Mary Anne Helton, Esquire
Address of Record
ALL 7
-
07-002713EPP
In Re: Progress Energy Florida, Crystal River Unit 3 Uprate Project Power Plant Siting Application No Pa77-09a2 vs. *
Status: Closed
Recommended Order on Thursday, June 5, 2008. -
07-002464EPP
In Re: Florida Municipal Power Agency, Jea, City Of Tallahassee, And Reedy Creek Improvement District Taylor Energy Center Power Plant Siting Application No. Pa 07-50 vs. *
Status: Closed
Settled and/or Dismissed prior to entry of RO/FO on Friday, July 13, 2007. -
05-004347EPP
In Re: Hillsborough County Resource Recovery Facility Expansion Power Plant Siting Application No. Pa 83-19a vs. *
Status: Closed
Recommended Order on Wednesday, August 2, 2006. -
04-003209EPP
In Re: New Hope Power Partnership Okeelanta Cogeneration Facilities Power Plant Siting Application No. Pa 04-46 vs. *
Status: Closed
Recommended Order on Thursday, March 31, 2005. -
04-002817EPP
In Re: Progress Energy Florida Hines Energy Center Power Block 4 Power Plant Siting Application No. Pa 92- 33sa3 vs. *
Status: Closed
Recommended Order on Tuesday, April 5, 2005. -
03-004391EPP
In Re: Florida Power And Light Turkey Point Unit Power Plant Siting Application No. Pa 03-45 vs. *
Status: Closed
Recommended Order on Thursday, November 18, 2004. -
03-001629TL
In Re: Florida Power And Light, Collier-Orange River No. 3, 230 Kv Project, Transmission Line Siting Application No. Ta03-12 vs. *
Status: Closed
Recommended Order on Monday, May 3, 2004.