99-002861 Vincent D`antoni vs. David Boston And Department Of Environmental Protection
 Status: Closed
Recommended Order on Wednesday, March 22, 2000.


View Dockets  
Summary: Applicant found to be qualified to use a noticed general permit to fill riverfront lot subject to the condition that he install an underground drainage culvert.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8VINCENT R. D'ANTONI, JR., )

13)

14Petitioner, )

16)

17vs. ) Case Nos. 99-1916

22) 99-2861

24DEPARTMENT OF ENVIRONMENTAL )

28PROTECTION and DAVID BOSTON, )

33)

34Respondents. )

36________________________________)

37RECOMMENDED ORDER

39Pursuant to notice, a formal hearing was held in these cases

50on September 28, 1999, and January 27, 2000, in Jacksonville,

60Florida, and by telephone on February 21, 2000, before Donald R.

71Alexander, the assigned Administrative Law Judge of the Division

80of Administrative Hearings.

83APPEARANCES

84For Petitioner: Vincent R. D'Antoni, Jr., pro se

923824 Wayland Street

95Jacksonville, Florida 32277

98For Respondent: Francine M. Ffolkes, Esquire

104(agency) Department of Environmental Protection

1093900 Commonwealth Boulevard

112Mail Station 35

115Tallahassee, Florida 32399-3000

118For Respondent: David Boston, pro se

124(Boston) 2262 Orchard Street

128Jacksonville, Florida 32209

131STATEMENT OF THE ISSUES

135The issues are whether David Boston should be issued an

145environmental resource permit and sovereign submerged lands

152authorization allowing him to construct 96 linear feet of rip rap

163revetment; construct a private dock of less than 1,000 square

174feet; and place 3,500 square feet of fill in non-jurisdictional

185areas; and whether he qualifies for a general permit to place a

197fill pad in isolated wetlands adjacent to the St. Johns River, a

209Class III waterbody.

212PRELIMINARY STATEMENT

214This matter began on November 5, 1998, when Respondent,

223Department of Environmental Protection, issued a letter advising

231Respondent, David Boston, that he "qualified" to "use a noticed

241general permit to fill less than 4,000 square feet of an isolated

254wetland to facilitate construction of a single family home"; that

264the project was not on state owned submerged lands, and therefore

275he needed no authority from the agency to use those lands for

287private purposes; and that the project was exempt from the

297Environmental Resources Program permitting. That matter has been

305assigned Case No. 99-2861. On January 21, 1999, the agency

315issued a Notice of Permit Issuance advising interested parties

324that Respondent, David Boston, was being issued an environmental

333resource permit and submerged lands authorization to "construct a

342rip rap revetment and dock" on his property located adjacent to

353the St. Johns River in Duval County, Florida. That matter has

364been assigned Case No. 99-1916.

369By letter dated January 26, 1999, Petitioner, Vincent R.

378D'Antoni, Jr., an adjacent property owner, objected to the

387issuance of a permit in Case No. 99-1916 on the grounds that the

400proposed dock would infringe on the navigable area of his own

411dock; the fill would increase flooding on his property; and the

422project would harm an endangered fern. On June 1, 1999,

432Petitioner filed an Amended Petition for Administrative Hearing

440in Case No. 99-2861 alleging that the applicant does not qualify

451for a general permit because the filling would cause flooding on

462Petitioner's property; the stormwater storage function would be

"470eradicated"; and the use of the permit would diminish water

480quality and wildlife habitat in the river, thereby adversely

489affecting the value of his property.

495The two matters were referred by the agency to the Division

506of Administrative Hearings on April 28 and June 30, 1999,

516respectively, with a request that an Administrative Law Judge be

526assigned to conduct a formal hearing. At the request of the

537agency, both cases were consolidated by Order dated August 20,

5471999.

548By Notice of Hearing dated June 10, 1999, a final hearing

559was scheduled in Case No. 99-1916 on September 28, 1999, in

570Jacksonville, Florida. Later, however, the order of

577consolidation provided that both matters would be heard at that

587time. On September 22, 1999, the cases were transferred from

597Administrative Law Judge P. Michael Ruff to the undersigned.

606At the final hearing on September 28, 1999, the Department

616of Environmental Protection made an ore tenus request for a

626continuance on the ground that it needed to depose Petitioner's

636expert witness. The unopposed request was granted, and the

645matters were later rescheduled to January 27, 2000, in

654Jacksonville, Florida. A continued hearing was held by telephone

663on February 21, 2000, for the limited purpose of allowing

673Petitioner's engineering expert to present rebuttal testimony.

680At the final hearing, Petitioner testified on his own behalf

690and presented the testimony of his wife, Nancy N. D'Antoni, and

701Ronnie D. Perron, a professional engineer. Also, he offered

710Petitioner's Exhibit Nos. 1-6, which were received in evidence.

719Petitioner's Exhibit No. 1 is the deposition testimony of Ronnie

729D. Perron. Respondent, Department of Environmental Protection,

736presented the testimony of Michael Eaton, manager of

744environmental resource permitting and accepted as an expert in

753permitting and environmental impact of projects on wetlands and

762surface waters; Robert M. Dunne, an environmental specialist II;

771David P. Apple, a professional engineer and accepted as an expert

782in stormwater engineering and design; and Respondent, David

790Boston. Also, it offered Respondent's Exhibit Nos. 1-14. All

799exhibits were received in evidence.

804The Transcript of the hearing (two volumes) was filed on

814February 25, 2000. Proposed Findings of Fact and Conclusions of

824Law were filed by the Department of Environmental Protection on

834March 10, 2000, and they have been considered by the undersigned

845in the preparation of this Recommended Order. None were filed by

856the other parties.

859FINDINGS OF FACT

862Based upon all of the evidence, the following findings of

872fact are determined:

8751. In this permitting dispute between neighbors,

882Petitioner, Vincent R. D'Antoni, Jr., contends generally that

890Respondent, David Boston (Boston), will cause flooding to

898Petitioner's property by reason of placing too much fill on an

909isolated wetland, which lies in the center of Boston's property.

919The filling is in conjunction with Boston's efforts to construct

929a single-family residence and private dock on his property,

938purchased in June 1998, which lies adjacent to the St. Johns

949River, a Class III waterbody, in Duval County, Florida.

9582. In preliminary decisions made on November 5, 1998, and

968January 21, 1999, Respondent, Department of Environmental

975Protection ( DEP), "acknowledge[d] receipt" of Boston's intent to

984use a noticed general permit "to fill less than 4,000 square feet

997of an isolated wetland to facilitate construction of a single

1007family home" on his lot (Case No. 99-2861), and gave notice of

1019its intent to issue Boston an environmental resource permit and

1029sovereign submerged lands authorization allowing him to construct

1037a rip rap revetment and a dock and to place 3,500 square feet of

1052fill in mainly non-jurisdictional areas (Case No. 99-1916).

10603. Although a number of objections were raised by

1069Petitioner in his original filings, as clarified at the final

1079hearing, Petitioner now contends that Boston placed excessive

1087fill on his lot, including an isolated wetland, and that the fill

1099has resulted in flooding, saturated soil, or standing water on

1109Petitioner's property. He also contends that the location of

1118Boston's proposed dock will affect the ability to use his own

1129dock. Because no evidence was presented on the docking issue,

1139and through admissions Petitioner acknowledged that there will be

1148no adverse environmental impacts, no consideration will be given

1157to those objections. Finally, Petitioner does not object to the

1167placement of the rip rap revetment on the shoreline.

1176Accordingly, the request for an environmental resource permit and

1185consent to use sovereign submerged lands in Case No. 99-1916

1195should be approved.

11984. The property in issue lies just south of the

1208Jacksonville University Country Club and a few blocks west of

1218University Boulevard North on Wayland Street, which fronts the

1227eastern side of the St. Johns River in a tract of land known as

1241University Park. Except for the Boston lot, all other waterfront

1251lots are now developed. When facing the river from Wayland

1261Street, Petitioner's lot lies to the right of Boston's lot, while

1272another lot owned by Robert Henderson (Henderson) lies to the

1282left of Boston's lot. The lots are up to 500 feet deep; Boston's

1295lot is around 96 feet wide, while Petitioner's lot has a similar

1307width but narrows to only 20 feet or so near the river.

13195. At the river end of the D'Antoni, Boston, and Henderson

1330lots is an area of contiguous wetlands. Until 1995, DEP

1340regulated those wetland areas and this prevented D'Antoni and

1349Henderson from placing any fill in those areas. Under DEP's

1359current wetland delineation rule, however, such areas are non-

1368jurisdictional, and any placement of fill at the river end is

1379outside the purview of DEP's jurisdiction.

13856. Before Boston's lot was cleared and filled, it was about

1396a foot lower in elevation than the D'Antoni lot; this was true

1408even though Petitioner has never changed the natural grade of his

1419property since it was purchased and developed. Therefore, water

1428tended to flow naturally from an upland area north or east of the

1441D'Antoni lot, through the D'Antoni lot to Boston's lot, and then

1452through the lower part of the Henderson lot populated by "very

1463mature cypress trees," and eventually into the St. Johns River.

14737. According to a 1977 aerial photograph, the Boston lot

1483contained what appears to be a tidal connection from an uplands

1494area through the wetlands on his property to the river. However,

1505construction on property adjacent to the Henderson lot sometime

1514after 1977 severed this connection, and a tidal connection

1523(direct hydrologic connection) to the river no longer exists.

15328. Under Rule 62-341.475(1)(f), Florida Administrative

1538Code, "a single family residence" is exempt from the

1547Environmental Resource Program permitting and a general permit

1555will be granted "as long as it is not part of a larger plan of

1570common development," and "the total area of dredging or filling

1580in isolated wetlands for the residence and associated residential

1589improvement shall not exceed 4000 square feet." Since there is

1599no longer a direct hydrologic connection between the wetlands on

1609Boston's property and the St. Johns River, the wetlands are

1619isolated within the meaning of this rule.

16269. Availing himself of the foregoing provision, on

1634October 19, 1998, Boston gave notice to DEP "of [his] intent to

1646use a noticed general permit to fill less than 4,000 square feet

1659of an isolated wetland" on his property. He also provided

1669certain drawings and other information (prepared by his surveyor)

1678to show that he qualified for the permit. DEP does not "issue" a

1691noticed general permit; rather, it only determines whether the

1700applicant qualifies for a permit and then "acknowledges" this

1709fact. Accordingly, on November 5, 1998, DEP "acknowledge[d]

1717receipt" of Boston's notice.

172110. Although DEP encourages the user of such a permit to

1732notify affected or adjoining property owners, there was no legal

1742requirement that Boston do so, and he proceeded to clear the lot

1754and then fill a part of the wetland area with two or three feet

1768of dirt without giving notice to Petitioner or Henderson, his two

1779neighbors. The filling raised the elevation of the Boston

1788property at least two feet above the D'Antoni and Henderson lots

1799and impeded the prior natural flow of water. At the same time,

1811Boston constructed a three to four-foot timber wall (consisting

1820of railroad ties) on the Henderson property line to retain the

1831fill and a similar two-foot wall on Petitioner's line. These

1841changes had the effect of impounding the water which had

1851previously flowed naturally in a north-south direction through

1859the wetlands from the D'Antoni lot to the Boston lot to the

1871Henderson lot. It also generated runoff from the Boston lot to

1882the D'Antoni lot, which had not previously occurred.

189011. When Petitioner observed the adjacent lot being cleared

1899and filled, and the resulting erosion of fill onto his property,

1910pooling of water, and damage to his chain link fence after a

1922heavy rain in January 1999, he filed a complaint with DEP. An

1934inspection was made by DEP, and Boston was told to stop work

1946until corrective changes were made to ensure that such flooding

1956would not occur. After a series of changes were made which

1967satisfied DEP's concerns, the stop work order was lifted. Boston

1977also signed a consent order and paid a $100.00 fine. However,

1988pending the outcome of these cases, no further construction work

1998has occurred.

200012. Petitioner has contended that Boston has placed more

2009than 7,200 square feet of fill on his property in violation of

2022the rule, which limits the amount of fill to less than 4,000

2035square feet. While this amount of filling has in fact occurred,

2046approximately 3,500 square feet of fill was placed in non-

2057jurisdictional areas between the shoreline and the isolated

2065wetlands, and the rule only requires that Boston limit his fill

2076to less than 4,000 square feet on the isolated wetland. Thus,

2088contrary to a suggestion by Petitioner's engineer, the

2096jurisdictional and non-jurisdictional filling are not totaled

2103together to determine whether the threshold within the rule has

2113been exceeded.

211513. Through photographs received in evidence and testimony

2123by Petitioner and his wife, it was established that flooding or

2134standing water has occurred on Petitioner's property during heavy

2143rainfalls since the filling occurred, even as recently as

2152January 2000. The evidence further shows that Petitioner's chain

2161link fence has been damaged through the weight of the fill

2172pressing against the fence. In addition, Petitioner has suffered

2181the loss of "a couple of trees" because of "mucky" and

" 2192oversaturated" soil caused by excessive water. Also, a dog

2201house on a raised platform in the back yard which was previously

2213dry now "stays in water." These affected areas lie immediately

2223adjacent to the filled area of the isolated wetland on Boston's

2234property. Finally, there is an erosion problem beyond the

2243isolated wetland consisting of sand and silt flowing from

2252Boston's lot onto Petitioner's lot during heavy rainfalls.

2260Despite these problems, Petitioner does not object to the

2269development of the lot; he only asks that Boston do so in a

2282manner which prevents these conditions from recurring in the

2291future.

229214. Petitioner's engineering expert, Ronnie D. Perron

2299( Perron), a professional engineer who visited the site in August

23101999, ran a computer model (Interconnected Channel and Pond

2319Routing, Version 2.11) showing runoff both before and after the

2329fill was placed on Boston's lot. He concluded that "there was

2340over one and a half feet of flooding in that wetlands due to

2353filling Mr. Boston's lot" during a "mean annual storm event,"

2363which assumes five inches of rain during a 24-hour period. Even

2374when he used more conservative estimates, Perron still arrived at

2384water accumulations ranging from 0.6 feet to 1.5 feet. This

2394excessive runoff is caused by the retaining wall and fill, which

"2405blocks off" the water and causes it to "spread out in

2416[Petitioner's] whole back yard."

242015. In response to Perron's model, a DEP professional

2429engineer, David P. Apple (Apple), ran another computer model

2438(PONDS, Version 2.25) received in evidence as Respondent's

2446Exhibit No. 14. That model shows that during a three-year, one-

2457hour storm event, the small depressed area on Boston's property

2467(including the isolated wetland) had sufficient storage capacity

2475to absorb up to six inches of runoff from off-site areas and not

2488overflow back onto Petitioner's property. This size of storm

2497event (which produces two and one-half inches of rain in an hour)

2509is typically used by the Department in calculations for single-

2519family residential property when the impervious area site is less

2529than fifty percent. In this case, Apple didn't "feel that the

2540impervious area out there was greater than [fifty] percent."

2549Therefore, Apple concluded that the storm event used by Perron

2559was too large, and that the smaller event used in his model was

2572more appropriate. He also concluded that the Boston property

2581could retain all water in a normal storm event without

2591discharging any stormwater onto the D'Antoni lot. He did not,

2601however, address the issue of the fill and retaining wall on the

2613Boston lot impounding the water on his neighbor's lot.

262216. In developing the input perameters for his model, Apple

2632assumed that water falling at the front (Wayward Street) side of

2643the D'Antoni property drained to the front roadway; in fact, much

2654of that water drains to the rear of the lot into the wetland

2667area. A similar incorrect assumption was made regarding runoff

2676on the Boston lot. If modifications were made to account for the

2688proper drainage patterns, the Apple model would show larger

2697amounts of water staging on the Boston property during rainfall

2707events, which would increase the possibility of runoff onto the

2717D'Antoni lot.

271917. Apple questioned the accuracy of the Perron model given

2729the fact that Perron had used a larger storm event than he

2741(Apple) believed was appropriate. However, even if Perron had

2750used a three-year, one-hour storm event on his computer model, as

2761advocated by Apple, he established that it would have resulted in

2772flood staging on Petitioner's property between 0.97 and 1.64 feet

2782during a smaller storm event.

278718. DEP proposed no solutions to the water problems on the

2798D'Antoni lot, presumably because it concluded that the rule was

2808satisfied; that by filling the Boston lot, it was no longer the

" 2820stormwater pond for the neighborhood runoff"; and that DEP had

2830no other regulatory authority to solve this peculiar situation.

2839The record shows clearly, however, that if no changes are made,

2850water will continue to back up on Petitioner's property by virtue

2861of the higher elevation on the Boston lot, and the possibility of

2873runoff from Boston's lot exists during certain storm events.

2882Neither condition existed before the fill was added.

289019. To correct the foregoing conditions, Perron proposes

2898two corrective measures. First, Boston should install a yard

2907drain (underground culvert) beginning in the wetlands area of his

2917property and outfalling to the cypress trees on the adjacent

2927Henderson lot. Besides providing an outfall for the excess

2936water, this would also help recharge the mature cypress trees on

2947the Henderson lot. Second, D'Antoni should install a series of

"2957yard drains" using high-density polyethylene pipes to convey the

2966standing water on his lot directly into the St. Johns River. The

2978expert opined that neither activity would require a permit from

2988DEP. These modifications are reasonable and appropriate and

2996should be used by the factioning parties. Accordingly, the

3005installation of a yard drain should be a condition for Boston to

3017use his noticed general permit.

3022CONCLUSIONS OF LAW

302520. The Division of Administrative Hearings has

3032jurisdiction over the subject matter and the parties hereto

3041pursuant to Sections 120.569 and 120.57(1), Florida Statutes.

304921. As the party filing an application, Boston bears the

3059burden of proving by a preponderance of the evidence that he is

3071entitled to an environmental resource permit and sovereign

3079submerged lands authorization and that he is qualified to use the

3090noticed general permit. See , e.g. , Cordes v. State, Dep't of

3100Envir. Reg. , 582 So. 2d 652, 654 (Fla. 1st DCA 1991)(permit

3111generally); Castoro et al. v. Palmer and Dep't of Envir. Prot. ,

3122Case Nos. 95-5879 and 96-0736 ( Dep't of Envir. Prot., October 16,

31341998) (noticed general permit).

313822. Because Petitioner either withdrew his objections,

3145admitted through requests for admission, or failed to present any

3155proof regarding the issues involved in Case No. 99-1916, Boston's

3165application for an environmental resource permit and consent to

3174sovereign submerged lands should be approved. This will allow

3183him to construct 96 linear feet of rip rap revetment at the mean

3196high water mark of the St. Johns River, construct a private dock

3208of less than 1,000 square feet, and place 3,500 square feet of

3222fill on non-jurisdictional areas of his property.

322923. Rule 62-341.475, Florida Administrative Code, governs

3236the use of noticed general permits for minor activities, a type

3247of permit for which Boston seeks qualification to use in Case

3258No. 99-2861. Pertinent to this controversy are the disputed

3267criteria found in Sections (1) and (2) of the rule.

3277Subparagraphs (1)(f)3. and 4. require that the filling be limited

3287to "isolated wetlands," and that it "not exceed 4000 square

3297feet," while Paragraph (2)(c) requires that the filling "not

3306impede the conveyance of a stream, river[,] or other watercourse

3317in a manner that would increase off-site flooding."

332524. The evidence is undisputed that the jurisdictional

3333filling on Boston's property will be limited to less than 4,000

3345square feet in an isolated wetland. In addition, the evidence

3355shows that there is no stream, river, or other watercourse within

3366the meaning of DEP rules or statutes on the isolated wetland.

3377Therefore, because no watercourse exists on the property, the

3386filling cannot increase the type of off-site flooding envisioned

3395by the regulation. Assuming this analysis to be correct, then

3405the computer modeling by both experts was an academic exercise

3415since any off-site flooding which might be increased because of

3425the filling would not affect Boston's qualifications to use this

3435type of permit.

343825. Even so, it is clear that the filling impedes the

3449natural flow of water that occurred before the changes were made.

3460As noted in the Findings of Fact, during heavy rains which have

3472occurred as recently as January 2000, the D'Antoni lot has

3482suffered standing water and saturated soil, erosion of sand and

3492silt from the Boston lot, and damage to a chain link fence. If

3505this forum can provide no relief, then D'Antoni can only hope

3516that the drought conditions prevelant in northeast Florida will

3525continue for an indefinite period of time, or he can raise the

3537elevation of his lot by adding at least two feet of fill. For

3550obvious reasons, neither alternative is practical.

355626. Given these considerations, the solution offered by

3564Witness Perron is both reasonable and appropriate and should be

3574incorporated into the use of any noticed general permit. This

3584will result in both parties bearing the cost of making

3594improvements to their respective lots and should alleviate the

3603conditions now experienced by Petitioner.

3608RECOMMENDATION

3609Based on the foregoing Findings of Fact and Conclusions of

3619Law, it is

3622RECOMMENDED that the Department of Environmental Protection

3629enter a final order granting the application for a permit and

3640consent in Case No. 99-1916 and confirming that David Boston

3650qualifies for use of a noticed general permit in Case No. 99-2861

3662provided, however, that such use be conditioned on Boston

3671constructing an underground culvert with a yard drain from the

3681wetland area on his lot to the St. Johns River.

3691DONE AND ENTERED this 22nd day of March, 2000, in

3701Tallahassee, Leon County, Florida.

3705___________________________________

3706DONALD R. ALEXANDER

3709Administrative Law Judge

3712Division of Administrative Hearings

3716The DeSoto Building

37191230 Apalachee Parkway

3722Tallahassee, Florida 32399-3060

3725(850) 488-9675 SUNCOM 278-9675

3729Fax Filing (850) 921-6847

3733www.doah.state.fl.us

3734Filed with the Clerk of the

3740Division of Administrative Hearings

3744this 22nd day of March, 2000.

3750COPIES FURNISHED:

3752Kathy Carter, Agency Clerk

3756Department of Environmental Protection

37603900 Commonwealth Boulevard

3763Mail Station 35

3766Tallahassee, Florida 32399-3000

3769Vincent R. D'Antoni, Jr.

37733824 Wayland Street

3776Jacksonville, Florida 32277

3779David Boston

37812262 Orchard Street

3784Jacksonville, Florida 32209

3787Francine M. Ffolkes, Esquire

3791Department of Environmental Protection

37953900 Commonwealth Boulevard

3798Mail Station 35

3801Tallahassee, Florida 32399-3000

3804Teri Donaldson, General Counsel

3808Department of Environmental Protection

38123900 Commonwealth Boulevard

3815Mail Station 35

3818Tallahassee, Florida 32399-3000

3821NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

3827All parties have the right to submit written exceptions within 15

3838days from the date of this Recommended Order. Any exceptions to

3849this Recommended Order should be filed with the agency that will

3860enter a final order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 05/08/2000
Proceedings: Final Order filed.
PDF:
Date: 05/05/2000
Proceedings: Agency Final Order
PDF:
Date: 03/22/2000
Proceedings: Recommended Order
PDF:
Date: 03/22/2000
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 09/28/99 & 01/27/2000.
Date: 03/10/2000
Proceedings: DEP`s Proposed Recommended Order filed.
Date: 03/09/2000
Proceedings: Department`s Exhibit 14 w/cover letter filed.
Date: 02/25/2000
Proceedings: Transcript filed.
Date: 02/21/2000
Proceedings: CASE STATUS: Hearing Held.
Date: 02/21/2000
Proceedings: Letter to Judge Alexander from R. Perron Re: Summary (filed via facsimile).
Date: 02/21/2000
Proceedings: Letter to Judge Alexander from R. Perron Re: Summary (filed via facsimile).
Date: 02/11/2000
Proceedings: ASEDFSD 2/11/2000)
Date: 02/11/2000
Proceedings: ASDFSDF
Date: 02/10/2000
Proceedings: Transcript filed.
Date: 02/02/2000
Proceedings: Order sent out. (Petitioner shall have until 2/10/00, to notify the undersigned whether he intends to offer testimony in response to Respondent`s Exhibit 14)
Date: 01/27/2000
Proceedings: CASE STATUS: Hearing Held.
Date: 01/18/2000
Proceedings: Amended Notice of Hearing sent out. (hearing set for January 27, 2000; 9:00 a.m.; Jacksonville, FL, amended as to TIME AND LOCATION)
Date: 12/02/1999
Proceedings: Amended Notice of Hearing sent out. (hearing set for January 27, 2000; 10:30 a.m.; Jacksonville, FL)
Date: 11/23/1999
Proceedings: Memorandum to Judge Alexander & Judge Ruff from V. D`Antoni Re: Date not available (filed via facsimile).
Date: 11/08/1999
Proceedings: Order Scheduling Hearing sent out. (hearing set for 12/22/99; 10:30am; Jacksonville)
Date: 10/26/1999
Proceedings: DEP`s Response to Order (filed via facsimile).
Date: 10/21/1999
Proceedings: Memorandum to Judge Alexander from V. D`Antoni Re: Dates not available (filed via facsimile).
Date: 10/11/1999
Proceedings: Order sent out. (parties shall respond within 15 days from the date of this order)
Date: 09/28/1999
Proceedings: Hearing Partially Held, continued to date not certain.
Date: 09/24/1999
Proceedings: (Respondent) Notice (filed via facsimile).
Date: 09/24/1999
Proceedings: Letter to Judge Alexander from V. D`Antoni Re: Late arrival of interrogatories; Interrogatories; Exhibits filed.
Date: 09/23/1999
Proceedings: DEP`s Prehearing Statement filed.
Date: 09/22/1999
Proceedings: Order sent out. (changing location of hearing)
Date: 09/22/1999
Proceedings: DEP`s Witness and Exhibit List; DEP`s Motion to Compel and for Admissions filed.
Date: 08/20/1999
Proceedings: Order of Consolidation sent out. (Consolidated cases are: 99-001916, 99-002861)
Date: 08/05/1999
Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
Date: 07/01/1999
Proceedings: Initial Order issued.
Date: 06/30/1999
Proceedings: (Respondent) Motion to Consolidate (Cases requested to be consolidated: 99-2861, 991916); Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Agency Action Letter filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
06/30/1999
Date Assignment:
09/21/1999
Last Docket Entry:
05/08/2000
Location:
Jacksonville, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
 

Related DOAH Cases(s) (2):

Related Florida Statute(s) (7):

Related Florida Rule(s) (6):