Agency for Health Care Administration, Certificate of Need  

  •  

    AGENCY FOR HEALTH CARE ADMINISTRATION
    Certificate of Need

    DECISION ON BATCHED APPLICATIONS

    The Agency for Health Care Administration made the following decisions on Certificate of Need applications for Hospital Beds and Facilities batching cycle with an application due date of March 12, 2008:

    County: MarionService District: 3

    CON # 10009Decision Date: 6/13/2008Decision: A

    Facility/Project: HealthSouth Rehabilitation Hospital of Ocala, LLC

    Applicant: HealthSouth Rehabilitation Hospital of Ocala, LLC

    Project Description: Establish a comprehensive medical rehabilitation with 40 beds

    Approved Cost: $19,620,449.00

    County: PascoService District: 5

    CON # 10010Decision Date: 6/13/2008Decision: A

    Facility/Project: Ten Broeck Tampa, Inc.

    Applicant: Ten Broeck Tampa, Inc.

    Project Description: Establish a 35 bed adult inpatient psychiatric hospital

    Approved Cost: $15,730,804.00

    County: PascoService District: 5

    CON # 10011Decision Date: 6/13/2008Decision: D

    Facility/Project: Morton Plant North Bay Psychiatric Hospital

    Applicant: Morton Plant Hospital Association d/b/a Morton Bay North Bay Hospital

    Project Description: Establish a 40 bed adult inpatient psychiatric hospital

    Approved Cost: $0

    County: PascoService District: 5

    CON # 10012Decision Date: 6/13/2008Decision: D

    Facility/Project: Morton Plant North Bay Psychiatric Hospital

    Applicant: Morton Plant Hospital Association d/b/a Morton Bay North Bay Hospital

    Project Description: Establish a 10 bed child/adolescent inpatient pscyhiatric hospital

    Approved Cost: $0

    County: PascoService District: 5

    CON # 10013Decision Date: 6/13/2008Decision: A

    Facility/Project: Ten Broeck Tampa, Inc.

    Applicant: Ten Broeck Tampa, Inc.

    Project Description: Establish a five bed adult substance abuse hospital

    Approved Cost: $15,730,804.00

    County: PascoService District: 5

    CON # 10014Decision Date: 6/13/2008Decision: D

    Facility/Project: Morton Plant North Bay Psychiatric Hospital

    Applicant: Morton Plant Hospital Association d/b/a Morton Bay North Bay Hospital

    Project Description: Establish a 20 bed adult substance abuse hospital

    Approved Cost: $0

    A request for administrative hearing, if any, must be made in writing and must be actually received by this department within 21 days of the first day of publication of this notice in the Florida Administrative Weekly pursuant to Chapter 120, Florida Statutes, and Chapter 59C-1, Florida Administrative Code.