74-1.004. Planning (Transferred)  


Effective on Monday, August 1, 2016
  • 1(1) In the Planning phase, the Agency develops and approves detailed project planning documents.

    15(2) The matrix provided below lists planning activities and documents required for the project based on the project’s Risk and Complexity (R&C) Category.

    38(a) Specific document types, templates, or formats are not prescribed – any documentation that contains the information specified in the requirements below is acceptable.

    62(b) This documentation, whether created separately or combined as a sin73gle document, constitutes the Project Management Plan.

    80PLANNING PHASE ‒ Requirements by Risk & Complexity Category

     

    894

    903

    912

    921

    93Project Scope

    95Required ‒ Clearly delineate the project scope, specifically what is in scope, what is out of scope, project objecti114ves, and deliverables. This will determine scope baselines and variances. Discuss how the project scope and objectives trace back through the Project Charter to initial project documents such as the Schedule IV-B.

     

    146Document the approach for project execution (identify the Software Development Life Cycle model that will be used – such as Agile, waterfall, etc.) Identify assumptions and constraints.

    173Required 174‒ Summarize the project scope (in scope and out of scope).

     

    1854

    1863

    1872

    1881

    189Work Breakdown Structure (WBS)

    193Required – Document the hierarchical and incremental decomposition of the project into phases, deliverables, and work packages. Identifies all the tasks re215quired to deliver the total project scope of work to produce each deliverable. Tasks must be decomposed into subtasks until they can be estimated, observed, and evaluated.

    242Not Required

     

    2444

    2453

    2462

    2471

    248Project Organizational and Governance Structure

    253Required – Document a representation of the project from an organizational perspective. Include an organization chart with stakeholder and governance structures identified. Include a detailed description of the project and the Agency’s governance process with roles, r290esponsibilities, and approval authorities identified for project documents or artifacts, including any processes for final product acceptance. Include reporting and escalation parameters for variances in baseline schedule, cost, and scope.

    320Required ‒ Ident323ify the project stakeholders and the responsibilities for decision-making and escalation.

     

    3344

    3353

    3362

    3371

    338Resource Plan

    340Required ‒ Document the resources required to complete the project and how these resources will be acquired.

    357For human resources – identify p363roject roles, skills, number, and resource type required, and specify the method(s) for acquiring new personnel or incorporating and backfilling the current responsibilities of existing personnel.

    389For equipment or materials ‒ identify types, quantities, an398d purpose, and specify the method(s) for acquiring equipment or materials.

    409Recommended: List the number and type of resources anticipated and what, if any, resources must be procured.

     

    4264

    4273

    4282

    4291

    430Schedule Management Plan

    433Required ‒ Document the approach to 439create an integrated master schedule that encompasses the total scope of the project and identifies the projects critical path. Describe the process for establishing and changing the schedule baseline. Describe the responsibilities, timeframes, and methods to manage, update and report progress (including Earned Value Analysis) throughout the project.

    487Recommended 488‒ Document the approach to create an integrated master schedule that encompasses the total scope of the project and identifies the projects critical path.

     

    5124

    5133

    5142

    5151

    516Project Schedule

    518Required ‒ Develop and maintain an integrated master project schedule tha529t identifies the total project scope of work (including milestones and deliverables); is task, 543resource, and cost 546loaded; identifies the project critical path, is baselined and updated with project progress; and contains the information necessary to provide earned value analysis and support schedule and cost performance index (SPI and CPI) variance analysis and reporting.

    583Required 584‒ Develop, and maintain a schedule that identifies the total project scope of work, assigned resources, and task start and end dates.

     

    6064

    6073

    6082

    6091

    610Project Budget

    612Required ‒ Develop and maintain a Project Budget, which must include specific fiscal year cost t628otals over the life of the project and the overall total cost of the project. Also include a description of the funding source(s) for the Project and a breakdown of the Project costs by major expense categories.

    665Required – Develop and maintain a Project Budget, which must include specific fiscal year cost totals over the life of the project and the overall total cost of the project.

     

    6954

    6963

    6972

    6981

    699Project Spending

    701Plan

    702Required 703‒ Develop and maintain a Project Spending Plan, which, as a component of the Project Budget, must include monthly planned (baselined) and actual expenditures (by expenditure or expenditure category) for each fiscal year.

    736Required ‒ Document current fiscal 741year planned expenditures and actual expenditures by month and Fiscal Year total to date. Include other expenditure detail as required for the Project Status Report.

    766Recommended ‒

    768Document current fiscal year planned expenditures and actual expenditures b778y month and Fiscal Year total to date.

     

    7864

    7873

    7882

    7891

    790Communications Management Plan

    793Required ‒ Identify the project information requirements of stakeholders and detail what, when, and how information will be collected and reported.

    814This will include the respo819nsibility, frequency, format, and distribution method for meeting summaries, project status reports, project governance meetings, and stakeholder communications, including reporting variances in schedule, cost, or scope and emerging risks or issues. Document the location of the project repository.

    857Include documentation for Decision Tracking and Action Item Tracking (see Rule 74-1.006, F.A.C. 870‒ Monitoring and 873Controlling874).

    875Required ‒ Identify the project information requirements of stakeholders and detail what, when, and how information will be collected and reported.

     

    8964

    8973

    8982

    8991

    900Change Management Plan

    903Required ‒ Document the change control proc910ess and documentation involved in identifying, analyzing impacts, escalating, approving, and managing project change requests related to the project’s schedule, cost, or scope baselines, or a change to project deliverables (see rule 74-1.006, F.A.C. ‒ Moni946toring and 948Controlling949).

     

    9504

    9513

    9522

    9531

    954Quality Management Plan

    957Required ‒ Document the processes and procedures for ensuring quality planning, quality assurance, and quality control are all conducted.

    976Required ‒ Document any method(s) for ensuring customer acceptance of the product or service.

     

    9904

    9913

    9922

    9931

    994Deliverable Acceptance Plan

    997Required ‒ Document each deliverable, the acceptance criteria for each deliverable, and the deliverable acceptance process (including roles and responsibilities).

    1017Required ‒ List the deliverables and the person(s) responsible for approving deliverables.

     

    10294

    10303

    10312

    10321

    1033Risk Management

    1035Plan

    1036Required ‒ Document the process for the descriptive identification (listing), evaluation (probability and impact), prioritization, and response to risks (specified mitigation strategies for each risk), as well as the nature of any time sensitivity to risks that may impact the project. Identify the roles and responsibilities of individuals assigned to risks. Identify and document the process to be used for tracking, periodic review, and update of Risks (see Rule 74-1.006, F.A.C. ‒ Monitoring and 1110Controlling1111).

    1112Required ‒ Describe the method for monitoring and controlling risk.

     

    11224

    11233

    11242

    11251

    1126Issue Management

    1128Plan

    1129Required ‒ Document the process for (and the documentation of) the identification, evaluation, management, and resolution to issues impacting the project. Identify and document the process to be used for tracking, periodic review, and update of Issues (see Rule 74-1.006, F.A.C. ‒ Monitoring and 1173Controlling1174). Identify the roles and responsibilities of project staff.

    1183Required ‒ Describe the method for monitoring and addressing issues.

     

    11934

    11943

    11952

    11961

    1197Procurement Management Plan

    1200Required ‒ If procurement is required by the project, document any products or services needed, identify the specific products and services to be purchased, along with the appropriate purchasing methods, rules, and statutes affecting these activities.

    1236Required ‒ List any procurements required for the project.

     

    12454

    12463

    12472

    12481

    1249Organizational Change Management Plan

    1253Required ‒ Document the impact of delivering the project’s products to the user organization and individual users; the readiness of the user organization and individual users to accept those changes; and describe and plan the action necessary to facilitate those changes.

    1294Required ‒ Document the impact of delivering the projects products to the user organization and the individual users.

    1312Recommended – Document the impact of delivering the projects products to the user organization and the individual users.

     

    13304

    13313

    13322

    13331

    1334Florida Cybersecurity Standards

    1337Required – Compliance with Rule Chapter 74-2, F.A.C.

     

    13454

    13463

    13472

    13481

    1349Requirements Traceability Matrix

    1352(RTM)

    1353Required ‒ Prepare a document (usually a table) that links high-level design and requirements with detailed requirements, detailed design, test plan, and test cases.

    1377The RTM ensures that all requirements are identified and correctly linked (from high-level to detailed and technical levels) throughout the project.

    1398Required ‒

    1400Document Requirements.

    1402Planning Gate R&C Assessment

    1406Required

    1407(3) The Agency must complete the Planning Gate R&C Assessment at the end of the Planning phase 1424(see rule 74-1.002 ‒ Risk and Complexity Assessment, F.A.C.)1433. This Assessment will confirm or adjust the project’s risk and complexity levels and the resulting R&C Category, validate Planning management control requirements, and set management control requirements for the subsequent Execution and Monitoring and 1468Controlling 1469phases.

    1470Rulemaking Authority 1472282.0051(18) 1473FS1474. Law Implemented 1477282.0041, 1478282.0051 FS. History‒New 7-16-15, Amended 8-1-16.

     

Rulemaking Events:

Historical Versions(1)

Select effective date to view different version.

Related Statutes: