99-003613 Northern Trust Bank Of Florida, N.A., As Personal Representative For Estate Of Hosea Edwin Blanton vs. Susan Negele And Department Of Environmental Protection
 Status: Closed
DOAH Final Order on Tuesday, August 1, 2000.


View Dockets  
Summary: Applicant failed to show an absence of significant impacts to a beach and dune system from placing a residence atop a frontal dune. Department improperly issued a permit prior to receiving a variance.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8NORTHERN TRUST BANK OF )

13FLORIDA, N.A., as personal )

18representative of the estate )

23of HOSEA EDWIN BLANTON, )

28)

29Petitioner, )

31)

32vs. ) Case No. 99-3613

37)

38SUSAN NEGELE and DEPARTMENT )

43OF ENVIRONMENTAL PROTECTION, )

47)

48Respondents. )

50______________________________)

51RECOMMENDED ORDER

53Robert E. Meale, Administrative Law Judge of the Division of

63Administrative Hearings, conducted the final hearing in

70Bradenton, Florida, on March 27, 2000.

76APPEARANCES

77For Petitioner: Adam Mohammadbhoy

81Harllee Porges

83Post Office Box 9320

87Bradenton, Florida 34205

90For Respondent Susan Negele:

94S.W. Moore

96Brigham Moore

98100 Wallace Avenue, Suite 310

103Sarasota, Florida 34237

106F or Respondent Department of Environmental Protection:

113Francine M. Ffolkes

116Senior Assistant General Counsel

120Department of Environmental Protection

124Mail Station 35

1273900 Commonwealth Boulevard

130Tallahassee, Florida 32399-9314

133STATEMENT OF THE ISSUE

137The issue is whether Respondent Negele is entitled to a

147coastal construction control line permit to construct a single-

156family residence seaward of the coastal construction control line

165on Anna Maria Island.

169PRELIMINARY STATEMENT

171Respondent Negel e applied for a permit to build a single-

182family residence seaward of the coastal construction control line

191on Anna Maria Island. Respondent Department of Environmental

199Protection issued a tentative Final Order to grant the permit.

209Petitioner filed a petition challenging the issuance of the

218permit. Neither respondent raised the affirmative defense of

226standing.

227At the hearing, Petitioner called three witnesses and

235offered into evidence three exhibits. Respondent Negele called

243two witnesses and offered into evidence eleven exhibits.

251Respondent Department of Environmental Protection called one

258witness and offered into evidence four exhibits. The parties

267jointly offered into evidence two exhibits. All exhibits were

276admitted.

277The court reporter filed the Transcript on April 10, 2000.

287FINDINGS OF FACT

2901. Respondent Susan Negele (Applicant) owns Lot 10, Block

29935, of the First Addition to Anna Maria Beach. Petitioner owns

310the legal interest in Lots 11 and 12 in the same block. Lot 11

324is adjacent to, and landward of, Lot 10, and Lot 12 is adjacent

337to, and landward of, Lot 11.

3432. As platted in 1912, Lot 10 was separated from the Gulf

355by 360 feet, consisting, from landward to seaward, of two 50-foot

366lots, an unnamed 10-foot alley, a 100-foot lot, a 50-foot-wide

376road known as Gulf Boulevard, and about 100 feet of beach

387(although this feature does not contain a stated distance and the

398plat map does not indicate the location of the mean or seasonal

410high water line). According to the plat, running perpendicular

419to Gulf Boulevard (and the shoreline) are Elm Avenue and another

430unnamed 10-foot alley. Elm Avenue, which is 50-feet wide, runs

440along the northwest property line of Lot 10, and the unnamed

451alley runs along the southeast property line of Lot 10.

4613. Today, Lot 10 is the first platted feature landward of

472the seasonal high water line of the Gulf of Mexico. The record

484does not reveal whether the platted features seaward of Lot 10

495were submerged at the time of the original subdivision or, if

506not, the process or processes that submerged these three lots,

516alley, road, and beach.

5204. Notwithstanding the clear evidence of the plat map,

529there is insufficient record evidence on which to base a finding

540that the mean or seasonal high water line has migrated landward a

552distance of 360 feet in 88 years. The record is contradictory on

564the issue of the stability of the beach seaward of Lot 10.

5765. On the one hand, as noted below, two rock groins of

588unknown age on either side of Lot 10 suggest an effort to deter

601offshore erosion, but the presence of these groins does not

611support an inference of a diminishing beach. The beach seaward

621of Lot 10 is included in the Comprehensive Beach Management Plan,

632which is reserved for beaches that are subject to erosion, but

643the record does not develop this point adequately.

6516. On the other hand, also as noted below, the anecdotal

662evidence suggests that the beach seaward of Lot 10 has been

673stable, at least for the past two or three decades. A recent

685survey, described below, suggests rapid growth in the beach and

695dune over the past 16 months. Even stronger evidence of the

706stability of the beach seaward of Lot 10 is its exclusion from

718the 30-year erosion projection. The record unfortunately does

726not disclose the proximity of this line to Lot 10, which, if in

739close proximity, would be important evidence of the condition of

749a beach and frontal dune system.

7557. In sum, the relative stability of the beach in the

766vicinity of Lot 10 is unclear. However, the exclusion of Lot 10

778from the 30-year erosion projection and the anecdotal evidence of

788stability slightly outweigh the contrary evidence of instability.

7968. Applicant's family has owned Lot 10 for 50 years.

806Originally, they occupied two buildings on Lot 10 that had once

817served as Coast Guard barracks. At one point, Applicant's father

827barged the houses up the Manatee River to his father's farm in

839Palmetto. The record does not reveal whether another building

848was ever constructed on Lot 10.

8549. From an engineering standpoint, Lot 10 is a buildable

864lot. Applicant seeks the necessary permits to allow residential

873construction, so as to raise the market value of Lot 10 prior to

886its sale in order to liquidate this asset following the death of

898her surviving parent.

90110. By application filed with Respondent Department of

909Environmental Protection (DEP) on June 16, 1997, Applicant

917requested a coastal construction control line (CCCL) permit to

926construct a single-family residence on Lot 10.

93311. On June 30, 1999, DEP issued a Final Order tentatively

944granting the permit, but authorizing the construction of a

953structure with a footprint of only 352 square feet. Finding the

964allowable footprint insufficient, Applicant challenged the

970tentative agency action in DOAH Case No. 99-3913. Finding even a

981352-square-foot footprint objectionable, Petitioner also

986challenged the tentative agency action in DOAH Case No. 99-3613.

996The Administrative Law Judge consolidated the two cases.

100412. Agency action in cases of this type is necessarily

1014tentative because it is subject to administrative challenge,

1022which, once resolved, allows final agency action to take place.

1032However, the tentative agency action in this case is tentative in

1043another important respect.

104613. DEP has approached the permitting decision in this case

1056through a bifurcated process. DEP has issued a Final Order

1066approving the proposed activity in concept, but has withheld

1075issuing a Notice to Proceed, which is necessary before

1084construction may commence. DEP has withheld issuing the Notice

1093to Proceed until it receives more detailed plans for grading and

1104revegetating the dune and it determines that these plans

1113adequately address the protection of the beach and dune system.

112314. As noted below, the bifurcated permitting process

1131defers DEP's examination of detailed grading and revegetation

1139plans until after its issuance of the Final Order. DEP's expert

1150testified that DEP provides a point of entry to challenge final

1161orders, but not notices to proceed. (Tr., p. 174.) The expert

1172testified that DEP would provide another point of entry

1181concerning the proposed activity, but only if DEP were to issue

1192another final order, such as for a "major modification" of the

1203project (Tr., p. 174).

120715. But nothing in the record suggests that DEP will be

1218issuing another final order following it's receipt of the more

1228detailed grading and revegetation plans, whose approval by DEP is

1238not subject to administrative challenge (absent successful

1245judicial action to force DEP to provide another point of entry).

1256(The record does not reveal whether DEP would provide Applicant

1266with another point of entry if DEP were to disapprove the more

1278detailed plans and decline to issue the Notice to Proceed.)

128816. The absence of an agency-recognized point of entry to

1298challenge the detailed plans means that the analysis necessary to

1308make the determinations required by law concerning the impacts of

1318the proposed activities must be limited to the Permit, as it

1329presently exists, and these determinations may not rely upon

1338additional protections that may be supplied by more detailed

1347plans that are not yet in existence.

135417. DEP and Applicant settled DOAH Case No. 99-3913 shortly

1364prior to the final hearing. The settlement stipulation

1372incorporates a new site plan showing the proposed residence moved

1382landward so that it is seven feet landward of the vegetation

1393line, but setback only three feet from the northeast property

1403line (adjoining Lot 11) and five feet from the southeast property

1414line (adjoining the alley).

141818. DEP approved the settlement on or about March 17, 2000.

1429By letter dated March 22, 2000, DEP's counsel advised Applicant's

1439counsel that DEP would announce at the final hearing that "it

1450intends to issue the [Permit] . . . in accordance with the agreed

1463location in [the revised site plan] and all other applicable

1473conditions of the June 29, 1999, final order and June 30, 1999,

1485letter from [DEP] to Charles Rose."

149119. The CCCL permit is dated June 29, 1999, and expires on

1503June 29, 2002. References to the "Permit" shall include the

1513subsequent modifications that resulted in the settlement of DOAH

1522Case No. 99-3913 and the modifications described below.

1530Petitioner objected to all evidence and any express or implied

1540amendment of the pleadings at the final hearing to encompass

1550subsequent Permit modifications, but the Administrative Law Judge

1558overruled these objections.

156120. The Permit authorizes Respondent to conduct activities

1569in a location that is seaward of the CCCL, but landward of the

158230-year erosion projection and the existing line of construction

1591established by major structures in the immediate area.

159921. According to the survey dated October 15, 1998, and

1609architect's plans dated November 12, 1998, the residence to be

1619constructed would be an elevated two-story frame structure, over

1628a concrete pad, with a footprint of 952 square feet. The

1639proposed structure would be similar in size and character to

1649other residences in the area. A registered architect has signed

1659and sealed all relevant construction plans.

166522. For the purpose of this recommended order, the seaward

1675side of Lot 10 is its 110-foot side facing the southwest. This

1687southwest property line runs from the west corner to the south

1698corner of Lot 10. The north and east corners mark the 110-foot

1710side of Lot 10 that abuts Lot 11; this is the northeast property

1723line. As already noted, the two 50-foot sides of Lot 10 abut Elm

1736Avenue and the unnamed 10-foot alley.

174223. As it exists in the ground, Elm Avenue is a strip of

1755pavement 17 feet wide located in the middle of the 50-foot wide

1767platted right-of-way. At present, the paved portion of Elm

1776Avenue does not extend seaward of the midpoint of Lot 11.

1787Applicant proposes the construction of a shell drive between the

1797Elm Avenue right-of-way and the north corner of Lot 10, but this

1809proposed activity is not the subject of the present case.

181924. The road right-of-way immediately adjacent to Lot 10

1828was occupied by a 60-foot wooden access walkway extending from

1838the end of the road seaward, between the rock groin and the

1850northwest line of Lot 10. However, this walkway was removed in

1861the past couple of years.

186625. At present, the rock groin parallel to the northwest

1876line of Lot 10 occupies the center of the road right-of-way,

1887extending from Lot 10's midpoint, which is landward of the

1897seasonal high water line, to a point seaward of mean sea level.

1909Another rock groin runs from the unnamed alley along the

1919southeast line of Lot 10, also from a point just landward of the

1932seasonal high water line, and extends seaward of mean sea level.

1943Running parallel to the two 50-foot lot lines of Lot 10 and

1955perpendicular to the shoreline, these two rock groins may offer

1965some protection from erosion by affecting sand traveling

1973offshore, but do not otherwise directly offer any protection to

1983the beach and dune system.

198826. As established by Applicant, landward from the Gulf,

1997relevant natural features are located as follows. Mean sea

2006level, which is 0.00 feet National Geodetic Vertical Datum

2015(NGVD), is over 50 feet seaward of the west corner of Lot 10 and

2029over 100 feet seaward of the south corner of Lot 10. Mean high

2042water, which is 1.2 feet NGVD, is 35 feet seaward of the west

2055corner of Lot 10 and about 75 feet seaward the south corner of

2068Lot 10. Seasonal high water, which is 3.63 feet NGVD, is about

208010 feet landward of the west corner of Lot 10 and about 25 feet

2094seaward of the south corner of Lot 10. About 15-20 square feet

2106of the relatively low west side of Lot 10 is submerged at

2118seasonal high water.

212127. In two respects, Petitioner's survey, which was dated

2130March 25, 2000, establishes that, at least for the past 16

2141months, the beach and dune system is flourishing, not eroding.

215128. First, mean high water is now farther from Lot 10 than

2163it was in late 1998. In the intervening 16 months, the mean high

2176water line has migrated to a point 77 feet seaward of the west

2189corner of Lot 10--a distance of 37 feet in less than one and one-

2203half years. During the same period, the mean high water line has

2215migrated from 75 feet to 102 feet--a distance of 27 feet--seaward

2226of the south corner of Lot 10.

223329. Second, the newer survey reveals that the seven-foot

2242contour, which is shown on Applicant's survey as a small area at

2254the midpoint of the southeast lot line, now extends across the

2265southeastern two-thirds of the central portion of the lot. It is

2276difficult to estimate from the surveys, but the area of at least

2288seven-foot elevation appears to be six or seven times larger than

2299it was 16 months ago, although a very small area of eight-foot

2311elevation shown on Applicant's survey appears to have

2319disappeared. Both surveys show that the six-foot contour line

2328roughly bisects Lot 10 diagonally from the north to the south

2339corners.

234030. Evidence of beach stability supplied from the March

23492000 survey is reinforced by anecdotal testimony that the beach

2359at this location has been stable for at least 20 years. In

2371general, the beach at this location is not as dynamic as beaches

2383found elsewhere in Florida.

238731. The CCCL is about 259 feet landward of the north corner

2399of Lot 10 and about 222 feet landward of the east corner of Lot

241310. The CCCL is landward of Petitioner's Lots 11 and 12, as well

2426as the next two 50-foot wide lots and nearly the entirety of Gulf

2439Drive (Snapper Street on the plat) adjoining this block.

244832. According to Applicant's survey, the seaward toe of the

2458frontal dune runs roughly along the seaward six-foot contour,

2467perhaps 10 feet seaward of this contour at the west corner and a

2480perhaps five feet landward of this contour at the south corner.

2491The vegetation line runs 3-5 feet landward of the surveyed

2501seaward toe of the dune. According to Applicant's survey, the

2511frontal dune continues over the landward half of Lot 10,

2521excluding only a 10-square-foot area at the east corner and

2531extending well across the southeastern line of Lot 11, so as to

2543capture about one-fifth of that lot.

254933. However, the surveys do not support an independent

2558determination of the toes of the frontal dune or, thus, its

2569width. DEP's expert testified that the landward toe of the dune

2580is probably landward of the surveyed location. Also, the scale

2590of the surveys did not facilitate analysis of subtle changes in

2601slope, which would be indicative of the toes of a low frontal

2613dune, such as is involved in this case. DEP's expert opined that

2625a maximum elevation of seven or eight feet NGVD meant, at this

2637general location, that the toes would probably be at the five-

2648foot contours. If so, the seaward toe would be about 10-15 feet

2660seaward of its surveyed location, and the landward toe would be

2671at an undetermined location landward of Lot 10.

267934. Several dynamic processes underlie the beach and

2687frontal dune system. Perhaps most obviously, plants rooted in a

2697dune capture sand and, thus, add to the size of a dune. The

2710absence of such plants facilitates a reduction in dune size.

272035. The stability of a dune is also affected by the slopes

2732of its seaward and landward sides and the size of the grains of

2745sand constituting the dune. When restoring a dune, adherence to

2755historic slopes and elevations enhances the possibility of a

2764successful dune restoration. Deviation from these slopes and

2772elevations raises the risk of failure. The same is true

2782regarding the size and characteristics of the grains of sand used

2793to restore a dune.

279736. Another factor important in dune stability, as well as

2807upland protection, is the continuity of the dune. A shorter

2817dune, in terms of its length running parallel to the shoreline,

2828is less stable and obviously offers less landward protection than

2838a longer dune.

284137. As originally proposed, Respondent's home would occupy

2849the east corner of Lot 10. The southwest side of the residence

2861(facing the Gulf) would have been about one foot seaward of the

2873vegetation line and only one to two feet landward of the surveyed

2885seaward toe of the frontal dune. The landward side of the

2896residence would have been 10 feet seaward of the northeast side

2907of Lot 10. The proposed home would have been setback 10 feet

2919from the northeast and southeast property lines.

292638. Shortly prior to the commencement of the hearing,

2935Applicant modified the proposed plans, and DEP modified the

2944Permit. These changes would relocate the proposed residence so

2953that it was seven feet landward of the vegetation line, but

2964setback only three feet from the northeast line and five feet

2975from the southeast line. Despite its relocation landward from

2984its original proposed location, the entire residence would occupy

2993the frontal dune. More specifically, the residence would sit on

3003the seaward side of the frontal dune.

301039. The Permit imposes a number of special conditions upon

3020the construction of Respondent's residence. Consistent with

3027DEP's bifurcation of the permitting process in this case, these

3037special conditions prohibit the commencement of construction

3044until Respondent submits plans and specifications "includ[ing] or

3052reflect[ing] the following:"

30551.1 A revised site plan including the

3062distances relative to coastal construction

3067control line to all the authorized structures

3074with dimensions. The revised site plan shall

3081depict the dwelling relocated to within 3

3088feet of the upland lot line and not exceeding

3097a distance of 244 feet seaward.

3103* * *

31061.5 A revised grading plan depicting the

3113restored dune extending across the entire

3119parcel with a minimum crest elevation of .0

3127feet (NGVD).

3129* * *

31325. The fill material shall be obtained from

3140a source landward of the control line and

3148shall consist of sand which is similar to

3156that already on the site in both grain size

3165and coloration. This fill material shall be

3172free of construction debris, rocks, or other

3179foreign matter. A sample of the sand shall

3187be provided to the staff representative

3193during the preconstruction conference.

31976. All permanent exterior lighting shall be

3204installed and maintained as depicted in

3210approved lighting schematic. No additional

3215exterior lighting is authorized.

3219CAVEAT:

3220Due to potential adverse impacts to the beach

3228and dune system that may result from

3235additional development on the property, the

3241shore-parallel and seaward extent of the

3247permitted structures shall not be increased,

3253nor will any additional major structures be

3260permitted which would exceed the limits

3266established by the permitted construction

3271seaward of the coastal construction control

3277line.

327840. The present proposed location of the residence is not

3288landward of a line running 244 feet seaward of the CCCL. Roughly

3300one-third of the proposed residence would be seaward of this

3310line, which is set forth in the Permit.

331841. Addressing the obvious conflict between the restriction

3326contained in Permit Paragraph 1.1 prohibiting any structure

3334seaward of a point 244 feet seaward of the CCCL and its approval

3347of the new location for the residence, DEP announced at the

3358hearing a new Permit Paragraph 1.1, which reads:

3366The revised site plan shall depict the

3373dwelling relocated within three feet of the

3380upland lot line and not exceeding a distance

3388of 250 feet seaward of the CCCL on the

3397southwest corner and 255 feet seaward of the

3405CCCL on the northwest corner.

3410(Tr., pp. 119-20.)

341342. The revised site plan clarifies that the reference to

"3423three feet" means the three-foot setback on the northeast lot

3433line. The references to the southwest and northwest corners

3442are, respectively, to the southernmost corner, which, when used

3451with respect to Lot 10 in this recommended order, is described as

3463the south corner, and the westernmost corner, which, when used

3473with respect to Lot 10 in this recommended order, is described as

3485the west corner. (For ease of reference at the hearing, counsel,

3496the witnesses, and Administrative Law Judge reoriented Lot 10 by

3506referring to the southwest lot line as the west lot line and

3518treating the Gulf, which is southwest of Lot 10, as though it

3530were due west of Lot 10.)

353643. At present, Applicant has submitted no grading plans,

3545which would address the seaward toe of the frontal dune after

3556construction. The landward toe is not on Applicant's property,

3565so Applicant will not be able to change the slope of the landward

3578side of the dune by adding sand to the portion of this dune not

3592contained within Lot 10.

359644. As identified to this point, the Permit's requirements

3605for dune restoration are sketchy, reliant upon more detailed

3614grading plans that are not yet in existence. Permit Paragraph 5

3625adequately specifies the grain size. However, the Permit fails

3634to specify the slopes, leaving this crucial element of the dune

3645to the more detailed grading plans.

365145. Under the Permit, Applicant would be required to supply

3661a specified volume of sand to the site. This volume was

3672calculated to be sufficient, based on Applicant's survey, to

3681raise the portion of the dune northwest of the seven-foot contour

3692to an elevation of seven feet NGVD. However, if Petitioner's

3702survey is correct, much less sand will be needed to raise the

3714elevation to seven feet NGVD, so the "excess" sand will widen the

3726dune. This recommended order has credited both surveys, so

3735Applicant's survey provides the relevant details except for the

3744more recent information supplied by Petitioner's survey

3751concerning the locations of the mean high water line and the

3762seven-foot contour.

376446. The widening of the dune authorized by the Final Order

3775necessarily changes the dune's profile by extending the seaward

3784toe closer to the shoreline and probably changes the slope of the

3796seaward toe of the dune. Additionally, raising the elevation of

3806the dune in the northeastern portion of Lot 10 will dramatically

3817change its landward profile, given the fact that Applicant cannot

3827add sand to the large portion of the dune landward of Lot 10.

384047. The effects of these alterations of the dune profile

3850are entirely unknown to Applicant and DEP. Failing to perform

3860the preliminary tasks of locating the existing dimensions of the

3870dune--in terms of its width (perpendicular to the shoreline) and

3880its length (parallel to the shoreline)-- Applicant and DEP lacked

3890the baseline data upon which they could then analyze the

3900construction and post-construction effects of placing Applicant's

3907residence atop this dune. The present stability of the beach and

3918dune system at Lot 10 does not dispense with the necessity of

3930such analysis in making the determinations required by the

3939relevant law.

394148. Additionally, the Permit fails to address the

3949revegetation of the dune, again leaving this issue to more

3959detailed plans not yet in existence. Specifically, Applicant has

3968submitted no plans establishing a replanting scheme with

3976specified species at specified distances, criteria by which to

3985measure the success of the revegetation process (e.g., X percent

3995coverage after one year), and a monitoring and enforcement

4004program.

400549. Lastly, although the City of Anna Maria issued a letter

4016approving of the proposed plans when Applicant proposed ten-foot

4025setbacks, the City of Anna Maria has not had a chance to comment

4038upon the proposal of three- and five-foot setbacks. Land use

4048regulations of the City of Anna Maria require greater setbacks

4058than these.

406050. As distinguished from its treatment of the dune profile

4070and vegetation, the Permit supplies ample assurances that the

4079proposed activities would be conducted in such a way as not to

4091disturb nesting sea turtles, which, according to the record,

4100infrequently occupy this specific location. Permit provisions,

4107such as those scheduling construction and governing construction

4115and post-construction lighting, adequately address the relatively

4122simple task of protecting this lightly used nesting habitat.

4131CONCLUSIONS OF LAW

413451. The Division of Administrative Hearings has

4141jurisdiction over the subject matter. Section 120.57(1), Florida

4149Statutes. (All references to Sections are to Florida Statutes.

4158All references to Rules are to the Florida Administrative Code.)

416852. As the party seeking a permit, Applicant bears the

4178burden of proving her entitlement to the Permit. Department of

4188Transportation v. J. W. C. Company, Inc. , 396 So. 2d 778 (Fla.

42001st DCA 1981).

420353. Section 161.053(1)(a) provides in part:

4209The Legislature finds and declares that the

4216beaches in this state and the coastal barrier

4224dunes adjacent to such beaches, by their

4231nature, are subject to frequent and severe

4238fluctuations and represent one of the most

4245valuable natural resources of Florida and

4251that it is in the public interest to preserve

4260and protect them from imprudent construction

4266which can jeopardize the stability of the

4273beach-dune system, accelerate erosion,

4277provide inadequate protection to upland

4282structures, endanger adjacent properties, or

4287interfere with public beach access. In

4293furtherance of these findings, it is the

4300intent of the Legislature to provide that the

4308department establish coastal construction

4312control lines . . . to define that portion of

4322the beach-dune system which is subject to

4329severe fluctuations based on a 100-year storm

4336surge . . .. Special siting and design

4344considerations shall be necessary seaward of

4350established coastal construction control

4354lines to ensure the protection of the beach-

4362dune system, proposed or existing structures,

4368and adjacent properties and the preservation

4374of public beach access.

437854. Section 161.053(5)(a) provides that DEP may issue a

4387CCCL permit "upon consideration of the facts and circumstances,

4396including:"

43971. Adequate engineering data concerning

4402shoreline stability and storm tides related

4408to shoreline topography;

44112. Design features of the proposed

4417structures or activities; and

44213. Potential impacts of the location of such

4429structures or activities, including potential

4434cumulative effects of any proposed structure

4440or activities upon such beach-dune system,

4446which, in the opinion of the department,

4453clearly justify such a permit.

445855. Section 161.053(5)(b) provides that DEP may issue a

4467CCCL permit if "a number of structures" immediately contiguous or

4477adjacent to the subject property "have established a reasonably

4486continuous and uniform construction line closer to the line of

4496mean high water than the [CCCL]." However, this section states

4506that DEP "shall not contravene setback requirements or zoning or

4516building codes established by a county or municipality which are

4526equal to, or more strict than, those requirements provided

4535herein." DEP may still consider the facts and circumstances

4544listed in Section 161.053(5)(a) or the natural resources

4552protected by the CCCL legislation.

455756. Section 161.053(6)(b) prohibits the location of nearly

4565all types of structures seaward of the 30-year erosion

4574projection. However, Section 161.053(6)(c) allows an exception

4581for a single-family dwelling on land that was platted prior to

4592October 1, 1985, and where the application of the prohibition

4602would preclude construction of a single-family residence.

4609However, this exception still requires that the structure be

4618located landward of the frontal dune.

462457. Section 161.053(21) authorizes DEP to promulgate rules

4632related to activities seaward of the CCCL.

463958. Rule 62B-33.005(1) states:

4643The beach and dune system is an integral part

4652of the coastal system and represents one of

4660the most valuable natural resources in

4666Florida, providing protection to adjacent

4671upland properties, recreational area and

4676habitat for wildlife. A coastal construction

4682control line is intended to define that

4689portion of the beach and dune system which is

4698subject to severe fluctuations caused by a

4705one-hundred-year storm surge, storm waves, or

4711other forces such as wind, wave or water

4719level changes. These fluctuations are a

4725necessary part of the natural functioning of

4732the coastal system and are essential to post-

4740storm recovery, long-term stability and the

4746preservation of the beach and dune system.

4753However, imprudent human activities can

4758adversely interfere with these natural

4763processes and alter the integrity and

4769functioning of the beach and dune system.

4776The control line . . . call[s] attention to

4785the special hazards and impacts associated

4791with the use of such property, but do[es] not

4800preclude all development or alteration of

4806coastal property seaward of such lines.

481259. Rule 62B-33.005(2) provides that an applicant shall

4820provide DEP with "sufficient information pertaining to the

4828proposed project to show that any impacts associated with the

4838construction have been minimized and that the construction will

4847not result in a significant adverse impact."

485460. Rule 62B-33.002(29)(b) provides that:

4859Significant Adverse Impacts are adverse

4864impacts of such magnitude that they may:

48711. Alter the coastal system by:

4877a. Measurably affecting the existing

4882shoreline change rate;

4885b. Significantly interfering with its

4890ability to recover from a coastal storm;

4897c. Disturbing topography or vegetation

4902such that the system becomes unstable, or

4909suffers catastrophic failure; or

49132. Cause a take, as defined in section

4921370.12(1), Florida Statutes, unless the take

4927is incidental pursuant to section

4932370.12(1)(f), Florida Statutes.

493561. Rule 62B-33.005(3)(a) states that DEP shall deny any

4944application for an

4947activity which either individually or

4952cumulatively would result in a significant

4958adverse impact including potential cumulative

4963effects. In assessing the cumulative effects

4969of a proposed activity, the Department shall

4976consider the short-term and long-term impacts

4982and the direct and indirect impacts the

4989activity would cause in combination with

4995existing structures in the area and any other

5003activities proposed with the same fixed

5009coastal cell.

501162. Rule 62B-33.005(3)(b) directs DEP to "[r]equire siting

5019and design criteria that minimize adverse impacts, and mitigation

5028of adverse or other impacts."

503363. Rule 62B-33.005(4) provides that DEP shall issue a CCCL

5043if the applicant has shown that issuance is "clearly justified"

5053by demonstrating compliance with all requirements of Chapter 161,

5062Part I, Florida Statutes, and the rules under Chapter 62B-33.

5072The applicant must show, among other things:

5079(a) The construction will not result in

5086removal or destruction of native vegetation

5092which will either destabilize a frontal,

5098primary or significant dune or cause a

5105significant adverse impact to the beach and

5112dune system due to increased erosion by wind

5120or water;

5122(b) The construction will not result in

5129removal or disturbance of in situ sandy soils

5137of the beach and dune system to such a degree

5147that a significant adverse impact to the

5154beach and dune system would result from

5161either reducing the existing ability of the

5168system to resist erosion during a storm or

5176lowering existing levels of storm protection

5182to upland properties and structures;

5187* * *

519064. Rule 62B-33.005(6) provides:

5194Major structures shall be located a

5200sufficient distance landward of the beach and

5207frontal dune to permit natural shoreline

5213fluctuations, to preserve and protect beach

5219and dune system stability and to allow

5226natural recovery to occur following storm-

5232induced erosion. . . .

523765. Rule 62B-33.005(7) states:

5241If in the immediate area a number of existing

5250major structures have established a

5255reasonably continuous and uniform

5259construction line and if the existing

5265structures have not been unduly affected by

5272erosion, except where not allowed by the

5279requirements of section 161.053(6), Florida

5284Statutes, and this Chapter, the Department

5290shall issue a permit for the construction of

5298a similar structure up to that line, unless

5306such construction would be inconsistent with

5312sections (3), (4), (6) or (8) of this rule.

532166. Rule 62B-33.008(1) requires persons seeking to build

5329seaward of the CCCL to obtain a CCCL permit from DEP. Rule

534162B -33.008(1)(d) requires that each application contain:

"5348Written information, provided by the appropriate local

5355governmental agency having jurisdiction over the activity, that

5363the proposed activity, as submitted to the Bureau, does not

5373contravene local setback requirements, zoning or building codes,

5381and is consistent with the state approved Local Comprehensive

5390Plan."

539167. Rule 62B-33.008(1)(f) requires copies of a topographic

5399survey from field survey work performed not more than six months

5410prior to the date of the application.

541768. Rule 62B-33.008(1)(j) requires copies of "detailed

5424final construction plans and specifications for all proposed

5432structures . . .."

543669. Rule 62B-33.008(4) authorizes an applicant to identify

5444which of the requirements in Rule 62B-33.008(1)(b), (f), (g),

5453(h), (i), (j), (k), and (l) may be unnecessary to "ensure

5464protection to the beach and dune system . . .." DEP shall waive

5477any such requirements that are unnecessary in the subject

5486application.

548770. The Legislature established CCCLs "to define that

5495portion of the beach-dune system which is subject to severe

5505fluctuations based on a 100-year storm surge." Finding that the

5515beach and dune system is "one of the most valuable natural

5526resources in Florida," the Legislature created the CCCL

5534permitting process to "ensure the protection of the beach-dune

5543system, proposed or existing structures, and adjacent properties

5551and the preservation of public beach access."

555871. Elaborating, DEP recognizes that that the "severe

5566fluctuations" characteristic of the land seaward of the CCCL "are

5576a necessary part of the natural functioning of the coastal system

5587and are essential to post-storm recovery, long-term stability and

5596the preservation of the beach and dune system."

560472. The law does not prohibit construction seaward of the

5614CCCL. By statute, DEP may issue a CCCL permit upon consideration

5625of the facts and circumstances, including consideration of

"5633adequate" engineering data concerning shoreline stability and

5640storm tides and the "potential impacts of the location of . . .

5653structures or activities . . .."

565973. By statute, DEP has the discretion to issue a CCCL if

5671other contiguous structures have established a reasonably

5678continuous construction line closer to mean high water than would

5688otherwise be permitted by the CCCL. However, DEP may not issue a

5700CCCL permit, if the proposed construction would violate local

5709setback laws, and DEP must still consider the relevant facts and

5720circumstances. Section 161.053(5)(b) effectively identifies a

5726factor in favor of a CCCL permit, not a safe harbor guaranteeing

5738a CCCL permit.

574174. The rules spell out the requirements imposed upon an

5751applicant for a CCCL. The applicant must show that the

5761construction will not result in a "significant adverse impact"

5770and that any impacts have been "minimized" and "mitigat[ed]."

5779DEP shall consider cumulative, as well as short- and long-term,

5789impacts to relevant natural resources.

579475. Restating the statutory language found at Section

5802161.053(5)(a)3, the rules require the applicant to show that the

5812issuance of the CCCL permit is "clearly justified." This

5821language does not change the typical standard of proof--i.e., a

5831preponderance of the evidence--but it does require that an

5840applicant show, by a preponderance of the evidence, that issuance

5850of the CCCL permit is clearly justified.

585776. Among the things that an applicant must show is that

5868the issuance of the CCCL permit will not result in the removal of

5881native vegetation that will destabilize a frontal dune or cause a

5892significant adverse impact to the beach and dune system. The

5902activity proposed by Applicant will destroy considerable native

5910vegetation presently occupying the frontal dune, but an adequate

5919revegetation plan--had there been one--could have satisfied this

5927requirement.

592877. Another thing that an applicant must show is that the

5939construction will not result in the removal or disturbance of in

5950situ sandy soils of the beach and dune system to such a degree

5963that a significant adverse impact to the system would result, in

5974terms of the reduction of the system's ability to reduce erosion

5985or the reduction of the system's ability to offer protection to

5996upland properties. The activity proposed by Applicant will

6004considerably alter the natural profile of the frontal dune, but

6014an adequate grading plan--had there been one--could have

6022satisfied this requirement. Less clear is the ability of

6031Applicant to show that the permanent addition of a residence atop

6042the dune would not result in these adverse impacts; in any event,

6054the record does not permit such a finding.

606278. The rules also require a showing that major structures

6072will be sufficiently "landward of the beach and frontal dune" to

"6083permit natural shoreline fluctuations, to preserve and protect

6091beach and dune system stability and to allow natural recovery to

6102occur following storm-induced erosion." The proposed location of

6110the residence is atop the seaward side of the frontal dune. Even

6122ignoring this serious fact, the record does not permit a finding

6133that the location of the residence will permit natural shoreline

6143fluctuations, preserve and protect the natural beach and dune

6152system, and allow natural recovery following storm-induced

6159erosion.

616079. The rules also address the interplay of the reasonably

6170continuous construction line seaward of the CCCL and the other

6180provisions restricting activities seaward of the CCCL. Rule

618862B -33.005(7) warns that the exception for a reasonably

6197continuous construction line does not mean that construction may

6206be inconsistent with the above-described rules.

621280. As appears to be the case with the statutes, under the

6224rules, the exception for a reasonably continuous construction

6232line seaward of the CCCL appears to be a factor, perhaps even an

6245important factor, to be weighed with respect to the other

6255enumerated factors. For the most part, the rules identify

6264factors, among other facts and circumstances, that DEP should

6273weigh in determining whether to issue a CCCL permit.

628281. The only rule that deviates from this pattern is Rule

629362B-33.005(6), which does not identify a permitting factor, but,

6302by implication, flatly prohibits permitting construction that is

6310not landward of the frontal dune. The better reading of this

6321rule may be that it is a flat prohibition, but this recommended

6333order shall treat it as identifying merely another permitting

6342factor, given that the resolution set forth below is not

6352dependent upon the reading of this rule as a flat prohibition.

636382. For the reasons already stated, Applicant has failed to

6373prove by a preponderance of the evidence that the proposed

6383activity would satisfy the above-stated requirements designed to

6391protect the beach and dune system. The dynamics of the beach and

6403dune system are adversely affected by the construction of a

6413residence atop the frontal dune, especially the seaward side of

6423the frontal dune.

642683. DEP implicitly concedes the importance of more-detailed

6434grading and revegetation plans in assuring that the beach and

6444dune system suffers no significant adverse impacts, but the

6453bifurcated permitting process does not relieve Applicant of the

6462necessity of providing the necessary assurances to obtain the a

6472CCCL permit. This showing would be required even if DEP provided

6483substantially affected persons with a point of entry to challenge

6493the notice to proceed; the absence of such an opportunity only

6504underscores the importance of requiring these assurances prior to

6513any permitting of the proposed activity.

651984. Additionally, DEP has improperly issued the final order

6528prior to its receipt of a variance from the local government for

6540the three- and five-foot setbacks.

6545RECOMMENDATION

6546It is

6548RECOMMENDED that the Department of Environmental Protection

6555enter a final order denying the application for a coastal

6565construction control line permit to construct a residence at the

6575location indicated at the hearing.

6580DONE AND ENTERED this 13th day of June, 2000, in

6590Tallahassee, Leon County, Florida.

6594___________________________________

6595ROBERT E. MEALE

6598Administrative Law Judge

6601Division of Administrative Hearings

6605The DeSoto Building

66081230 Apalachee Parkway

6611Tallahassee, Florida 32399-3060

6614(850) 488-9675 SUNCOM 278-9675

6618Fax Filing (850) 921-6847

6622www.doah.state.fl.us

6623Filed with the Clerk of the

6629Division of Administrative Hearings

6633this 13th day of June, 2000.

6639COPIES FURNISHED:

6641Kathy Carter, Agency Clerk

6645Office of the General Counsel

6650Department of Environmental Protection

6654Mail Station 35

66573900 Commonwealth Boulevard

6660Tallahassee, Florida 32399-3000

6663Teri Donaldson, General Counsel

6667Department of Environmental Protection

6671Mail Station 35

66743900 Commonwealth Boulevard

6677Tallahassee, Florida 32399-3000

6680Adam Mohammadbhoy

6682Harllee Porges

6684Post Office Box 9320

6688Bradenton, Florida 34205

6691S.W. Moore

6693Brigham Moore

6695100 Wallace Avenue, Suite 310

6700Sarasota, Florida 34237

6703Francine M. Ffolkes

6706Senior Assistant General Counsel

6710Department of Environmental Protection

6714Mail Station 35

67173900 Commonwealth Boulevard

6720Tallahassee, Florida 32399-9314

6723NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

6729All parties have the right to submit written exceptions within 15

6740days from the date of this recommended order. Any exceptions to

6751this recommended order must be filed with the agency that will

6762issue the final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 08/01/2000
Proceedings: Final Order issued. CASE CLOSED. Hearing held
Date: 07/07/2000
Proceedings: Petitioner`s Response to Respondent`s Exceptions to the Recommended Order (filed via facsimile)
PDF:
Date: 06/13/2000
Proceedings: Recommended Order
PDF:
Date: 06/13/2000
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held March 27, 2000.
Date: 04/20/2000
Proceedings: DEP`s Proposed Recommended Order filed.
Date: 04/20/2000
Proceedings: Respondent`s Proposed Recommended Order (For Judge Signature) (filed via facsimile).
Date: 04/19/2000
Proceedings: Proposed Recommended Order (filed via facsimile).
Date: 04/10/2000
Proceedings: (2 Volumes) Transcript filed.
Date: 03/28/2000
Proceedings: CASE STATUS: Hearing Held.
Date: 03/27/2000
Proceedings: Susan Negele`s Prehearing Statement (filed via facsimile).
Date: 03/27/2000
Proceedings: (M. Nelson) Notice of Service of Answers to DEP`s Interrogatories; Notice of Service of Answers to Negele`s Interrogatories filed.
Date: 03/27/2000
Proceedings: DEP`s Prehearing Statement (filed via facsimile).
Date: 03/27/2000
Proceedings: Case 99-003913, unconsolidated due to closing of 99-3913 only.
Date: 03/23/2000
Proceedings: Joint Settlement Stipulation and Motion to Relinquish Jurisdiction filed.
Date: 03/17/2000
Proceedings: (S. Moore) Notice of Serving Answers to Interrogatories; Response to Request for Production (filed via facsimile).
Date: 03/13/2000
Proceedings: (M. Nelson) Motion for Order Compelling Discovery filed.
Date: 03/03/2000
Proceedings: (F. Ffolkes) Notice of Substitution of Counsel for Department of Environmental Protection filed.
Date: 02/22/2000
Proceedings: Order Denying Continuance sent out.
Date: 02/10/2000
Proceedings: (Petitioner) Motion for Continuance or for Different Hearing Dates filed.
Date: 02/09/2000
Proceedings: (S. W. Moore) Response to Intervenor`s Motion for Different Hearing Dates (filed via facsimile).
Date: 01/26/2000
Proceedings: Notice of Hearing sent out. (hearing set for March 28 and 29, 2000; 9:00am; Bradenton)
Date: 01/14/2000
Proceedings: (DEP) Status Report filed.
Date: 01/14/2000
Proceedings: Petitioner`s Date of Availability for Hearing filed.
Date: 01/07/2000
Proceedings: (M. Nelson) Response to Susan Negel`s Request for Production; Response to Department of Environmental Protection`s First Request for Production of Documents filed.
Date: 12/10/1999
Proceedings: (DEP) Notice and Certificate of Service of Interrogatories filed.
Date: 12/10/1999
Proceedings: Respondent Department of Environmental Protection`s Response to Petitioner Northern Trust Bank of Florida, N.A., as Personal Representative for the Estate of Hosea Edwin Blanton`s First Request for Production filed.
Date: 12/10/1999
Proceedings: Respondent Department of Environmental Protection`s Response to Petitioner Northern Trust bank of Florida, N.A., as personal Representative for the Estate of Hosea Edwin Blanton`s First Request for Production (filed via facsimile).
Date: 12/10/1999
Proceedings: (DEP) Notice and Certificate of Service of Interrogatories (filed via facsimile).
Date: 11/24/1999
Proceedings: DEP`s Notice of Service of Answers to Petitioner, Susan Negele`s First Set of Interrogatories filed.
Date: 11/24/1999
Proceedings: Respondent Department of Environmental Protection`s Response to Petitioner Susan Negele`s First Request for Production filed.
Date: 11/23/1999
Proceedings: Order of Abatement sent out. (12/1/99 hearing cancelled; Parties to advise status by 1/14/2000)
Date: 11/23/1999
Proceedings: (S. Moore) Response to Joint Motion for Continuance (filed via facsimile).
Date: 11/22/1999
Proceedings: Joint Motion for Continuance filed.
Date: 11/08/1999
Proceedings: Northern Trust`s First Request for Production of Documents to Negele; Northern Trust`s First Request for Production of Documents to DEP; (2) Notice of Service of Interrogatories filed.
Date: 10/26/1999
Proceedings: (S. Negele) Request for Production from DEP filed.
Date: 10/26/1999
Proceedings: (S. Negele) Notice of Service of First Interrogatoreis to Bank; (S. Negele) Request for Production from Bank; (S. Negele) Notice of Service of First Interrogatoreis to DEP filed.
Date: 10/14/1999
Proceedings: (M. Nelson) Notice of Substitution of Counsel filed.
Date: 10/07/1999
Proceedings: Order of Consolidation sent out. (Consolidated cases are: 99-003613, 99-003913)
Date: 10/05/1999
Proceedings: Notice of Hearing sent out. (hearing set for December 1 and 2, 1999; 9:00 a.m.; Bradenton, FL)
Date: 09/30/1999
Proceedings: (D. Alcorn) Amended Petition for Administrative Hearing filed.
Date: 09/16/1999
Proceedings: Order Dismissing Petition for Administrative Hearing With Leave to Amend sent out. (petition is dismissed with leave to file an amended petition if petitioner serves the amended petition by 10/1/99)
Date: 09/16/1999
Proceedings: Department of Environmental Protection`s Joint Response to Initial Order filed.
Date: 09/02/1999
Proceedings: (S. Moore) Motion to Dismiss Petition for Administrative Hearing Filed by Northern Trust Bank (filed via facsimile).
Date: 08/30/1999
Proceedings: Initial Order issued.
Date: 08/26/1999
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Petition for Administrative Hearing; Agency Action Letter filed.

Case Information

Judge:
ROBERT E. MEALE
Date Filed:
08/26/1999
Date Assignment:
08/30/1999
Last Docket Entry:
08/01/2000
Location:
Bradenton, Florida
District:
Middle
Agency:
Department of Environmental Protection
 

Related DOAH Cases(s) (2):

Related Florida Statute(s) (2):

Related Florida Rule(s) (5):