Andy Bachman, on behalf of William E. Groves Construction, Inc., filed on April 24, 2015.; The petition seeks the Board’s interpretation of Sections 489.505(12) F.S., as to whether a Florida Electrical Contractor’s license is required for contract ...  

  •  

    DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION

    Electrical Contractors Licensing Board

    NOTICE IS HEREBY GIVEN that the Electrical Contractors’ Licensing Board has received the petition for declaratory statement from Andy Bachman, on behalf of William E. Groves Construction, Inc., filed on April 24, 2015. The petition seeks the agencys opinion as to the applicability of Section 489.505(12), F.S., as it applies to the petitioner.

    The petition seeks the Board’s interpretation of Sections 489.505(12) F.S., as to whether a Florida Electrical Contractor’s license is required for contract work for a public utility company. Except for good cause shown, motions for leave to intervene must be filed within 21 days after publication of this notice.

    A copy of the Petition for Declaratory Statement may be obtained by contacting: Ruthanne Christie, Executive Director, Electrical Contractors’ Licensing Board, 1940 North Monroe Street, Tallahassee, FL 32399-0783, Ruthanne.Christie@myfloridalicense.com or by telephoning (850)487-1395.

Document Information

Meeting:
Section 489.505(12) F.S.,
Contact:
Ruthanne Christie, Executive Director, Electrical Contractors’ Licensing Board, 1940 North Monroe Street, Tallahassee, FL 32399-0783, Ruthanne.Christie@myfloridalicense.com or by telephoning (850) 487-1395.