97-001682 Collier Cattle Corporation And Tropical Ranch Properties, Inc. vs. South Florida Water Management District And Department Of Environmental Protection
 Status: Closed
Recommended Order on Thursday, June 25, 1998.


View Dockets  
Summary: District provided reasonable assurance as to criteria in Rules 40E-4.302 and 40E-4.301, Florida Administrative Code, for issuance of environmental resource permit for weir in Merritt Canal.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8COLLIER CATTLE CORPORATION, and )

13TROPICAL RANCH PROPERTIES, INC., )

18)

19Petitioners, )

21)

22and )

24)

25WALTER R. SHAW, SR., )

30)

31Intervenor, )

33vs. ) Case No. 97-1682

38)

39SOUTH FLORIDA WATER MANAGEMENT )

44DISTRICT and DEPARTMENT OF )

49ENVIRONMENTAL PROTECTION, )

52)

53Respondents. )

55___________________________________)

56RECOMMENDED ORDER

58Robert E. Meale, Administrative Law Judge of the Division

67of Administrative Hearings, conducted the final hearing in

75Naples, Florida, on August 12, 13, 28, and 29, October 1, 2,

878, and 9, November 13, 14, 17, 18, and 19, 1997, and

99January 6, 7, and 8, 1998.

105APPEARANCES

106For Petitioners: James W. McDonald, Jr.

112McDonald & Associates

115Co mmunity Plaza, Suite 306

12015600 Southwest 288th Street

124Homestead, Florida 33030

127A. Glenn Simpson

130Qualified Representative

1325961 22d Avenue Southwest

136Naples, Florida 34116

139For Respondent South Florida Water Management District:

146Marcy I. LaHart

149Associate Attorney

151South Florida Water Management District

1563301 Gun Club Road

160West Palm Beach, Flo rida 33416-4680

166For Respondent Department of Environmental Protection:

172Francine M. Ffolkes

175Assistant General Counsel

178Department of Environmental Protection

182Mail Station 35

1853900 Commonwealth Boulevard

188Tallahassee, Florida 32399-3000

191For Intervenor Walter R. Shaw, Sr.:

197Walter R. Shaw, Sr., pro se

2031400 Northwest 62nd Avenue

207Sunrise, Florida 33313-6138

210For Intervenor Clifford L. Fort:

215Cliffort L. Fort

2188410 Northwest 16th Street

222Pembroke Pines, Florida 33024

226STATEMENT OF THE ISSUE

230The issue is whether Respondent South Florida Water

238Management District is entitled to an environmental resource

246permit from Respondent Department of Environmental Protection

253to construct a weir in Collier County on the Merritt Canal

264about 3600 feet south of Interstate 75 for the purpose of

275extending the hydroperiod on the Florida Panther Federal

283Wildlife Refuge.

285PRELIMINARY STATEMENT

287Respondent South Florida Water Management District

293applied to Respondent Department of Environmental Protection

300for an environmental resource permit to construct a weir in

310the Merritt Canal to be operated by the water management

320district. On January 29, 1997, Respondent Department of

328Environmental Protection issued a Notice of Intent to Issue

337with several general and specific conditions. During the

345hearing, the department attached new monitoring conditions to

353the draft permit.

356Petitioners timely challenged the intended agency action

363and demanded a formal hearing. The administrative law judge

372granted the petitions to intervene of both Intervenors.

380The court reporter filed the final portion of the

389transcript on February 2, 1998.

394The administrative law judge specifically finds that,

401based on his presentation of Petitioners' case, Mr. Simpson is

411a qualified representative for the purpose of representing

419other parties in administrative hearings before the Division

427of Administrative Hearings. The administrative law judge

434denies Mr. Shaw's post-hearing request for summary relief.

442FINDINGS OF FACT

445I. Proposed Permit

4481. On April 17, 1996, Respondent South Florida Water

457Management District (District) filed with Respondent

463Department of Environmental Protection (DEP) an application

470for the construction of a water-control structure in the

479Merritt Canal. The stated purpose of the structure, which is

489a weir, is to extend the hydroperiod of the Lucky Lake Strand.

5012. The application states that the District is the owner

511of a drainage easement covering the land proposed as the site

522of the weir. According to the application, Collier County, in

532which the Merritt Canal lies, originally held the drainage

541easement. The District later adopted the Merritt Canal as a

"551Works of the District," which transferred operational

558responsibility for the canal from the County to the District.

568(A sub-unit of the District, the Big Cypress Basin Board has

579jurisdiction for District projects of the type involved in

588this case. References to the District shall include the Big

598Cypress Basin Board.)

6013. The application requests a permit to construct an

610adjustable sheet-pile weir within the 80-foot Merritt Canal

618right-of-way. The application accurately describes the

624Merritt Canal as a Class III waterbody that is not an

635Outstanding Florida Water.

6384. By Notice of Intent to Issue Environmental Resource

647Permit dated January 29, 1997 (NOI), DEP proposed to issue an

658environmental resource permit (ERP) to the District for the

667construction of the Lucky Lake Strand Water Control Structure.

676The structure would be an adjustable weir with operating

685levels of 7.0 feet National Geodetic Vertical Datum (NGVD) in

695the wet season and 9.5 feet NGVD in the dry season.

7065. As stated in the NOI, the Merritt Canal is 12 miles

718long and one of four main north-south canals within a larger

729system of 183 miles of canals--all Class III waters--

738constructed in the 1960s by Gulf American Land Corporation to

748drain wetlands for development of the Southern Golden Gate

757Estates area. These four north-south canals drain water south

766through the Faka Union Canal and into Faka Union Bay, which is

778part of the 10,000 Islands/Cape Romano Aquatic Preserve. The

788preserve contains Class II Outstanding Florida Waters.

7956. The NOI notes that the U.S. Fish and Wildlife Service

806(FWS) and District entered into an agreement in September 1994

816to construct two weirs in the Merritt Canal "to partially

826restore historic hydroperiods into two major wetland features

834within the federally owned lands of the USFWS Florida Panther

844National Wildlife Refuge, Lucky Lake Strand and Stumpy Strand

853(Class III Outstanding Florida Waters)." As stated in the

862NOI, these federally owned wetlands constitute over 3000 acres

871of cypress and mixed swamps, wet prairies, marshes, and ponds.

8817. The NOI relates that FWS staff proposed the project

891to counteract "subtle vegetational changes and accelerated

898pond draw-downs [that] were taking place in the strands as a

909result of shortened hydroperiods caused by a three-year

917drought, I-75 widening activities, and subsequent canal

924modifications."

9258. The NOI correctly states that water in the wet season

936historically flowed southerly through Stumpy Strand, Lucky

943Lake Strand, and Picayune Strand, before entering the larger

952Fakahatchee Strand. Lucky Lake Strand narrows to 1000 feet at

962its south end, which is at Interstate 75 (I-75).

9719. The NOI accurately asserts that the construction of

980the Merritt Canal and the I-75 borrow canals combined to draw

991down the upstream wetlands, thus reducing their hydroperiods.

999The effect of the Merritt Canal is reportedly significant

1008because of its confluence with the southern tip of Lucky Lake

1019Strand.

102010. The NOI discloses that the original agreement

1028between the District and FWS called for the construction of

1038two weirs south of I-75, one at the headwaters of the Merritt

1050Canal and another about 1800 feet downstream in the Merritt

1060Canal. However, the proposed permit eliminates one weir,

1068whose function was performed by plugs in the north I-75 borrow

1079canal, and relocates the remaining proposed weir about 3600

1088feet south of I-75, rather than immediately south of I-75,

1098reportedly because of difficulties in accessing the proposed

1106weir at I-75.

110911. The NOI states that the Merritt Canal is within the

112080-foot drainage easement originally acquired by Collier

1127County. The uplands adjacent to the weir are reportedly owned

1137by DEP.

113912. The NOI describes the proposed weir as a sheet pile

1150weir with adjustable partitions. As proposed, during the wet

1159season, the District would start to open the gates at 7 feet

1171NGVD and start to close them at 6.5 feet NGVD. During the dry

1184season, the District would start to open the gates at 9.8 feet

1196NGVD and start to close them at 9.3 feet NGVD. Also, the

1208proposed permit would anticipate that the District would

1216dredge the canal to a trapezoidal cross-section having a

1225bottom elevation of -1.5 feet NGVD and a width of about 49

1237feet at the weir and transitioning to 20-foot bottom widths

1247upstream and downstream of the weir.

125313. According to the NOI, the purpose of the proposed

1263weir is

1265to reduce over-drainage of the upstream

1271wetlands in Lucky Lake and Stumpy Strands

1278by extending the hydroperiod further into

1284the dry season. No increase in water

1291levels during the wet season is expected.

1298Although the historic extended hydroperiod

1303is not expected to be achieved, the weir

1311structure is expected to improve current

1317conditions to the upstream wetlands.

1322Holding back water in these wetlands [is]

1329also expected to improve water quality

1335downstream by removal of excess nutrient,

1341sediments, and chemicals. Wildlife values

1346are expected to be enhanced in preferred

1353waterfowl and wading bird habitat,

1358including areas for the endangered wood

1364stork and threatened bald eagle. Forage

1370areas are also expected to be improved for

1378white-tailed deer and other wildlife

1383species which are essential prey for the

1390endangered Florida panther. Aquifer

1394recharge is also expected as the ground

1401water reserves will be raised by raising

1408the canal water levels, while maintaining

1414the existing level of flood protection for

1421adjacent private landowners.

142414. The NOI states that FWS will monitor post-

1433construction environmental conditions and will recommend to

1440the District adjustments to the weir elevations. The NOI

1449reports that the District will be the "main operator" of the

1460weir to adjust elevations to maintain flood control for

1469adjacent lands. The NOI adds:

1474The project was designed so as not to

1482decrease the peak discharge capacity in

1488the canal or increase flood stages in the

1496Upper Merritt Canal watershed. Hydraulic

1501modeling by the District indicates that

1507there will be no additional surface water

1514flooding to private property as a result

1521of the project, and the current level of

1529service will be maintained.

153315. Based on this analysis, the NOI concludes that the

1543District has provided reasonable assurance that the proposed

1551activity will comply with Part IV, Chapter 373, Florida

1560Statutes, and the underlying rules, including Chapter 62-330

1568and Rules 40E-4.301 and 40E-4.302, Florida Administrative

1575Code. The NOI states that the District has demonstrated that

1585the activity is clearly in the public interest, pursuant to

1595Section 373.414(1)(a), Florida Statutes.

159916. The proposed permit conforms to the NOI's

1607description. Specific Condition 13 sets the fixed crest of

1616the proposed weir at 4.5 feet NGVD and the width of the weir

1629at 48 feet.

163217. Although the proposed permit is nowhere explicitly

1640conditioned on a successful wetland enhancement project,

1647Specific Condition 12 states that "the" wetland enhancement

1655project shall be considered successful if, after five years,

1664Lucky Lake Strand and Stumpy Strand display wetland-

1672appropriate vegetation and the "viability of adjacent upland

1680sites [is] not negatively impacted by increased ground water

1689or surface water levels resulting from the authorized

1697project."

169818. Specific Condition 17 requires the District to

1706document the operation of the gates and notify DEP, within

1716three days, whenever any of the permitted elevations are

1725exceeded. Annually, the District must supply DEP detailed

1733data and analysis of the operational history of the weir,

1743including "reasons for going to nonstandard operation and a

1752narrative description of the effectiveness of initiating the

1760nonstandard operation to include areas not flooded (or

1768flooded, if applicable) and other associated impacts."

177519. During the final hearing, the District proposed, and

1784DEP approved, a modification of Specific Condition 18. As

1793modified, Specific Condition 18 requires the District to

"1801monitor the effects of the operation" of the weir, pursuant

1811to the revised monitoring plan incorporated by reference into

1820this condition.

182220. The revised monitoring plan, which is dated

1830November 12, 1997, alters the original monitoring plan by

1839adding two sites for the installation of water-table wells.

1848One of the new sites (Site A) is 1200 feet north of the weir,

1862and the other new site (Site B) is 1200 feet north and 2000

1875feet west of the weir. These are the only water-table

1885monitoring devices.

188721. Five other sites are surface-water monitoring sites.

1895Three of the these sites are in the Merritt Canal: one

1906immediately upstream of the weir, one immediately downstream

1914of the weir, and one farther upstream at I-75. The other two

1926surface-water monitoring sites are farther upstream. One is

1934in Lucky Lake about 1.75 miles north of the weir, and the

1946other is about three miles northeast of Lucky Lake.

195522. Three other sites are rainfall-monitoring sites.

1962Two rainfall-monitoring sites are north of the weir. The site

1972just north of I-75 is at the Ford Motor Company test track,

1984which is immediately west of Lucky Lake and Stumpy Strands,

1994and the site more directly north of the Merritt Canal is about

2006ten miles north of I-75.

201123. Specific Condition 18 states the frequency with

2019which someone (presumably a District employee or contractor)

2027is to collect the data from these 10 monitoring sites, but

2038contains no performance criteria. The monitoring plan thus

2046commits the District to collecting data, but not to analyzing

2056the data, nor, more importantly, taking specified actions when

2065certain performance parameters are exceeded.

207024. Neither the revised monitoring plan nor the

2078application in any way commits the District to using the data

2089collected from the revised monitoring plan to develop a set of

2100criteria, based on rainfall amounts, groundwater levels, and

2108surface water levels, to fine-tune the operation of the gates

2118so as not to exacerbate present flooding. Nothing in the

2128revised monitoring plan or the application suggests that the

2137District will use the data collected from the revised

2146monitoring plan to identify more clearly the relationships

2154between storm events and water levels to understand better the

2164relationship between flooding, on the one hand, and the

2173existence of the proposed weir and the operation of its gates.

2184II. Faka Union Canal Watershed and

2190Southern Golden Gate Estates

219425. What is now known as the Faka Union Canal Watershed

2205historically covered about 234 square miles. It ran from an

2215area about four miles north of what is now known as Immokalee

2227Road south in a widening expanse that approached 12 miles at

2238what is now U.S. Route 41. It then ran south until it emptied

2251into the Gulf of Mexico at Faka Union Bay in what is now the

2265Cape Romano Ten Thousand Islands State Aquatic Preserve east

2274of Marco Island.

227726. Land alterations due to road and canal construction

2286and urban and agricultural development eventually reduced the

2294Faka Union Canal Watershed to about 189 square miles. Most

2304noticeably, these changes narrowed the drainage area at U. S.

2314Route 41 from almost 12 miles to little more than the width of

2327the Faka Union Canal.

233127. The Faka Union Canal Watershed is characterized by

2340low relief and poorly defined drainage patterns. At the north

2350boundary of the watershed, which now ends at Immokalee Road,

2360the elevation reaches 24 feet NGVD. Twenty-eight miles to the

2370south, at the outlet of the basin, the elevation is two feet

2382NGVD. The water flows generally in a southwest direction.

239128. Historically, water ran slowly through the watershed

2399in sheetflow several miles wide and a few inches to a few feet

2412deep. Drainage concentrated in slightly lower sloughs and

2420strands, which generally dried out in the dry season.

2429Historically, the watershed featured flat, swampy lands

2436containing cypress trees, islands of pine forests, and wet and

2446dry prairies. Prior to development, much of the watershed

2455remained inundated by several feet of water during the five-

2465month wet season (roughly from mid-May through mid-October).

2473In this undisturbed state, the prominent features of the

2482watershed were the storage of runoff in depressional areas,

2491attenuated peak flows, and a longer hydroperiod into the dry

2501season.

250229. In the early 1960s, Gulf American Land Corporation

2511subdivided a 173 square-mile area in Collier County into many

2521thousands of lots as small as 1.25 acres. The development was

2532Golden Gate Estates. The portion of Golden Gate Estates south

2542of I-75 is known as Southern Golden Gate Estates. Golden Gate

2553Estates is west of the Merritt Canal.

256030. Gulf American's purpose in dredging the 183-mile

2568canal system was to allow it to market as land, available for

2580continuous occupation, subdivided lots superimposed over an

2587area that was land during the dry months and water during the

2599wet months. To achieve this objective, Gulf American Land

2608Corporation constructed one group of canals that drains to the

2618west and another group of canals drains to the south into the

2630Faka Union Canal. Gulf American dredged the canals draining

2639to the south, which form the Faka Union Canal System, from

26501968 through 1971.

265331. Four north-south canals spaced two miles apart drain

2662Southern Golden Gate Estates and the portion of the Faka Union

2673Canal Watershed north of I-75. From west to east, the canals

2684are the Miller Canal, Faka Union Canal, Merritt Canal, and

2694Prairie Canal. Only the two westerly canals run north of

2704I -75. The Miller Canal extends almost seven miles north of

2715I -75, and the Faka Union Canal extends about 14 miles north of

2728I-75. The Merritt Canal starts in the immediate vicinity of

2738I-75, and the Prairie Canal starts about two miles south of

2749I -75.

275132. The average excavated depth of the four canals is

2761about ten feet from the top of the bank to the bottom of the

2775channel. Given the relatively close proximity of the water

2784table to the surface in this area, excavation to these depths

2795thus established a direct hydraulic connection with the

2803surficial aquifer. The canals are large, ranging from 45 to

2813over 200 feet wide.

281733. Although unable to convey without flooding the water

2826from even a ten-year storm event, which is the level of

2837service standard set by Collier County for Southern Golden

2846Gate Estates, the Faka Union Canal system has nonetheless

2855severely impacted the water resources of Collier County.

2863According to the Hydrologic Restoration of Southern Golden

2871Gate Estates, prepared in February 1996 by the Big Cypress

2881Basin Board (Southern Golden Gate Estates Restoration Plan):

2889. . . Construction of the canals has led

2898to both increased volumes and rates of

2905runoff from the watershed which has had

2912lasting effects on the area's water

2918supply, vegetation, wildlife, and coastal

2923estuaries.

2924The canals intercept large volumes of

2930surface and subsurface flow and quickly

2936divert them to the Faka Union Bay and the

2945Ten Thousand Island Estuary of the Gulf of

2953Mexico resulting in less surface water

2959available for storage. Since groundwater

2964recharge is achieved primarily through

2969infiltration from surface detention

2973storage, reduced groundwater recharge

2977threatens both groundwater supply for the

2983region and the natural barrier to salt

2990water intrusion. Continued overdrainage

2994has caused an eventual lowering of the

3001groundwater table. This has caused

3006vegetation to change from wetland dominant

3012to transitional and upland systems with

3018invasive exotic species. The extreme dry

3024conditions caused by overdrainage have

3029resulted in more frequent and more intense

3036wildfires with a greater destructive

3041impact on vegetation.

3044The increased runoff rate has had severe

3051effects on the receiving estuaries.

3056Historically, the estuaries would receive

3061broad, slow moving sheets of water that

3068were capable of carrying essential

3073nutrients but not high sediment loads.

3079This has been replaced with point loads of

3087freshwater at the Faka Union Canal outlet

3094that push salinity levels down and result

3101in freshwater discharge shocks throughout

3106the Ten Thousand Island Estuary. The

3112increased runoff rate drains the area

3118quickly and does not allow the

3124hydroperiods necessary to sustain wetland

3129vegetation. . . .

3133Southern Golden Gate Estates Restoration Plan, pages

31408-9.

314134. The major roadway affecting the Faka Union Canal

3150Watershed is State Road 84, which was a two-lane road

3160constructed in 1966. In 1990, construction was completed

3168transforming State Road 84 into four-lane I-75. These road

3177projects have hastened drainage of the lands to the north of

3188I-75 and east of the Faka Union Canal.

319635. The land north of the Merritt Canal is largely

3206undeveloped. If one were to extend the Merritt Canal due

3216north of I-75, it would run through the middle of Lucky Lake

3228Strand and much of Stumpy Strand, which is immediately to the

3239north of Lucky Lake Strand. Agricultural land owned by

3248Collier Enterprises is just north of the Ford Motor Company

3258test track and immediately west of Lucky Lake Strand.

3267Agricultural land owned by Baron Collier Company is

3275immediately north of Stumpy Strand.

328036. This imaginary extension of Merritt Canal would mark

3289the west boundary of the Florida Panther National Wildlife

3298Refuge, which was established in June 1989. The Florida

3307Panther National Wildlife Refuge constitutes 26,000 relatively

3315undisturbed acres immediately north of I-75. Intervenor

3322Clifford Fort owns property south of the refuge on the south

3333side of I-75.

333637. The Florida Panther National Wildlife Refuge

3343features mostly wetlands, oak hammocks, pine flatwoods, and

3351prairies. The refuge receives runoff from stormwater and

3359possibly agricultural pumping of the water table from the

3368adjacent farmland. In addition to draining into the

3376headwaters of the Merritt Canal near the southwest corner of

3386the refuge, the refuge also drains into the northerly borrow

3396canal running along the north side of I-75. In the vicinity

3407of the Merritt Canal, the four borrow canals running along the

3418north and south sides of I-75, on both sides of the Merritt

3430Canal, drain in the direction of the Merritt Canal.

343938. Listed species using the Florida Panther National

3447Wildlife Refuge include the Florida panther, Florida black

3455bear, wood stork, roseate spoonbill, limpkin, and Eastern

3463Indigo snake. In October 1995, an inordinate amount of rain

3473fell in the area. Attracted by the increased water depths,

3483which more closely approximated historic conditions, 75 wood

3491storks nested in the Lucky Lake Strand; in drier years, wood

3502storks do not nest in the strand.

350939. Lucky Lake Strand occupies the southwest corner of

3518the Florida Panther National Wildlife Refuge. Lucky Lake and

3527two other ponds are present in this area. When full, Lucky

3538Lake and one of the ponds are about 50 meters wide, and the

3551third pond is about half of this width. During the dry

3562season, a person can throw a stone across any of the ponds.

357440. Historically, Lucky Lake and Stumpy strands passed

3582surface water into the Picayune Strand, which is west of the

3593Merritt Canal and south of I-75, from which the water ran into

3605the Fakahatchee Strand. Lucky Lake Strand presently narrows

3613to about 1000 feet at I-75.

361941. The hydrologic connection between the outlet of

3627Lucky Lake Strand and the headwaters of the Merritt Canal has

3638contributed significantly to the overdrainage of these two

3646strands, which occupy a significant area within the federal

3655refuge. The FWS wildlife biologist stationed at the Florida

3664Panther National Wildlife Refuge reported in a habitat

3672assessment report prepared in August 1996 that four ponds in

3682the strand dried out by December so that they could not

3693sustain fish or provide feeding habitat for birds.

3701III. Permitting Criteria

3704A. Public Health, Safety, or Welfare or Others' Property

371342. One of the main disputes between the parties is the

3724affect of the proposed weir on flooding. This case is largely

3735about flooding or, more generally, the amount of water to be

3746stored for a specified period of time. Petitioners and

3755Intervenors fear that the District's effort will cause

3763flooding to areas south of I-75 and east and west of the

3775Merritt Canal.

377743. Occupying property within a vast area whose natural

3786drainage patterns have been greatly disrupted, Petitioners and

3794Intervenors justifiably fear the ravages of flood and fire.

3803Although this area was undoubtedly subject to these hazards

3812prior to man's alteration of the natural landscape, large-

3821scale alterations to natural drainage in Southwest Florida

3829have artificially heightened the risk presented by these

3837natural hazards.

383944. Destructive flooding follows the inhabitation of

3846areas historically devoted to the storage of considerable

3854volumes of water; the flooding is exacerbated where, as here,

3864natural drainage features have been replaced by artificial

3872facilities that are inadequate for both the natural flows and

3882the new, artificial flows generated by development. Although

3890inadequate for the natural and artificial flows generated by

3899even design storm events, the artificial drainage facilities

3907nevertheless change historic drainage rates, accelerating the

3914rate and volume of natural drainage and shortening the

3923hydroperiod. In this manner, the artificial drainage

3930facilities contribute to the desiccation of previously

3937saturated soils and foster conditions suitable for dangerous

3945fires.

394645. Initially, Petitioners and Intervenors contend that

3953the District seeks approval of the proposed weir as an

3963indirect means of implementing the Southern Golden Gate

3971Estates Rehydration Plan. Little evidence supports this

3978concern.

397946. The Southern Golden Gate Estates Rehydration Plan

3987outlines several alternatives for the proposed rehydration of

3995Southern Golden Gate Estates. The preferred alternative does

4003not call for a weir at the proposed location. The purpose of

4015the proposed weir is to rehydrate an area north of the

4026Southern Golden Gate Estates. As discussed below, the role of

4036the proposed weir in rehydrating Southern Golden Gate Estates

4045appears insubstantial to the point of nonexistent.

405247. Focusing on the location of the proposed weir over

4062half of a mile downstream from the southernmost part of the

4073area intended to be rehydrated, Petitioners and Intervenors

4081dispute the stated purpose of the project, focusing on the

4091District's earlier relocation of the proposed weir from

4099positions just north and then just south of I-75 to its

4110present position a half-mile farther to the south.

411848. The District did nothing to allay this concern of

4128Petitioners and Intervenors when its employees could not

4136provide a reasonably detailed explanation of the process by

4145which someone moved the proposed site to the south. From the

4156District's evidence, one would infer that the decision to

4165relocate the proposed weir to the south spontaneously emerged,

4174without human sponsor, in the course of bureaucratic

4182decisionmaking.

418349. The District asserted that the northerly sites were

4192impractical due to access problems. However, the District

4200made little, if any, real effort to see if the Department of

4212Transportation would allow access to these more northerly

4220sites--one of which the District might be able to access

4230without the consent of the Department of Transportation.

423850. The record does not reveal why the District

4247relocated the proposed weir to its present location,

4255considerably south of its initial two locations at I-75.

4264Again, though, the evidence does not support the contention of

4274Petitioners and Intervenors that the relocation decision was

4282part of a private plan among District employees to incorporate

4292the proposed weir as part of a more ambitious project to

4303rehydrate Southern Golden Gate Estates.

430851. Nor does the evidence establish, as Petitioners and

4317Intervenors contend, that the relocation decision was driven

4325by the concerns of three influential landholders to the north

4335of I-75--Collier Enterprises, Barron Collier Company, and Ford

4343Motor Company. These three landholders approved the proposed

4351weir in its present location over a half-mile to the south of

4363its original locations and may have expressed concern that the

4373original locations at I-75 would unreasonably raise the risk

4382of flooding their land and business and agricultural

4390activities to the north of I-75.

439652. If the District's real reason for relocating the

4405proposed weir was due to objections from these landowners to

4415the north of I-75, this reason would not itself help

4425Petitioners and Intervenors. If the District acceded to the

4434demands of these landowners to the north, it does not

4444necessarily follow that the District lacked confidence in its

4453flood calculations. A relocation decision under these

4460circumstances would have as likely reflected political, as

4468scientific, concerns.

447053. Additionally, if the District moved the proposed

4478weir at the insistence or suggestion of the landowners to the

4489north, any flooding concerns voiced by these landowners raise

4498different issues from the flooding concerns raised by

4506Petitioners and Intervenors. Owners of land immediately to

4514the north and west of the federal refuge are more directly

4525within the area of the intended effects than are Petitioners

4535and Intervenors.

453754. More substantially, Petitioners and Intervenors

4543claim that the proposed activity is so negligently designed or

4553will be so negligently operated as to result in heightened and

4564more frequent flooding of areas to the west and east of the

4576proposed weir.

457855. The District's record in operating weirs in Collier

4587County is not flawless. In recent years, the District

4596constructed and maintained a weir with unlawfully high gates

4605and did not correct the noncompliant water-control structure

4613for several months after first learning of the violation.

4622However, this appears to have been an isolated violation.

463156. The division of responsibility between the District

4639and Collier County for the maintenance of drainage canals is

4649based on whether the canal is a primary or secondary drainage

4660facility. The District has assumed responsibility for all of

4669the primary drainage facilities in Collier County.

4676Surprisingly, though, the record reveals no master map or

4685index of the primary drainage facilities and at least the

4695larger nonprimary drainage facilities.

469957. However, Petitioners and Intervenors failed to show

4707that any confusion concerning maintenance responsibilities

4713that may exist between the District and Collier County would

4723appreciably raise the probabilities that the District would

4731operate the proposed weir in such a way as to exacerbate

4742present flooding concerns. The District and Collier County

4750agree that the District has jurisdiction over the Merritt

4759Canal. Petitioners and Intervenors have also failed to show

4768that any confusion concerning secondary-drainage contributions

4774that may exist between the District and Collier County would

4784have a substantial impact on the successful operation of the

4794proposed weir.

479658. The most significant claim raised by Petitioners and

4805Intervenors asserts that the District failed to provide

4813reasonable assurance that the proposed weir would not

4821exacerbate flooding. Although the weir gates would be closed

4830only during the dry season, the proposed activity requires

4839analysis of the risk of heightened water elevations upstream

4848of the proposed weir. In theory, flooding could result from

4858the effects of the weir even when the gates are open, as well

4871as the possibility of an extreme storm event during the dry

4882season.

488359. Expert witnesses on both sides clashed over whether

4892the design of the proposed weir was sufficient not to

4902exacerbate existing levels, rates, and frequencies of flooding

4910of adjacent uplands. The crucial feature over which the

4919experts disagreed was the spoil banks running along the canal.

492960. When the Merritt Canal was constructed, the spoil

4938was dumped along the banks. In the ensuing years, vegetation

4948colonized and stabilized the spoil banks, which now function

4957as levees.

495961. The expert witness called by Petitioners and

4967Intervenors disregarded the spoil banks in his calculations.

4975His lack of confidence in the opposing expert witness's use of

4986top-of-bank elevations was partly justified for the reasons

4994stated below. Although a minor point, part of the argument of

5005Petitioners and Intervenors' expert witness proved too much by

5014asserting that levees cannot maintain water levels higher

5022inside the levee than the existing ground elevation outside

5031the levee.

503362. On the other hand, in showing that the proposed weir

5044would not exacerbate flooding, the District's expert witness

5052relied, not entirely justifiably, on the top-of-bank

5059elevations. The District took only spot elevations of the

5068spoil bank and then assumed that these elevations prevailed

5077along the entire 3600 feet of canal upstream of the weir. The

5089District did not inspect the upstream banks for unpermitted

5098culverts, of which at least one was discovered during the

5108lengthy hearing in this case.

511363. There is a possibility of material differences in

5122elevations along the spoil banks. These spoil banks were not

5132constructed to a specified elevation; they were an excavation

5141byproduct that was haphazardly deposited beside the excavated

5149canal. Additionally, the record suggests that this general

5157area has been the site of unpermitted works, such as the

5168installation of a culvert and creation of unpermitted canal

5177plugs.

517864. In the months over which the hearing took place,

5188Petitioners and Intervenors alertly found a culvert breaching

5196the spoil bank upstream of the proposed weir. At least one of

5208their representatives demonstrated superior familiarity with

5214the spoil bank over the familiarity demonstrated by the

5223District's representatives. It is a fair inference that, if

5232the spoil bank was substantially missing at any point upstream

5242of the proposed weir, Petitioners and Intervenors would have

5251brought such evidence to the hearing. The absence of such

5261evidence, coupled with the reasonable inferences that may be

5270drawn from the concededly more cursory investigation of the

5279site by the District, precludes a finding that the spoil bank

5290is substantially missing at any material point so as to

5300warrant the use of ground elevations, as used by the expert

5311witness called by Petitioners and Intervenors. At best, from

5320the perspective of Petitioners and Intervenors, the record

5328supports the finding that the spoil banks may not be as

5339continuously as high as the District posits, but they are not

5350nearly as low (i.e., nonexistent) at any point as Petitioners

5360and Intervenors contend.

536365. The two experts also disagreed over two subordinate

5372inputs used in running the flood calculations. The expert

5381called by Petitioners and Intervenors claimed that initial

5389tailwaters (i.e., water elevations downstream of the weir) in

5398excess of 8.53 feet were appropriate. Although the canal has

5408experienced historically higher tailwaters than 8.53 feet, the

5416expert did not explain adequately why such higher tailwaters

5425should be used in running the model, especially since flood

5435calculations are not used to predict flooding conditions in

5444all storms, such as a 1000-year storm. Absent a showing that

5455tailwater in excess of 8.53 feet would be present at the

5466relevant time preceding or during the design storm event, the

5476expert called by Petitioners and Intervenors failed to show

5485why the District's tailwater input was unreasonable.

549266. On the other hand, the District's expert claimed

5501that the model required an adjustment to the friction factor

5511or Manning's N coefficient. This adjustment, which decreased

5519the friction factor by an order of magnitude, approximated a

5529bottom that was many times smoother than the actual bottom of

5540the Merritt Canal. The District's expert did not explain

5549adequately why the lower friction factor should be used in

5559running the model, and he frankly did not demonstrate the same

5570familiarity with this friction factor as did the expert called

5580by Petitioners and Intervenors. The most likely inference is

5589that the District's expert erred in making this adjustment.

559867. There was another controversy between the parties

5606regarding a subordinate input for the flooding calculations.

5614Petitioners and Intervenors raised the possibility that

5621agricultural discharges from the Collier properties adjacent

5628to the federal refuge, which the District ignored in its

5638calculations, might further undermine any assurances as to

5646flooding. This could have been useful information if

5654developed in the record, but the record permits no basis to

5665quantify the value of this additional discharge or ascertain

5674its timing relative to wet and dry seasons and storm events,

5685if in fact this agricultural discharge takes place at all.

5695Also, offsetting any such discharge would be two factors: the

5705District ran its calculations assuming a runoff rate 25

5714percent greater than that appropriately used by the Florida

5723Department of Transportation for modeling the design storm

5731event, and the District ignored the plugs in the I-75 borrow

5742canals, which attenuate the runoff into the Merritt Canal.

575168. Although Petitioners and Intervenors incorrectly

5757inputted ground elevation in place of the top-of-bank

5765elevation--when the best elevation is somewhere in between

5773these two values--their expert's calculations are useful for

5781illustrating a scenario that, for this reason, exceeds the

5790worst-case scenario. Again, this is an illustration of a

5799scenario that predicts greater flooding than reasonably should

5807be predicted because, in actuality, the restraining elevation

5815is higher than ground elevation.

582069. Using the 8.53-feet initial value for tailwater,

5828Petitioners' Exhibit 27 illustrates the different water

5835elevations resulting from running the model with and without

5844the excessive reduction of the friction factor. Petitioners

5852Exhibit 27 illustrates the effect of the design storm on

5862upstream water elevations with the gates open. Petitioners

5870Exhibit 27 ignores the spoil banks and instead uses prevailing

5880ground elevations.

588270. At the site of the proposed weir, the canal bottom

5893is at about -1.5 feet NGVD. The proposed weir would add fixed

5905barriers up to an elevation of 5.0 feet NGVD; the adjustable

5916gates would, when closed, extend the barrier from 5.0 feet

5926NGVD to 9.5 feet NGVD. Approximate existing ground elevation

5935averages about 10 feet NGVD downstream of I-75, with one dip

5946to below 9 feet NGVD about 600 feet downstream of I-75. For

5958about 6000 feet upstream of I-75, where there is no spoil bank

5970whatsoever, the average ground elevation, outside of the

5978slough, is about 13 feet. The slough bottom in this area

5989gently slopes from about 9 feet NGVD to 10 feet NGVD.

600071. Ignoring the spoil bank, Petitioners Exhibit 27

6008predicts flooding in two major areas in the design storm

6018event, even with the gates open. One of these is about 300

6030feet long, starting about 400 feet downstream of I -75. The

6041other is at least 300 feet long, starting near the northern

6052extreme of the modeled area and running off the modeled area.

6063The District did not survey in detail the spoil bank along the

6075300 feet downstream of I-75. There is no spoil bank upstream

6086of I-75 because there is no dredged canal.

609472. The water elevation about 400 feet downstream of

6103I -75 would be almost one foot greater than the ground

6114elevation. The water elevation about 6000 feet upstream of

6123I -75 will be as much as half of a foot greater than the ground

6138elevation. At the more downstream point, the actual water

6147elevation would exceed the District's projection by nearly

6155three-quarter of one foot. At the more upstream point, the

6165actual water elevation would exceed the District's projection

6173by over 1.5 feet.

617773. Although the record could have been better developed

6186on this important point, there is reasonable assurance that

6195the existing spoil-bank elevations are sufficient to contain

6203these flood elevations predicted by the expert called by

6212Petitioners and Intervenors.

621574. Petitioners and Intervenors claimed that the

6222District could achieve its stated purpose of extending the

6231hydroperiod in the Florida Panther National Wildlife Refuge

6239without increasing the risk or extent of flooding of adjacent

6249uplands. Petitioners and Intervenors suggested that the

6256District repair an existing plug in the Merritt Canal just

6266south of I-75. (This "plug" is actually the original ground

6276surface, which evidently was undisturbed during the

6283construction of I-75. Given the excavation of canals on both

6293sides of what is now a narrow strip of earth, the land

6305resembles a plug, and this recommended order refers to it as a

6317plug, although this term is descriptive only of the feature's

6327present appearance, not its method of creation.)

633475. There are actually six plugs--again, in the broad

6343sense of the word--in the vicinity of the junction of the

6354Merritt Canal and I-75. Two plugs interrupt the flow into the

6365Merritt Canal of the borrow canals to the north of I-75. Two

6377plugs likewise interrupt the flow into the Merritt Canal of

6387the borrow canals to the south of I-75. The last two plugs

6399are in the Merritt Canal, a few feet north and south of I-75.

641276. Repairing the plug immediately south of I-75 would

6421raise the water elevation by about 1.3 feet under the I-75

6432bridge. By about 2000 feet upstream of I-75, there is no

6443significant difference between the water elevation using the

6451model of Petitioners and Intervenors' expert for the proposed

6460weir 3600 feet downstream of I-75 and the water elevation for

6471the proposed plug repair just south of I-75. Repairing the

6481plugs would have reduced the water elevation downstream of I-

649175 by less than one half of a foot.

650077. Petitioners, Intervenors, and their expert have

6507proposed a promising alternative to the proposed weir. The

6516alternative appears to serve the stated purpose of the

6525proposed activity at least as well as the proposed weir would,

6536if not somewhat better due to its closer proximity to the

6547targeted federal refuge, and the alternative project would

6555cost much less to construct, maintain, and operate. The

6564restorative nature of the work would probably relieve the

6573District of the necessity of obtaining a permit. Perhaps the

6583prospect of such work might motivate other state and federal

6593agencies to grant the District access to the area at I-75 to

6605build the weir at one of its first two locations.

661578. However, the issue is whether the District has

6624provided reasonable assurance for the activity that it has

6633proposed. As to flooding, the District has provided

6641reasonable assurance that the proposed activity will not

6649exacerbate flooding during the design storm events or even

6658more severe storm events.

666279. Even assuming an absence of reasonable assurance as

6671to flooding, the first criterion requires consideration of

6679whether the proposed activity would adversely affect the

6687public health, safety, and welfare or the property of others.

6697Extending the hydroperiod of the federal refuge protects the

6706property of others by reducing the period of time that the

6717turf is dried out. This provides a wide range of

6727environmental protection, including protection against the

6733risk of fire caused by excessive drainage, for the federal

6743refuge and other property in the area.

675080. Retarding the artificially high rate of drainage

6758will improve water quality in at least two respects. The

6768proposed weir will retard and reduce the nutrients conveyed

6777down the canal and into the estuary into which it eventually

6788empties. The proposed weir will also tend to restore somewhat

6798the rate and timing of historic freshwater inputs on which the

6809viability of the estuary and its inhabitants depends.

6817Concerns about public health, safety, and welfare, as well as

6827the property of others, cannot be severed from these

6836broadscale environmental benefits to be derived from the

6844proposed activity. Public health concerns are tied to these

6853considerations.

685481. Thus, even if the District had failed to provide

6864reasonable assurance as to flooding alone, the District has

6873provided reasonable assurance that, on balance, the proposed

6881weir will not adversely affect the matters set forth in the

6892first criterion.

6894B. Conservation of Fish and Wildlife, Including

6901Endangered or Threatened Species, or Their Habitats

690882. The proposed weir will serve the conservation of a

6918wide range of flora and fauna, as well as their wetlands

6929habitat, within the targeted federal refuge. These species

6937include listed species. The evidence does not support a

6946finding that extending the hydroperiod of the federal refuge

6955would in any way disturb the Florida panther.

6963C. Navigation, Flow of Water, or Harmful Erosion

6971or Shoaling

697383. The proposed weir will have not adversely affect

6982navigation or the flow of water within the canal, and it will

6994not cause erosion or shoaling.

6999D. Fishing or Recreational Values or Marine

7006Productivity in the Vicinity of the Activity

701384. The proposed weir will not adversely affect fishing

7022or recreational values or marine productivity in the vicinity

7031of the proposed weir. To the contrary, the proposed weir will

7042enhance these values in the immediate vicinity of the proposed

7052weir and downstream at the estuary at the mouth of the Merritt

7064Canal.

7065E. Temporary or Permanent Nature

707085. The proposed weir will be of a permanent nature.

7080F. Significant Historic and Archaeological Resources

708686. The record provides no basis for a finding that the

7097proposed weir jeopardizes significant historic and

7103archaeological resources.

7105G. Current Condition and Relative Value of Functions

7113of Areas Affected by the Proposed Activity

712087. The federal refuge is functioning well

7127environmentally, despite the adverse impact of dramatic

7134disruptions of the natural drainage regime. The value of

7143these functions is high. Likewise, the receiving estuarine

7151waters are functioning well, despite the adverse impact of

7160dramatic disruptions of the natural drainage regime.

7167Extending the hydroperiod of the federal refuge will partially

7176offset these historic disruptions. Thus, the proposed weir

7184will assist in the functioning of natural systems that are now

7195functioning well, but could use some help.

7202H. Public Interest

720588. The proposed weir is not in an Outstanding Florida

7215Water. Thus, the question is whether the proposed activity is

7225not contrary to the public interest. The District has

7234provided reasonable assurances as to the preceding seven

7242criteria sufficient to demonstrate that, on balance, the

7250proposed activity is not contrary to the public interest.

7259I. Cumulative Impacts

726289. There is no evidence that the proposed weir will

7272cause any adverse cumulative impacts upon wetlands or surface

7281waters.

7282J. Other Criteria

728590. The District has proved that the proposed weir would

7295not violate any water quality standards. To the contrary, any

7305effect from the proposed activity would be to improve water

7315quality, especially downstream at the estuary. The

7322restoration of conditions more typical of historic drainage

7330would allow more nutrients to be captured upstream and would

7340tend to restore the historic timing and volume of freshwater

7350inputs into the estuary.

735491. For the reasons set forth above, the District has

7364also provided reasonable assurance that the proposed activity

7372meets the 11 criteria contained in Rule 40E-4.301, which

7381largely duplicate the seven criteria discussed above, and the

7390relevant provisions of the Basis of Review. It is true that

7401the monitoring provisions are largely illusory because they

7409provide no quantifiable parameter beyond which the District

7417must take specified action. In other words, at best, the

7427monitoring provisions assure that the District will collect

7435post-operational flooding data, but they do not promise that

7444the District will take any action if certain levels of

7454flooding take place. However, the monitoring provisions are

7462of little importance given the factual findings concerning

7470flooding, as discussed above, and the legal requirements of

7479the Basis of Review, as discussed below.

7486CONCLUSIONS OF LAW

748992. The Division of Administrative Hearings has

7496jurisdiction over the subject matter. Section 120.57(1),

7503Florida Statutes. (All references to Sections are to Florida

7512Statutes, except for references to Sections of the District's

7521Basis of Review (BOR). All references to Rules are to the

7532Florida Administrative Code.)

753593. Section 373.413(1) provides that the District or DEP

7544may require permits and impose "reasonable conditions" that

7552are "necessary to assure" that the construction or alteration

7561of any stormwater management system or dam, among other

7570activities, "will comply with the provisions of this part and

7580applicable rules . . . and will not be harmful to the water

7593resources of the district."

759794. Section 373.414(1) adds that the District or DEP

7606shall require an applicant to provide "reasonable assurance"

7614that the proposed activity will not violate state water

7623quality standards and is not "contrary to the public

7632interest." If the proposed activity "significantly degrades

7639or is within an Outstanding Florida Water," the applicant must

7649provide "reasonable assurance" that the proposed activity will

7657be "clearly in the public interest."

766395. Pursuant to Section 373.414(1)(a), the public-

7670interest determination requires the issuing agency to

"7677consider and balance" seven criteria:

76821. Whether the activity will adversely

7688affect the public health, safety, or

7694welfare or the property of others;

77002. Whether the activity will adversely

7706affect the conservation of fish and

7712wildlife, including endangered or

7716threatened species, or their habitats;

77213. Whether the activity will adversely

7727affect navigation or the flow of water or

7735cause harmful erosion or shoaling;

77404. Whether the activity will adversely

7746affect the fishing or recreational values

7752or marine productivity in the vicinity of

7759the activity;

77615. Whether the activity will be of

7768temporary or permanent nature;

77726. Whether the activity will adversely

7778affect or will enhance significant

7783historical and archaeological resources

7787under the provisions of s. 267.061; and

77947. The current condition and relative

7800value of functions being performed by

7806areas affected by the proposed activity.

781296. Section 373.414(1)(b) adds that, if an applicant is

7821unable to meet these seven criteria, then the District or DEP

7832shall consider mitigation measures. Section 373.414(8)

7838requires that the District or DEP "consider the cumulative

7847impacts upon surface water and wetlands" when deciding whether

7856to issue a permit. Rule 40E-4.302 restates the seven criteria

7866stated in Section 373.414(1)(a) and otherwise tracks the

7874statutory requirements.

787697. Rule 40E-4.301 identifies eleven criteria that

7883largely, if not entirely, overlap the seven criteria

7891identified in Section 373.414(1)(a) and Rule 40E-4.302. The

7899application and purpose of Rule 40E-4.301 are unclear. For

7908instance, in applying Rule 40E-4.301, it is unclear whether

7917the factfinder should balance the eleven criteria; unlike Rule

792640E-4.302 and Section 373.414(1)(a), Rule 40E-4.301 does not

7934expressly so provide. More importantly, if the two sets of

7944criteria are not wholly duplicative, the District's rules fail

7953to explain what happens when a proposed activity meets the

7963seven criteria identified in the statute and Rule 40E-4.302,

7972but fails to meet the eleven criteria identified in

7981Rule 40E -4.301.

798498. Rule 40E-4.302(3) incorporates the District's Basis

7991of Review in the determination whether an applicant has

8000provided the reasonable assurances required by Rules 40E-4.301

8008and 40E-4.302.

801099. In this case, the District is the applicant, not the

8021permitting agency; DEP is the permitting agency. In

8029Rules 62 -330.100(1) and 62-330.200(4), DEP adopts various

8037rules of the water management districts for the issuance of

8047ERPs, including the relevant rules already discussed. In

8055Rule 62 -330.200(4)(b), DEP adopted the District's Basis of

8064Review (BOR), except for Sections 1.0 through 3.1.2.9, 4.4,

8073and 4.5, and revised Section 4.2.2.

8079100. BOR Section 4.0 states that the District's

8087permitting goal is "no net loss in wetland and other surface

8098water functions." (Although a DEP rule converts all

8106references to the "District" to "DEP," this recommended order

8115retains the actual language of the BOR.) BOR Section 4.0

8125provides that the District requires permits so it can

"8134conserve the beneficial functions of . . . wetlands or other

8145surface waters."

8147101. BOR Subsection 4.2.1 states, in part:

8154The degree of impact to wetland and other

8162surface water functions caused by a

8168proposed system, whether the impact to

8174these functions can be mitigated and the

8181practicability of design modifications for

8186the site, as well as alignment

8192alternatives for a proposed linear system,

8198which could eliminate or reduce impacts to

8205these functions, are all factors in

8211determining whether an application will be

8217approved by the District. Design

8222modifications to reduce or eliminate

8227adverse impacts must be explored, as

8233described in subsection 4.2.1.1. Any

8238adverse impacts remaining after

8242practicable design modifications have been

8247implemented may be offset by mitigation as

8254described in subsections 4.3-4.3.8. . . .

8261To receive District approval, a system

8267cannot cause a net adverse impact on

8274wetland functions and other surface water

8280functions which is not offset by

8286mitigation.

8287102. The preceding section outlines a two-step process

8295of minimization and mitigation. However, according to BOR

8303Subsection 4.2.1.1, the District will not require project

8311modifications to achieve minimization unless the proposed

8318activity fails to meet the requirements of Subsections 4.2.2

8327through 4.2.3.7.

8329103. Subsection 4.2.2 requires that an applicant provide

8337reasonable assurance that a proposed activity will not impact

8346the values of wetlands and other surface water functions so as

8357to impact adversely the abundance, diversity, or habitat of

8366fish, wildlife, and listed species.

8371104. Subsection 4.2.2.4 requires that an applicant

8378provide reasonable assurance that the regulated activity will

8386not change the hydroperiod or a wetland or other surface

8396water, so as to affect adversely wetland functions or other

8406surface water functions.

8409105. Subsection 4.2.2.4(b) addresses proposed activities

8415that may increase the "depth, duration, or frequency of

8424inundation through changing the rate or method of discharge or

8434water to wetlands or other surface waters or by impounding

8444water in wetlands or other surface waters." Applicants for

8453permits for such activities must provide reasonable assurance

8461that the activities will not "adversely affect the functioning

8470of the specific wetland or other surface water subject to the

8481increased discharge or water level."

8486106. Subsection 4.2.2.4(c) requires that an applicant

8493proposing an activity that "could have the effect of altering

8503water levels in wetlands or surface waters" " shall be

8512required . . . to monitor the wetland or other surface waters

8524to demonstrate that such alterations has not resulted in

8533adverse impacts . . . or calibrate the system to prevent

8544adverse impacts." This subsection states: "Monitoring

8550parameters, methods, schedules, and reporting requirements

8556shall be specified in permit conditions."

8562107. Subsection 4.2.3 addresses the seven statutory

8569criteria detailing the public-interest test.

8574108. Subsection 4.2.3.1 states that, in balancing the

8582seven criteria, the District must determine whether the

8590proposed activity will cause, among other things, flooding and

8599environmental impacts to the property of others, although not

8608with respect to property values or taxes.

8615Subsection 4.2.3.1(c) adds, as to flooding: "There is at least

8625a neutral factor in the public interest balance with respect

8635to the potential for causing or alleviating flooding problems

8644if the applicant meets the water quantity criteria in section

8654six of this Basis of Review."

8660109. BOR Section 6 addresses water quantity criteria.

8668Subsection 6.2 provides that the offsite discharge rate may

8677not cause "adverse impacts to existing offsite properties" and

8686is limited to "historic discharge rates," previously permitted

8694rates, or rates specified in District criteria stated in an

8704appendix for various canals. Subsection 6.3 identifies the

8712design storm as the three-day, 25-year storm.

8719110. Historically, the land in question was inundated

8727during the wet season, so Section 6 is satisfied. Thus, by

8738operation of the BOR, the presumption is that the proposed

8748activity is no worse than neutral as to flooding. In fact,

8759though, the District has provided reasonable assurance as to

8768flooding. Because the proposed activity satisfies the

8775requirements of BOR Subsections 4.2.2 through 4.2.3.7, the

8783District is not required to consider alternative alignments to

8792this proposed linear system.

8796111. The proposed activity satisfies the other factors

8804mentioned by the BOR. As found above, the monitoring

8813provisions of the proposed permit, although largely illusory,

8821nonetheless satisfy the BOR requirements concerning

8827monitoring, as these requirements themselves do not require

8835the imposition of enforceable performance standards in the

8843monitoring provisions.

8845112. Based on the findings set forth above, the District

8855has provided reasonable assurance that, on balance, the

8863proposed activity meets the seven criteria identified in the

8872statute and Rule 40E-4.302.

8876113. Based on the findings set forth above, the District

8886has provided reasonable assurance that the proposed activity

8894meets the eleven criteria identified in Rule 40E-4.301.

8902RECOMMENDATION

8903It is

8905RECOMMENDED that the Department of Environmental

8911Protection enter a final order granting the permit for the

8921construction of the proposed weir about 3600 feet south of

8931I -75 in the Merritt Canal.

8937DONE AND ENTERED this 25th day of June, 1998, in

8947Tallahassee, Leon County, Florida.

8951___________________________________

8952ROBERT E. MEALE

8955Administrative Law Judge

8958Division of Administrative Hearings

8962The DeSoto Building

89651230 Apalachee Parkway

8968Tallahassee, Florida 32399-3060

8971(850) 488-9675 SUNCOM 278-9675

8975Fax Filing (850) 921-6847

8979Filed with the Clerk of the

8985Division of Administrative Hearings

8989this 25th day of June, 1998.

8995COPIES FURNISHED:

8997James W. McDonald, Jr., Esquire

9002McDonald & Associates

9005Community Plaza, Suite 306

900915600 Southwest 288th Street

9013Homestead, Florida 33030

9016A. Glenn Simpson

9019Qualified Representative

90215961 22nd Avenue Southwest

9025Naples, Florida 34116

9028Marcy I. LaHart

9031Associate Attorney

9033South Florida Water Management District

90383301 Gun Club Road

9042West Palm Beach, Florida 33416-4680

9047Francine M. Ffolkes

9050Assistant General Counsel

9053Department of Environmental Protection

9057Mail Station 35

90603900 Commonwealth Boulevard

9063Tallahassee, Florida 32399-3000

9066Walter R. Shaw, Sr., pro se

90721400 Northwest 62nd Avenue

9076Sunrise, Florida 33313-6138

9079Cliffort L. Fort

90828410 Northwest 16th Street

9086Pembroke Pines, Florida 33024

9090Kathy Carter, Agency Clerk

9094Department of Environmental Protection

9098Mail Station 35

91013900 Commonwealth Boulevard

9104Tallahassee, Florida 32399-3000

9107F. Perry Odom, General Counsel

9112Department of Environmental Protection

9116Mail Station 35

91193900 Commonwealth Boulevard

9122Tallahassee, Florida 32399-3000

9125NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

9131All parties have the right to submit written exceptions within

914115 days from the date of this recommended order. Any

9151exceptions to this recommended order must be filed with the

9161agency that will issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 09/28/1998
Proceedings: Letter to C. Tears from J. McDonald Re: Flooding filed.
Date: 09/23/1998
Proceedings: Letter to C. Tears from J. McDonald Re: Property Flooding filed.
Date: 08/06/1998
Proceedings: Final Order filed.
PDF:
Date: 08/04/1998
Proceedings: Agency Final Order
PDF:
Date: 08/04/1998
Proceedings: Recommended Order
PDF:
Date: 06/25/1998
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 08/12, 13. 28 & 29/97 & 10/01,02,08, & 09/97 & 11/1 3,14,17,18, & 19/97 & 01/06-08/98.
Date: 03/20/1998
Proceedings: Notice of Intervenor Action for Motion to Dismiss for Mootness and/or the Division of Administrative Hearings Lacked Subject Matter Jurisdiction or in the Alternative Recommended Order (filed via facsimile).
Date: 03/16/1998
Proceedings: Intervenor Clifford Fort`s Recommended Order Including Supplemental Material to Petitioners` Proposed Recommended Order and Notice of Filing filed.
Date: 03/16/1998
Proceedings: Petitioner`s Notice of Filing Proposed Recommended Order; (Petitioner) Proposed Recommended Order filed.
Date: 03/16/1998
Proceedings: South Florida Water Management District`s Proposed Recommended Order filed.
Date: 03/02/1998
Proceedings: (Intervenor) Emergency Motion for Extension of Time to Produce Recommended Order and/or the Filing of Other Motions filed.
Date: 03/02/1998
Proceedings: (SFWMD) Exhibits filed.
Date: 02/27/1998
Proceedings: Corrected Petitioner`s Motion for Extension of Time to Submit Proposed Recommended Order (filed via facsimile).
Date: 02/27/1998
Proceedings: Petitioner`s Motion for Extension of Time to Submit Proposed Recommended Order filed.
Date: 02/19/1998
Proceedings: (DEP) Exhibits filed.
Date: 02/09/1998
Proceedings: (From J. McDonald) Notice of Filing Trial Exhibit Nos. 30, 31 and 32; Exhibits filed.
Date: 02/04/1998
Proceedings: (From W. Shaw, Jr.) Notice of Filing Trial Exhibits; Exhibits filed.
Date: 02/02/1998
Proceedings: (3 Volumes) Transcript filed.
Date: 01/30/1998
Proceedings: (From J. McDonald) Notice of Providing Exhibits to Respondent filed.
Date: 01/30/1998
Proceedings: (From W. Shaw) Emergency Motion for Extension of Time for Production of Exhibits filed.
Date: 01/28/1998
Proceedings: Petitioner`s Motion for Extension of Time for Production of Petitioners` Trial Exhibit Nos. 30, 31 and 32; Cover Letter (filed via facsimile).
Date: 01/28/1998
Proceedings: DEP`s hearing Exhibits filed.
Date: 01/27/1998
Proceedings: (From J. McDonald) Notice of Filing Trial Exhibits filed.
Date: 01/27/1998
Proceedings: Intervenor, Cliff Fort`s Trial Exhibits List; Intervenor`s Exhibits ; Cover Letter to Judge Meale from J. McDonald filed.
Date: 01/27/1998
Proceedings: (W. Shaw) Exhibit 12 ; Cover Letter to Judge Meale from J. McDonald filed.
Date: 01/27/1998
Proceedings: SFWMD Exhibits 1-2, 4,-5, 6a-6d, 8, 16 - 22 filed.
Date: 01/27/1998
Proceedings: Emergency Motion for Extension of time for production of exhibits (Intervenor) (filed via facsimile).
Date: 01/26/1998
Proceedings: (From J. McDonald) Notice of Filing Trial Exhibits; Exhibits filed.
Date: 01/14/1998
Proceedings: (I Volume) Transcript of Proceedings filed.
Date: 01/06/1998
Proceedings: CASE STATUS: Hearing Held.
Date: 01/06/1998
Proceedings: (From F. Ffolkes) Notice of Substitution of Counsel for Department of Environmental Protection filed.
Date: 12/22/1997
Proceedings: Transcripts (volumes 1 thru 4, tagged) filed.
Date: 12/15/1997
Proceedings: (3 Volumes) Transcript filed.
Date: 12/12/1997
Proceedings: Letter to J. McDonald from M. LaHart Re: Continuance of Deposition filed.
Date: 12/05/1997
Proceedings: Second Supplemental Notice of Hearing sent out. (hearing set for 1/6/98; 9:00am; Naples)
Date: 11/17/1997
Proceedings: Hearing Partially Held, continued to date not certain.
Date: 11/13/1997
Proceedings: Hearing Partially Held, continued to date not certain.
Date: 11/03/1997
Proceedings: (4 Volumes) Transcript filed.
Date: 10/30/1997
Proceedings: CC: Letter to James W. McDonald, Jr. from Marcy I. LaHart (RE: response to letter concerning the scheduling of witnesses for the remainder of the hearing) filed.
Date: 10/29/1997
Proceedings: (From W. Matturro) Notice of Appearance of Counsel for Department of Environmental Protection filed.
Date: 10/27/1997
Proceedings: Respondent South Florida Water Management District`s Motion to Quash (filed via facsimile).
Date: 10/27/1997
Proceedings: Copy of Letter to A. Nath from James McDonald (filed via facsimile).
Date: 10/27/1997
Proceedings: Copy of Letter to Marcy LaHart from James McDonald (re:witnesses) filed.
Date: 10/16/1997
Proceedings: Supplemental Notice of Hearing sent out. (hearing set for 11/13/97; 9:00am; Naples)
Date: 10/08/1997
Proceedings: CASE STATUS: Hearing Held.
Date: 10/01/1997
Proceedings: CASE STATUS: Hearing Partially Held, continued to Oct. 8-9, 1997.
Date: 09/29/1997
Proceedings: (Petitioner) Motion for Case Management Conference filed.
Date: 09/29/1997
Proceedings: (Petitioner) Response to Petitioner`s Motion for Case Management Conference; (Petitioner) Witness and Exhibit List (filed via facsimile).
Date: 09/26/1997
Proceedings: (From J. McDonald) Notice of Unavailability filed.
Date: 09/17/1997
Proceedings: Letter to J. McDonald from M. LaHart Re: Subpoenas filed.
Date: 08/29/1997
Proceedings: (From J. McDonald) Re-Notice of Taking Deposition Duces Tecum (Location change only); Second Amendment to Witness and Exhibit List filed.
Date: 08/28/1997
Proceedings: CASE STATUS: Hearing Partially Held, continued to Oct. 1-2, 1997.
Date: 08/28/1997
Proceedings: (From W. Shaw) Amended Notice of Taking Deposition; Amended Witness and Exhibit List filed.
Date: 08/26/1997
Proceedings: (Clifford Fort) Subpoena for Trial (filed via facsimile).
Date: 08/26/1997
Proceedings: Respondents Sputh Florida Water Management District`s and Florida Department of Environmental Protection`s Joint Motion to Quash (filed via facsimile).
Date: 08/26/1997
Proceedings: Respondent South Florida Water Management District`s Motion to Quash (filed via facsimile).
Date: 08/26/1997
Proceedings: (From W. Shaw) Witness and Exhibit List filed.
Date: 08/25/1997
Proceedings: First Amendment to Witness and Exhibit List; Request for Production of Documents; Petitioner`s Notice of Service of Interrogatories filed.
Date: 08/25/1997
Proceedings: (Petitioners) Witness and Exhibit List; (16) Subpoena for Trial ; (2) Notice of Taking Depositions Duces Tecum; (2) Corrected Subpoena for Deposition Duces Tecum; (4) Subpoena for Deposition Duces Tecum filed.
Date: 08/15/1997
Proceedings: Letter to Judge Meale from J. McDonald Re: Taking deposition filed.
Date: 08/14/1997
Proceedings: Supplemental Notice of Hearing sent out. (hearing set for Aug. 28-29, Oct. 1-2 & 8-9, 1997; 9:00am; Naples)
Date: 08/13/1997
Proceedings: Intervenor`s Notice of Filing Answers to First Set of Interrogatories Propounded by South Florida Water Management District filed.
Date: 08/13/1997
Proceedings: (From J. McDonald) Motion for Continuance; (From W. Shaw) Motion for Continuance filed.
Date: 08/12/1997
Proceedings: South Florida Water Management District`s Motion to Take Official Recognition filed.
Date: 08/12/1997
Proceedings: Hearing Partially Held, continued to date not certain.
Date: 08/11/1997
Proceedings: Letter to Judge Meale from J. McDonald Re: Motion for Continuance; Letter to Judge Meale from J. McDonald Re: Deposition filed.
Date: 08/08/1997
Proceedings: (SFWMD) Motion in Opposition to Continuance (filed via facsimile).
Date: 08/05/1997
Proceedings: Order Denying Amended Motion to Dismiss sent out.
Date: 08/01/1997
Proceedings: South Florida Water Management District`s Amended Motion to Dismiss (filed via facsimile).
Date: 07/24/1997
Proceedings: Order Denying Request for Change in Venue and Continuance sent out.
Date: 07/21/1997
Proceedings: Petitioners` Notice of Filing Amended Answers to Interrogatories Propounded by South Florida Water Management District; Answers filed.
Date: 07/21/1997
Proceedings: (W. Shaw) Statement of Facts filed.
Date: 07/17/1997
Proceedings: Order Compelling Discovery sent out.
Date: 07/17/1997
Proceedings: South Florida Water Management District`s Motion to Dismiss; Petitioners` Declaratory Statements Pursuant to Order Granting Motion to Intervene and Denying District`s Motions in Opposition Executed June 30, 1997 (filed via facsimile).
Date: 07/15/1997
Proceedings: Petitioners` Notice of Filing Answers to Interrogatories Propounded by South Florida Water Management District filed.
Date: 07/11/1997
Proceedings: (SFWMD) Notice of Service of Interrogatories filed.
Date: 07/10/1997
Proceedings: Respondent South Florida Water Management District`s Motion to Compel Discovery (filed via facsimile).
Date: 06/30/1997
Proceedings: Order Granting Motion to Intervene and Denying District`s Motions in Opposition sent out. (W. Shaw Granted Intervenor Status)
Date: 05/19/1997
Proceedings: (SFWMD) Notice of Service of Interrogatories filed.
Date: 05/16/1997
Proceedings: Notice of Hearing sent out. (hearing set for Aug. 12-13, 1997; 9:00am; Naples)
Date: 05/13/1997
Proceedings: South Florida Water Management District`s Motion in Opposition to Motion for Intervention (filed via facsimile).
Date: 04/22/1997
Proceedings: (Walter Shaw) Motion to Intervene (filed via facsimile).
Date: 04/18/1997
Proceedings: Joint Response to Initial Order filed.
Date: 04/15/1997
Proceedings: South Florida Water Management Distraict`s Motion In Opposition to Petition for Administrative Hearing (filed via facsimile).
Date: 04/14/1997
Proceedings: (Marcy Lahart) Notice of Appearance (filed via facsimile).
Date: 04/14/1997
Proceedings: Initial Order issued.
Date: 04/04/1997
Proceedings: Petition For Administrative Hearing; Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Agency Action Letter filed.

Case Information

Judge:
ROBERT E. MEALE
Date Filed:
04/04/1997
Date Assignment:
04/14/1997
Last Docket Entry:
09/28/1998
Location:
Naples, Florida
District:
Middle
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (4):

Related Florida Rule(s) (6):