62-17.625. Alternate Corridor Processing  


Effective on Monday, May 24, 2010
  • 1(1) The Department shall reject a proposed alternate corridor if one or more of the following criteria is met:

    20(a) The alternate does not have appropriate end points which connect to the remainder of the transmission line;

    38(b) The quality of the filing is so poor as to make it difficult for the Department to evaluate the proposal; or

    60(c) The information required by Section 66403.5271(1)(a), F.S., 68has not been submitted; however, this shall be without prejudice to refile within the timeframes set forth in Section 87403.5271(1), F.S.

    89(2) Acceptance by the Department of an alternate corridor proposed for consideration pursuant to Section 104403.5271(1), F.S., 106above shall not require the Department to support or oppose certification of such alternate corridor.

    121(3) Acceptance by the applicant of an alternate corridor proposed for certification shall not require the applicant to support or oppose certification of such alternate corridor.

    147Rulemaking Authority 149403.523(1) FS. 151Law Implemented 153403.5271 FS. 155History–New 6-26-84, Formerly 17-17.625, Amended 5-24-10.

     