14-91.007: Selection and Award Process
PURPOSE AND EFFECT: A new subsection (9) is added to Rule 14-91.007, F.A.C., to clarify the compensation of short-listed design-build firms.
SUMMARY: A new subsection(9) is being added to Rule 14-91.007, F.A.C.
SUMMARY OF STATEMENT OF ESTIMATED REGULATORY COSTS: No Statement of Estimated Regulatory Cost was prepared.
Any person who wishes to provide information regarding a statement of estimated regulatory costs, or provide a proposal for a lower cost regulatory alternative must do so in writing within 21 days of this notice.
SPECIFIC AUTHORITY: 334.044(2), 337.11(7)(b), 337.11(8) FS.
LAW IMPLEMENTED: 337.025, 337.11(7), 337.11(8) FS.
IF REQUESTED WITHIN 21 DAYS OF THE DATE OF THIS NOTICE, A HEARING WILL BE SCHEDULED AND ANNOUNCED IN FAW.
THE PERSON TO BE CONTACTED REGARDING THE PROPOSED RULE IS: Deanna R. Hurt, Assistant General Counsel and Clerk of Agency Proceedings, Florida Department of Transportation, Office of the General Counsel, 605 Suwannee Street, Mail Station 58, Tallahassee, Florida 32399-0458
THE FULL TEXT OF THE PROPOSED RULE IS:
14-91.007 Selection and Award Process.
(1) through (8) No change.
(9) The Department shall pay short-listed design-build firms submitting fully responsive proposals that are not selected a lump sum amount, stipend, as determined by the solicitation in order to stimulate competition and for the work product contained in the firms responsive proposals. The Department will not pay the selected design-build firm a stipend. An unselected short list design-build firm that submits a responsive proposal in response to and in accordance with the Department request for detailed proposals will receive a stipend in exchange for the work product contained in that proposal. The Department reserves the right to use any of the concepts, ideas, technologies, techniques, methods, processes, and information that are contained within the proposals without any further compensation therefore.
(a) In order to receive the stipend, the unselected short listed design-build firms must enter into a contract with the Department immediately after short listing. The contract is required to document the terms and conditions for the stipend. The Department shall issue the stipend contract on the Departments Design/Build Stipend Agreement, Form No. 700-011-14, incorporated herein by reference.
(b) The Departments criteria to determine the stipend amount shall include the following: complexity of the project, technical expertise, time and resources required for the proposal, and value of work product contained in the technical proposal. The intent to compensate and the stipulated amount of the stipend will be set forth in the request for proposals package.
(c) A stipend is not intended to compensate the design-build firms for the total cost of preparing the proposal.
Rulemaking Specific Authority 334.044(2), 337.11(7)(b), 337.11(8) FS. Law Implemented 337.025, 337.11(7), 337.11(8) FS. History New 3-13-88, Amended 6-13-90, 2-20-96, 9-3-96, 10-18-00, 5-3-09,________.