29A-3.005. Timeframes  


Effective on Sunday, November 13, 1994
  • 1(1) The initial settlement meeting shall be scheduled and held within 30 days of the date of the receipt of the initiation letter at a time and place convenient to the named parties.

    34(2) Additional settlement meetings, mediation or advisory decision-making shall be completed within forty-five (45) days of the date of the conclusion of the initial settlement meeting.

    60(3) All time frames specified in this rule may be shortened or extended by mutual agreement of the named parties.

    80(4) The parties may by mutual agreement utilize procedures in the RDRP in any order.

    95(5) Where necessary to allow this process to be effectively carried out, named parties should address deferring or seeking stays of judicial or administrative proceedings.

    120Specific Authority 122186.509 FS. 124Law Implemented 126186.509 FS. 128History–New 11-13-94.

     

Rulemaking Events:

Related Statutes: