29F-3.105. Timeframes  


Effective on Wednesday, December 8, 1999
  • 1(1) The initial meeting of the participating parties shall be scheduled and held within 30 days of the date of receipt of the last response letter or conclusion of the 21 calendar day response period referenced in subsection 3929F-3.103(3), 40F.A.C., whichever occurs first.

    44(2) Additional settlement meetings, mediation or advisory decision-making shall be completed within forty-five (45) days of the date of the conclusion of the initial settlement meeting.

    70(3) Excepting the 30-day period for the initial meeting, all time frames specified or agreed to in this process may be shortened or extended by mutual agreement of the named parties.

    101(4) Where necessary to allow this process to be effectively carried out, named parties should address deferring or seeking stays of judicial or administrative proceedings.

    126(5) The participating parties may, by agreement, utilize procedures in the RDRP in any order.

    141Rulemaking Authority 143186.505 FS. 145Law Implemented 147186.509 FS. 149History–New 12-8-99.

     

Rulemaking Events: