Emergency Authorization of Permits for Activities Regulated Under Part IV of Chapter 373, F.S, Forms and Instructions  


  • RULE NO: RULE TITLE
    40D-1.1021: Emergency Authorization of Permits for Activities Regulated Under Part IV of Chapter 373, F.S
    40D-1.659: Forms and Instructions
    NOTICE OF CHANGE
    Notice is hereby given that the following changes have been made to the proposed rule in accordance with subparagraph 120.54(3)(d)1., F.S., published in Vol. 35 No. 50, December 18, 2009 issue of the Florida Administrative Weekly.

    Changes are made to add language to the Emergency Field Authorization form, incorporated by reference in subsection 40D-1.1021(2), F.A.C., that includes the Title of the form being adopted (Emergency Field Authorization) and an explanation of how that form can be obtained from the District. The District has modified the form by adding a section at the beginning for use by District staff to document the existence of an emergency and describe the emergency conditions existing at the site. Grammatical errors in the form have also been corrected.

    40D-1.659 Forms and Instructions.

    The following forms and instructions have been approved by the Governing Board and are incorporated by reference into this chapter or into a specific District rule as indicated. Copies of these forms may be obtained from the District offices or the District’s website at www.watermatters.org.

    (1) GROUND WATER

    (a) through (hh) No change.

    (2) SURFACE WATER

    (a) through (m) No change.

    (n) EMERGENCY FIELD AUTHORIZATION FORM, FORM NO. LEG-R.049.00 (11/09), incorporated by reference in subsection 40D-1.1021(2), F.A.C.

    (3) OTHER

    (a) through (d) No change.

    Rulemaking Authority 373.044, 373.113, 373.149, 373.171, 373.337 FS. Law Implemented 373.083, 373.0831(3), 373.083(5), 373.116, 373.196(1), 373.1961(3), 373.206, 373.207, 373.209, 373.216, 373.219, 373.229, 373.239, 373.306, 373.308, 373.309, 373.313, 373.323, 373.324, 373.413, 373.414, 373.416, 373.419, 373.421, 668.50 FS. History–New 12-31-74, Amended 10-24-76, Formerly 16J-0.40, 40D-1.901, 40D-1.1.901, Amended 12-22-94, 5-10-95, 10-19-95, 5-26-96, 7-23-96, 2-16-99, 7-12-99, 7-15-99, 12-2-99, 5-31-00, 9-3-00,10-26-00, 6-26-01, 11-4-01, 6-12-02, 8-25-02, 2-26-03, 9-14-03, 9-30-04, 2-1-05, 6-5-05, 10-19-05, 2-6-07, 2-26-07, 9-27-07, 11-11-07, 11-25-07, 1-8-08, 4-7-08, 5-12-08, 5-20-08, 8-19-08, 12-30-08, 3-26-09, 7-1-09, 8-30-09, 9-1-09, 10-26-09,________.

     

    40D-1.1021 Emergency Authorizations for Activities Regulated Under Part IV of Chapter 373, F.S.

    The District shall authorize activities regulated under Part IV of Chapter 373, F.S. when emergency conditions exist. Emergency conditions are defined as those conditions which pose a present or imminent danger and require immediate action to protect the public health, safety or welfare; the health of animals, birds, fish or aquatic life; a public water supply; or recreational, commercial, industrial, agricultural or other reasonable uses. Mere carelessness or the lack of planning on the part of an applicant for an emergency authorization shall not be sufficient grounds to warrant the granting of an emergency authorization.

    (1) Authorization begin construction that requires a permit under Chapters 40D-4, 40D-40 and 40D-400, F.A.C., prior to the issuance of a permit currently under consideration by the District may be applied for in writing, when emergency conditions exist. The Executive Director or his or her designee is authorized to issue emergency authorizations pursuant to this paragraph.

    (2) Emergency field authorizations may be requested when emergency conditions exist and no environmental resource permit application is currently under consideration by the District. The entity requesting the emergency field authorization shall complete District Emergency Field Authorization Form No. LEG-R.049.00 (11/09), incorporated herein by reference. This form may be obtained from the District’s website at www.watermatters.org or from the District offices. The activity authorized by the emergency field authorization may commence upon approval by the District’s field representative. The recipient of an emergency field authorization is responsible for compliance with all the terms and conditions of the authorization. Within ninety (90) days of issuance of an emergency field authorization the recipient shall either restore the site to the conditions existing before the emergency or apply for an environmental resource permit.

    Rulemaking Specific Authority 120.54(5), 373.044, 373.113, 373.149 FS. Law Implemented 120.54(5), 120.569(2)(n), 373.119, 373.083, 373.083(5), 373.413, 373.416, 373.426, 373.439 FS. History– Readopted 10-5-74, Amended 10-24-76, Formerly 16J-4.16, Amended 10-1-84, Formerly 40D-4.451, Amended 7-2-98, 6-17-99,________.