1(1) The standard duration of permits issued pursuant to this chapter shall be as follows.
16(a) Five years duration for noticed general, general, and individual permits authorizing the construction or alteration of a work or development in a Works of the District. When a permit is issued for construction or alteration and the subsequent operation and maintenance, the portion of the permit authorizing construction or alteration shall be limited to five years from the date of issuance. 78The portion of the permit for the subsequent operation and maintenance shall be perpetual.
92(b) 93Five years’ duration for conceptual permits unless, within that period, application for a W107orks of the District 111permit for any part of the project is filed. If such application is filed, the conceptual permit is valid for the duration of the project.
136(c) 137Five years duration for abandonment permits to remove a work or development in a Work of the District.
155(2) 156Permits may not be authorized with durations that are greater than the standard durations found in subsection 17340B-4.1100(1), 174F.A.C.
175Rulemaking Authority 177373.044, 178373.113 FS. 180Law Implemented 182373.084, 183373.085, 184373.413, 185373.416, 186373.426 FS. 188History–New 9-25-85, Amended 12-22-92, 9-13-04, 10-14-13, 1-5-21.