The Suwannee River Water Management District (District) gives notice that it is initiating rulemaking to amend rules 40B-1.703, 40B-1.704, 40B-1.706, and 40B-1.709, F.A.C.; and repeal rule 40B-1.1010, F.A.C. The purpose ....  

  •  

    WATER MANAGEMENT DISTRICTS

    Suwannee River Water Management District

    RULE NOS.:RULE TITLES:

    40B-1.1010Point of Entry into Proceedings

    40B-1.703Procedures for Consideration of Permit Applications

    40B-1.704Bond

    40B-1.706Fees

    40B-1.709Suspension, Revocation, and Modification of District Permits

    PURPOSE AND EFFECT: The Suwannee River Water Management District (District) gives notice that it is initiating rulemaking to amend rules 40B-1.703, 40B-1.704, 40B-1.706, and 40B-1.709, F.A.C.; and repeal rule 40B-1.1010, F.A.C. The purpose of this rulemaking is to correct rule citations and a misspelling, align procedural rules with agency delegated authorities, and assign a lower cost fee for minor modifications of Works of the District permits as set forth in rule 40B-4.1110, F.A.C.

    SUBJECT AREA TO BE ADDRESSED: General and procedural rules.

    RULEMAKING AUTHORITY: 373.044, 373.083, 373.109, 373.113, 373.118, 373.171, 373.4141 FS.

    LAW IMPLEMENTED: 120.57, 120.59, 120.60, 218.075, 373.084, 373.085, 373.086, 373.103, 373.106, 373.116, 373.118, 373.119, 373.219, 373.229, 373.313, 373.413, 373.414, 373.416, 373.426, 373.429 FS.

    IF REQUESTED IN WRITING AND NOT DEEMED UNNECESSARY BY THE AGENCY HEAD, A RULE DEVELOPMENT WORKSHOP WILL BE NOTICED IN THE NEXT AVAILABLE FLORIDA ADMINISTRATIVE REGISTER.

    Pursuant to the provisions of the Americans with Disabilities Act, any person requiring special accommodations to participate in this workshop/meeting is asked to advise the agency at least 5 days before the workshop/meeting by contacting: SRWMD at (386)362-1001 or 1(800)226-1066 (FL only). If you are hearing or speech impaired, please contact the agency using the Florida Relay Service, 1(800)955-8771 (TDD) or 1(800)955-8770 (Voice).

    THE PERSON TO BE CONTACTED REGARDING THE PROPOSED RULE DEVELOPMENT AND A COPY OF THE PRELIMINARY DRAFT, IF AVAILABLE, IS: Warren Zwanka, P.G., Suwannee River Water Management District, 9225 CR 49, Live Oak, Florida 32060, (386)362-1001 or 1(800)226-1066 (FL only)

     

    THE PRELIMINARY TEXT OF THE PROPOSED RULE DEVELOPMENT IS:

     

    40B-1.1010 Point of Entry into Proceedings.

    Rulemaking Authority 120.54(5), 373.044, 373.113 FS. Law Implemented 120.54(5), 120.60, 253.115, 373.079(4)(a), 373.083(5), 373.216, 373.219, 373.308, 373.309, 373.323, 373.413, 373.4136, 373.414, 373.416, 373.418, 373.421, 373.426, 373.427 FS. History–New 4-8-15, Repealed [DATE].

     

    40B-1.703 Procedures for Consideration of Permit Applications.

    (1) General Permits.

    (a) through (c) no change.

    (d) General permits by rule, as defined in rule 40B-2.041, F.A.C., are a category of general permits for activities which have established standards and conditions for issuance of permits in district rules. A permit application is not required for any use that meets the requirements of rule 40B-2.041, F.A.C. 40B-24.041, F.A.C., and is thereby considered to be an existing legal use user of water.

    (2) Individual Permits.

    (a) through (b) no change.

    (c) The Governing Board hereby delegates authority to the Executive Director or their designee Assistant Executive Director to issue individual environmental resource permits that require no special limiting conditions or that require only the following special limiting conditions pursuant to subsection 40B-4.1140(1), Florida Administrative Code (F.A.C.), under chapters 40B-4 and 40B-400, F.A.C.:

    1. Permits that identify non-profit associations as operation and maintenance entities under subsection 40B-4.2035(3), F.A.C.; or

    2. Permits that require the following documents to be recorded in legal records:

    a. Final plats; and

    b. Deed restrictions; and

    c. Drainage easements.

    unless Unless objection to the permit application or the notice of application proposed agency action is made according to statute and these rules by a substantially affected person, the Executive Director or Assistant Executive Director shall either issue the permit or place the application on the agenda of the next regularly scheduled meeting of the Governing Board.

    (3) no change.

    Rulemaking Authority 373.044, 373.083, 373.113, 373.118, 373.171, 373.4141 FS. Law Implemented 120.57, 120.59, 120.60, 373.084, 373.085, 373.086, 373.106, 373.116, 373.118, 373.229, 373.313, 373.413, 373.416, 373.426 FS. History–New 6-16-88, Amended 12-22-92, 10-3-95, 1-29-01, 12-10-07, 10-25-09, 3-24-14, 4-8-15, [DATE].

     

    40B-1.704 Bond.

    (1) no change.

    (2) Applicants for environmental resource permits under chapters 40B-4 and 40B-400, Florida Administrative Code (F.A.C.), shall furnish a bond or other form of surety for certification of completion of construction as required by paragraphs 40B-4.1140(2)(c) and 40B-400.091(2) 40B-400.115(1)(j), F.A.C. The forms of surety acceptable to the District include but are not limited to, cash deposit, letter of credit, and performance bond. Bonds and other forms of surety shall be in the following amounts: project area less than one acre, $1,000; project area less than 10 acres, $2,000; project area less than 40 acres, $3,000; project area less than 100 acres, $4,000; project area less than 200 acres, $5,000; project area greater than or equal to 200 acres, $10,000. The District shall release the bond or other form of surety, without interest, upon final acceptance of certification of completion of construction and transfer of operation and maintenance to an entity approved by the District as required by rule 40B-400.091(2) 40B-4.2035, F.A.C.

    (3) through (4) no change.

    Rulemaking Authority 373.044, 373.113 FS. Law Implemented 373.085, 373.103, 373.219, 373.413, 373.414, 373.416 FS. History–New 9-15-81, Amended 1-10-10, [DATE].

     

    40B-1.706 Fees.

    (1) no change.

    (2) Upon delegation of the administration of a permitting program from the department to the district, the fees for such permits established by department rule shall be collected by the district pursuant to section 373.109, F.S.

    TABLE 1.A. SCHEDULE OF PERMIT FEES

     

    WATER USE PERMITS

     

    Water Use Permits less than 2,000,000 GPD-ADR

    $230

    Modification or Renewal of Water Use Permits less than 2,000,000 GPD-ADR

    $115

    Water Use Permits equal to or greater than 2,000,000 GPD-ADR

    $530

    Modification or Renewal of Water Use Permits equal to or greater than 2,000,000 GPD-ADR

    $265

    TABLE 1.B. SCHEDULE OF PERMIT FEES

     

    ENVIRONMENTAL RESOURCE AND WORKS OF THE DISTRICT PERMITS

     

    Use of the reviewing agency’s electronic self-certification system

    $0

    Verification of exemption under sections 373.406, 403.813, F.S., chapter 62-330 or 40B-4, F.A.C.

    $100

    Verification of qualification to use a General Permit under chapter 62-330, F.A.C., or Noticed General under chapter 40B-4, F.A.C.

    $250

    Variance or Waiver under section 120.542, F.S.

    $0

    Variances or Waivers

    $550

    Works of the District General Permits

    $490

    Major Modification of a Works of the District General Permit

    $245

    Minor Modification of a Works of the District Permit

    $100

    All Individual or Conceptual Approval Permits under chapters 62-330 or 40B-4, F.A.C.:

     

    (1)    through (3) no change.

     

    New Determinations of the Landward Extent of Wetlands and Other Surface Waters.

     

    (1) through (2) no change.

     

    Reissuance of Informal Determinations.

    $50

    Reissuance of Formal Determinations, in accordance with subsection 62-330.201(5), F.A.C.

    $350

    Application for any activity when submitted by the Department of Defense.

    $0

    Any fee in excess of $100, as determined by this section, shall be reduced to this amount, which shall not exceed $100, for public projects when the applicant is a county or municipality (or under contract thereto) that qualifies under section 218.075, F.S.

    $100

    Rulemaking Authority 373.044, 373.109, 373.113, 373.118, 373.171 FS. Law Implemented 218.075, 373.109 FS. History–New 6-16-88, Amended 11-25-90, 12-22-92, 10-16-94, 11-8-94, 10-3-95, 1-3-96, 6-22-99, 5-6-12, 10-1-13, 3-24-14, [DATE].

     

    40B-1.709 Suspension, Revocation, and Modification of District Permits.

    (1) through (3) no change.

    (4) The Board shall consider any timely filed petition for a sections 120.569 and 120.57, F.S., hearing at the next available regular regulatory meeting following expiration of the 14-day time period in subsection (2).

    (5) no change.

    Rulemaking Authority 373.044, 373.113 FS. Law Implemented 120.53(1)(b), (c), 120.60(2), 373.119, 373.429 FS. History–New 9-15-81, Repromulgated 3-17-88, Amended 12-21-88, 10-25-09, [DATE].

     

Document Information

Purpose:
The Suwannee River Water Management District (District) gives notice that it is initiating rulemaking to amend rules 40B-1.703, 40B-1.704, 40B-1.706, and 40B-1.709, F.A.C.; and repeal rule 40B-1.1010, F.A.C. The purpose of this rulemaking is to correct rule citations and a misspelling, align procedural rules with agency delegated authorities, and assign a lower cost fee for minor modifications of Works of the District permits as set forth in rule 40B-4.1110, F.A.C.
Rulemaking Authority:
373.044, 373.083, 373.109, 373.113, 373.118, 373.171, 373.4141 FS.
Law:
120.57, 120.59, 120.60, 218.075, 373.084, 373.085, 373.086, 373.103, 373.106, 373.116, 373.118, 373.119, 373.219, 373.229, 373.313, 373.413, 373.414, 373.416, 373.426, 373.429 FS.
Related Rules: (5)
40B-1.1010. Point of Entry into Proceedings
40B-1.703. Procedures for Consideration of Permit Applications
40B-1.704. Bond
40B-1.706. Fees
40B-1.709. Suspension, Revocation, and Modification of District Permits