No Notice General Permit for Activities in Uplands  


  • RULE NO: RULE TITLE
    40E-400.315: No Notice General Permit for Activities in Uplands
    NOTICE OF CHANGE
    Notice is hereby given that the following changes have been made to the proposed rule in accordance with subparagraph 120.54(3)(d)1., F.S., published in Vol. 35 No. 25, June 26, 2009 issue of the Florida Administrative Weekly.

    40E-400.315 No Notice General Permit for Activities in Uplands.

    (1) No change.

    (2) A no notice general permit is hereby granted for the construction or alteration of surface water management systems, provided that the surface water management system meets all of the conditions and thresholds of paragraphs (a) and (b) below, and all thresholds and conditions of at least one of the paragraph (b) or (c) below.

    (a) through (b) No change.

    (c) Thresholds and Additional Conditions Within Collier County.

    1. The project must have less than 40 acres total land area.

    2. The project and surface water management system must have been approved by Collier County subsequent to September 17, 1980.

    Rulemaking Specific Authority 373.044, 373.113, 373.118, 373.171, 403.813, 403.814 FS. Law Implemented 373.118, 373.413, 373.416, 373.426 FS. History–New 10-3-95, Amended 4-14-03,________.