99-000689
J. Howard Lovett vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Friday, July 30, 1999.
Recommended Order on Friday, July 30, 1999.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8J. HOWARD LOVETT, )
12)
13Petitioner, )
15)
16vs. ) Case No. 99-0689
21)
22DEPARTMENT OF ENVIRONMENTAL )
26PROTECTION, )
28)
29Respondent. )
31)
32RECOMMENDED ORDER
34Notice was provided and on June 7, 1999, a formal hearing
45was held in this case. The hearing location was the Washington
56County Courthouse, 1293 Jackson Avenue, Chipley, Florida.
63Authority for conducting the hearing is set forth in Sections
73120.569 and 120.57(1), Florida Statutes. The hearing was
81conducted by Charles C. Adams, Administrative Law Judge.
89APPEARANCES
90For Petitioner: J. Howard Lovett, pro se
973131 Lovett Road
100Post Office Box 225
104Chipley, Florida 32428
107For Respondent: Ricardo Muratti
111Assistant General Counsel
114Department of Environmental
117Protection
118Douglas Building
1203900 Commonwealth Boulevard
123Mail Station 35
126Tallahassee, Florida 32399-3000
129STATEMENT OF THE ISSUES
133Is Petitioner entitled to an after-the-fact coastal
140construction control line ( CCCL) permit for existing construction
149seaward of the CCCL in Gulf County, Florida? If not, should the
161existing construction be removed? See Section 161.053, Florida
169Statutes; and Chapter 62B-33, Florida Administrative Code.
176PRELIMINARY STATEMENT
178On December 21, 1998, a proposed final order was entered by
189Respondent denying Petitioner's request for an after-the-fact
196CCCL permit and requiring the removal of that construction. On
206January 19, 1999, Respondent received Petitioner's challenge to
214the proposed agency action. On February 16, 1999, the Division
224of Administrative Hearings received a request from Respondent to
233assign an Administrative Law Judge to conduct a hearing to
243resolve the dispute between the parties. The case was initially
253assigned to P. Michael Ruff, Administrative Law Judge. The
262hearing was conducted by the undersigned based upon the
271unavailability of Judge Ruff.
275At hearing, Petitioner testified in his own behalf.
283Petitioner's Exhibits 1 through 7, 9, and 11-16, were admitted.
293Petitioner's Exhibit 10, was denied admission. Robert M.
301Brantly, Jr., P.E., testified for Respondent. Respondent's
308Exhibits 1 through 10, and 12 were admitted.
316A hearing transcript was filed on June 23, 1999. Post-
326hearing, Petitioner submitted correspondence as argument with an
334attachment. Respondent submitted a proposed recommended order.
341Subsequently, Respondent moved to strike portions of Petitioner's
349correspondence and the attachment from consideration.
355Specifically, Respondent has moved to strike portions of
363Petitioner's written argument with attachment as evidence not
371properly introduced at hearing. Petitioner's correspondence in
378reference to the attachment and the attachment itself have not
388been considered in preparing the recommended order. Nor has
397paragraph two in the correspondence been considered in preparing
406the recommended order. Those items described are stricken from
415consideration. Otherwise, the correspondence from Petitioner and
422the proposed recommended order by Respondent have been considered
431in preparing this recommended order.
436FINDINGS OF FACT
4391. Respondent exercises permitting authority for
445construction seaward of the CCCL under terms set forth in
455Chapter 161, Florida Statutes, and Chapter 62B-33, Florida
463Administrative Code. The CCCL is a regulatory line established
472in each coastal Florida county which demarks the landward extent
482of storm erosion for a major 100-year storm.
4902. The CCCL has been established for Gulf County, Florida.
5003. Petitioner owns property in Gulf County, Florida, at
5092560 Indian Pass Road, Port St. Joe, Florida. The property
519includes a beach house and dock. The dock is seaward of the
531CCCL. The dock is subject to Respondent's permit requirements
540under Chapter 161, Florida Statutes, and Chapter 62B-33, Florida
549Administrative Code.
5514. Petitioner's property at that address is located on the
561eastern end of Indian Peninsula, adjacent to Indian Pass across
571from St. Vincent Island.
5755. Petitioner's Gulf County address is not his permanent
584residence. Petitioner's permanent residence is in Washington
591County, Florida.
5936. Petitioner seeks an after-the-fact permit for
600construction of a dock seaward of the CCCL.
6087. Petitioner's dock contains six pilings. Three pilings
616are perpendicular to the shoreline. Three pilings are parallel
625to the shoreline. A narrow catwalk traverses the pilings. This
635forms an "L" shaped dock.
6408. The two spans in the dock are approximately 25 feet in
652length each. The pilings that support the dock are approximately
66216 inches in diameter. The width of the catwalk is approximately
673one and one-half feet. The catwalk is about one and one-half
684feet above mean high water.
6899. The dock design allows for the planks in the catwalk to
701be removed in several minutes.
70610. The CCCL bisects Petitioner's property in a manner that
716places the dock more than 200 feet seaward of the CCCL.
72711. The area in the vicinity of the dock is subject to
739storm waves and storm tides from the open ocean, the Gulf of
751Mexico. The area in question is not sheltered from the
761influences of the storm waves and storm tides.
76912. The property here is also proximate to an inlet at
780Indian Pass. As such, the processes involved with tides,
789currents, and wave effects off of the shoals around the inlet
800have influence on the property. The processes are more dynamic
810than would be found on an open coast shoreline not adjacent to an
823inlet.
82413. The dock is in the surf zone of the beach-dune system.
836That is the area where breaking waves occur. It is the most
848dynamic area in the coastal profile.
85414. At one time there were seven pilings that had been
865installed by the Petitioner at the location. One piling has been
876dislodged and removed by events associated with waves and tides,
886possibly during a storm. If pilings were dislodged during a
896storm, a potential risk of damage to uplands through the creation
907of a wind or waterborne missile existed.
91415. Storms which took place around the time that the piling
925was removed were Hurricanes Georges and Earl. Georges came
934ashore in Alabama near Perdido Key along the Alabama-Florida
943state line. It was a Category II storm when it made landfall,
955considered a severe storm. Earl came ashore near Mexico Beach
965close by the location of Petitioner's property. While Earl had
975been a strong storm, it decreased in strength, and at the time it
988made landfall was a minimal hurricane, a Category I. Earl and
999Georges are considered routine hurricanes in comparison to a
1008hurricane such as Opal, which came ashore in Pensacola, Florida,
1018100 miles away from Petitioner's property. Opal was a Category
1028IV storm, stronger in its influence than Earl and Georges.
1038Hurricanes of greater force than Earl and Georges can be more
1049destructive to Petitioner's remaining dock than has been the case
1059with the removal of the seventh piling. In the event of a
1071Category V hurricane it is very likely that the present dock
1082pilings would be dislodged.
108616. To protect the catwalk against destruction from storm
1095surge, it would need to be much higher in elevation from the mean
1108sea level than is contemplated by its design. In the area of
1120Petitioner's property, the mean high water line is approximately
1129one and one-half feet above mean sea level. The decking in the
1141dock would need to be constructed a minimum of 10 feet above mean
1154sea level to avoid a storm surge from a twenty-year storm. The
1166requirement for a 10-foot elevation is in relation to ocean or
1177fishing piers. The dock in question is an ocean or fishing pier.
118917. Storm surge associated with hurricane Georges, in the
1198vicinity of Petitioner's property, was on the order of a ten-year
1209storm. Hurricane Earl, in the vicinity of Petitioner's property,
1218was in the nature of a ten to twenty-year storm event.
122918. The Petitioner's pilings and the catwalk, if subjected
1238to a ten or twenty-year storm event, would fail and become wind
1250driven and waterborne missiles.
125419. In the event that the structural members of the dock
1265failed in a storm event and were generated as wind or waterborne
1277missiles, they could damage the upland dwellings during the storm
1287event.
128820. The portability of the structural members of the
1297catwalk does not relieve Petitioner of the obligation to design
1307the overall structure in a manner to minimize the potential for
1318generation of wind or waterborne debris. From Respondent's
1326policy perception portability of the catwalk does not overcome
1335the concern about the catwalk as part of the basic dock design
1347and the risk that all features within the dock design are
1358susceptible to becoming wind or waterborne in a storm event when
1369considered as an entire structure.
137421. Petitioner in his testimony indicated that his normal
1383residence is about two hours from the dock location by
1393automobile. Petitioner recognizes that in the event of an
1402evacuation from the coastal area where his dock is found, in an
1414anticipation of a storm, Petitioner might not have access to
1424remove the catwalk.
142722. Petitioner's dock is a major structure with potential
1436to create an adverse impact to the coastal system, in particular
1447upland structures if removed by the forces of nature.
1456Petitioner's dock is not a typical ocean mooring, such as a
1467floating buoy. The dock is not designed for expendability. It
1477is designed to be permanent. By its permanency it presents the
1488risk of an adverse impact to the coastal system, to include
1499upland properties.
150123. The perpendicular pilings in the project are more
1510shallow in their anchoring when compared to the parallel pilings.
1520Both sets of pilings create concern that they will become wind or
1532waterborne missiles. The parallel pilings are at the seaward
1541limits of the structure. They are subject to being scoured and
1552removed by a major storm event, no less so than the perpendicular
1564pilings in their shallow placement. In addition to the scouring
1574action at the base of the pilings, removing the material that
1585forms the embedment for the pilings, wave action, and
1594hydrodynamic forces exert an adverse influence on the pilings.
160324. Unlike dune walkovers, the dock located in the surf
1613zone is in the area where waves break and dissipate energy. That
1625process typically transpires before the waves reach the dunes
1634themselves where the dune walkovers are found. The dune area is
1645less dynamic in this sense. In addition to dissipation of energy
1656in the surf zone, energy from wave action is dissipated across
1667the beach before reaching the upland location where the dune
1677walkovers are found. It would take a more severe storm, which
1688has a lesser probability of occurring, before a dune walkover
1698would be at risk of deteriorating and becoming part of debris
1709that poses a threat to upland structures.
171625. The perpendicular piling nearest the beach presents an
1725interference with lateral beach access.
173026. Petitioner in presenting his application for an after-
1739the-fact permit has not refuted Respondent's concerns about the
1748potential for the pilings and deck to become displaced in a storm
1760event placing the uplands at risk. Petitioner has not countered
1770Respondent's proof presented through Robert M. Brantly, Jr., P.E.
1779Mr. Brantly in his testimony offered the opinion that the
1789structural members of the dock would be dislodged in a storm
1800event and present a risk of becoming wind and waterborne missiles
1811presenting the potential for destruction to upland property in
1820the area. That opinion is accepted.
1826CONCLUSIONS OF LAW
182927. The Division of Administrative Hearings has
1836jurisdiction of the subject matter and the parties to this action
1847in accordance with Sections 120.569 and 120.57(1), Florida
1855Statutes.
185628. Petitioner's dock is seaward of the CCCL. The CCCL is
1867established to define that portion of the beach-dune system that
1877is subject to severe fluctuations based on a 100-year storm
1887surge, storm waves, or other predictable weather conditions.
1895Section 161.053(1)(a), Florida Statutes. Unless Petitioner
1901obtains a permit from Respondent the dock may not remain.
1911Section 161.053(5) and (7), Florida Statutes.
191729. The permit process is designed to be ". . . in the
1930public interest to preserve and protect them from imprudent
1939construction" which can ". . . provide inadequate protection to
1949upland structures, endanger adjacent properties, or interfere
1956with public beach access." Section 161.053(1)(a), Florida
1963Statutes.
196430. In particular, Section 161.053(5)(a), Florida Statutes,
1971concerning permitting states:
1974(5) Except in those areas where local zoning
1982and building codes have been established
1988pursuant to subsection (4), a permit to
1995alter, excavate, or construct on property
2001seaward of established coastal construction
2006control lines may be granted by the
2013department as follows:
2016(a) The department may authorize an
2022excavation or erection of a structure at any
2030coastal location as described in subsection
2036(1) upon receipt of an application from a
2044property and/or riparian owner and upon the
2051consideration of facts and circumstances,
2056including:
20571. Adequate engineering data concerning
2062shoreline stability and storm tides related
2068to shoreline topography;
20712. Design features of the proposed
2077structures or activities; and
20813. Potential impacts of the location of such
2089structures or activities, including potential
2094cumulative effects of any proposed structures
2100or activities upon such beach-dune system,
2106which, in the opinion of the department,
2113clearly justify such a permit.
211831. Additional requirements for permitting the dock are set
2127forth in Rule 62B-33.005, Florida Administrative Code, which
2135states:
2136(3) After reviewing all information required
2142pursuant to this Chapter, the Department
2148shall:
2149(a) Deny any application for an activity
2156which either individually or cumulatively
2161would result in a significant adverse impact
2168including potential cumulative effects. . . .
2175(b) Require citing and design criteria that
2182minimize adverse impacts, and mitigation of
2188adverse or other impacts.
2192(4) The Department shall issue a permit for
2200construction which an applicant has shown to
2207be clearly justified by demonstrating that
2213all standards, guidelines and other
2218requirements set forth in the applicable
2224provisions of Part I, Chapter 161, Florida
2231Statutes, and this Chapter are met, including
2238the following:
2240* * *
2243(e) The construction will minimize the
2249potential for wind and waterborne missiles
2255during a storm.
225832. Petitioner is not entitled to an after-the-fact permit.
2267Petitioner has not given the necessary reasonable assurances
2275concerning the design features of the dock as the construction
2285would minimize the potential for wind and waterborne missiles
2294during a storm and their adverse effect on upland structures, and
2305endangerment to adjacent properties. To the contrary,
2312Respondent, through its expert, established that the upland
2320structures and adjacent properties to the dock are at risk by the
2332structural members of the dock becoming wind and waterborne
2341missiles during a storm event. Finally, Petitioner's dock
2349presents a limited interference with public beach access.
235733. Petitioner is not entitled to an exemption from
2366permitting under terms set forth in Section 161.053, Florida
2375Statutes, or Rule 62B-33.004, Florida Administrative Code.
238234. Petitioner's dock is not subject to permitting under
2391Section 161.041, Florida Statutes, in that it does not constitute
2401the type activity contemplated by that permit process.
2409RECOMMENDATION
2410Upon consideration of the facts found and conclusions of law
2420reached, it is
2423RECOMMENDED:
2424That a final order be entered which denies an after-the-fact
2434permit for Petitioner's dock and calls for the removal of that
2445dock upon a date established in the final order.
2454DONE AND ENTERED this 30th day of July, 1999, in
2464Tallahassee, Leon County, Florida.
2468CHARLES C. ADAMS
2471Administrative Law Judge
2474Division of Administrative He arings
2479The DeSoto Building
24821230 Apalachee Parkway
2485Tallahassee, Florida 32399-3060
2488(850) 488-9675 SUNCOM 278-9675
2492Fax Filing (850) 921-6847
2496www.doah.state.fl.us
2497Filed with the Clerk of the
2503Division of Administrative Hearings
2507this 30th day of July, 1999.
2513COPIES FURNISHED:
2515J. Howard Lovett
25183131 Lovett Road
2521Post Office Box 225
2525Chipley, Florida 32428
2528Ricardo Muratti, Esquire
2531Department of Environmental
2534Protection
2535Douglas Building
25373900 Commonwealth Boulevard
2540Mail Station 35
2543Tallahassee, Florida 32399-3000
2546Kathy Carter, Agency Clerk
2550Department of Environmental
2553Protection
2554Douglas Building
25563900 Commonwealth Boulevard
2559Mail Station 35
2562Tallahassee, Florida 32399-3000
2565F. Perry Odom, General Counsel
2570Department of Environmental
2573Protection
2574Douglas Building
25763900 Commonwealth Boulevard
2579Mail Station 35
2582Tallahassee, Florida 32399-3000
2585NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2591All parties have the right to submit written exceptions within
260115 days from the date of this recommended order. Any exceptions to
2613this recommended order should be filed with the agency that will
2624issue the final order in this case.
- Date
- Proceedings
- Date: 09/13/1999
- Proceedings: Final Order filed.
- Date: 07/22/1999
- Proceedings: Department`s Motion to Strike (filed via facsimile).
- Date: 07/06/1999
- Proceedings: Letter to Judge Adams from J. Lovett Re: Proposed Recommended Order filed.
- Date: 07/06/1999
- Proceedings: Department`s Proposed Recommended Order filed.
- Date: 06/23/1999
- Proceedings: Transcript filed.
- Date: 06/09/1999
- Proceedings: Exhibits w/cover letter filed.
- Date: 06/07/1999
- Proceedings: CASE STATUS: Hearing Held.
- Date: 03/24/1999
- Proceedings: Notice of Hearing sent out. (hearing set for 6/7/99; 1:00pm; Chipley)
- Date: 03/01/1999
- Proceedings: Department of Environmental Protection`s Response to Initial Order (filed via facsimile).
- Date: 02/19/1999
- Proceedings: Initial Order issued.
- Date: 02/16/1999
- Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Petition for Administrative Proceeding (letter form); Final Order rec`d