74-1.006. Monitoring and Controlling (Transferred)  


Effective on Monday, August 1, 2016
  • 1(1) Project Monitoring and Controlling spans all phases of the project and involves the regular review of project status in order to identify variances from baselined project schedule, cost, and scope. In addition, all project management plan components developed pursuant to rule 4374-1.44004, F.A.C., Planning, must be monitored, controlled and maintained.

    53(2) Risk and Complexity (R&C) Category 4 and 3 Projects will use Earned Value analysis to ensure that the schedule provides an accurate representation of project status.

    80(a) Schedule Performance Index (SPI)

    851. SPI is a measure of schedule efficiency expressed as a ratio of Earned Value (EV) to Planned Value (PV): SPI = EV/PV, where Earned Value is the measure of work performed expressed in terms of the budget amount authorized for that work, and Planned Value is the authorized budget assigned to scheduled work. Planned Value corresponds to the approved baseline budget.

    1472. A SPI value of less than 1.0 indicates that less work was completed, in a given time frame, than was planned.

    1693. A SPI value greater than 1.0 indicates that more work was completed, in a given time frame, than was planned.

    190(b) Cost Performance Index (CPI)

    1951. CPI is a measure of cost efficiency of budgeted resources for the work completed. CPI is expressed as a ratio of Earned Value (EV) to Actual Cost (AC): CPI = EV/AC, where Earned Value is the measure of work performed expressed in terms of the budget amount authorized for that work, and Actual Cost is the realized cost incurred for the work performed on an activity or set of activities during a specific time period.

    2712. A CPI value of less than 1.0 indicates a cost overrun for work completed, in a given time frame.

    2913. A CPI value greater than 1.0 indicates a cost underrun of performance to date.

    306(3) The following matrix details specific Monitoring and Controlling documentation and activities required for the project based on the project’s R&C Category.

    328MONITORING AND CONTROLLING 331‒ Requirements by Risk & Complexity Category

     

    3384

    3393

    3402

    3411

    342Monitor and Control Project 346Change

    347Required ‒ Follow the change control process(es) documented in the Change Management Plan. Complete an Event-Driven Risk & Complexity (R&C) Assessment for significan370t change requests 373(see rule 74-1.002, F.A.C. ‒ Risk and Complexity Assessment)382. This assessment will confirm or adjust the project’s cumulative risk and complexity levels and R&C Category, and assist the Agency in determining whether changes to any project 410management plan documents and baselines are needed. Maintain a change tracking log that includes change description, project impact (scope, schedule, and cost), owner, and status. This log is used to track, enter, review, analyze, approve, update, and report on project changes.

     

    4514

    4523

    4532

    4541

    455Monitor and Control Project Schedule

    460Required 461‒ Update the schedule at least weekly to reflect actual progress toward completion of scheduled tasks, milestones, and deliverables.

    480Required ‒ Update the schedule at least biweekly to reflect actual progress toward completion of scheduled tasks, milestone498s, and deliverables.

    501Required ‒ Use SPI to assess schedule variance. If SPI analysis indicates a trend towards a variance equal to or greater than 10% (SPI score ≤ 0.90 or ≥ 1.10), communicate the variance explanation to the project’s key stakeholder(s).

    540Required ‒ Evaluate the baselined schedule against current progress.

    5491. Identify overdue tasks and compute the percentage of late tasks related to total tasks to date (Number of Overdue Tasks/Number of Total Tasks).

    5732. If this analysis indicates a trend t581owards a variance, 584equal to or greater than 10%, communicate the variance explanation to the project’s key stakeholders.

     

    5994

    6003

    6012

    6021

    603Monitor and Control Project Cost

    608Required ‒ Monitor project costs monthly to identify both positive and negative variances b622etween planned and actual expenditures.

    6271. Compare baselined planned expenditures to actual expenditures captured in the spending plan or the budget.

    6432. Identify the difference in baselined planned and actual expenditures and compute the percentage of cost variance for the period (Cost Variance/Total Planned Cost).

    6673. If there is a variance (positive or negative) equal to or greater than 10%, communicate the variance explanation to the project’s key stakeholder(s).

    691Required 692‒ Use CPI to assess cost variance.

    699If the CPI analysis indicates a trend towards a variance equal to or greater than 10% (CPI score ≤ 0.90 or ≥ 1.10), communicate the variance explanation to the project stakeholders.

    730Not Required

     

    7324

    7333

    7342

    7351

    736Monitor and Con739trol Project 741Scope

    742Required ‒ Monitor project scope, and manage changes to the original and agreed-upon scope as documented in the approved project planning documents.

    764Required ‒ Monitor project scope and document changes.

     

    7724

    7733

    7742

    7751

    776Monitor and Control Pr780oject 781Quality

    782Required ‒ Monitor and Control quality as documented in the Quality Management Plan.

     

     

    7954

    7963

    7972

    7981

    799Monitor and Control Project 803Risks

    804Required ‒ Monitor and control risks as documented in the approved Risk Management Plan.

    818Perform risk reassessm821ents to identify new risks, reassess current risks, escalate risks to issues, and close outdated risks.

    837Maintain a risk tracking log that includes risk description, owner, response/mitigation strategy, risk probability, impact, priority, status and open/close dates. This log is used to track, enter, review, analyze, update, monitor, and report on risks.

    872Required – Monitor, document, and address risks.

     

    8794

    8803

    8812

    8821

    883Monitor and Control Project 887Issues

    888Required 889‒ Monitor and control issues as documented in the approved Issue Management Plan.

    902Review issues to identify new issues, reassess current issues, and close resolved issues.

    915Maintain an issue tracking log, which includes Issue description, owner, status, and 927dates opened, due and closed. This log is used to track, enter, review, analyze, update, monitor, and report on issues.

    947Required ‒ Monitor, document, and resolve issues.

     

    9544

    9553

    9562

    9571

    958Decision Tracking

    960Required ‒ Maintain a decision tracking log that includ969es decision description, approval authority, date of entry, due date, actual date of decision, project impact (scope, schedule, and cost), and status.

    991This log is used to track, enter, review, analyze, update, monitor, and report on decisions.

    1006Recommended

     

    10074

    10083

    10092

    10101

    1011Action Item

    1013Tracking

    1014Required 1015‒ Maintain an action item log that includes Action Item description, owner, dates assigned and due, and status. This log is used to track, enter, review, analyze, update, monitor, and report on action items.

    1049Recommended

     

    10504

    10513

    10522

    10531

    1054Florida Cybersecurity Sta1057ndards

    1058Required – 1060Monitor and control project compliance with 1066rule chapter 74-2, F.A.C.

     

    10704

    10713

    10722

    10731

    1074Requirements Traceability Matrix

    1077(RTM)

    1078Required ‒ Review and amend the RTM to capture progressive detail of requirements linkage throughout the project.

    1095Thi1096s matrix is used to document and link requirements from their origin to the deliverables that satisfy them.

    1114Required ‒ Update requirements documentation as necessary.

     

    11214

    11223

    11232

    11241

    1125Lessons Learned

    1127Required ‒ Capture lessons learned from project team and stake1137holders throughout the project.

    1141(4) The Agency will report project status based on 1150the project’s 1152R&C Category at least monthly. 1157Form AST-F-0505B, Project Status Report (07/16), is hereby incorporated by reference in this rule. Form AST-F-0505B can be found at 1177https://www.flrules.org/Gateway/refer1178e1179nce.asp?No=Ref-072221181. 1182Status reports will include:

    1186PROJECT STATUS REPORT – Requirements by Risk & Complexity Category

     

    11964

    11973

    11982

    11991

    1200Section 1 –

    1203Project Status Overview

    1206A. Overview of Project Progress.

    1211B. Overall Status

    1214C. Schedule Performance Index (SPI)

    1219Cost Performance Index (CPI)

    1223Not Required

     

    12254

    12263

    12272

    12281

    1229Section 2 –

    1232Project Progress

    1234A. Project Milestones, Deliverables & Major Tasks

    1241Not Required

    1243B. Scope Changes

    1246Summarize in Section 1B Only

     

    12514

    12523

    12532

    12541

    1255Section 3 – Project

    1259Issues and Risks

    1262A. Project Issues

    1265Summarize in Section 1B Only

    1270B. Project Risks

    1273Summarize in Section 1B Only

     

    12784

    12793

    12802

    12811

    1282Section 4 – Project

    1286Spending Plan

    1288A. Identify Baselined Planned Expenditures vs. Actual Expenditures

    1296Not Required

    1298B. Major Project Expenditures

    1302Not Required

    1304Attach current project spend plan

    1309Not Required

    1311Rulemaking Authority 1313282.0051(18) 1314FS. Law Implemented 1317282.0041, 1318282.0051 1319FS. History‒New 7-16-15, Amended 8-1-16.

     