40B-3.492. Violations of Permits  


Effective on Tuesday, June 22, 1999
  • 1(1) Actions, omissions, or conduct which are considered as violations for the purposes of Part II shall include, but are not limited to, the following:

    26(a) Failure to obtain a permit where required under Rule 3640B-3.041, 37F.A.C.

    38(b) Failure to comply with any or all permit conditions.

    48(c) Failure to submit a completion report within 30 days of the completion of the construction, repair, or abandonment of any well.

    70(d) Failure to file an accurate completion report.

    78(e) Failure to report to the district within 30 days of expiration of the permit when no work is performed or the well is not completed.

    104(f) Failure to notify the District 24 hours prior to the grouting of the annular space of any public supply well.

    125(2) Actions which may be taken by District staff upon determination that a violation has occurred are outlined in Chapter 40B-1, F.A.C.

    147Specific Authority 149373.044, 150373.113, 151373.171 FS. 153Law Implemented 155373.308, 156373.309, 157373.342 FS. 159History–New 7-1-85, Amended 6-22-99.

     

Rulemaking Events: