NOTICE OF AVAILABILITY
The Department of Environmental Protection has determined that the City of North Ports proposed project to expand their wastewater treatment facility, to expand their deep injection well system, and to construct new collection and transmission facilities will not have a significant adverse impact on the environment. The total estimated construction cost is $32,500,000. The project is expected to qualify for a State Revolving Fund loan composed of federal and state matching funds.
A full copy of the Florida Categorical Exclusion Notice can be obtained by writing to: Thomas Montgomery, Bureau of Water Facilities Funding, Department of Environmental Protection,