Other Agencies and Organizations, Florida A&M University Facilities Planning, Construction and Safety  

  •  

    OTHER AGENCIES AND ORGANIZATIONS

    Florida A&M University Facilities Planning, Construction and Safety

    FAMU Student Housing Phase 1A (FINROCK Construction)

    ·         Description of Project:

    The project is located near the intersection of Wahnish Way and Orange Avenue in Tallahassee, FL on the FAMU campus.  This project consists of two 4-story dormitory student housing facilities towers that approximately 91,000 GSF, 186 units/357 beds per building and includes ground floor Amenity space for a total of 372 units/714 beds. 

    A pre-bid meeting shall be held on Wednesday, January 23, 2019, 11:00 a.m. – 12:00 Noon at Office of Procurement Services located at 2380 Wahnish Way, Suite 214, Tallahassee, FL  32307.  Please come to this meeting with any questions/comments for the project.

    Our team will be soliciting bids for the following scopes of work:

    ·         Site Demolition/SWPPP Management

    ·         Cast-In-Place Concrete

    ·         Steel Handrails

    ·         Aluminum Canopies

    ·         Casework/Countertops

    ·         Roofing

    ·         Doors, Frames, and Hardware

    ·         Aluminum storefront/window wall systems

    ·         Vinyl Windows

    ·         Tiling

    ·         Vinyl Flooring & Associated Floor Base

    ·         Interior/Exterior Painting

    ·         Interior Signage

    ·         Toilet Accessories/Shelving

    ·         Window Treatments – Vertical Blinds and Roller Shades

    ·         Site work including grading and underground utilities

    ·         Hardscape

    ·         Landscape/Irrigation

    We are planning on breaking ground for Phase 1.A in June 2019 with a turnover completed by July 2020 (in time for the Fall 2020 semester).

    You will find below a link to access the most recent Design Documents that consist of the following:

    ·         Summary of Work and Clarifications

    ·         60% Architectural, Structural, MEP/FP Construction Documents

    ·         60% Civil Construction Documents

    ·         FAMU Student Housing Building Standards (MEP and IT is broken out separately).  We have also made markups in red and blue to their documents, so please let me know if there are any additional  comments/concerns   that you may have

    ·         Preliminary Renderings

    ·         Photos of USF dorm that was basis of design (these are for reference only)

    ·         Preliminary Door Schedule

    ·         Preliminary Construction Schedule

    ·         Preliminary Flooring Plan & Take-Off

    ·         Preliminary Storefront Take-Off

    ·         Preliminary Toilet Accessories Schedule

    ·         Preliminary Finish Schedule

    ·         Preliminary Site Plan (currently we are only pricing Phase 1.A that is boxed in red)

    ·         Painted MEPFP Ceilings

    ·         Sample Contract

    ·         Civil Grading Plan

    ·         Preliminary Geotechnical Report

    ·         Preliminary Foundation Plan

    Proposals shall be electronically submitted via email my attention at bdavis@finfrock.com by Wednesday, February 6th, by 5:00 p.m.  This will not be a sealed bid process so the Finfrock team will review bids as they are received.  Please email all RFI’s to my attention via email so that I can respond to all proposers. 

    INSTRUCTIONS TO BIDDERS

    ·         Please download the Design Documents via the following Drop Box link: 

    https://www.dropbox.com/sh/it8jq33qkpofa6f/AAB4gTRx1AVBfBshhoYpliwUa?dl=0

    ·         Make sure that you provide a stand-alone price for each of the following (the building are identical for now):

    o   Building H (North)

    o   Building I (South)

    ·         Include additional pricing breakout for each of the above as applicable:

    o   Exterior

    o   Interior including dormitory units, corridors, amenity, and BOH areas

    ·         Include a break out of any allowances

    ·         Contractor initiated VE Alternates

    ·         Provide alternate for PP bond.

    ·         Email me with any questions you have.

    Thanks,

    Brad Davis  |  Project Director 2400 Apopka Boulevard  |  Apopka, Florida 32703

    bdavis@finfrock.com (407)293-4000,  (850)316-7902