62-330.351. General Conditions for Conceptual Approval Permits  


Effective on Friday, June 1, 2018
  • 1The following general conditions are binding on all conceptual approval permits issued under this chapter, except where the conditions are not applicable to the activity or where the conditions must be modified to accommodate 35project-specific situations. In addition to these general conditions, the Agency shall impose any additional special conditions necessary to assure the permitted activities will not be harmful to the water resources, as set forth in rules 7062-330.301 71and 7262-330.302, 73F.A.C., Volumes I and II, as applicable, and the rules incorporated by reference in this chapter.

    89(1) This permit does not authorize any construction, alteration, maintenance, operation, removal, or abandonment, except where such activities are specifically authorized as the first phase of an individual permit or are authorized to occur in accordance with a general permit or exemption under chapter 62-330, F.A.C.

    135(2) This permit does not:

    140(a) Convey to the permittee any property rights or privileges, or any other rights or privileges other than those specified herein or in chapter 62-330, F.A.C.;

    166(b) Convey to the permittee or create in the permittee any interest in real property;

    181(c) Relieve the permittee from the need to obtain and comply with any other required federal, state, and local authorization, law, rule, or ordinance; or

    206(d) Authorize any entrance upon or work on property that is not owned, held in easement, or controlled by the permittee.

    227(3) 228The permittee shall notify the Agency in writing:

    236(a) Immediately if any previously submitted information is discovered to be inaccurate; and

    249(b) 250Within 30 days of any conveyance or division of ownership or control of the property or the system, the name and contact information for the new owner.

    277(4) Upon reasonable notice to the permittee, Agency staff with proper identification shall have permission to enter, inspect, sample, and test the project site to ensure conformity with the permit.

    307(5) Any delineation of the extent of a wetland or other surface water submitted as part of the permit application, including plans or other supporting documentation, shall not be considered binding unless a specific condition of this permit or a formal determination under rule 35162-330.201, 352F.A.C., provides otherwise.

    355(6) This conceptual approval permit only authorizes design concepts for a master or future plan to construct, alter, operate, maintain, remove, or abandon projects that require a permit under part IV of chapter 373, F.S. It does not authorize any construction, alteration, operation, maintenance, removal, or abandonment, or the establishment and operation of a mitigation bank, or relieve the permit holder of any requirements to obtain such permits.

    423(7) Subsequent applications to construct and operate activities shall be prepared and submitted using the applicable procedures in rules 44262-330.052, 44362-330.054, 44462-330.060, 445and 44662-330.402, 447F.A.C., and sections 4.2.2, 4.2.3, 4.3, and 4.4 of Volume I. An application for conceptual approval for a mitigation bank shall also include the materials required by chapter 62-342, F.A.C.

    477(8) Issuance of this conceptual approval permit is a determination, within the level of detail provided in the application, that the activities approved in this permit are consistent with applicable rules at the time of issuance. This permit provides the conceptual approval permit holder with a rebuttable presumption, during the duration of this permit, that the engineering design and scientific principles upon which the conceptual approval permit approved herein are likely to meet applicable rule criteria for issuance of permits for subsequent phases of the project, provided all of the following are met at the time of receipt of a complete application to construct and operate the future phases:

    586(a) The application to construct and operate the future phases remains consistent with the designs and conditions of this permit. Primary areas for consistency comparisons include the size, location, and extent of the activities proposed, the type and nature of the activities, percent imperviousness, allowable discharge and points of discharge, location and extent of wetland and other surface water impacts, mitigation plans implemented or proposed, control elevations, extent of stormwater reuse, detention and retention volumes, and the extent of flood elevations.

    667If an application for construction of any portion of the land area covered by this permit is inconsistent with the design concepts and conditions approved herein, the application will be reviewed to determine the extent to which the inconsistency will affect the designs and conditions for the remainder of the lands contained in this permit. If the inconsistency will materially affect those designs and conditions, then the applicant must demonstrate that the holder of this permit agrees to that inconsistency. In such a case, the holder of the conceptual approval permit may:

    7591. Modify the conceptual approval permit to conform to the revised design;

    7712. Abandon reliance on the conceptual approval permit; or

    7803. Rely on those portions of the conceptual approval permit for only those areas that were not affected by the inconsistency.

    801(b) There are no changes to state water quality standards that would be affected by activities authorized in the conceptual approval permit that have not already been authorized for construction or operation.

    833(c) There have been no amendments to Florida law governing special basin criteria that would affect future activities authorized by the conceptual approval permit that have not already been authorized for construction.

    865(d) There are no substantive changes in the site characteristics that would affect whether the design concepts approved in the conceptual approval permit can continue to be reasonably expected to meet the conditions for authorizing construction of future phases. This shall include such things as changes in the designation of listed species, and changes to nesting, denning, and critical designation status of listed species that exist within the lands served by the project area.

    939(9) If changes are proposed to the design of existing or future phases, or where there have been changes to state water quality standards, special basins, or site characteristics as described in conditions paragraphs (3)(a) through (d), above, during the duration of this permit, the applicant must modify this permit if it wishes to continue to rely on this permit as a basis that reasonable assurance exists for the Agency to issue future construction or operation permits under the terms and conditions of this permit. If the permittee fails to do this, this conceptual approval permit can no longer be relied upon as a basis, in part or whole, under which permits to construct or operate future phases will be issued, and the Agency will reevaluate the terms and conditions of this permit at the time a permit application is received to construct the next phase of activities, or at the next requested extension of this permit’s duration in accordance with subsection 110162-330.056(11), 1102F.A.C., whichever occurs first.

     

Rulemaking Events: