Florida Administrative Code (Last Updated: November 11, 2024) |
60. Department of Management Services |
60GG. Florida Digital Service |
60GG-1. Department of Management Services Project Management and Oversight |
1(1) Project Monitoring and Controlling spans all phases of the project and involves the regular review of project status in order to identify variances from baselined project schedule, cost, and scope. In addition, all project management plan components developed pursuant to Rule 4360GG-1.44004, F.A.C., Planning, must be monitored, controlled and maintained.
53(2) Risk and Complexity (R&C) Category 4 and 3 Projects will use Earned Value analysis to ensure that the schedule provides an accurate representation of project status.
80(a) Schedule Performance Index (SPI)
851. SPI is a measure of schedule efficiency expressed as a ratio of Earned Value (EV) to Planned Value (PV): SPI = EV/PV, where Earned Value is the measure of work performed expressed in terms of the budget amount authorized for that work, and Planned Value is the authorized budget assigned to scheduled work. Planned Value corresponds to the approved baseline budget.
1472. A SPI value of less than 1.0 indicates that less work was completed, in a given time frame, than was planned.
1693. A SPI value greater than 1.0 indicates that more work was completed, in a given time frame, than was planned.
190(b) Cost Performance Index (CPI)
1951. CPI is a measure of cost efficiency of budgeted resources for the work completed. CPI is expressed as a ratio of Earned Value (EV) to Actual Cost (AC): CPI = EV/AC, where Earned Value is the measure of work performed expressed in terms of the budget amount authorized for that work, and Actual Cost is the realized cost incurred for the work performed on an activity or set of activities during a specific time period.
2712. A CPI value of less than 1.0 indicates a cost overrun for work completed, in a given time frame.
2913. A CPI value greater than 1.0 indicates a cost underrun of performance to date.
306(3) The following matrix details specific Monitoring and Controlling documentation and activities required for the project based on the project’s R&C Category.
328MONITORING AND CONTROLLING 331‒ Requirements by Risk & Complexity Category
3384
3393
3402
3411
342Monitor and Control Project 346Change
347Required ‒ Follow the change control process(es) documented in the Change Management Plan. Complete an Event-Driven Risk & Complexity (R&C) Assessment for significan370t change requests 373(see Rule 37560GG376-1.002, F.A.C. ‒ Risk and Complexity Assessment)383. This assessment will confirm or adjust the project’s cumulative risk and complexity levels and R&C Category, and assist the Agency in determining whether changes to any proje411ct management plan documents and baselines are needed. Maintain a change tracking log that includes change description, project impact (scope, schedule, and cost), owner, and status. This log is used to track, enter, review, analyze, approve, update, and report on project changes.
4534
4543
4552
4561
457Monitor and Control Project Schedule
462Required 463‒ Update the schedule at least weekly to reflect actual progress toward completion of scheduled tasks, milestones, and deliverables.
482Required ‒ Update the schedule at least biweekly to reflect actual progress toward completion of scheduled tasks, milestone500s, and deliverables.
503Required ‒ Use SPI to assess schedule variance. If SPI analysis indicates a trend towards a variance equal to or greater than 10% (SPI score ≤ 0.90 or ≥ 1.10), communicate the variance explanation to the project’s key stakeholder(s).
542Required ‒ Evaluate the baselined schedule against current progress.
5511. Identify overdue tasks and compute the percentage of late tasks related to total tasks to date (Number of Overdue Tasks/Number of Total Tasks).
5752. If this analysis indicates a trend t583owards a variance, 586equal to or greater than 10%, communicate the variance explanation to the project’s key stakeholders.
6014
6023
6032
6041
605Monitor and Control Project Cost
610Required ‒ Monitor project costs monthly to identify both positive and negative variances b624etween planned and actual expenditures.
6291. Compare baselined planned expenditures to actual expenditures captured in the spending plan or the budget.
6452. Identify the difference in baselined planned and actual expenditures and compute the percentage of cost variance for the period (Cost Variance/Total Planned Cost).
6693. If there is a variance (positive or negative) equal to or greater than 10%, communicate the variance explanation to the project’s key stakeholder(s).
693Required 694‒ Use CPI to assess cost variance.
701If the CPI analysis indicates a trend towards a variance equal to or greater than 10% (CPI score ≤ 0.90 or ≥ 1.10), communicate the variance explanation to the project stakeholders.
732Not Required
7344
7353
7362
7371
738Monitor and Con741trol Project 743Scope
744Required ‒ Monitor project scope, and manage changes to the original and agreed-upon scope as documented in the approved project planning documents.
766Required ‒ Monitor project scope and document changes.
7744
7753
7762
7771
778Monitor and Control Pr782oject 783Quality
784Required ‒ Monitor and Control quality as documented in the Quality Management Plan.
7974
7983
7992
8001
801Monitor and Control Project 805Risks
806Required ‒ Monitor and control risks as documented in the approved Risk Management Plan.
820Perform risk reassessm823ents to identify new risks, reassess current risks, escalate risks to issues, and close outdated risks.
839Maintain a risk tracking log that includes risk description, owner, response/mitigation strategy, risk probability, impact, priority, status and open/close dates. This log is used to track, enter, review, analyze, update, monitor, and report on risks.
874Required – Monitor, document, and address risks.
8814
8823
8832
8841
885Monitor and Control Project 889Issues
890Required 891‒ Monitor and control issues as documented in the approved Issue Management Plan.
904Review issues to identify new issues, reassess current issues, and close resolved issues.
917Maintain an issue tracking log, which includes Issue description, owner, status, and 929dates opened, due and closed. This log is used to track, enter, review, analyze, update, monitor, and report on issues.
949Required ‒ Monitor, document, and resolve issues.
9564
9573
9582
9591
960Decision Tracking
962Required ‒ Maintain a decision tracking log that includ971es decision description, approval authority, date of entry, due date, actual date of decision, project impact (scope, schedule, and cost), and status.
993This log is used to track, enter, review, analyze, update, monitor, and report on decisions.
1008Recommended
10094
10103
10112
10121
1013Action Item
1015Tracking
1016Required 1017‒ Maintain an action item log that includes Action Item description, owner, dates assigned and due, and status. This log is used to track, enter, review, analyze, update, monitor, and report on action items.
1051Recommended
10524
10533
10542
10551
1056Florida Cybersecurity Sta1059ndards
1060Required – 1062Monitor and control project compliance with 1068rule Chapter 60GG-2, F.A.C.
10724
10733
10742
10751
1076Requirements Traceability Matrix
1079(RTM)
1080Required ‒ Review and amend the RTM to capture progressive detail of requirements linkage throughout the project.
1097T1098his matrix is used to document and link requirements from their origin to the deliverables that satisfy them.
1116Required ‒ Update requirements documentation as necessary.
11234
11243
11252
11261
1127Lessons Learned
1129Required ‒ Capture lessons learned from project team and sta1139keholders throughout the project.
1143(4) The Agency will report project status based on 1152the project’s 1154R&C Category at least monthly. 1159Form DMS-F-0505B, Project Status Report (07/19), is hereby incorporated by reference in this rule. Form DMS-F-0505B can be found at 1179https://www.flrules.org/Gateway/refer1180e1181nce.asp?No=Ref-072221183. 1184Status reports will include:
1188PROJECT STATUS REPORT – Requirements by Risk & Complexity Category
11984
11993
12002
12011
1202Section 1 –
1205Project Status Overview
1208A. Overview of Project Progress.
1213B. Overall Status
1216C. Schedule Performance Index (SPI)
1221Cost Performance Index (CPI)
1225Not Required
12274
12283
12292
12301
1231Section 2 –
1234Project Progress
1236A. Project Milestones, Deliverables & Major Tasks
1243Not Required
1245B. Scope Changes
1248Summarize in Section 1B Only
12534
12543
12552
12561
1257Section 3 – Project
1261Issues and Risks
1264A. Project Issues
1267Summarize in Section 1B Only
1272B. Project Risks
1275Summarize in Section 1B Only
12804
12813
12822
12831
1284Section 4 – Project
1288Spending Plan
1290A. Identify Baselined Planned Expenditures vs. Actual Expenditures
1298Not Required
1300B. Major Project Expenditures
1304Not Required
1306Attach current project spend plan
1311Not Required
1313Rulemaking Authority 1315282.0051(6) 1316FS. Law Implemented 1319282.0041, 1320282.0051 1321FS. History‒New 7-16-15, Amended 8-1-16, Formerly 74-1.006.