40A-7.004 Determination and Notice of a Contractor Suspension.
(1) No change.
(2) The Governing Board shall consider the following Wwhen determining whether a contractor should be temporarily suspended from doing business with the District for a period of time of no more than 5 years 1 year, the Governing Board shall consider whether:
(a) through (d) No change.
(e) The contractor committed a material breach which involved discrimination on the basis of race, color, creed, national origin, sex, age, or handicap;
(f) The contractor committed a material breach which involved willful or gross misconduct;
(g) No change.
(h) The contractor committed a material breach which involved the commission of any act indicating a lack of business integrity or honesty; and,
(i) The contractor committed a material breach which involved knowingly doing business with a suspended contractor.; or
(h) The contractor has materially breached a contract with the District on more than one occasion within the last 3 calendar years by having financial consequences imposed by the District or having forfeited a portion or all of a performance bond.
(3) The Governing Board shall consider the following Wwhen making a determination whether a contractor should be permanently suspended from doing business with the District, the Governing Board shall consider, in addition to those criteria in section (2) above, whether:
(a) through (b) No change.
(c) The material breach involved discrimination on the basis of race, color, creed, national origin, sex, age, or handicap;
(c)(d) The contractor violated a District solicitation to ensure the fair award of District contracts, including price fixing between competitors, allocation of customers between competitors, and bid rigging; or and,
(d)(e) The contractor committed a material breach which involved the commission of a criminal offense, including public entity crimes as defined in Section 287.133(1)(g), F.S.;
(4) No change.
(5) Upon written request to the District, a contractor placed on the Temporary Suspension List will be reinstated at the conclusion of the contractor’s suspension period after reimbursing the District for all re-procurement costs.The conditions for reinstatement for a contractor placed on the Temporary Suspension List shall be:
(a) the contractor shall make a written request to the District for reinstatement;
(b) the contractor’s temporary suspension period must be completed; and
(c) the contractor shall have reimbursed the District for all re-procurement costs incurred by the District resulting from the contractor’s breach.