Notice of Request for Proposals
District Office BayCare I/T Renovations 706-D-06-1
Peter R. Brown Construction, Inc. (CGC-061419), the Construction Manager for the St. Petersburg College District Office BayCare I/T Renovations 706-D-06-1 hereby solicits sealed proposals for the referenced project in accordance with the proposal documents to include but not limited to the following:
The Scope of Work for this project includes but is not limited to interior renovations for a portion of the St. Petersburg College EpiCenter Campus District Office. Renovations will be limited to the 9,000 sq. ft. BayCare space and are as follows:
Demolition of existing floor and ceiling finishes, doors and frames, GWB partitions and the removal of wallpaper finishes on walls to remain. Installation of new doors, frames, hardware, GWB partitions, acoustical ceiling system and miscellaneous accessories as needed. The removal of existing roof-top HVAC unit and existing fiberglass ductwork and the installation of a new roof-top HVAC unit and sheet metal supply and return are ductwork with accessories. Minor adjustment to the existing light fixture layout and the addition of a limited number of receptacles and data drops to accommodate the new floor plan.
A pre-proposal meeting will be held at 10:30 a.m. (Local Time), Thursday November 15, 2007 at the following location:
District Office Conference Room
6021 142 Avenue, North
Deadline for receipt of All Proposal Packages has been set for 2:00 p.m., November 21, 2007. Only proposals received on or before the time and date listed will be considered. All proposals received after 2:00 p.m., of the day specified above, will be returned unopened.
All interested subcontractors must be pre-qualified or have completed the pre-qualification process within the last year. Please contact the following person to obtain information or documents about the pre-qualification requirements for this project:
Jenny Sanchez, Estimator
Phone: (727)535-6407 Fax: (727)539-8485
One set of plans and specifications will be supplied to all pre-qualified trade contractors at no cost. Trade contractors are responsible for the cost of shipping. Additional sets may be purchased directly from the copy center. Copy center information will be distributed with the Proposal Packages.
No verbal instruction or directives will be accepted regarding this project during the proposal period. All instructions or directives must be clarified through written Addenda or Supplements. All questions regarding the work should be directed to the Construction Manager, in writing by November 16, 2007. The Owner and Architect will not accept calls regarding this project.