96-001955
Scout Development Corporation vs.
Nansep3 Corporation And Department Of Environmental Protection
Status: Closed
Recommended Order on Wednesday, August 6, 1997.
Recommended Order on Wednesday, August 6, 1997.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8SCOUT DEVELOPMENT CORPORATION, )
12)
13Petitioner, )
15)
16vs. ) Case No. 96-1955
21)
22NANSEP3 CORPORATION and DEPARTMENT )
27OF ENVIRONMENTAL PROTECTION, )
31)
32Respondents. )
34___________________________________)
35)
36700 OCEAN DRIVE HOMEOWNERS' )
41ASSOCIATION, INC., )
44)
45Petitioner, )
47)
48vs. ) Case No. 96-1956
53)
54NANSEP3 CORPORATION and DEPARTMENT )
59OF ENVIRONMENTAL PROTECTION, )
63)
64Respondents. )
66___________________________________)
67RECOMMENDED ORDER
69Pursuant to Notice, this cause was heard by Linda M. Rigot,
80the assigned Administrative Law Judge of the Division of
89Administrative Hearings, on April 21, 1997, in West Palm Beach,
99Florida.
100APPEARANCES
101For Petitioners: Alfred A. LaSorte, Jr., Esquire
108United National Bank Tower
112Suite 1000
1141645 Palm Beach Lakes Boulevard
119West Palm Beach, Florida 33401
124For Respondent
126Nansep3 Corporation: Patrick O'Hara, Esquire
131324 Datura Street
134Suite 100
136West Palm Beach, Florida 33401
141For Respondent Department
144of Environmental Protection:
147Jeffrey Brown, Esquire
150Department of Environmental Protection
1543900 Commonwealth Boulevard
157Tallahassee, Florida 32399-3000
160STATEMENT OF THE ISSUE
164The issue presented is whether Respondent Nansep3
171Corporation should be issued a permit to construct a dune
181walkover.
182PRELIMINARY STATEMENT
184Respondent Department of Environmental Protection issued to
191Respondent Nansep3 Corporation a permit to construct a dune
200walkover, and Petitioners timely requested an evidentiary hearing
208to contest the issuance of that permit. This cause was
218thereafter transferred to the Division of Administrative Hearings
226to conduct that evidentiary proceeding.
231Respondent Nansep3 Corporation presented the testimony of
238Susan Kenney, Clinton "Red" E. Taylor, Robert Barron, Dallas
247Durrance, Cory S. Cross, and Rodney Sarkela. Petitioners
255presented the testimony of Srinivas Tammisetti, James Molter, and
264Erik J. Olsen. Respondent Department of Environmental Protection
272presented the testimony of Rodney Sarkela and Barry Manson-Hing.
281Additionally, Joint Exhibits numbered 1-44 were admitted in
289evidence.
290The two-volume transcript of the proceeding was filed post
299hearing, and all parties filed proposed recommended orders.
307Those documents have been considered in the entry of this
317Recommended Order.
319FINDINGS OF FACT
3221. The subject property is an approximately three-acre,
330oceanfront site located within the Town of Juno Beach.
339Respondent Nansep3 Corporation purchased the site with an
347existing site plan approved by the Town. The approved site plan
358included a public access easement running parallel to the south
368property boundary from the public road to the beach. Nansep
378constructed a 59-unit condominium high-rise on the property.
3862. Petitioners Scout Development Corporation and 700 Ocean
394Drive Homeowners' Association, Inc., are the developer and
402homeowners' association, respectively, of a ten-unit beachfront
409residential community located immediately south of the subject
417site. The units therein consist of large, oceanfront, zero-lot-
426line, single-family residences. As of the final hearing in this
436cause, Scout had sold the eight southernmost units and was
446holding the two northernmost units for sale.
4533. The wall surrounding Petitioners' northernmost unit is
461located within approximately two feet of Petitioner's north
469property line, which is the same property line as Nansep's south
480property line. Nansep's public access easement is 10-feet wide
489and runs along that common property line. The subject dune
499walkover is located four feet from that property line.
5084. The Town of Juno Beach provides an incentive to
518developers for the construction of public access dune walkovers.
527Developers can obtain an additional two dwelling units per acre
537if they agree to convey a ten-feet wide access easement to the
549public and construct a six-feet wide dune walkover with
558landscaping, irrigation, and lighting. That additional "bonus"
565was included in the approved site plan in place when Nansep
576purchased the subject site.
5805. Nansep's agreement with the Tow n required that the dune
591walkover extend straight off the sidewalk leading to it for
601security reasons, i.e. , in order to make it easier for the Town
613to patrol the public access easement. In addition, Nansep had
623filed a declaration of condominium with the State of Florida
633depicting the dune walkover and sidewalk located within the
642public access easement and running in a straight line from the
653public road fronting the property to the beach. Nansep was
663concerned that a relocation of the walkover could be a material
674change that could enable purchasers to void their purchase
683agreements or could enable the Town to vacate its site plan
694approval.
6956. On November 10, 1995, Nansep submitted to the Department
705an application for a permit to construct a dune walkover seaward
716of the coastal construction control line. Also submitted was a
726topographic survey of the subject property depicting the location
735of the public access easement at the south property line where
746the walkover structure would be located and its relationship to
756existing seagrapes. The architectural drawings also depicted the
764location of the dune walkover in relation to Nansep's south
774property line and showed the dune walkover to be six-feet wide
785with eight-inch diameter pilings.
7897. On February 1, 1996, the Department issued to Nansep
799Permit PB-536 and a Notice to Proceed. Those documents were
809accompanied by a transmittal letter advising that substantially
817affected persons could challenge the issuance of that Permit
826within 21 days and that if Nansep proceeded with construction
836within that 21-day period, it would be at Nansep's own risk.
8478. Standard Permit Condition numbered (1)(a) required
854Nansep to carry out the construction activities in accordance
863with the plans and specifications approved by the Department and
873prohibited any modification thereof. Special Permit Condition
880numbered 2 provided that:
884The optimum siting of the walkover structure shall
892be determined by the staff representative of the
900Bureau of Beaches and Coastal Systems during the
908preconstruction [sic] conference to provide maximum
914protection to the existing dune topography and
921vegetation located on the site.
9269. There is a conflict in the documents issued by the
937Department that day in that the Special Permit Conditions
946describe a four-feet wide structure on four-inch-by-four-inch
953pilings whereas the Notice to Proceed describes a six-feet wide
963structure. However, the plans approved by the Department clearly
972describe a six-feet wide structure on eight-inch diameter
980pilings. Further, the Town requires a six-feet wide structure
989for public access walkovers.
99310. When there is a conflict between the plans that are
1004approved and a permit condition, the plans are deemed to prevail
1015over the permit condition.
101911. The fact that the structure is wider and on larger
1030pilings than described in the permit does not remove the
1040structure from the definition of a "minor structure" under the
1050Department's rules and the applicable statutes. By definition, a
1059minor structure is one that is expendable during high frequency
1069storm events. Nansep's dune walkover meets that definition.
107712. On February 19, 1996, Petitioners filed petitions
1085challenging Nansep's permit. Petitioners alleged impacts to
1092seagrapes as well as erosion impacts resulting from the
1101structure. Petitioners also complain that they were not invited
1110to participate in the pre-construction meeting and that there is
1120a conflict in the permit as to whether a four-feet wide or six-
1133feet wide walkover was permitted.
113813. Nansep constructed its walkover notwithstanding the
1145petitions for administrative hearing. Its architect certified
1152compliance with the approved plans by letter dated March 6, 1996.
116314. Seagrapes are one of approximately 100 to 150 species
1173that can constitute a coastal dune community. Their root mass
1183helps resist erosion, although research shows that seagrapes are
1192less resistant than other plants installed on the foredune at the
1203project site. The seagrape and other woody, shrubby plant
1212species moderate the impact of wind and salt spray to other
1223species upland of the coastal community.
122915. Dune walkovers confer a benefit to dune vegetation by
1239protecting plants from pedestrian traffic. They also protect the
1248dune itself by controlling foot traffic which erodes the dune.
125816. The permit application showed a semi-circular area of
1267seagrapes on the southeast corner of the project site and in the
1279footprint of the proposed walkover, extending throughout the
1287width of the access easement. The depiction regarding the extent
1297of seagrapes accurately reflected existing site conditions.
1304Thus, in order to relocate the walkover in such a way as to avoid
1318the seagrapes, it would be necessary to place the walkover
1328outside of the public access easement.
133417. As a matter of routine, the Department would not, for
1345the purpose of avoiding impacts to seagrapes, require the
1354developer to re-negotiate a development agreement with a local
1363government or to locate a dune walkover outside of an access
1374easement required by an approved site plan.
138118. Before construction, virtually all of the seagrape
1389component of the project area was contaminated by invasive exotic
1399species.
140019. Nansep installed seagrapes, sea oats, and other grasses
1409along the dune and the dune face under a mitigation plan approved
1421by the Town of Juno Beach. The seagrape hedge Nansep planted
1432along the top of the dune runs from the north end of the property
1446to the south end. The overall dune vegetation community was
1456enhanced and is now more substantial than before construction
1465began.
146620. It is common practice to place dune walkover structures
1476in areas where seagrapes must be removed to accommodate the
1486structure. Nansep removed only the seagrapes directly in the
1495path of the walkover structure. The impact of the removal on the
1507seagrapes was a minor impact. Further, the dune vegetation
1516community, as a whole, was not damaged or harmed as a result of
1529the construction.
153121. Petitioners fear that their property will be impacted
1540by excessive erosion upon the occurrence of certain storm events
1550because the walkover is located within four feet of their north
1561property line. Public access walkovers in the Town of Juno Beach
1572which access the beach across private property run along property
1582lines and have a four-feet wide landscape strip from the property
1593line to where the dune walkover starts.
160022. Scour erosion refers to the interaction of the waves
1610and currents with pilings and the beach surface. Under a rule-
1621of-thumb method commonly relied upon in the field of coastal
1631engineering, the maximum vertical extent of scour erosion is
1640approximately twice the diameter of the piling, and the maximum
1650horizontal extent of the erosion is approximately three times the
1660diameter of the piling.
166423. Applying this method, the maximum horizontal extent of
1673scour erosion for the dune walkover can be expected to be 24 to
168630 inches out from the pilings, and the maximum vertical extent
1697of scour erosion can be expected to be around 18 inches below
1709grade. Accordingly, the maximum extent of the scour erosion
1718would not be likely to encroach upon the property of Petitioners
1729since there is four feet between the walkover and Petitioners'
1739property line except where the walkover juts out for benches at
1750the toe of the dune, east of the coastal construction control
1761line.
176224. Notwithstanding severe storms last fall, no erosion has
1771resulted from the structure. Instead, accretion, or build-up of
1780sand, has occurred. Further, the localized scour erosion cannot
1789be expected to adversely impact the dune vegetation community or
1799the dune system as a whole.
180525. The purpose of a pre-construction conference is for the
1815Department to review the permit conditions with the permit holder
1825and to verify the location of the coastal construction control
1835line and the location of the structure. Although other persons
1845are permitted to attend a pre-construction conference, the
1853Department does not require that adjoining property owners be
1862invited to attend. A Department memorandum opines that pre-
1871construction meetings are necessary for the approval of "major
1880structures" and shore protection projects. There does not appear
1889to be such a requirement for "minor structures" such as the
1900subject dune walkover.
190326. The Department's field engineer misread Nansep's permit
1911and did not notice that the permit called for a pre-construction
1922conference. Nevertheless, he met with Nansep's representatives
1929on-site on February 14, 1996, during the construction of the
1939walkover. He determined that the actual siting of the dune
1949walkover is the optimum siting to provide maximum protection to
1959the existing dune topography and vegetation on the site.
196827. Other than the directive in the permit to determine the
1979best siting with respect to existing dune topography and to dune
1990vegetation, the terms of the permit stated no other matters to be
2002considered in the pre-construction meeting. Nothing more would
2010have been accomplished in an actual pre-construction meeting than
2019occurred in the on-site visit by the Department's field engineer
2029during construction.
203128. The location of the walkover was clearly depicted in
2041the plans which the Department approved in issuing the permit.
2051Even though the permit called for a pre-construction conference
2060at which the optimum siting for the walkover would be selected,
2071no permit condition authorized the Department's representative to
2079direct a material change to the project, such as requiring the
2090relocation of the walkover to outside of the existing public
2100access easement.
210229. Comparing the benefits conferred on the dune system by
2112protection from pedestrian traffic with any negative impacts, the
2121benefits conferred offset any negative impacts to the dune
2130system.
2131CONCLUSIONS OF LAW
213430. The Division of Administrative Hearings has
2141jurisdiction over the parties hereto and the subject matter
2150hereof. Sections 120.569 and 120.57(1), Florida Statutes.
215731. Petitioners assert issues as to whether the walkover
2166structure was constructed in full compliance with the permit.
2175However, this proceeding is limited to the issues involved in the
2186issuance of the permit itself. Whether Nansep violated permit
2195conditions as to the height of the structure is a matter for the
2208Department to consider for any enforcement proceeding, not in
2217this proceeding to determine whether a permit should be issued.
222732. The law is well settled that a permit applicant bears
2238the burden of proving entitlement to the permit sought. Nansep
2248has met its burden.
225233. Section 161.053, Florida Statutes, sets forth standards
2260for the establishment of coastal construction control lines as
2269well as activities that may be permitted seaward of that line.
2280Part of the legislative intent is instructive. Section
2288161.053(1)(a), Florida Statutes, provides for the protection of
2296the beaches and coastal barrier dunes in this State from:
2306. . . construction which can jeopardize the
2314stability of the beach-dune system, accelerate
2320erosion, provide inadequate protection to upland
2326structures, endanger adjacent properties, or
2331interfere with public beach access.
233634. The statute's focus is on protection of the beach-dune
2346system, not the scour erosion which can occur around a piling.
2357Further, the statute focuses on endangerment of adjacent
2365properties, not inconvenience to their owners.
237135. The Department has promulgated rules to implement that
2380statute. Rule 62B-33.002(23), Florida Administrative Code,
2386quantifies construction impacts and provides that adverse impacts
2394are those which interfere with the natural functioning of the
2404system, a consideration not present in this cause. That Rule
2414also defines "other impacts" as those which may result in damage
2425to existing structures or property or interference with lateral
2434beach access. No damage to existing structures has been alleged,
2444and the possible damage of scour erosion around the pilings on
2455Nansep's property which may, or may not, extend onto Petitioners'
2465property by several inches cannot be considered significant
2473enough to constitute an adverse impact.
247936. Under Rule 62B-33.005(10), Florida Administrative
2485Code, construction is required to be located in previously-
2494disturbed areas when practicable. The only way Nansep could have
2504avoided the existing seagrapes would have been to site the
2514walkover at some place other than the public access easement that
2525had been approved by the local government. Petitioners propose
2534an alignment which would require the walkover to turn at a right-
2546angle, move outside the public access easement, run along the
2556swimming pool wall, turn at another right-angle, and then proceed
2566across the dune to the beach. It is not "practicable" to require
2578Nansep to vacate the approved site plan and re-design its project
2589to move the walkover out of the public access easement or to
2601require Nansep to convey more of its private property to the
2612public.
261337. The Department did commit a procedural irregularity in
2622the processing of this permit application either by requiring a
2632pre-construction conference or by not conducting one when it was
2642required by the permit conditions. However, the record in this
2652cause reveals that the Department's field engineer would have
2661approved the siting of the walkover had he conducted his on-site
2672visit before construction rather than during.
267838. Petitioners assert that Nansep graded the dune top for
2688the walkover but the plans Nansep submitted to the Department and
2699the Department's permit did not contemplate such excavation.
2707Yet, the evidence reveals that the one to two feet of excavation
2719was required for access by handicapped persons and, if asked, the
2730Department would have allowed it.
2735RECOMMENDATION
2736Based upon the foregoing Findings of Fact and Conclusions of
2746Law, it is
2749RECOMMENDED THAT a final order be entered granting Nansep's
2758application and issuing Permit PB-536 to Respondent Nansep3
2766Corporation.
2767DONE AND ENTERED this 6th day of August, 1997, at
2777Tallahassee, Leon County, Florida.
2781___________________________________
2782LINDA M. RIGOT
2785Administrative Law Judge
2788Division of Administrative Hearings
2792The DeSoto Building
27951230 Apalachee Parkway
2798Tallahassee, Florida 32399-30 60
2802(904) 488-9675 SUNCOM 278-9675
2806Fax Filing (904) 921-6847
2810Filed with the Clerk of the
2816Division of Administrative Hearings
2820this 6th day of August, 1997.
2826COPIES FURNISHED:
2828Alfred A. LaSorte, Jr., Esquire
2833United National Bank Tower
2837Suite 1000
28391645 Palm Beach Lakes Boulevard
2844West Palm Beach, Florida 33401
2849Patrick O'Hara, Esquire
2852324 Datura Street
2855Suite 100
2857West Palm Beach, Florida 33401
2862Jeffrey Brown, Esquire
2865Department of Environmental Protection
28693900 Commonwealth Boulevard
2872Tallahassee, Florida 32399-3000
2875Kathy Carter, Agency Clerk
2879Office of the General Counsel
2884Department of Environmental Protection
2888Mail Station 35
28913900 Commonwealth Boulevard
2894Tallahassee, Florida 32399-3000
2897F. Perry Odom, General Counsel
2902Office of the General Counsel
2907Department of Environmental Protection
2911Mail Station 35
29143900 Commonwealth Boulevard
2917Tallahassee, Florida 32399-3000
2920NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2926All parties have the right to submit written exceptions within 15
2937days from the date of this Recommended Order. Any exceptions to
2948this Recommended Order should be filed with the agency that will
2959issue the Final Order in this case.
- Date
- Proceedings
- Date: 09/22/1997
- Proceedings: Final Order received.
- Date: 06/12/1997
- Proceedings: Department of Environmental Protection`s Proposed Recommended Order received.
- Date: 06/12/1997
- Proceedings: Nansep3 Corporation`s Proposed Recommended Order Administrative Order received.
- Date: 06/11/1997
- Proceedings: (From A. LaSorte) Findings of Fact, Conclusions of Law and Recommendations received.
- Date: 05/29/1997
- Proceedings: Transcript of Proceedings ; Continuation of Video Conference Proceedings Volume II received.
- Date: 04/30/1997
- Proceedings: (5) Subpoena Duces Tecum (from P. O`Hara); (5) Return of Service Affidavit received.
- Date: 04/28/1997
- Proceedings: (2) Subpoena Duces Tecum (from P. O`Hara); (2) Return of Service Affidavit received.
- Date: 04/23/1997
- Proceedings: (From P. O`Hara) Notice of Taking Telephone Deposition received.
- Date: 04/21/1997
- Proceedings: CASE STATUS: Hearing Held.
- Date: 04/18/1997
- Proceedings: Notice of Service of Answers to First Interrogatories Propounded Upon Petitioner, Scout Development Corporation, By Respondent, State of Florida Department of Environmental Protection (filed via facsimile) received.
- Date: 04/18/1997
- Proceedings: (Joint) Pretrial Stipulation (filed via facsimile) received.
- Date: 04/17/1997
- Proceedings: Order sent out. (Petitioners` Motion to add party Respondent is denied)
- Date: 04/16/1997
- Proceedings: Department`s Memorandum of Law in Opposition to Motion to Add Party Respondent received.
- Date: 04/16/1997
- Proceedings: Department of Environmental Protection`s Request for Official Recognition received.
- Date: 04/16/1997
- Proceedings: (A. LaSorte) 3/Subpoena Ad Testificandum (filed via facsimile) received.
- Date: 04/14/1997
- Proceedings: (From P. O`Hara) Notice of Taking Deposition received.
- Date: 04/10/1997
- Proceedings: (Alfred Lasorte) Notice of Hearing (filed via facsimile) received.
- Date: 02/12/1997
- Proceedings: Notice of Hearing sent out. (Video Final Hearing set for 4/21/97; 9:30am; West Palm Beach & Tallahassee)
- Date: 01/31/1997
- Proceedings: Department of Environmental Protection`s Status Report (filed via facsimile) received.
- Date: 12/11/1996
- Proceedings: Order sent out. (parties to file status report by 1/31/97)
- Date: 12/06/1996
- Proceedings: Department of Environmental Protection`s Status Report received.
- Date: 09/05/1996
- Proceedings: Order Granting Continuance sent out. (hearing cancelled; parties to file status report by 12/5/96)
- Date: 09/03/1996
- Proceedings: (Respondent) Agreed Motion to Continue Final Hearing (Pending Settlement) (filed via facsimile) received.
- Date: 08/21/1996
- Proceedings: (Nasep3 Corp.) Notice of Trial Conflict received.
- Date: 07/31/1996
- Proceedings: (Alfred Lasorte) 6/Notice of Taking Deposition Duces Tecum; (3) Subpoena Ad Testificandum; (2) Subpoena Duces Tecum (filed via facsimile) received.
- Date: 07/19/1996
- Proceedings: Notice of Service of Answers to Interrogatories Propounded Upon Petitioner, 700 Ocean Drive Homeowners` Association, Inc., By Respondent, Nansep3 Corporation; Notice of Service of Answers to Interrogatories Propounded Upon Petitioner, Scout Development
- Date: 07/15/1996
- Proceedings: (Nansep 3 Corp.) Response to First Request to Produce received.
- Date: 07/15/1996
- Proceedings: Notice of Service of Answers to Interrogatories Propounded Upon Nansep 3 Corporation by 700 Ocean Drive Homeowners` Association, Inc. and Scout Development Corporation; Interrogatories received.
- Date: 07/15/1996
- Proceedings: Notice of Service of Answers to Expert Interrogatories Propounded Upon Nansep 3 Corporation by 700 Ocean Drive Homeowners` Associaiton, Inc. and Scout Development Corporation; Interrogatories received.
- Date: 07/09/1996
- Proceedings: (From J. Brown) Notice of Appearance of Counsel for Department of Environmental Protection received.
- Date: 07/09/1996
- Proceedings: (DEP) (2) Notice and Certificate of Service of Interrogatories; Department of Environmental Protection`s First Request for Production of Documents to Petitioners, Scout Development Corporation and 700 Ocean Drive Homeowners` Association, Inc. received.
- Date: 06/28/1996
- Proceedings: (Petitioners) Certificate of Serving Interrogatories received.
- Date: 06/17/1996
- Proceedings: (Petitioners) Certificate of Serving Expert Interrogatories received.
- Date: 06/17/1996
- Proceedings: (Respondent) Notice of Interrogatories to Petitioner 700 Ocean Drive Homeowners` Association, Inc; (Respondent) Notice of Interrogatories to Petitioner Scout Development Corporation received.
- Date: 06/06/1996
- Proceedings: (Petitioners) Certificate of Serving Interrogatories received.
- Date: 05/30/1996
- Proceedings: (From P. O`Hara) Response to Initial Order received.
- Date: 05/15/1996
- Proceedings: Order sent out. (re: governing rules)
- Date: 05/15/1996
- Proceedings: Order of Prehearing Instructions sent out.
- Date: 05/15/1996
- Proceedings: Notice of Hearing sent out. (hearing set for 9/12/96; 9:30am; West Palm Beach)
- Date: 05/15/1996
- Proceedings: Order of Consolidation sent out. (Consolidated cases are: 96-1955 & 96-1956)
- Date: 05/13/1996
- Proceedings: (Petitioner) Response to Initial Order received.
- Date: 05/10/1996
- Proceedings: (From A. LaSorte) Motion to Consolidate received. (Cases to be consolidated: 96-1955, 96-1956); (Petitioner) Stipulation for Substitution of Counsel
- Date: 05/01/1996
- Proceedings: Initial Order issued.
- Date: 04/25/1996
- Proceedings: Notice Of Related Cases (DOAH related case Nos. 96-1955 & 96-1956); Request for Assignment of Hearing Officer and Notice of Preservation ofRecord (2); Agency Intent to Issue; Agency Action Letter; Request forFormal Administrative Hearing, Letter Form re