97-000692 Joyce (Joy) E. Towles Cummings vs. Buckeye Florida, L.P., And Department Of Environmental Protection
 Status: Closed
Recommended Order on Thursday, September 11, 1997.


View Dockets  
Summary: Petitions should be dismissed for lack of standing and lack of verified petitions.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8JOYCE (JOY) E. TOWLES CUMMINGS , )

14ET AL. , )

17)

18Petitioners , )

20)

21vs. ) Case Nos. 97-0692

26) 97-0930

28STATE OF FLORIDA, DEPARTMENT OF ) 97-1449

35ENVIRONMENTAL PROTECTION, and )

39BUCKEYE FLORIDA, L.P. , )

43)

44Respondents. )

46__________________________________)

47RECOMMENDED ORDER

49Pursuant to notice, Administrative Law Judge Don W. Davis,

58duly designated by the Division of Administrative Hearings, held

67a formal hearing in the above-styled case on July 7-10, 1997, in

79Perry, Florida. The following appearances were entered:

86APPEARANCES

87For Petitioner Sharon Cutter:

91Sharon Cutter, pro se

95Route 1, Box 1130

99Perry, Florida 32347

102For Petitioners Ronnie Edwards,

106Rebecca Edwards, and Mitchell Edwards:

111Ronnie Edwards

113Rebecca Edwards

115Mitchell Edwards, pro se

119Route 1, Box 160

123Perry, Florida 32347

126For Petitioner Joyce T. Cummings:

131No Appearance

133For Respondent Department of Environmental Protection:

139Lynette L. Ciardulli, Esquire

143Jennifer L. Fitzwater, Esquire

147Department of Environmental

150Protection,

1512600 Blair Stone Road

155Tallahassee, Florida 32399

158For Respondent Buckeye Florida, L.P.:

163Terry Cole, Esquire

166Pat Renovitch, Esquire

169Post Office Box 6507

173Tallahassee, Florida 32314-6507

176STATEMENT OF THE ISSUE

180Whether Respondent Buckeye Florida L.P., (Buckeye), has

187provided reasonable assurances to Respondent Department of

194Environmental Protection (Department) that construction activity

200for the proposed project will comply with applicable provisions

209of Chapter 373, Florida Statutes, and related administrative

217rules.

218PRELIMINARY STATEMENT

220Buckeye filed an application with the Department for a

229permit to construct a pipeline, conveying treated effluent from

238the current discharge point near Buckeye’s pulp mill in Perry,

248Florida, to a discharge point in the estuary of the Fenholloway

259River. Subsequently, the Department issued its Notice of Intent

268to permit the proposed project on December 31, 1996.

277Between February 10-27, 1997, the Department forwarded the

285Petitioners’ challenges to the Division of Administrative

292Hearings for conduct of formal administrative proceedings.

299The cases of the various Petitioners were consolidated by

308order issued March 31, 1997, and, following one continuance , the

318matter was set for final hearing to be convened on July 7, 1997.

331At the final heari ng, Petitioners presented testimony of

340eight witnesses and six exhibits. Respondents presented nine

348witnesses and 25 exhibits. Petitioner Cummings did not appear at

358the final hearing and no evidence was presented on her behalf.

369Upon commencement of the final hearing, the Petition of

378Cummings was dismissed upon motion of Buckeye. Petitioner

386Cummings was the only party who challenged the construction

395variance related to the proposed permit and was also the only

406party who asserted that closed loop technology should be

415considered. The parties stipulated that these matters were no

424longer at issue.

427The transcript of the final hearing was filed with the

437Division of Administrative Hearings on August 11, 1997.

445Petitioners requested, and were granted, leave in excess of ten

455days of the transcript’s receipt in which to file proposed

465findings of fact. Proposed findings submitted by the parties

474have been utilized in the preparation of this Recommended Order.

484FINDINGS OF FACT

487The Parties

4891 . Petitioner Sharon Cutter lives in Taylor County,

498Florida. Her home is about two miles south of the closest point

510of the pipeline project.

5142 . Petitioners Ronnie, Rebecca, and Mitchell Edwards also

523reside in Taylor County. Their home is about two miles north of

535the closest point of the pipeline project.

5423 . The Department is the state agency that reviewed

552Buckeye's application for the proposed permit and issued notice

561of intention to permit the construction activity.

5684 . Buckeye is the applicant for the proposed permit. Since

5791993, the Florida limited partnership has owned and operated a

589softwood dissolving kraft pulp mill in Taylor County, southeast

598of Perry.

600BACKGROUND

601Mill Operation

6035 . Two stand-alone pulp manufacturing lines at the mill in

614Perry daily produce about 1200 tons of cellulose. The first line

625manufactures unique and highly specialized products used in meat

634casings, rayon tire cord, rayon textile filament,

641pharmaceuticals, rocket propellants, cellulose ethers for food,

648and a variety of other products. The second line manufactures

658fluff pulp for the disposable diaper industry, a specialty

667product.

6686 . The mill directly employs about 825 people. In economic

679terms, the mill pays about $40 million annually in salaries and

690has an overall annual regional impact of approximately $180

699million.

7007 . The mill’s wastewater system captures effluent from the

710manufacturing process and includes 150 acres of aerated and

719treatment lagoons. This system is common in terms of its use in

731the industry.

7338 . The mill discharges about 50 million gallons daily (MGD)

744of treated effluent from an aeration pond into the Fenholloway

754River near the river crossing of U.S. Highway 19, approximately

76424.6 miles upstream from the Gulf of Mexico.

7729 . Headwaters of the 27-mile Fenholloway River originate in

782the San Pedro Bay at 100 feet above sea level. The river

794generally runs from east to west through Taylor County to the

805Gulf of Mexico at sea level. The major freshwater input to the

817Fenholloway River below the current discharge point is Spring

826Creek at mile point (MP) 13.6. The river is tidally influenced

837and subject to salt water influence to about MP 3.5, and would

849not be affected by reductions in flow from the current discharge

860point.

861History of the Fenholloway River

86610 . Buckeye's discharge of treated industrial wastewater to

875the Fenholloway River is regulated by state and federal permits.

885The river has traditionally been a Class V (industrial use) water

896body.

89711 . A use attainability analysis is required by the Clean

908Water Act every three years for any waterbody that is not at

920least Class III (possible to use for recreation, propagation, and

930maintenance of a healthy, well-balanced population of fish and

939wildlife). The purpose of this analysis is to determine if

949Class III uses are attainable, considering economic,

956technological, and social factors. Historically, use

962attainability analyses have primarily focused on changes in the

971manufacturing process, as well as any modifications to the

980treatment of the wastewaters.

98412 . In 1991, the Department began a use attainability

994analysis on the feasibility of reclassifying the Fenholloway

1002River from Class V to Class III. The three-year analysis was

1013completed in 1994 and indicated that Class III (fishable and

1023swimmable) designated uses and water quality criteria in the

1032Fenholloway River were technologically and economically feasible

1039through installation of technologies, involving mill changes, to

1047reduce pollutant generation. The technologies also include

1054construction of a pipeline to an area downstream where more

1064dilution of Buckeye’s discharged waste water will be available.

1073Additionally, the technologies include augmentation of natural

1080flow of the river with mitigative measures at the river

1090headwaters. Under these plans, the pipeline would remove the

1099mill discharge from about 20 miles of the river.

110813 . Specifically, three major elements in the completed use

1118analysis are change in the manufacturing process to reduce the

1128color of the effluent by 50 percent; relocation of the discharge

1139point from its present location to a location 1.7 miles upstream

1150from the mouth of the river where there is more assimilative

1161capacity and dilution; and restoration of portions of the 7,000-

1172acre San Pedro Bay to wetlands by construction of a water control

1184structure.

118514 . As a result of the completed 1994 Use Attainability

1196Analysis, the Environmental Regulation Commission (ERC) voted on

1204December 15, 1994, to repeal the Class V designation of the

1215Fenholloway River. The reclassification decision designating the

1222river as a Class III water body is effective December 31, 1997.

123415. The action of the ERC wa s subject to review by the

1247United States Environmental Protection Agency (EPA). Upon

1254review, the EPA approved the change after concluding that Class

1264III water standards could be attained with implementation of the

1274proposed pipeline and restoration of portions of San Pedro Bay

1284wetlands through construction of a water control structure. The

1293EPA also concluded that "the only other alternative that would

1303result in the attainment of Class III standards would also have

1314widespread economic and social impacts, i.e., closure of the

1323mill."

132416. The Department and Buckeye executed the Fenholloway

1332River Agreement on March 29, 1995. In that agreement, the

1342parties set forth steps and schedules necessary to achieve

1351standards required for reclassification of the Fenholloway River

1359to a Class III water body. The agreement was publicly noticed

1370and was not challenged by anyone.

1376Permit Application

137817. Buckeye applied for the proposed permit on August 31,

13881995, in accordance with the terms of the Fenholloway River

1398Agreement. The Department then requested and received additional

1406information from Buckeye. Thereafter, on December 31, 1996, the

1415Department notified Buckeye of its intention to issue the

1424proposed permit.

142618. Buckeye has applied for other authorizations and

1434permits that are required from the Department for the pipeline

1444project, but which are not part of this proceeding. For example,

1455Buckeye applied for an easement from the state for private use of

1467sovereignty submerged lands and an operation and discharge permit

1476for its wastewater treatment system.

1481Pipeline Project

148319. Buckeye proposes to construct a 15.3-mile underground,

1491linear pipeline from the mill (MP 24.6) in Perry to an underwater

1503discharge point (MP 1.7) in the Fenholloway River. The project

1513also includes a water control structure in the San Pedro Bay, an

1525effluent pump station at the Perry mill, an oxygenation facility

1535near the end of the pipeline, and an outfall diffuser structure

1546at the discharge point.

155020. The pipeline route is 80,200 feet l ong. It was

1562selected over alternative routes to minimize environmental

1569impacts. The river crossings are underground primarily to

1577minimize water quality impacts during construction.

158321. The underground pipeline will be constructed from 20-

1592foot sections of semi-flexible ductile iron pipe manufactured by

1601the American Cast Iron Pipe Company in Birmingham, Alabama. The

1611sections will be connected with flexible joints. Most of the

1621pipeline will have 30 inches of earth over it; however, the pipe

1633is strong enough to support 20 feet of earth. At the underground

1645river crossings and outfall/diffuser area, the pipe will have

1654five feet of earth over it.

166022. The ductile iron pipe is 60 inches in diameter and 1/2

1672inch thick. The pipe is lined with 1/4 inch thick cement to

1684prevent internal erosion and wrapped with polyethylene (double

1692wrapped for the last 9000 feet of wetlands ) to prevent external

1704corrosion. The treated effluent that will flow through the pipe

1714is an easy material to handle from a corrosion viewpoint, as it

1726is a weak and stable effluent, similar to water. Ductile iron

1737pipe is routinely used to transmit raw sewage.

174523. The diffuser will be made of concrete pipe, with a

1756steel core and wrap wires around it, since the durability of

1767concrete is proven in a saltwater environment. At the

1776outfall/diffuser, the river is about 700-900 feet wide and 8 to

178711 or 12 feet deep (low to high tide).

179624. The maximum working pressure in the pipeline will be

180650-60 pounds per square inch (psi). The ductile iron pipe is

1817rated at 150 psi.

182125. The pump station will have capacity to transmit about

183176 million gallons of treated effluent per day. The pipeline is

1842capable of receiving up to 100 MGD of the type of treated

1854effluent now discharged by the mill.

186026. Presuming correct installation, the pipeline will not

1868leak or crack. It will be tested for water tightness before,

1879during, and after construction.

188327. Monitoring of the pressure in the pipeline will occur

1893at the effluent pump station near the mill. Any significant

1903change in pressure will activate an alarm system. The mill can

1914immediately shut off the pumps.

191928. The pipeline meets all industry standards and should

1928last well over 100 years. The concrete diffuser may have to be

1940replaced every 10-20 years, but there is easy access for

1950replacement.

195129. Test borings along the pipeline route have revealed no

1961sinkholes. If sinkholes are encountered during construction,

1968they will be filled before the pipe is installed. The

1978predominant type of sinkholes that could develop after

1986installation are doline or solution sinks. They typically settle

1995at a rate of 1 foot every 5,000-6,000 years. The pipe and

2009flexible joints (which flex 12 inches) will easily tolerate this

2019minimal movement.

202130. The diffuser has 20 ports, spaced five feet apart which

2032can be rotated based on desired direction of discharge. Some

2042will face upstream and some downstream to ensure good mixing of

2053the treated effluent and river water. At mean low water, there

2064will be about six feet of clearance above the ports. When the

2076plume from the ports reaches the surface, it will have a ripple

2088of about a quarter of an inch. The ripple will not impact a

2101canoe. The closest port to the west bank is 25 feet, but due to

2115the angle of that port, effect of any discharge from that port

2127will be 73 feet from the bank.

213431. The contractor selected to construct the pipeline is

2143believed to have an outstanding reputation for construction

2151projects similar to this one. Buckeye will accept responsibility

2160for the pipeline and implement its usage only after extensive

2170tests (culminating in final hydrostatic testing), assuring that

2178construction meets all requirements of the proposed permit and

2187industry standards.

218932. Buckeye will operate, maintain, and inspect the

2197pipeline and related facilities once they are completed, using

2206acceptable

2207management practices. Coverage will be seven days a week, the

2217same as for the mill facility at present.

222533. Cleaning the pipe will be a mechanical process, not

2235using cleaning agents. Barnacles will not be a problem due to

2246the constant flow in the pipe.

2252Water Quality Standards

225534. Buckeye will meet all water quality standards, except

2264for turbidity during construction at the two river crossings and

2274outfall/diffuser. A variance for turbidity at these three

2282locations during construction was requested by Buckeye and

2290approved by the Department. The only challenge to that variance

2300has been dismissed.

230335. Buckeye will minimize turbidity during construction by

2311using a series of best management practices. For example,

2320Buckeye will use silt curtains, silt fences and filtration bags.

2330As a consequence, turbidity will be minimal, temporary in nature

2340and negligible.

234236. The technologies which Buckeye will employ is expected

2351at this time to improve the water quality in the river, estuary

2363and Gulf.

2365Environmental Impacts

236737. Buckeye provided reasonable assurance to the Department

2375that construction of the proposed pipeline project will not

2384adversely affect the public health, safety, welfare, or property

2393of others. Overall, the proposed project will positively affect

2402the public health, safely, welfare, and property of others.

241138. There is no risk to humans and ecological receptors

2421that may be associated with metals or dioxin in river sediments.

2432Conservation

243339. There are no threatened or endangered wildlife species

2442that will be impacted by the proposed project. The four species

2453of special concern (gopher tortoise, American alligator, eastern

2461indigo snake, and Sherman fox squirrel) in the project area will

2472be minimally affected due to special protection programs and

2481temporary relocation.

248340. The draft permit contains conditions providing for the

2492protection of species of special concern that were recommended by

2502the Florida Game and Fresh Water Fish Commission. The relocation

2512of gopher tortoises and the eastern indigo snake are examples.

2522These conditions are typically used to ensure the protection of

2532species.

253341. Buckeye will provide for the protection of manat ees

2543that was recommended by the Department's Bureau of Protected

2552Species Management, even though none have been observed in the

2562project area.

256442. There will be minimal or negligible effect on the

2574habitat value of fish and wildlife.

2580Navigation, Erosion or Shoaling

258443. At each of the two subaqueous river crossings (upstream

2594at MP 17.8 and MP 24.4), boats will not be able to navigate

2607approximately 100 feet of the river for the six-seven days during

2618construction of the coffer dam structures. However, a canoeist

2627could portage around these sites. Due to tree-falls in this

2637upper reach of the river, portages are required anyway.

264644. The permit conditions require Buckeye to work 24-hours

2655per day while constructing the subaqueous river crossings in

2664order to minimize adverse affects to navigation.

267145. At the outfall/diffuser area downstream in the estuary,

2680boat traffic will never be prevented from moving up and down the

2692river. However, it will be slowed or temporarily stopped (no

2702more than 20 minutes during four blasts) during a 30-day

2712construction period. Detonation will be conducted in a manner to

2722reduce total acoustical shockwave. The minimum six-foot

2729clearance above the diffuser ports will not be an impedance to

2740navigation.

274146. Presently, there is erosion of the banks at the

2751outfall/diffuser site due to boat wake and tidal influence. The

2761construction of the last 80 feet of the diffuser has the

2772potential of temporarily accelerating this erosion on the west

2781bank of the river by causing boat traffic to be moved closer to

2794that bank during construction. To protect this bank during

2803construction, Buckeye has agreed to place filter fabric overlaid

2812with sandbags on the exposed sections of the bank. This will

2823prevent erosion caused by the construction of the diffuser.

283247. The permit requires Buckeye to use the best management

2842practices to control erosion during construction. With those in

2851place, there will be minimal erosion or shoaling during

2860construction.

286148. Construction will not adversely a ffect the fishing or

2871recreational values or marine productivity.

287649. The proposed project will not cause adverse water

2885quantity impacts to receiving waters or adjacent lands. It will

2895not cause permanent dewatering.

289950. The proposed project will not cause sedimentation

2907downstream of the outfall/diffuser, decrease the storage of

2915waters, reduce the floodway conveyance, or reduce surface water

2924storage volumes.

2926Project Nature

292851. The project will be permanent. The construction

2936trestle at the diffuser/outfall will be temporary.

294352. Most of the impacts of the project to vegetation and

2954wildlife are temporary during construction. Natural revegetation

2961will return most areas to their normal condition.

296953. The only permanent impact to wetlands is the loss of

29800.39 acres for construction of the oxygenation facility in a

2990river swamp area. In addition, 5.48 acres of forested wetlands

3000will be converted to shrub wetlands condition. These are the

3010only permanent impacts to wetlands associated with the proposed

3019project. Disturbance of wetlands will be minimized.

302654. The construction of the proposed pipeline project is

3035expected to take less than one year. All of the necessary

3046easements on private lands have been obtained. Buckeye's

3054requested easements on sovereign submerged land are pending.

3062Buckeye owns all of the other land for the proposed project.

3073Historical And Archaeological Resources

307755. An extensive study of the pipeline corridor by an

3087archeological firm with an excellent reputation reveals that

3095there are no significant archeological sites found along the

3104corridor. In addition to the study, subsequent examinations of

3113the corridor by state and private archeologists (including

3121underwater explorations by a consultant) confirmed this

3128conclusion.

312956. The Department of State has advised the Department that

3139the Buckeye project will not affect any sites eligible for

3149listing in the National Register of Historic Places or any sites

3160of historical or archaeological value. There are 16 possible

3169historical sites along the project route. None are deemed

3178significant or eligible for listing on the National Historic

3187Registry.

318857. A study of the San Pedro Bay mitigation area also

3199revealed no significant archeological sites.

320458. There is a significant archeological site (site 142) on

3214the west bank of the river near the outfall/diffuser. Neither

3224construction of the pipeline nor discharge of the treated

3233effluent transmitted by the pipeline will impact that site,

3242including the banks, due to the planned erosion control plan.

3252Wetland Areas Affected

325559. The proposed project affects wetlands. However, any

3263impacts to wetlands are sufficiently offset by the proposed

3272mitigation plan in the San Pedro Bay.

3279Cumulative Impacts

328160. There are no significant adverse cumulative impacts

3289which would result from the proposed project. There is a

3299beneficial cumulative impact in the improvement to the water

3308quality of the river, allowing reclassification of the river from

3318Class V to Class III.

332361. Along the p ipeline route, there will be no adverse

3334hydrological impact to the wetlands.

333962. The removal of Buckeye’s treated effluent from the

3348current discharge point near the mill will cause a drop in the

3360surface water elevations of the river’s upper reach (above

3369Hampton Springs) by one-half foot, a drop which is not considered

3380significant. Due to tidal effects in the river at the diffuser

3391location, there will be no hydraulic difference at the proposed

3401location of the discharge.

340563. Downstream of Spring Cree k, the Fenholloway River picks

3415up flow from springs, groundwater, discharge from Spring Creek

3424and tidal effect. There will be no impact on water levels

3435downstream of Spring Creek caused by the relocation of the

3445discharge point from the mill to the estuary, due to these

3456additional flow contributions.

3459Mitigation Area in San Pedro Bay

346564. The proposed permit requires Buckeye to restore 25

3474acres of drained wetlands in San Pedro Bay included within a

34857,000-acre parcel that Buckeye owns. In the past, the area was

3497hydrologically altered due to forestry activities.

350365. The San Pedro Bay area is the headwaters of the

3514Fenholloway River. Construction of the proposed water control

3522structure in the part of the Bay that Buckeye owns will rehydrate

3534the area and restore it to natural conditions.

354266. Through the development of a computer model of the San

3553Pedro Bay, Buckeye studied how the hydrology and hydraulics in

3563this area would be affected by the proposed water control

3573structure. The model shows that the structure will enable the

3583area to hold more water and return to more natural conditions (to

3595rehydrate the area).

359867. The water control structure will reduce the low-flow

3607days in the Main Bay Canal (connecting San Pedro Bay to the mill

3620area). It will not cause flooding or affect any off-site

3630property. It will reduce erosion.

363568. The proposed mitigation is sufficient to offset the

3644impacts of the proposed project.

3649Other Facts Relating to Petitioners

365469. Petitioners' properties are located about t wo miles

3663from any part of the pipeline project. Construction of the

3673pipeline project will have no substantial affect on Petitioners'

3682properties or any other interest of Petitioners which is unique

3692to them to the exclusion of the general public.

370170. Petitioners will continue to be able to travel to the

3712river, use their boats on the river, and view the plants and

3724wildlife along the river from their boats. Even during

3733construction, they will be able to access the river and launch

3744their boats from the Hicks Landing, located on Buckeye property.

3754After construction, they will be able to launch from this site

3765and at Peterson's Landing. Thus, construction of the project

3774will not substantially affect access to the river or uses of the

3786river related to boating activity.

3791CONCLUSIONS OF LAW

379471. The Division of Administrative Hearings has

3801jurisdiction over the parties and the subject matter. Section

3810120.57(1), Florida Statutes.

3813Standing

381472. In their Amended Petitions, Petitioners state that they

3823submitted their petitions pursuant to Section 120.57(1), Florida

3831Statutes. That statute provides standing to Petitioners in this

3840proceeding only if their "substantial interests will be affected

3849by the proposed agency action." Yet, insofar as real property is

3860concerned, Petitioners do not contend that their real property

3869will be substantially affected by the proposed pipeline project,

3878real property which is at least two miles from any portion of the

3891project.

389273. Petitioners have the burden of showing, as a matter of

3903fact, that they have "substantial interests" that will be

3912adversely affected if the Department issues the proposed permit

3921to Buckeye. The purpose of this standing requirement:

3929[I]s to ensure that a party

3935has a "sufficient interest in

3940the outcome of the litigation

3945which warrants the court's

3949entertaining it," and to

3953assure that a party has a

3959personal stake in the outcome.

3964Gregory v. Indian River Co. , 610 So. 2d 547, 554 (Fla. 1st DCA

39771992).

397874. The record is devoid of competent, substantial evidence

3987demonstrating that the Department's action in issuing the

3995proposed permit affects any substantial interest of Petitioners

4003which is unique to Petitioners to the exclusion of the general

4014public. Consequently, Petitioners failed to demonstrate any

4021right to a 120.57 proceeding wherein they could challenge

4030Buckeye's entitlement to the proposed permit. See Florida

4038Department of Transportation v. J.W.C. Co., Inc. , 396 So. 2d 778,

4049787 (Fla. 1st DCA 1981)

405475. In order to demonstrate that the Department's action

4063affects their "substantial interests," Petitioners must prove the

4071degree and nature of their alleged interests. Agrico Chemical

4080Co. v. Department of Environmental Regulation , 406 So. 2d 478,

4090482 (Fla. 2nd DCA 1981). To do this, they must demonstrate that

4102they will suffer injury in fact which is of sufficient immediacy

4113to entitle them to a Section 120.57 hearing and that such

4124substantial injury is of a type or nature which the proceeding is

4136designed to protect. Petitioners have not proven standing

4144pursuant to provisions of Section 120.57(1), Florida Statutes.

415276. In the course of this proceeding, Petitioners have also

4162disclosed that they rely upon provisions of Section 403.412(5),

4171Florida Statutes, to permit their standing and participation.

4179Section 403.412(5), Florida Statutes, provides:

4184In any administrative, licensing, or other

4190proceedings authorized by law for the

4196protection of the air, water, or other

4203natural resources of the state from

4209pollution, impairment, or destruction, the

4214Department of Legal Affairs, a political

4220subdivision or municipality of the state, or

4227a citizen of the state shall have standing to

4236intervene as a party on the filing of a

4245verified pleading asserting that the

4250activity, conduct, or product to be licensed

4257or permitted has or will have the effect of

4266impairing, polluting, or otherwise injuring

4271the air, water or other natural resources of

4279the state. (emphasis supplied).

428377. Notably, the Petitioners' entry into the proceeding,

4291pursuant to Section 403.412(5), Florida Statutes, is considered

4299to be in the capacity of intervenors with the implied requirement

4310of an existing controversy. Such a controversy may be considered

4320to exist after an agency has entered, as in this case, an

4332intended decision to grant the requested permit. MANASOTA-88,

4340Inc. v. Department of Environmental Regulation , (Fla. App. 1st

4349Dist. 1983).

435178. Although MANASOTA , supra , creates an opportunity for

4359Petitioners to challenge the proposed permit, they must comply

4368with procedures established by Section 403.412(5), Florida

4375Statutes, requiring that any such intervention must be by

"4384verified" petitions. It is observed that Petitioners did not

4393provide such verified petitions. Consequently, all the Petitions

4401are found to be deficit in that respect and, accordingly, should

4412be dismissed on that basis.

441779. Alternatively, if it is assumed that Petitioners have

4426standing, Buckeye has affirmatively provided the Department with

4434the required "reasonable assurance that state water quality

4442standards . . . will not be violated and reasonable assurance

4453that such activity [construction of the pipeline project] . . .

4464is not contrary to the public interest." Section 373.414(1),

4473Florida Statutes; and Rule 62-312.080, Florida Administrative

4480Code.

448180. Just as Petitioners are required to offer proof of

4491standing, Buckeye must demonstrate entitlement to the proposed

4499permit by a preponderance of the competent, substantial evidence.

4508See J.W.C. , supra . Buckeye has met this requirement.

451781. The proof establishes that the proposed pipeli ne

4526project complies with the applicable surface water quality

4534standards in Rule Chapters 62-302, Florida Administrative Code;

4542and that the proposed project satisfies the "public interest

4551test" of Section 373.414(1)(a), Florida Statutes, as well as

4560related Rules 40B-4.2030 and 40B-400.103-.104, Florida

4566Administrative Code.

456882. Finally, Section 373.414(8), Florida Statutes, requires

4575a consideration of the "cumulative impacts upon surface water and

4585wetlands." Respondents demonstrated at hearing that the proposed

4593project will meet all surface water quality standards, with the

4603exception of turbidity during construction. However, such

4610turbidity during construction is allowed by the temporary

4618construction variance issued by the Department. Consequently,

4625Buckeye has demonstrated compliance with applicable requirements

4632of Section 373.414, Florida Statutes and related rules.

4640RECOMMENDATION

4641Based on the foregoing findings of fact and conclusions of

4651law, it is

4654RECOMMENDED that a final order be entered dismissing all the

4664Petitions and issuing the proposed draft environmental resource

4672permit to Buckeye.

4675DONE AND ENTERED this 11th day of September, 1997, in

4685Tallahassee, Leon County, Florida.

4689___________________________________

4690DON W. DAVIS

4693Administrative Law Judge

4696Division of Administrative Hearings

4700The DeSoto Building

47031230 Apalachee Parkway

4706Tallahassee, Florida 32399-3060

4709(904) 488-9675 SUNCOM 278-9675

4713Fax Filing (904) 921-6847

4717Filed with the Clerk of the

4723Division of Administrative Hearings

4727this 11th day of September, 1997.

4733ENDNOTES

47341 / For a site to be significant, it must be eligible to be listed

4749on the National Historic Registry. For an archeological site,

4758that means the archeological site must have contributed in the

4768past or be able to contribute in the future information

4778significant to the region's prehistory. (Tr. IV at 429 - Hardin;

4789Tr. VI at 626 - Kammerer)

4795The following procedure is followed to determine if a site is

4806significant: test the site and collect artifact, evaluate the

4815stratigraphy of the site to ascertain if it has been disturbed in

4827the past, examine the collected information to learn the type and

4838time of the site, and determine if the site can provide new

4850information. (Tr. VI at 623-624 - Kammerer)

48572 / Hydrology is the science involving the calculations or the

4868methods to convert rainfall and distribution of rainfall to a

4878particular runoff or a quantity of water. It takes into account

4889the rainfall distribution, the quantity or rain, the cover of the

4900land that you're looking at, the slope, the topography, and so

4911forth, and converts all of that through systems of known

4921relationship to a runoff quantity. (Tr. II at 209- Vickstrom)

49313 / Hydraulics is taking a known quantity of water and routing it

4944through structures like bridges or culverts or control structures

4953like weirs or over dam embankments, through ditches, to convert

4963that quantity of water to a flood elevation or a stage. (Tr. II

4976at 209 - Vickstrom)

4980COPIES FURNISHED:

4982Ronnie Edwards

4984Rebecca Edwards

4986Mitchell Edwards

4988Route 1, Box 167

4992Perry, Florida 32347

4995Terry Cole, Esquire

4998Post Office Box 6507

5002Tallahassee, Florida 32314-6507

5005Sharon Cutter

5007Route 1, Box 1130

5011Perry, Florida 32347

5014Lynette Ciardulli, Esquire

5017Department of Environmental Protection

50213900 Commonwealth Boulevard

5024Tallahassee, Florida 32399-3000

5027Kathy Carter, Agency Clerk

5031Department of Environmental Protection

5035Mail Station 35

50383900 Commonwealth Boulevard

5041Tallahassee, Florida 32399-3000

5044F. Perry Odom, Esquire

5048Department of Environmental Protection

50523900 Commonwealth Boulevard

5055Tallahassee, Florida 32399-3000

5058Virginia B. Wetherell, Secretary

5062Department of Environmental Protection

50663900 Commonwealth Boulevard

5069Tallahassee, Florida 32399-3000

5072NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

5078All parties have the right to submit written exceptions within

508815 days from the date of this Recommended Order. Any exceptions

5099to this Recommended Order should be filed with the agency that

5110will issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 10/24/1997
Proceedings: Final Order filed.
PDF:
Date: 10/22/1997
Proceedings: Agency Final Order
PDF:
Date: 10/22/1997
Proceedings: Recommended Order
Date: 10/08/1997
Proceedings: Transcript (Pending Motions) filed.
Date: 10/03/1997
Proceedings: Respondent Department of Environmental Protection`s Response to Petitioner Cutter`s Exceptions to Recommended Order filed.
Date: 09/30/1997
Proceedings: Respondent Department of Environmental Protection`s Response to Petitioner`s Exceptions to Recommended Order filed.
PDF:
Date: 09/11/1997
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 07/07-10/97.
Date: 09/10/1997
Proceedings: Buckeye Florida, L.P.`s Response to Petitioner`s Proposed Recommended Order filed.
Date: 09/05/1997
Proceedings: Proposed Recommended Order of Petitioner Cutter filed.
Date: 09/02/1997
Proceedings: (Petitioner) A Motion for Objection of Hearing Transcript (filed via facsimile).
Date: 08/29/1997
Proceedings: Petitioners Edwards, Ronnie, Rebecca and Mitchell Proposed Recommended Order; Cover Letter filed.
Date: 08/26/1997
Proceedings: Order on Request for Extension of Time to File Proposed Findings of Fact sent out.
Date: 08/26/1997
Proceedings: (Petitioner) Motion for Extension of Time for Filing a Recommended Order filed.
Date: 08/21/1997
Proceedings: Respondent Department of Environmental Protection`s Proposed Recommended Order; Disk filed.
Date: 08/21/1997
Proceedings: Proposed Recommended Order of Buckeye Florida, L.P.; Disk ; Buckeye Florida, L.P.`s Objection to Request for Extension filed.
Date: 08/11/1997
Proceedings: Respondent`s Exhibit 38; Cover Letter filed.
Date: 08/11/1997
Proceedings: Transcripts (Volumes 1 thru 7, tagged) filed.
Date: 07/08/1997
Proceedings: Governor Lawton Chiles` Motion to Quash Subpoena filed.
Date: 07/07/1997
Proceedings: CASE STATUS: Hearing Held.
Date: 07/07/1997
Proceedings: (Cutter and Edwards) An Affidavit of Service of the Following Subpoena`s; Cover Letter (filed via facsimile).
Date: 07/03/1997
Proceedings: Order Denying Continuance and Motion to Compel sent out.
Date: 07/03/1997
Proceedings: Buckeye Florida, L.P.`s Motion to Quash Subpoenas and Motion for Protective Order Regarding Charles S. Aiken; (2) Subpoena Duces Tecum (from S. Cutter, R. Edwards) filed.
Date: 07/01/1997
Proceedings: (DEP) Response to Petitioner`s Motion to Reschedule Hearing; Certificate of Service (Inadvertently failed to include in the Joint Pre-Hearing Stipulation) filed.
Date: 07/01/1997
Proceedings: Buckeye Florida, L.P Response in Opposition to Petitioners` Request to Reschedule Hearing filed.
Date: 06/30/1997
Proceedings: (Signed by P. Renovitch, L. Ciardulli) Joint Pre-Hearing Stipulation filed.
Date: 06/30/1997
Proceedings: (Petitioner) Motion to Reschedule Hearing; (Petitioner) A Motion for Order to Compel for Petitioner to a Full Discovery and a Request for a Continuance (filed via facsimile).
Date: 06/27/1997
Proceedings: (DEP`s) Order Closing File (Order filed in DOAH case 97-931) filed.
Date: 06/27/1997
Proceedings: (Respondent) Motion to Admit Matters Specified in Respondent`s Request for Admissions by Operation of Law and motion in Limine filed.
Date: 06/27/1997
Proceedings: (Respondent) Motion for Summary Recommended Order filed.
Date: 06/25/1997
Proceedings: Order Denying Consolidation sent out. (for 97-2902 to be added to 97-0692, 97-0930 & 97-1449)
Date: 06/18/1997
Proceedings: Response of Buckeye Florida, L.P. in Support of The Motion to Consolidate Filed by the Department of Environmental Protection filed.
Date: 06/18/1997
Proceedings: (2) Respondent, Department of Environmental Protection`s Response to Petitioner`s Request for Production of Documents filed.
Date: 06/17/1997
Proceedings: (Petitioners) Response to DEP`s Motion to Consolidate filed.
Date: 06/17/1997
Proceedings: Response (Including Objections) of Buckeye Florida, L.P. to Discovery Requests by Petitioners Cutter and Edwards; Notice of Answering Interrogatories of Petitioners Cutter and Edwards filed.
Date: 06/12/1997
Proceedings: Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection filed. (for 97-0692, 97-0930, 97-1449 & 97-2902)
Date: 06/12/1997
Proceedings: Buckeye Florida, L.P.`s Witness List; Amended Notice of Taking Deposition filed.
Date: 06/06/1997
Proceedings: (Buckeye) Notice of Taking Deposition filed.
Date: 06/02/1997
Proceedings: (Ronnie, Rebecca and Mitchell Edwards) Notice to Obtain for Subpoenas filed.
Date: 05/30/1997
Proceedings: (Buckeye Fl. L.P.) Amended Notice of Taking Depositions Duces Tecum by Videotape filed.
Date: 05/28/1997
Proceedings: (Buckeye Fl. L.P.) Notice of Taking Depositions Duces Tecum filed.
Date: 05/23/1997
Proceedings: (From P. Renvoitch) (3) Request for Admissions filed.
Date: 05/22/1997
Proceedings: Case No/s: unconsolidated. 97-000928
Date: 05/22/1997
Proceedings: Order Closing File sent out. CASE 97-928 ONLY CLOSED.
Date: 05/22/1997
Proceedings: Case No/s: unconsolidated. 97-000931 Order Closing File sent out. CASE NO 97-931 ONLY CLOSED.
Date: 05/21/1997
Proceedings: (From R., R., M. Edwards) Notice of Service of Interrogatories and Production of Documents to Respondent Buckeye Florida L.P.; Notice of Service of Interrogatories and Production of Documents to Respondents Environmental Protection filed.
Date: 05/21/1997
Proceedings: (Petitioner) A Motion to Withdraw Petition (Filed by Fax) filed.
Date: 05/20/1997
Proceedings: (Buckeye Fl. L.P.) Second Motion for Order Compelling Discovery and Sanctions and Request for Expedited Hearing on Motion filed.
Date: 05/20/1997
Proceedings: (From P. Renovitch) Third Amended Notice of Taking Depositions Duces Tecum filed.
Date: 05/19/1997
Proceedings: (Petitioner) Notice to Obtain Subpoenas (filed via facsimile).
Date: 05/19/1997
Proceedings: (Petitioner) A Motion to Withdraw My Petition filed.
Date: 05/19/1997
Proceedings: Memo to DWD from Sharon Cutter (RE: request for subpoenas) (filed via facsimile).
Date: 05/15/1997
Proceedings: CASE NO. 97-927 ONLY CLOSED, per Petitioner`s notice of withdrawal sent out.
Date: 05/15/1997
Proceedings: Case No/s: unconsolidated. 97-000927
Date: 05/14/1997
Proceedings: (Petitioner) A Motion to Withdraw My Petition filed.
Date: 05/13/1997
Proceedings: Order Closing File, case 97-927 only filed.
Date: 05/07/1997
Proceedings: Order sent out.
Date: 05/05/1997
Proceedings: (Buckeye Fl. L.P.) Notice of Filing Interrogatory Answers; Interrogatories to Roy D. Sadler; Interrogatories to Margaret Terry; Interrogatories to James Green; Interrogatories to Ronnie Edwards, Rebecca Edwards and Mitchell Edwards filed.
Date: 05/05/1997
Proceedings: (Respondent) Motion for Order Compelling Discovery and Sanctions and Request for Expedited Hearing on Motion filed.
Date: 04/30/1997
Proceedings: (From P. Renovitch) Order Upon Request for Prehearing Conference; Disk w/cover letter filed.
Date: 04/29/1997
Proceedings: Order Providing Notice of Prehearing Conference sent out. (set for 5/8/97; 10:00am; Perry)
Date: 04/22/1997
Proceedings: Order Upon Pending Motions sent out.
Date: 04/21/1997
Proceedings: Letter to DWD from Joy Towles (RE: notice of telephone hearing) (filed via facsimile).
Date: 04/21/1997
Proceedings: Notice of Filing Department`s December 31, 1996, Notice of Intent to Issue Environmental Resource Permit and Related Documents; Exhibits filed.
Date: 04/18/1997
Proceedings: Response of Buckeye Florida, L.P., to April 15, 1995 Ex Parte Communications by Petitioners Edwards filed.
Date: 04/18/1997
Proceedings: Response of Buckeye Florida, L.P., in Opposition to Petitioners` "Motion to Strike Some of Interrogatories Questions" and Request for Oral Argument filed.
Date: 04/17/1997
Proceedings: (Petitioner) A Motion to Strike Some of Interrogatories Questions filed.
Date: 04/17/1997
Proceedings: (Buckeye) Amended Notice of Taking Deposition Duces Tecum filed.
Date: 04/17/1997
Proceedings: (Buckeye) Amended Notice of Hearing filed.
Date: 04/16/1997
Proceedings: Order Upon Ex Parte Communication sent out. (Relief Requested by Exhibit "A" is Denied; Re: Fl Stats 120.66)
Date: 04/15/1997
Proceedings: (From M. Edwards) A Motion for the Removal of the Presiding Hearing Officer filed.
Date: 04/15/1997
Proceedings: (From R. & R. Edwards) A Motion for the Removal of the Presiding Hearing Officer filed.
Date: 04/14/1997
Proceedings: Order Granting Motion to Reschedule Final Hearing sent out. (hearing set for July 7-11, 1997; 10:00am; Perry)
Date: 04/10/1997
Proceedings: (Respondent) Notice of Hearing filed.
Date: 04/08/1997
Proceedings: Response of Buckeye Florida, L.P. to Initial Order in Sharon Cutter Case, Status Report Concerning Prehearing Meeting, and Updated Information About April 14 and 21, 1997, Motion Hearings filed.
Date: 04/08/1997
Proceedings: (Buckeye) Amended Notice of Hearing filed.
Date: 04/07/1997
Proceedings: Case No/s: unconsolidated. 97-000929
Date: 04/07/1997
Proceedings: Order Closing File sent out. CASE 97-929 ONLY CLOSED, per Motion to Withdraw Petition filed.
Date: 03/31/1997
Proceedings: Order of Consolidation sent out. (Cases to be consolidated: 97-692, 97-927, 97-928, 97-930, 97-931, 97-1449)
Date: 03/31/1997
Proceedings: (Buckeye) Notice of Hearing filed.
Date: 03/28/1997
Proceedings: (Respondent) Notice of Scheduling Conflict and Motion to Reschedule Hearing filed.
Date: 03/27/1997
Proceedings: (Buckeye) Notice of Service of Interrogatories to Petitioner James Green filed.
Date: 03/27/1997
Proceedings: (Buckeye) Notice of Service of Interrogatories to Petitioner Roy D. Sadler; (Respondent) Motion for Expedited Discovery filed.
Date: 03/27/1997
Proceedings: (Buckeye) Notice of Service of Interrogatories to Petitioners Ronnie Edwards, Rebecca Edwards and Mitchell Edwards; Notice of Service of Interrogatories to Petitioner Margaret Terry filed.
Date: 03/27/1997
Proceedings: (Buckeye) Notice of Service of Interrogatories to Petitioner Ruby Morgan filed.
Date: 03/27/1997
Proceedings: Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner Margaret Terry filed.
Date: 03/27/1997
Proceedings: Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner Roy D. Sadler; Buckeye Florida, l.P.`s Request for Production of Documents to Petitioner Ruby Morgan filed.
Date: 03/27/1997
Proceedings: Buckeye Florida, L.P.`s Request for Production of Documents to Petitioners Ronnie Edwards, Rebecca Edwards and Mitchell Edwards; Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner James Green filed.
Date: 03/21/1997
Proceedings: Amended Order of Prehearing Instructions sent out.
Date: 03/21/1997
Proceedings: Amended Notice of Hearing sent out. (hearing set for May 5-9, 1997; 10:00am; Perry)
Date: 03/21/1997
Proceedings: (From T. Cole) Notice of Service of Interrogatories to Petitioner; Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner, Joyce (Joy) Towles Cummings filed.
Date: 03/20/1997
Proceedings: Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection and Buckeye Florida, L. P. filed.
Date: 03/20/1997
Proceedings: Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection filed.
Date: 03/17/1997
Proceedings: Order of Prehearing Instructions sent out.
Date: 03/17/1997
Proceedings: Notice of Hearing sent out. (hearing set for 05/05-09/97;10:00a.m.;Perry)
Date: 03/17/1997
Proceedings: Joint Response of Buckeye Florida, L.P. and Florida Department of Environmental Protection to Initial Orders and Request for Scheduling Conference filed.
Date: 03/14/1997
Proceedings: Order of Consolidation sent out. Consolidated case are: 97-000692 97-000927 97-000928 97-000929 97-000930 97-000931 . CONSOLIDATED CASE NO - CN002664
Date: 03/07/1997
Proceedings: Response of Buckeye Florida, to Amended Petition for Administrative Hearing on Environmental Resource Permit Including Motion to Strike Irrelevant Issues Motion for A More Definite Statement, Motion to Dismiss Challenge to Variance etc... filed.
Date: 03/07/1997
Proceedings: (Cont) Motion to Dismiss "Amended" Petition, and Request for Oral Argument filed.
Date: 03/07/1997
Proceedings: Response of Buckeye Florida, L.P., to Amended "Petition for Administrative Hearing on Environmental Resource Permit," Including Motion to Strike Irrelevant Issues, Motion for A More Definite Statement, Motion to Dismiss Challenge to Variance, filed.
Date: 03/07/1997
Proceedings: Response of Buckeye In Support of Department`s Motion to Consolidate filed.
Date: 03/04/1997
Proceedings: Amended Response of Buckeye Florida, L.P., to Initial Order and Request for Scheduling Conference filed.
Date: 03/04/1997
Proceedings: Notice of Related Case and Motion to Consolidate By Respondent Department of Environmental Protection filed.
Date: 02/27/1997
Proceedings: Motion to Strike Allegations Contained in the Amended Petition (Respondent) filed.
Date: 02/25/1997
Proceedings: Response of Buckeye Florida, L.P. to Initial Order filed.
Date: 02/19/1997
Proceedings: Response of Buckeye Florida, L.P., to "Petition for Administrative Hearing on Environmental Resource Permit," Including Motion to Strike Irrelevant Issues, Motion for a More Definite Statement, Motion to Dismiss Challenge to Variance, and Request for Oral
Date: 02/13/1997
Proceedings: (From P. Renovitch) Notice of Appearance filed.
Date: 02/13/1997
Proceedings: Initial Order issued.
Date: 02/10/1997
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Agency Action Letter; Petition for Administrative Hearing On Environmental Resource Permit; Notice Of Intent To Issue Permit; Draft Permit; Intent To Grant Variance;

Case Information

Judge:
DON W. DAVIS
Date Filed:
02/10/1997
Date Assignment:
02/13/1997
Last Docket Entry:
10/24/1997
Location:
Perry, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Related Florida Statute(s) (3):

Related Florida Rule(s) (2):