40E-3.301. Conditions for Issuance of Permits  


Effective on Monday, July 14, 2014
  • 1(1) The applicant shall comply with the applicable provisions of Chapter 373, F.S., and this chapter.

    17(2) A water use permit, if applicable under Chapter 40E-2, F.A.C., must have already been obtained. If a water use permit has not been obtained, an application for a consumptive use permit must be submitted concurrently with the well construction application and must also be approved by the District prior to issuance of the well construction permit.

    74(3) The proposed well must not harm the water resources of the District or interfere with existing legal users.

    93(4) The application must be complete and must meet the requirements of Chapter 373, F.S., and this chapter.

    111(5) The District or delegated agency shall impose on any permit issued under this chapter such reasonable conditions as are necessary to protect the water resource and to assure that the permitted activity will be consistent with the overall objectives of the District. The District or delegated agency shall attach such conditions to the well construction, repair, or abandonment permit and the conditions shall be performed accordingly.

    178Rulemaking Authority 180373.044, 181373.113, 182373.171 FS. 184Law Implemented 186373.103, 187373.306, 188373.308, 189373.309, 190373.313, 191373.342 FS. 193History–New 1-1-85, Amended 3-16-05, 7-14-14.

     