The Suwannee River Water Management District (District) gives notice that it is initiating rulemaking to amend its rules to describe the point of entry into proceedings for District permitting decisions.  

  •  

    WATER MANAGEMENT DISTRICTS

    Suwannee River Water Management District

    RULE NO.:RULE TITLE:

    40B-1.703Procedures for Consideration of Permit Applications

    PURPOSE AND EFFECT: The Suwannee River Water Management District (District) gives notice that it is initiating rulemaking to amend its rules to describe the point of entry into proceedings for District permitting decisions.

    SUMMARY: Noticing of District permitting decisions; Point of entry into proceedings

    SUMMARY OF STATEMENT OF ESTIMATED REGULATORY COSTS AND LEGISLATIVE RATIFICATION: The Agency has determined that this will not have an adverse impact on small business or likely increase directly or indirectly regulatory costs in excess of $200,000 in the aggregate within one year after the implementation of the rule. A SERC has not been prepared by the Agency.

    The Agency has determined that the proposed rule is not expected to require legislative ratification based on the statement of estimated regulatory costs or if no SERC is required, the information expressly relied upon and described herein: The District has completed for the Governor’s Office of Fiscal Accountability and Regulatory Reform (OFARR) the “Is a SERC Required?” form and prepared a summary of the proposed rule amendment, which are both available upon request. Based on the completed “Is a SERC Required?” form and summary and the analysis performed by the District, the proposed rule amendment is not expected to require legislative ratification pursuant to subsection 120.541(3), F.S.

    Any person who wishes to provide information regarding a statement of estimated regulatory costs, or provide a proposal for a lower cost regulatory alternative must do so in writing within 21 days of this notice.

    RULEMAKING AUTHORITY: 373.044, 373.083, 373.113, 373.118, 373.171, 373.4141 FS.

    LAW IMPLEMENTED: 120.57, 120.59, 120.60, 373.084, 373.085, 373.086, 373.106, 373.116, 373.118, 373.229, 373.313, 373.413, 373.416, 373.426 FS.

    IF REQUESTED WITHIN 21 DAYS OF THE DATE OF THIS NOTICE, A HEARING WILL BE SCHEDULED AND ANNOUNCED IN THE FAR.

    THE PERSON TO BE CONTACTED REGARDING THE PROPOSED RULE IS: Warren Zwanka, Senior Hydrologist, Suwannee River Water Management District, 9225 CR 49, Live Oak, Florida 32060, (386)362-1001 or 1(800)226-1066 (FL only)

     

    THE FULL TEXT OF THE PROPOSED RULE IS:

     

    40B-1.703 Procedures for Consideration of Permit Applications.

    (1)(a) through (d) No change.

    (2) Individual Permits.

    (a) No change.

    (b) Upon receipt of an application for an individual permit, the District will cause to be published and distributed the notices of application required by Sections 373.116, 373.413(3), and 373.413(4), F.S. The notice of application shall specify a date not less than 14 days from the date of publication and distribution by which comments or objections to the application may be filed with the District. A notice of proposed agency action on an individual permit application will be prepared whenever possible. The notice of proposed agency action will be sent to the applicant or any other person requesting such notice. If no substantial objection to the application or notice of proposed agency action is received, the Governing Board may, at its discretion, consider the application at its next regularly scheduled meeting, which is at least 14 days after issuance of a notice of proposed agency action. If a substantial objection is received, the Board shall proceed under the procedures in Chapter 28, F.A.C., and, if appropriate, set a time for a hearing in accordance with the provisions of Chapter 120, F.S. When there is not a reasonable opportunity for the District to issue a notice of proposed agency action, the Governing Board may, at its discretion, consider the application and advise the applicant and all other persons requesting notice of the Governing Board’s action and providing an opportunity to request an administrative hearing on the action pursuant to Section 120.60(3), F.S., and Chapter 28, F.A.C.

    (c) No change.

    (3) No change.

    Rulemaking Authority 373.044, 373.083, 373.113, 373.118, 373.171, 373.4141 FS. Law Implemented 120.57, 120.59, 120.60, 373.084, 373.085, 373.086, 373.106, 373.116, 373.118, 373.229, 373.313, 373.413, 373.416, 373.426 FS. History–New 6-16-88, Amended 12-22-92, 10-3-95, 1-29-01, 12-10-07, 10-25-09, 3-24-14, [DATE].

     

    NAME OF PERSON ORIGINATING PROPOSED RULE: Warren Zwanka, Senior Hydrologist

    NAME OF AGENCY HEAD WHO APPROVED THE PROPOSED RULE: Suwannee River Water Management District Governing Board

    DATE PROPOSED RULE APPROVED BY AGENCY HEAD: December 9, 2014

    DATE NOTICE OF PROPOSED RULE DEVELOPMENT PUBLISHED IN FAR: August 25, 2014

Document Information

Comments Open:
2/5/2015
Summary:
Noticing of District permitting decisions; Point of entry into proceedings
Purpose:
The Suwannee River Water Management District (District) gives notice that it is initiating rulemaking to amend its rules to describe the point of entry into proceedings for District permitting decisions.
Rulemaking Authority:
373.044, 373.083, 373.113, 373.118, 373.171, 373.4141 FS.
Law:
120.57, 120.59, 120.60, 373.084, 373.085, 373.086, 373.106, 373.116, 373.118, 373.229, 373.313, 373.413, 373.416, 373.426 FS.
Contact:
Warren Zwanka, Senior Hydrologist, Suwannee River Water Management District, 9225 CR 49, Live Oak, Florida 32060, (386)362-1001 or (800)226-1066 (FL only).
Related Rules: (1)
40B-1.703. Procedures for Consideration of Permit Applications