Found about 3 matches
-
21-001939TL In Re: Orlando Utilities Commission; St. Cloud East-Magnolia Ranch North 230 Kv Transmission Line Siting Application No. Ta21-18 vs. *
Status: Closed
Settled and/or Dismissed prior to entry of RO/FO on Tuesday, November 9, 2021. -
07-005691TL In Re: Tampa Electric Company And Progress Energy Company`s Lake Agnes-Gifford Transmission Line Siting Application No. Ta07-16 vs. *
Status: Closed
Recommended Order on Wednesday, October 22, 2008. -
07-004745TL In Re: Tampa Electric Company Willow Oak-Wheeler-Davis Transmission Line Siting Application No. Ta07-15 vs. *
Status: Closed
Recommended Order on Tuesday, May 13, 2008.