96-001955 Scout Development Corporation vs. Nansep3 Corporation And Department Of Environmental Protection
 Status: Closed
Recommended Order on Wednesday, August 6, 1997.


View Dockets  
Summary: Permit for dune walkover properly issued where no adverse impact to dune system as a whole or to adjacent properties shown to be likely.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8SCOUT DEVELOPMENT CORPORATION, )

12)

13Petitioner, )

15)

16vs. ) Case No. 96-1955

21)

22NANSEP3 CORPORATION and DEPARTMENT )

27OF ENVIRONMENTAL PROTECTION, )

31)

32Respondents. )

34___________________________________)

35)

36700 OCEAN DRIVE HOMEOWNERS' )

41ASSOCIATION, INC., )

44)

45Petitioner, )

47)

48vs. ) Case No. 96-1956

53)

54NANSEP3 CORPORATION and DEPARTMENT )

59OF ENVIRONMENTAL PROTECTION, )

63)

64Respondents. )

66___________________________________)

67RECOMMENDED ORDER

69Pursuant to Notice, this cause was heard by Linda M. Rigot,

80the assigned Administrative Law Judge of the Division of

89Administrative Hearings, on April 21, 1997, in West Palm Beach,

99Florida.

100APPEARANCES

101For Petitioners: Alfred A. LaSorte, Jr., Esquire

108United National Bank Tower

112Suite 1000

1141645 Palm Beach Lakes Boulevard

119West Palm Beach, Florida 33401

124For Respondent

126Nansep3 Corporation: Patrick O'Hara, Esquire

131324 Datura Street

134Suite 100

136West Palm Beach, Florida 33401

141For Respondent Department

144of Environmental Protection:

147Jeffrey Brown, Esquire

150Department of Environmental Protection

1543900 Commonwealth Boulevard

157Tallahassee, Florida 32399-3000

160STATEMENT OF THE ISSUE

164The issue presented is whether Respondent Nansep3

171Corporation should be issued a permit to construct a dune

181walkover.

182PRELIMINARY STATEMENT

184Respondent Department of Environmental Protection issued to

191Respondent Nansep3 Corporation a permit to construct a dune

200walkover, and Petitioners timely requested an evidentiary hearing

208to contest the issuance of that permit. This cause was

218thereafter transferred to the Division of Administrative Hearings

226to conduct that evidentiary proceeding.

231Respondent Nansep3 Corporation presented the testimony of

238Susan Kenney, Clinton "Red" E. Taylor, Robert Barron, Dallas

247Durrance, Cory S. Cross, and Rodney Sarkela. Petitioners

255presented the testimony of Srinivas Tammisetti, James Molter, and

264Erik J. Olsen. Respondent Department of Environmental Protection

272presented the testimony of Rodney Sarkela and Barry Manson-Hing.

281Additionally, Joint Exhibits numbered 1-44 were admitted in

289evidence.

290The two-volume transcript of the proceeding was filed post

299hearing, and all parties filed proposed recommended orders.

307Those documents have been considered in the entry of this

317Recommended Order.

319FINDINGS OF FACT

3221. The subject property is an approximately three-acre,

330oceanfront site located within the Town of Juno Beach.

339Respondent Nansep3 Corporation purchased the site with an

347existing site plan approved by the Town. The approved site plan

358included a public access easement running parallel to the south

368property boundary from the public road to the beach. Nansep

378constructed a 59-unit condominium high-rise on the property.

3862. Petitioners Scout Development Corporation and 700 Ocean

394Drive Homeowners' Association, Inc., are the developer and

402homeowners' association, respectively, of a ten-unit beachfront

409residential community located immediately south of the subject

417site. The units therein consist of large, oceanfront, zero-lot-

426line, single-family residences. As of the final hearing in this

436cause, Scout had sold the eight southernmost units and was

446holding the two northernmost units for sale.

4533. The wall surrounding Petitioners' northernmost unit is

461located within approximately two feet of Petitioner's north

469property line, which is the same property line as Nansep's south

480property line. Nansep's public access easement is 10-feet wide

489and runs along that common property line. The subject dune

499walkover is located four feet from that property line.

5084. The Town of Juno Beach provides an incentive to

518developers for the construction of public access dune walkovers.

527Developers can obtain an additional two dwelling units per acre

537if they agree to convey a ten-feet wide access easement to the

549public and construct a six-feet wide dune walkover with

558landscaping, irrigation, and lighting. That additional "bonus"

565was included in the approved site plan in place when Nansep

576purchased the subject site.

5805. Nansep's agreement with the Tow n required that the dune

591walkover extend straight off the sidewalk leading to it for

601security reasons, i.e. , in order to make it easier for the Town

613to patrol the public access easement. In addition, Nansep had

623filed a declaration of condominium with the State of Florida

633depicting the dune walkover and sidewalk located within the

642public access easement and running in a straight line from the

653public road fronting the property to the beach. Nansep was

663concerned that a relocation of the walkover could be a material

674change that could enable purchasers to void their purchase

683agreements or could enable the Town to vacate its site plan

694approval.

6956. On November 10, 1995, Nansep submitted to the Department

705an application for a permit to construct a dune walkover seaward

716of the coastal construction control line. Also submitted was a

726topographic survey of the subject property depicting the location

735of the public access easement at the south property line where

746the walkover structure would be located and its relationship to

756existing seagrapes. The architectural drawings also depicted the

764location of the dune walkover in relation to Nansep's south

774property line and showed the dune walkover to be six-feet wide

785with eight-inch diameter pilings.

7897. On February 1, 1996, the Department issued to Nansep

799Permit PB-536 and a Notice to Proceed. Those documents were

809accompanied by a transmittal letter advising that substantially

817affected persons could challenge the issuance of that Permit

826within 21 days and that if Nansep proceeded with construction

836within that 21-day period, it would be at Nansep's own risk.

8478. Standard Permit Condition numbered (1)(a) required

854Nansep to carry out the construction activities in accordance

863with the plans and specifications approved by the Department and

873prohibited any modification thereof. Special Permit Condition

880numbered 2 provided that:

884The optimum siting of the walkover structure shall

892be determined by the staff representative of the

900Bureau of Beaches and Coastal Systems during the

908preconstruction [sic] conference to provide maximum

914protection to the existing dune topography and

921vegetation located on the site.

9269. There is a conflict in the documents issued by the

937Department that day in that the Special Permit Conditions

946describe a four-feet wide structure on four-inch-by-four-inch

953pilings whereas the Notice to Proceed describes a six-feet wide

963structure. However, the plans approved by the Department clearly

972describe a six-feet wide structure on eight-inch diameter

980pilings. Further, the Town requires a six-feet wide structure

989for public access walkovers.

99310. When there is a conflict between the plans that are

1004approved and a permit condition, the plans are deemed to prevail

1015over the permit condition.

101911. The fact that the structure is wider and on larger

1030pilings than described in the permit does not remove the

1040structure from the definition of a "minor structure" under the

1050Department's rules and the applicable statutes. By definition, a

1059minor structure is one that is expendable during high frequency

1069storm events. Nansep's dune walkover meets that definition.

107712. On February 19, 1996, Petitioners filed petitions

1085challenging Nansep's permit. Petitioners alleged impacts to

1092seagrapes as well as erosion impacts resulting from the

1101structure. Petitioners also complain that they were not invited

1110to participate in the pre-construction meeting and that there is

1120a conflict in the permit as to whether a four-feet wide or six-

1133feet wide walkover was permitted.

113813. Nansep constructed its walkover notwithstanding the

1145petitions for administrative hearing. Its architect certified

1152compliance with the approved plans by letter dated March 6, 1996.

116314. Seagrapes are one of approximately 100 to 150 species

1173that can constitute a coastal dune community. Their root mass

1183helps resist erosion, although research shows that seagrapes are

1192less resistant than other plants installed on the foredune at the

1203project site. The seagrape and other woody, shrubby plant

1212species moderate the impact of wind and salt spray to other

1223species upland of the coastal community.

122915. Dune walkovers confer a benefit to dune vegetation by

1239protecting plants from pedestrian traffic. They also protect the

1248dune itself by controlling foot traffic which erodes the dune.

125816. The permit application showed a semi-circular area of

1267seagrapes on the southeast corner of the project site and in the

1279footprint of the proposed walkover, extending throughout the

1287width of the access easement. The depiction regarding the extent

1297of seagrapes accurately reflected existing site conditions.

1304Thus, in order to relocate the walkover in such a way as to avoid

1318the seagrapes, it would be necessary to place the walkover

1328outside of the public access easement.

133417. As a matter of routine, the Department would not, for

1345the purpose of avoiding impacts to seagrapes, require the

1354developer to re-negotiate a development agreement with a local

1363government or to locate a dune walkover outside of an access

1374easement required by an approved site plan.

138118. Before construction, virtually all of the seagrape

1389component of the project area was contaminated by invasive exotic

1399species.

140019. Nansep installed seagrapes, sea oats, and other grasses

1409along the dune and the dune face under a mitigation plan approved

1421by the Town of Juno Beach. The seagrape hedge Nansep planted

1432along the top of the dune runs from the north end of the property

1446to the south end. The overall dune vegetation community was

1456enhanced and is now more substantial than before construction

1465began.

146620. It is common practice to place dune walkover structures

1476in areas where seagrapes must be removed to accommodate the

1486structure. Nansep removed only the seagrapes directly in the

1495path of the walkover structure. The impact of the removal on the

1507seagrapes was a minor impact. Further, the dune vegetation

1516community, as a whole, was not damaged or harmed as a result of

1529the construction.

153121. Petitioners fear that their property will be impacted

1540by excessive erosion upon the occurrence of certain storm events

1550because the walkover is located within four feet of their north

1561property line. Public access walkovers in the Town of Juno Beach

1572which access the beach across private property run along property

1582lines and have a four-feet wide landscape strip from the property

1593line to where the dune walkover starts.

160022. Scour erosion refers to the interaction of the waves

1610and currents with pilings and the beach surface. Under a rule-

1621of-thumb method commonly relied upon in the field of coastal

1631engineering, the maximum vertical extent of scour erosion is

1640approximately twice the diameter of the piling, and the maximum

1650horizontal extent of the erosion is approximately three times the

1660diameter of the piling.

166423. Applying this method, the maximum horizontal extent of

1673scour erosion for the dune walkover can be expected to be 24 to

168630 inches out from the pilings, and the maximum vertical extent

1697of scour erosion can be expected to be around 18 inches below

1709grade. Accordingly, the maximum extent of the scour erosion

1718would not be likely to encroach upon the property of Petitioners

1729since there is four feet between the walkover and Petitioners'

1739property line except where the walkover juts out for benches at

1750the toe of the dune, east of the coastal construction control

1761line.

176224. Notwithstanding severe storms last fall, no erosion has

1771resulted from the structure. Instead, accretion, or build-up of

1780sand, has occurred. Further, the localized scour erosion cannot

1789be expected to adversely impact the dune vegetation community or

1799the dune system as a whole.

180525. The purpose of a pre-construction conference is for the

1815Department to review the permit conditions with the permit holder

1825and to verify the location of the coastal construction control

1835line and the location of the structure. Although other persons

1845are permitted to attend a pre-construction conference, the

1853Department does not require that adjoining property owners be

1862invited to attend. A Department memorandum opines that pre-

1871construction meetings are necessary for the approval of "major

1880structures" and shore protection projects. There does not appear

1889to be such a requirement for "minor structures" such as the

1900subject dune walkover.

190326. The Department's field engineer misread Nansep's permit

1911and did not notice that the permit called for a pre-construction

1922conference. Nevertheless, he met with Nansep's representatives

1929on-site on February 14, 1996, during the construction of the

1939walkover. He determined that the actual siting of the dune

1949walkover is the optimum siting to provide maximum protection to

1959the existing dune topography and vegetation on the site.

196827. Other than the directive in the permit to determine the

1979best siting with respect to existing dune topography and to dune

1990vegetation, the terms of the permit stated no other matters to be

2002considered in the pre-construction meeting. Nothing more would

2010have been accomplished in an actual pre-construction meeting than

2019occurred in the on-site visit by the Department's field engineer

2029during construction.

203128. The location of the walkover was clearly depicted in

2041the plans which the Department approved in issuing the permit.

2051Even though the permit called for a pre-construction conference

2060at which the optimum siting for the walkover would be selected,

2071no permit condition authorized the Department's representative to

2079direct a material change to the project, such as requiring the

2090relocation of the walkover to outside of the existing public

2100access easement.

210229. Comparing the benefits conferred on the dune system by

2112protection from pedestrian traffic with any negative impacts, the

2121benefits conferred offset any negative impacts to the dune

2130system.

2131CONCLUSIONS OF LAW

213430. The Division of Administrative Hearings has

2141jurisdiction over the parties hereto and the subject matter

2150hereof. Sections 120.569 and 120.57(1), Florida Statutes.

215731. Petitioners assert issues as to whether the walkover

2166structure was constructed in full compliance with the permit.

2175However, this proceeding is limited to the issues involved in the

2186issuance of the permit itself. Whether Nansep violated permit

2195conditions as to the height of the structure is a matter for the

2208Department to consider for any enforcement proceeding, not in

2217this proceeding to determine whether a permit should be issued.

222732. The law is well settled that a permit applicant bears

2238the burden of proving entitlement to the permit sought. Nansep

2248has met its burden.

225233. Section 161.053, Florida Statutes, sets forth standards

2260for the establishment of coastal construction control lines as

2269well as activities that may be permitted seaward of that line.

2280Part of the legislative intent is instructive. Section

2288161.053(1)(a), Florida Statutes, provides for the protection of

2296the beaches and coastal barrier dunes in this State from:

2306. . . construction which can jeopardize the

2314stability of the beach-dune system, accelerate

2320erosion, provide inadequate protection to upland

2326structures, endanger adjacent properties, or

2331interfere with public beach access.

233634. The statute's focus is on protection of the beach-dune

2346system, not the scour erosion which can occur around a piling.

2357Further, the statute focuses on endangerment of adjacent

2365properties, not inconvenience to their owners.

237135. The Department has promulgated rules to implement that

2380statute. Rule 62B-33.002(23), Florida Administrative Code,

2386quantifies construction impacts and provides that adverse impacts

2394are those which interfere with the natural functioning of the

2404system, a consideration not present in this cause. That Rule

2414also defines "other impacts" as those which may result in damage

2425to existing structures or property or interference with lateral

2434beach access. No damage to existing structures has been alleged,

2444and the possible damage of scour erosion around the pilings on

2455Nansep's property which may, or may not, extend onto Petitioners'

2465property by several inches cannot be considered significant

2473enough to constitute an adverse impact.

247936. Under Rule 62B-33.005(10), Florida Administrative

2485Code, construction is required to be located in previously-

2494disturbed areas when practicable. The only way Nansep could have

2504avoided the existing seagrapes would have been to site the

2514walkover at some place other than the public access easement that

2525had been approved by the local government. Petitioners propose

2534an alignment which would require the walkover to turn at a right-

2546angle, move outside the public access easement, run along the

2556swimming pool wall, turn at another right-angle, and then proceed

2566across the dune to the beach. It is not "practicable" to require

2578Nansep to vacate the approved site plan and re-design its project

2589to move the walkover out of the public access easement or to

2601require Nansep to convey more of its private property to the

2612public.

261337. The Department did commit a procedural irregularity in

2622the processing of this permit application either by requiring a

2632pre-construction conference or by not conducting one when it was

2642required by the permit conditions. However, the record in this

2652cause reveals that the Department's field engineer would have

2661approved the siting of the walkover had he conducted his on-site

2672visit before construction rather than during.

267838. Petitioners assert that Nansep graded the dune top for

2688the walkover but the plans Nansep submitted to the Department and

2699the Department's permit did not contemplate such excavation.

2707Yet, the evidence reveals that the one to two feet of excavation

2719was required for access by handicapped persons and, if asked, the

2730Department would have allowed it.

2735RECOMMENDATION

2736Based upon the foregoing Findings of Fact and Conclusions of

2746Law, it is

2749RECOMMENDED THAT a final order be entered granting Nansep's

2758application and issuing Permit PB-536 to Respondent Nansep3

2766Corporation.

2767DONE AND ENTERED this 6th day of August, 1997, at

2777Tallahassee, Leon County, Florida.

2781___________________________________

2782LINDA M. RIGOT

2785Administrative Law Judge

2788Division of Administrative Hearings

2792The DeSoto Building

27951230 Apalachee Parkway

2798Tallahassee, Florida 32399-30 60

2802(904) 488-9675 SUNCOM 278-9675

2806Fax Filing (904) 921-6847

2810Filed with the Clerk of the

2816Division of Administrative Hearings

2820this 6th day of August, 1997.

2826COPIES FURNISHED:

2828Alfred A. LaSorte, Jr., Esquire

2833United National Bank Tower

2837Suite 1000

28391645 Palm Beach Lakes Boulevard

2844West Palm Beach, Florida 33401

2849Patrick O'Hara, Esquire

2852324 Datura Street

2855Suite 100

2857West Palm Beach, Florida 33401

2862Jeffrey Brown, Esquire

2865Department of Environmental Protection

28693900 Commonwealth Boulevard

2872Tallahassee, Florida 32399-3000

2875Kathy Carter, Agency Clerk

2879Office of the General Counsel

2884Department of Environmental Protection

2888Mail Station 35

28913900 Commonwealth Boulevard

2894Tallahassee, Florida 32399-3000

2897F. Perry Odom, General Counsel

2902Office of the General Counsel

2907Department of Environmental Protection

2911Mail Station 35

29143900 Commonwealth Boulevard

2917Tallahassee, Florida 32399-3000

2920NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

2926All parties have the right to submit written exceptions within 15

2937days from the date of this Recommended Order. Any exceptions to

2948this Recommended Order should be filed with the agency that will

2959issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 09/22/1997
Proceedings: Final Order received.
PDF:
Date: 09/19/1997
Proceedings: Agency Final Order
PDF:
Date: 09/19/1997
Proceedings: Recommended Order
PDF:
Date: 08/06/1997
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 04/21/97.
Date: 06/12/1997
Proceedings: Department of Environmental Protection`s Proposed Recommended Order received.
Date: 06/12/1997
Proceedings: Nansep3 Corporation`s Proposed Recommended Order Administrative Order received.
Date: 06/11/1997
Proceedings: (From A. LaSorte) Findings of Fact, Conclusions of Law and Recommendations received.
Date: 05/29/1997
Proceedings: Transcript of Proceedings ; Continuation of Video Conference Proceedings Volume II received.
Date: 04/30/1997
Proceedings: (5) Subpoena Duces Tecum (from P. O`Hara); (5) Return of Service Affidavit received.
Date: 04/28/1997
Proceedings: (2) Subpoena Duces Tecum (from P. O`Hara); (2) Return of Service Affidavit received.
Date: 04/23/1997
Proceedings: (From P. O`Hara) Notice of Taking Telephone Deposition received.
Date: 04/21/1997
Proceedings: CASE STATUS: Hearing Held.
Date: 04/18/1997
Proceedings: Notice of Service of Answers to First Interrogatories Propounded Upon Petitioner, Scout Development Corporation, By Respondent, State of Florida Department of Environmental Protection (filed via facsimile) received.
Date: 04/18/1997
Proceedings: (Joint) Pretrial Stipulation (filed via facsimile) received.
Date: 04/17/1997
Proceedings: Order sent out. (Petitioners` Motion to add party Respondent is denied)
Date: 04/16/1997
Proceedings: Department`s Memorandum of Law in Opposition to Motion to Add Party Respondent received.
Date: 04/16/1997
Proceedings: Department of Environmental Protection`s Request for Official Recognition received.
Date: 04/16/1997
Proceedings: (A. LaSorte) 3/Subpoena Ad Testificandum (filed via facsimile) received.
Date: 04/14/1997
Proceedings: (From P. O`Hara) Notice of Taking Deposition received.
Date: 04/10/1997
Proceedings: (Alfred Lasorte) Notice of Hearing (filed via facsimile) received.
Date: 02/12/1997
Proceedings: Notice of Hearing sent out. (Video Final Hearing set for 4/21/97; 9:30am; West Palm Beach & Tallahassee)
Date: 01/31/1997
Proceedings: Department of Environmental Protection`s Status Report (filed via facsimile) received.
Date: 12/11/1996
Proceedings: Order sent out. (parties to file status report by 1/31/97)
Date: 12/06/1996
Proceedings: Department of Environmental Protection`s Status Report received.
Date: 09/05/1996
Proceedings: Order Granting Continuance sent out. (hearing cancelled; parties to file status report by 12/5/96)
Date: 09/03/1996
Proceedings: (Respondent) Agreed Motion to Continue Final Hearing (Pending Settlement) (filed via facsimile) received.
Date: 08/21/1996
Proceedings: (Nasep3 Corp.) Notice of Trial Conflict received.
Date: 07/31/1996
Proceedings: (Alfred Lasorte) 6/Notice of Taking Deposition Duces Tecum; (3) Subpoena Ad Testificandum; (2) Subpoena Duces Tecum (filed via facsimile) received.
Date: 07/19/1996
Proceedings: Notice of Service of Answers to Interrogatories Propounded Upon Petitioner, 700 Ocean Drive Homeowners` Association, Inc., By Respondent, Nansep3 Corporation; Notice of Service of Answers to Interrogatories Propounded Upon Petitioner, Scout Development
Date: 07/15/1996
Proceedings: (Nansep 3 Corp.) Response to First Request to Produce received.
Date: 07/15/1996
Proceedings: Notice of Service of Answers to Interrogatories Propounded Upon Nansep 3 Corporation by 700 Ocean Drive Homeowners` Association, Inc. and Scout Development Corporation; Interrogatories received.
Date: 07/15/1996
Proceedings: Notice of Service of Answers to Expert Interrogatories Propounded Upon Nansep 3 Corporation by 700 Ocean Drive Homeowners` Associaiton, Inc. and Scout Development Corporation; Interrogatories received.
Date: 07/09/1996
Proceedings: (From J. Brown) Notice of Appearance of Counsel for Department of Environmental Protection received.
Date: 07/09/1996
Proceedings: (DEP) (2) Notice and Certificate of Service of Interrogatories; Department of Environmental Protection`s First Request for Production of Documents to Petitioners, Scout Development Corporation and 700 Ocean Drive Homeowners` Association, Inc. received.
Date: 06/28/1996
Proceedings: (Petitioners) Certificate of Serving Interrogatories received.
Date: 06/17/1996
Proceedings: (Petitioners) Certificate of Serving Expert Interrogatories received.
Date: 06/17/1996
Proceedings: (Respondent) Notice of Interrogatories to Petitioner 700 Ocean Drive Homeowners` Association, Inc; (Respondent) Notice of Interrogatories to Petitioner Scout Development Corporation received.
Date: 06/06/1996
Proceedings: (Petitioners) Certificate of Serving Interrogatories received.
Date: 05/30/1996
Proceedings: (From P. O`Hara) Response to Initial Order received.
Date: 05/15/1996
Proceedings: Order sent out. (re: governing rules)
Date: 05/15/1996
Proceedings: Order of Prehearing Instructions sent out.
Date: 05/15/1996
Proceedings: Notice of Hearing sent out. (hearing set for 9/12/96; 9:30am; West Palm Beach)
Date: 05/15/1996
Proceedings: Order of Consolidation sent out. (Consolidated cases are: 96-1955 & 96-1956)
Date: 05/13/1996
Proceedings: (Petitioner) Response to Initial Order received.
Date: 05/10/1996
Proceedings: (From A. LaSorte) Motion to Consolidate received. (Cases to be consolidated: 96-1955, 96-1956); (Petitioner) Stipulation for Substitution of Counsel
Date: 05/01/1996
Proceedings: Initial Order issued.
Date: 04/25/1996
Proceedings: Notice Of Related Cases (DOAH related case Nos. 96-1955 & 96-1956); Request for Assignment of Hearing Officer and Notice of Preservation ofRecord (2); Agency Intent to Issue; Agency Action Letter; Request forFormal Administrative Hearing, Letter Form re

Case Information

Judge:
LINDA M. RIGOT
Date Filed:
04/25/1996
Date Assignment:
05/01/1996
Last Docket Entry:
09/22/1997
Location:
West Palm Beach, Florida
District:
Southern
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (2):

Related Florida Statute(s) (3):

Related Florida Rule(s) (2):