Florida Administrative Code (Last Updated: November 11, 2024) |
74. Agency for State Technology |
D74. Departmental |
74-1. Project Management And Oversight |
1(1) Project Monitoring and Controlling spans all phases of the project and involves the regular review of project status in order to identify variances from baselined project schedule, cost, and scope. In addition, all project management plan components developed pursuant to rule 4374-1.44004, F.A.C., Planning, must be monitored, controlled and maintained.
53(2) Risk and Complexity (R&C) Category 4 and 3 Projects will use Earned Value analysis to ensure that the schedule provides an accurate representation of project status.
80(a) Schedule Performance Index (SPI)
851. SPI is a measure of schedule efficiency expressed as a ratio of Earned Value (EV) to Planned Value (PV): SPI = EV/PV, where Earned Value is the measure of work performed expressed in terms of the budget amount authorized for that work, and Planned Value is the authorized budget assigned to scheduled work. Planned Value corresponds to the approved baseline budget.
1472. A SPI value of less than 1.0 indicates that less work was completed, in a given time frame, than was planned.
1693. A SPI value greater than 1.0 indicates that more work was completed, in a given time frame, than was planned.
190(b) Cost Performance Index (CPI)
1951. CPI is a measure of cost efficiency of budgeted resources for the work completed. CPI is expressed as a ratio of Earned Value (EV) to Actual Cost (AC): CPI = EV/AC, where Earned Value is the measure of work performed expressed in terms of the budget amount authorized for that work, and Actual Cost is the realized cost incurred for the work performed on an activity or set of activities during a specific time period.
2712. A CPI value of less than 1.0 indicates a cost overrun for work completed, in a given time frame.
2913. A CPI value greater than 1.0 indicates a cost underrun of performance to date.
306(3) The following matrix details specific Monitoring and Controlling documentation and activities required for the project based on the project’s R&C Category.
328MONITORING AND CONTROLLING 331‒ Requirements by Risk & Complexity Category
3384
3393
3402
3411
342Monitor and Control Project 346Change
347Required ‒ Follow the change control process(es) documented in the Change Management Plan. Complete an Event-Driven Risk & Complexity (R&C) Assessment for significan370t change requests 373(see rule 74-1.002, F.A.C. ‒ Risk and Complexity Assessment)382. This assessment will confirm or adjust the project’s cumulative risk and complexity levels and R&C Category, and assist the Agency in determining whether changes to any project 410management plan documents and baselines are needed. Maintain a change tracking log that includes change description, project impact (scope, schedule, and cost), owner, and status. This log is used to track, enter, review, analyze, approve, update, and report on project changes.
4514
4523
4532
4541
455Monitor and Control Project Schedule
460Required 461‒ Update the schedule at least weekly to reflect actual progress toward completion of scheduled tasks, milestones, and deliverables.
480Required ‒ Update the schedule at least biweekly to reflect actual progress toward completion of scheduled tasks, milestone498s, and deliverables.
501Required ‒ Use SPI to assess schedule variance. If SPI analysis indicates a trend towards a variance equal to or greater than 10% (SPI score ≤ 0.90 or ≥ 1.10), communicate the variance explanation to the project’s key stakeholder(s).
540Required ‒ Evaluate the baselined schedule against current progress.
5491. Identify overdue tasks and compute the percentage of late tasks related to total tasks to date (Number of Overdue Tasks/Number of Total Tasks).
5732. If this analysis indicates a trend t581owards a variance, 584equal to or greater than 10%, communicate the variance explanation to the project’s key stakeholders.
5994
6003
6012
6021
603Monitor and Control Project Cost
608Required ‒ Monitor project costs monthly to identify both positive and negative variances b622etween planned and actual expenditures.
6271. Compare baselined planned expenditures to actual expenditures captured in the spending plan or the budget.
6432. Identify the difference in baselined planned and actual expenditures and compute the percentage of cost variance for the period (Cost Variance/Total Planned Cost).
6673. If there is a variance (positive or negative) equal to or greater than 10%, communicate the variance explanation to the project’s key stakeholder(s).
691Required 692‒ Use CPI to assess cost variance.
699If the CPI analysis indicates a trend towards a variance equal to or greater than 10% (CPI score ≤ 0.90 or ≥ 1.10), communicate the variance explanation to the project stakeholders.
730Not Required
7324
7333
7342
7351
736Monitor and Con739trol Project 741Scope
742Required ‒ Monitor project scope, and manage changes to the original and agreed-upon scope as documented in the approved project planning documents.
764Required ‒ Monitor project scope and document changes.
7724
7733
7742
7751
776Monitor and Control Pr780oject 781Quality
782Required ‒ Monitor and Control quality as documented in the Quality Management Plan.
7954
7963
7972
7981
799Monitor and Control Project 803Risks
804Required ‒ Monitor and control risks as documented in the approved Risk Management Plan.
818Perform risk reassessm821ents to identify new risks, reassess current risks, escalate risks to issues, and close outdated risks.
837Maintain a risk tracking log that includes risk description, owner, response/mitigation strategy, risk probability, impact, priority, status and open/close dates. This log is used to track, enter, review, analyze, update, monitor, and report on risks.
872Required – Monitor, document, and address risks.
8794
8803
8812
8821
883Monitor and Control Project 887Issues
888Required 889‒ Monitor and control issues as documented in the approved Issue Management Plan.
902Review issues to identify new issues, reassess current issues, and close resolved issues.
915Maintain an issue tracking log, which includes Issue description, owner, status, and 927dates opened, due and closed. This log is used to track, enter, review, analyze, update, monitor, and report on issues.
947Required ‒ Monitor, document, and resolve issues.
9544
9553
9562
9571
958Decision Tracking
960Required ‒ Maintain a decision tracking log that includ969es decision description, approval authority, date of entry, due date, actual date of decision, project impact (scope, schedule, and cost), and status.
991This log is used to track, enter, review, analyze, update, monitor, and report on decisions.
1006Recommended
10074
10083
10092
10101
1011Action Item
1013Tracking
1014Required 1015‒ Maintain an action item log that includes Action Item description, owner, dates assigned and due, and status. This log is used to track, enter, review, analyze, update, monitor, and report on action items.
1049Recommended
10504
10513
10522
10531
1054Florida Cybersecurity Sta1057ndards
1058Required – 1060Monitor and control project compliance with 1066rule chapter 74-2, F.A.C.
10704
10713
10722
10731
1074Requirements Traceability Matrix
1077(RTM)
1078Required ‒ Review and amend the RTM to capture progressive detail of requirements linkage throughout the project.
1095Thi1096s matrix is used to document and link requirements from their origin to the deliverables that satisfy them.
1114Required ‒ Update requirements documentation as necessary.
11214
11223
11232
11241
1125Lessons Learned
1127Required ‒ Capture lessons learned from project team and stake1137holders throughout the project.
1141(4) The Agency will report project status based on 1150the project’s 1152R&C Category at least monthly. 1157Form AST-F-0505B, Project Status Report (07/16), is hereby incorporated by reference in this rule. Form AST-F-0505B can be found at 1177https://www.flrules.org/Gateway/refer1178e1179nce.asp?No=Ref-072221181. 1182Status reports will include:
1186PROJECT STATUS REPORT – Requirements by Risk & Complexity Category
11964
11973
11982
11991
1200Section 1 –
1203Project Status Overview
1206A. Overview of Project Progress.
1211B. Overall Status
1214C. Schedule Performance Index (SPI)
1219Cost Performance Index (CPI)
1223Not Required
12254
12263
12272
12281
1229Section 2 –
1232Project Progress
1234A. Project Milestones, Deliverables & Major Tasks
1241Not Required
1243B. Scope Changes
1246Summarize in Section 1B Only
12514
12523
12532
12541
1255Section 3 – Project
1259Issues and Risks
1262A. Project Issues
1265Summarize in Section 1B Only
1270B. Project Risks
1273Summarize in Section 1B Only
12784
12793
12802
12811
1282Section 4 – Project
1286Spending Plan
1288A. Identify Baselined Planned Expenditures vs. Actual Expenditures
1296Not Required
1298B. Major Project Expenditures
1302Not Required
1304Attach current project spend plan
1309Not Required
1311Rulemaking Authority 1313282.0051(18) 1314FS. Law Implemented 1317282.0041, 1318282.0051 1319FS. History‒New 7-16-15, Amended 8-1-16.