28/1993
Proceedings: Petitioner`s Response to Respondent Motion to Compel Answers to Interrogatories or, In the Alternative Motion to Dismiss; Petitioner`s Response to Respondent`s Motion to Strike Untimely Response filed.
Date: 06/28/1993
Proceedings: Petitioner`s Response to Respondent`s Motion to Compel Answers to Interrogatories or, In the Alternative, Motion to Dismiss; Petitioner`s Response to Respondent`s Motion to Strike Untimely Response filed.
Date: 06/25/1993
Proceedings: Notice of Motion Hearing filed. (From Marcia Penman Parker)
Date: 06/17/1993
Proceedings: Respondent, Tana Hubbard`s Motion to Strike Untimely Response; Respondent, Tana Hubbard`s Motion to Compel Answers to Interrogatories or, in the Alternative, Motion to Dismiss w/Exhibits 1&2 filed.
Date: 06/16/1993
Proceedings: Petitioner`s Response to Respondent`s Second Motion to Strike filed.
Date: 06/04/1993
Proceedings: Second Notice of Hearing sent out. (hearing set for 8/30/93; 9:00am;Crystal River)
Date: 06/03/1993
Proceedings: Department of Environmental Regulation's Motion for Continuance filed.
Date: 06/01/1993
Proceedings: Respondent, Tana Hubbard's Second Motion to Strike filed.
Date: 05/28/1993
Proceedings: (Petitioner) Objection to Respondents` First Interrogatories to Petitioner and Responses to Interrogatories; Objection to First Request for Admissions to Petitioner and Response to First Request for Admissions to Petitioner filed.
Date: 05/26/1993
Proceedings: Second Amended Petition for Administrative Hearing filed. (From John H. Rains, III)
Date: 05/20/1993
Proceedings: Order sent out. (Motion to strike petitioner`s response to motion to dismiss, denied)
Date: 05/06/1993
Proceedings: (Respondent) Notice of Motion Hearing filed.
Date: 05/04/1993
Proceedings: Petitioner's Response to Motion to Strike filed.
Date: 05/03/1993
Proceedings: Respondent, Tana Hubbard`s First Request for Admissions to Petitioner filed.
Date: 04/22/1993
Proceedings: Respondent, Tana Hubbard's Motion to Convene A Prehearing Conference filed.
Date: 04/22/1993
Proceedings: (Respondent) Notice of Service of Respondent, Tana Hubbard's First Interrogatories to Petitioner filed.
Date: 04/21/1993
Proceedings: Respondent, Tana Hubbard`s Motion to Strike Untimely Response w/Exhibits A-C filed.
Date: 04/16/1993
Proceedings: Response to Respondent Tana Hubbard's Motion to Dismiss or, in the Alternative, Motion to Strike filed.
Date: 04/05/1993
Proceedings: (Petitioner) Amended Response to Initial Order filed.
Date: 04/05/1993
Proceedings: Notice of Hearing sent out. (hearing set for 6-30-93; 11:00am; Crystal River)
Date: 04/02/1993
Proceedings: Respondent, Tana Hubbard's Motion to Dismiss or, in the Alternative, Motion to Strike filed.
Date: 04/01/1993
Proceedings: (Respondent) Response to Initial Order filed.
Date: 04/01/1993
Proceedings: (Respondent) Notice of Appearance filed.
Date: 03/22/1993
Proceedings: Initial Order issued.
Date: 03/15/1993
Proceedings: Request for Assignment of Hearing Officer and Notice of Preservation of Record; Agency Intent to Issue; Amended Petition for Formal Administrative Hearing filed.

Case Information

Judge:
DANIEL MANRY
Date Filed:
03/15/1993
Date Assignment:
03/07/1994
Last Docket Entry:
07/14/1995
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
 

Related DOAH Cases(s) (2):

Related Florida Statute(s) (9):

Related Florida Rule(s) (4):