  • 1A permit application processing fee is required and shall be paid to the District when certain applications are filed pursuant to District rules. An application shall not be considered complete until the appropriate application fee is submitted. These fees are assessed in order to defray the cost of evaluating, processing, monitoring, and inspecting for compliance required in connection with consideration of such applications. Fees are non-refundable in whole or part unless the activity for which an application is filed is determined by the District to be exempt or the fee submitted is determined by the District to be incorrect. Failure of any person to pay the applicable fees established herein will result in denial of an application. Activities that do not require a permit and are exempt pursuant to Rule 13140E-2.051 132or 13340E-3.051, 134F.A.C., are not subject to the following permit application fees. The District’s permit application processing fees are as follows:

    153(1) Water Use Permit Application processing fees are in the following table:

    165TABLE 16640E-1.607(1)

    167PERMIT APPLICATION PROCESSING FEES FOR

    172WATER USE PERMIT APPLICATIONS

    176REVIEWED PURSUANT TO CHAPTER 40E-2, F.A.C.

    182Fee amounts shall apply to applications for new permits, permit modifications, and permit renewals, except as noted.

    199Category

    200Amount

    201Individual Permit, except Mining/Dewatering (applies to all durations). Maximum monthly allocation:

     

    212Up to 3 million gallons per month (mgm).

    220$350

    221Greater than 3 mgm through 15 mgm.

    228$1,000

    230Individual Public Water Supply with a duration less than 20 years.

     

    241Maximum monthly allocation:

     

    244Greater than 15 mgm through 30 mgm

    251$2,700

    253Greater than 30 mgm through 300 mgm

    260$5,500

    262Greater than 300 mgm

    266$7,000

    268Individual Public Water Supply with a duration of at least 20 years.

     

    280Maximum monthly allocation:

     

    283Greater than 15 mgm through 30 mgm.

    290$4,200

    292Greater than 30 mgm through 300 mgm.

    299$8,500

    301Greater than 300 mgm.

    305$11,500

    307Individual Irrigation with a duration less than 20 years.

     

    316Maximum monthly allocation:

     

    319Greater than 15 mgm.

    323$1,000

    325Individual Irrigation with a duration of at least 20 years.

     

    335Maximum Monthly allocation:

     

    338Greater than 15 mgm through 30 mgm.

    345$1,600

    347Greater than 30 mgm through 300 mgm.

    354$3,400

    356Greater than 300 mgm.

    360$5,600

    362Individual Mining/Dewatering.

     

    364Standard Individual Permit with a total project duration of up to one year.

    377$500

    378Standard Individual Permit with a total project duration of greater than one year.

    391$1,800

    393Master Individual Permit.

    396$4,000

    398Individual Commercial/Industrial with a duration less than 20 years.

     

    407Maximum monthly allocation:

     

    410Greater than 15 mgm through 30 mgm.

    417$1,400

    419Greater than 30 mgm through 300 mgm.

    426$2,750

    428Greater than 300 mgm.

    432$3,500

    434Individual Commercial/Industrial with a duration of at least 20 years.

     

    444Maximum monthly allocation:

     

    447Greater than 15 mgm through 30 mgm.

    454$2,000

    456Greater than 30 mgm through 300 mgm.

    463$3,650

    465Greater than 300 mgm.

    469$5,600

    471Individual Diversion and Impoundment with a duration less than 20 years. Maximum monthly allocation:

     

    485Greater than 15 mgm through 30 mgm.

    492$1,400

    494Greater than 30 mgm through 300 mgm.

    501$2,750

    503Greater than 300 mgm.

    507$3,500

    509Individual Diversion and Impoundment with a duration of at least 20 years. Maximum monthly allocation:

     

    524Greater than 15 mgm through 30 mgm.

    531$2,000

    533Greater than 30 mgm through 300 mgm.

    540$3,950

    542Greater than 300 mgm.

    546$6,200

    548Independent Secondary User of a Diversion and Impoundment (applies to all durations).

     

    560Maximum monthly allocation:

     

    563Greater than 15 mgm through 30 mgm.

    570$1,000

    572Greater than 30 mgm through 300 mgm.

    579$2,000

    581Greater than 300 mgm.

    585$3,200

    587Noticed General Water Use Permit.

     

    592Applications filed electronically at www.sfwmd.gov/ePermitting.

    597$100

    598Application filed by other means.

    603$350

    604Aquifer Storage and Recovery: cost added to the applicable use type listed above.

    617$1,000

    619Permit Transfer to Another Entity Pursuant to Rules 62740E-0.107 628and 62940E-2.351, 630F.A.C.

    631$300

    632Letter Modification.

    634no fee

    636General Permit by Rule.

    640no fee

    642(2) Water Well Construction Permit Application processing fees are in the following table:

    655TABLE 65640E-1.607(2)

    657PERMIT APPLICATION PROCESSING FEES FOR

    662WATER WELL CONSTRUCTION PERMIT APPLICATIONS

    667REVIEWED PURSUANT TO CHAPTER 40E-3, F.A.C.

    673Category

    674Amount

    675Water Well Construction.

    678$100

    679Water Well Abandonment.

    682no fee

    684(3)(a) Environmental Resource Permit Application processing fees are in the following table:

    696TABLE 69740E-1.607(3)(a)

    698PERMIT APPLICATION PROCESSING FEES FOR

    703ENVIRONMENTAL RESOURCE PERMIT APPLICATIONS

    707REVIEWED PURSUANT TO CHAPTER 62-330, F.A.C.

    713For the purposes of determining the applicable processing fee, “project area” means the total area wherein works occur as part of an activity requiring a permit under Chapter 373, Part IV, F.S., including all portions of the stormwater management system serving the project area.

    7571. Use of the reviewing agency’s electronic self-certification system.

    766$0

    7672. Verification of exemption under Section 773373.406 774or 775403.813(1), F.S. 777or under Rules 78062-330.050 781through 62-33.051, F.A.C.

     

    784$100

    7853. Verification of qualification to use a General Permit.

    794$250

    7954. Individual or Conceptual Approval Permits, excluding Permits for a Mitigation Bank.

     

    807a. New applications – the processing fee for a new permit application shall be as determined from the categories below:

     

    827(I) Total project area of less than 10 acres and no activities in, on or over wetlands or other surface waters, except where exempt under paragraphs 85362-330.051(9)(a) 854through (c), F.A.C.

    857$2,000

    859(II) Project exceeds any of the thresholds in sub-sub-subparagraphs (3)(a)4.a.(I), above involves a total project area of less than 10 acres, less than 1 acre of works (i.e. dredging, filling, construction, or alteration) in, on or over wetlands and other surface waters, AND less than 10 new boat slips.

    908$3,500

    910(III) Project exceeds any of the thresholds in sub-sub-subparagraph (3)(a)4.a.(II), above, but involves a total project area of less and 40 acres, less than 3 acres of works in, on or over wetlands and other surface waters, AND less than 30 new boat slips.

    954$5,500

    956(IV) Project exceeds any of the thresholds in sub-sub-subparagraph (3)(a)4.a.(III), above, but involves a total project area of less than 100 acres, less than 10 acres of works in, on or over wetlands and other surface waters, AND less than 50 new boats ships.

    1000$7,500

    1002(V) Project exceeds any of the thresholds in sub-sub-subparagraph (3)(a)4.a.(IV), above, but involves a total project area of less than 640 acres, AND less than 50 acres of works in, on or over wetlands and other surface waters.

    1040$13,125

    1042(VI) Project exceeds any of the thresholds sub-sub-subparagraph (3)(a)4.a.(V), above.

    1052$25,000

    1054(VII) Projects that are exclusively for agriculture or silviculture, and that involve a total project area of less than 10 acres AND less than 1 acre of works (i.e. dredging, filling, construction, or alternatiion) in, on or over wetlands and other surface waters.

    1097$859

    1098(VIII) Projects that are exclusively for agriculture of silviculture, and that exceed any of the thresholds in sub-sub-subparagraph (3)(a)4.a.(VII), above, but involves a total project area of less than 40 acres AND less than 3 acres of works in, on or over wetlands and other surface waters.

    1145$2,444

    1147(IX) Projects that are exclusively for agriculture or silviculture, and that exceed any of the thresholds in sub-sub- subparagraph (3)(a)4.a.(VIII), above, but involve a total project area of less than 100 acres AND less than 10 acres of works in, on or over wetlands and other surface waters.

    1195$4,029

    1197(X) Projects that are exclusively for agriculture or silviculture, and that exceed any of the thresholds in sub-sub-subparagraph (3)(a)4.a.(IX), above, but involve a total project area of less than 640 acres AND less than 50 acres of works in, on or over wetlands and other surface waters.

    1244$5,284

    1246(XI) Projects that are exclusively for agriculture or silviculture, and that exceed any of the thresholds in sub-sub-subparagraph (3)(a)4.a.(X), above.

    1266$6,605

    1268(XII) Individual or Conceptual Permits solely for environmental restoration or enhancement activities, provided such activities are not associated with a mitigation bank and are not being implemented as mitigation for other activities that require a permit under Chapter 373, Part IV, F.S. For the purposes of this provision, the term “environmental restoration or enhancement” means an action or actions designed and implemented solely to convert degraded or altered uplands, wetlands, or other surface waters to intact communities typical of those historically present, or to improve the quality and condition of currently degraded wetlands or other surface waters to the more healthy, functional, and sustaining condition for fish, wildlife, and listed species.

    1379$250

    1380(XIII) Individual or Conceptual Permit solely to retrofit an existing stormwater management system or systems to add treatment to and reduce stormwater pollutant loadings from the system or systems.

    1409$250

    1410(XIV) An Individual Permit for a phase of construction that is consistent with an existing Conceptual Approval Permit.

    1428$1,500

    1430b. Major Modifications that exceed any of the thresholds in subsection 144162-330.315(3), 1442F.A.C.

     

    1443(I) Major Modification to an Individual or Conceptual Approval Permit that increase the project area.

    145860% of fee for new permit for the same activity

    1468(II) All other Major Modification.

    147360% of fee for new permit for the same activity

    1483c. Minor Modifications that do not exceed any of the thresholds in subsection 149662-330.315(2), 1497F.A.C.

     

    1498(I) Time Extensions of Permits, where not exempt from fees under Florida Statutes.

    1511$500

    1512(II) Minor Modifications to correct minor errors that do not involve technical review, to transfer ownership of a permit, or to transfer a permit from the construction to the operation phase.

    1543$0

    1544(III) All other Minor Modifications.

    1549$250

    15505. Individual or Conceptual Permits for a Mitigation Bank.

     

    1559a. New applications.

     

    1562(I) For a Mitigation Bank with a permit area less than 100 acres.

    1575$7,500

    1577(II) For a Mitigation Bank with a permit area greater than 100 acres but less than 640 acres.

    1595$13,125

    1597(III) For a Mitigation Bank with a permit area of 640 acres or more.

     

    1611b. Major Modifications involving changes to one or more of the following components: service area; credit assessment; success or release criteria; hydrologic structures or alterations; constructions or mitigation design that does not increase the project area; elimination of lands; or monitoring or management plans:

    1655$25,000

    1657(I) Affecting one of the above components.

    166420% of the fee under 5.a.

    1670(II) Affective to of the above components.

    167740% of the fee under 5.a.

    1683(III) Affective three of the above components.

    169060% of the fee under 5.a.

    1696(IV) Major modifications affecting four or more of the above components of the increase the project

    1712area.

    1713100% of the fee under 5.a.

    1719c. Major Modification that do not involve changes to the components listed in sub-subparagraph

    1733(3)(a)5.b. above, but that exceed any of the thresholds in subsection 174462-330.315(2), 1745F.A.C.

    1746100% of the fee under 5.a.

    1752d. Minor Modifications that do not exceed any of the thresholds in subsection 176562-330.315(2), 1766F.A.C.

     

    1767(I) Time Extensions of Permits, where not exempt from fees under Florida Statutes.

    1780$500

    1781(II) To correct minor errors that do not involve technical review, to transfer ownership of a permit, or to transfer a permit from the construction to the operation phase.

    1810$0

    1811(III) All other Minor Modifications.

    1816$250

    1817e. Mitigation Bank Credit Release.

    1822$0

    1823f. Mitigation Bank Credit Withdrawal.

    1828$0

    18296. Informal Wetland Determination.

     

    1833a. Where total area included is less than 1 acre.

    1843$250

    1844b. Where total area included is greater than 1 acre.

    1854$500

    18557. Variance or Waiver:

     

    1859a. Under Section 120.532, F.S.

    1864$0

    1865b. Under Section 1868373.414(17), F.S.

    1870$1,125

    18728. Fee reductions.

     

    1875a. Applications by an entity qualifying under Section 1883218.075, F.S., 1885when the fee exceeds $100.00.

    1890$100.00

    1891b. Applications submitted by the U.S. Department of Defense.

    1900$0

    1901c. For resubmittal, within 365 days, of an application for the same project that was previously

    1917withdrawn, under subsection 192062-330.071(3), 1921F.A.C., any fee paid as part of the previous application

    1931will be applied toward the fee required for the application under this rule.

    1944Previously paid fee shall be applied

    19509. When used in Table paragraph 195640E-1.607(3)(a), 1957F.A.C., “Agriculture” shall be defined as set forth in Section 1967570.02, F.S.

    196910. For permit applications which involve a combination of fee categories, the highest fee that applies shall be charged.

    198811. Any individual permit application submitted concurrently with a conceptual approval application – where the individual permit application represents a phase of the conceptual approval application – is exempt from the above environmental resource permit fees.

    202412. For projects grandfathered pursuant to Section 2031373.414, F.S., 2033the letter modification, conceptual approval, individual or general surface water management permit application fee shall be the same as listed in Table paragraph 205640E-1.607(3)(a), 2057F.A.C.

    205813. The District shall use the Consumer Price Index (CPI) adopted by the United States Department of Labor since the most recently revised fee increase for revising fees under Chapter 373, Part IV, F.S., pursuant to Section 2095373.109, F.S. 2097The inflation index used is the price paid by all urban consumers for a market basket of consumer goods and services; specifically, the CPI figures for the “CPI-U, U.S. City Average. All Items” established for the previous five years by the Bureau of Labor Statistics (BLS) (2144www.bls.gov/cpi2145), computed as provided in the BLS publication Bureau of Labor Staticstics Handbook of Methods, Chapter 17 (2163www.bls.gov/opub/hom/pdf/homch17.pdf)2164.

    2165(b) Permit application processing fees for projects grandfathered pursuant to Section 2176373.414, F.S., 2178wetland resource (dredge and fill) are in the following table:

    2188TABLE 218940E-1.607(3)(b)

    2190PERMIT APPLICATION PROCESSING FEES FOR

    2195PROJECTS GRANDFATHERED PURSUANT TO SECTION 2200373.414, F.S.

    2202WETLAND RESOURCE (DREDGE AND FILL) PERMIT APPLICATIONS

    2209REVIEWED PURSUANT TO CHAPTERS 40E-4, 40E-40, AND 40E-400, F.A.C.

    2218Category

    2219Amount

    2220Construction projects up to and including 5 years.

     

    2228Standard form projects including dredge and fill activities that affect 10 or more acres of jurisdictional area, pursuant to subsection 224862-312.070(2), 2249F.A.C. (1993).

    2251$7,500

    2253Short form construction projects including dredging and filling activities that affect less than 10 acres of jurisdictional area, pursuant to subsection area, pursuant to subsection area, pursuant to subsection.

    2282$750

    2283Variance associated with a wetland resource permit application.

     

    2291From the prohibition of subsection 229662-312.080(7), 2297F.A.C.

    2298$132

    2299From other permitting standards, permit conditions, or water quality standards.

    2309$661

    2310General Permits.

    2312$132

    2313Minor modifications of permits that do not require substantial technical evaluation by the District, in conformance with subsections 233162-4.050(6) 2332and (7), F.A.C. (1993), do not require a new site inspection by the District, and will not lead to substantially different environmental impacts or will lessen the impacts of the original permit:

    2364$66

    2365Transfer of permits or time extensions. Minor technical changes.

     

    2374Existing permit fee is less than $300, except for modification to permits issued pursuant to Section 2390403.816, F.S.

    2392$66

    2393Existing permit fee is equal to or more than 300.

    2403$330

    24041. For the purposes of determining the fee for wetland resource management permits, the term of duration for the permit shall be reduced by the period of time (in yearly increments) during which no dredging or filling activity occurs or no reclamation, restoration, or mitigation occurs and only minor monitoring and maintenance activities are required.The fee for the full term shall be submitted with the application. After the District determines the period of time that the term of the permit can be reduced, the excess fee shall be returned.

    24932. For permit applications which involve a combination of the project fee categories listed above, the highest fee that applies to the appropriate standard form or short form project, pursuant to Rule 252562-312.070, 2526F.A.C., shall be charged.

    25303. A single additional fee of $500 shall be required for projects in which monitoring and evaluation to determine the success of the mitigation will be required beyond the period of time to which the permit fee will ordinarily apply. If it is determined at the time of the permit application that monitoring and evaluation to determine the success of the mitigation will be required beyond the time period to which the permit fee will ordinarily apply, then this single additional fee shall be due when it is determined that this monitoring and evaluation is required.

    2626(4) Application for proprietary authorization under Chapters 253 and 258, F.S., except consent of use authorizations, processing fees are in the following table:

    2649TABLE 265040E-1.607(4)

    2651PERMIT APPLICATION PROCESSING FEES FOR

    2656PROPRIETARY AUTHORIZATIONS UNDER

    2659CHAPTERS 253 AND 258, F.S.,

    2664EXCEPT CONSENT OF USE AUTHORIZATIONS

    2669See Chapter 18-21, F.A.C. for application fees for proprietary authorizations, specifically as follows:

    2682Subparagraph 268318-21.008(1)(a)8., 2684F.A.C.

    2685Applications for Lease (eff. 8-10-05)

    2690Paragraph 269118-21.0081(1)(k), 2692F.A.C.

    2693Grandfather Structure Applications (eff. 8-10-05)

    2698Paragraph 269918-21.009(1)(g), 2700F.A.C.

    2701Applications for Public Easement (eff. 8-10-05)

    2707Paragraph 270818-21.010(1)(i), 2709F.A.C.

    2710Applications for Private Easement (eff. 8-10-05)

    2716Paragraph 271718-21.013(1)(l), 2718F.A.C.

    2719Applications to Purchase Lands Riparian to Uplands (eff. 3-27-82)

    2728Subsection 272918-21.019(7), 2730F.A.C.

    2731Applications for Disclaimers, Quitclaim Deeds or Certificates to Clear Title to Filled Sovereignty Lands and for Disclaimers for Lands Lost Due to Avulsion or to Reclaim Lands Lost due to Artificial Erosion or Artificial Erosion and Avulsion (eff. 4-13-98)

    2770(5) Petition for Formal Determination of Wetlands and Other Surface Waters processing fees are in the following table:

    2788TABLE 278940E-1.607(5)

    2790DETERMINATION PETITION PROCESSING FEES FOR

    2795FORMAL DETERMINATION OF WETLANDS AND

    2800OTHER SURFACE WATERS

    2803For the validation of informal, non-binding wetland determinations pursuant to Section 2814373.421(6), F.S., 2816the fees shall be the same as formal determinations listed in Table subsection 282940E-1.607(5), 2830F.A.C.

    2831Category

    2832Amount

    2833Property less than or equal to 10 acres.

    2841$500

    2842Property greater than 10 acres but less than or equal to 40 acres.

    2855$1,000

    2857Property greater than 40 acres but less than or equal to 100 acres.

    2870$1,500

    2872Additional fee per 100 acres (or portion thereof) beyond the first 100 acres.

    2885$350

    2886Reissuance of a Formal Determination.

    2891$350

    2892(6) Permit Processing Fee Waiver for Certain Local Governments.

    2901Notwithstanding the provisions set forth above in this rule, the District shall waive permit processing fees for permit applications submitted by the governing body of a county with a population of less than 50,000, a municipality with a population of less than 25,000, a county or municipality not included within a metropolitan statistical area, or a third party under contract with such a county or municipality, provided:

    2970(a) The project for which the fee waiver is sought serves a public purpose; and

    2985(b) The governing body submits Form No. 889 certifying that the fee reduction is necessary due to an environmental need for a particular project or activity; or

    3012(c) The governing body submits Certification of Waiver of Permit Application Processing Fee, Form No. 0889, certifying that the permit processing fee is a fiscal hardship due to one of the following factors:

    30451. Per capita taxable value is less than the statewide average for the current fiscal year;

    30612. Percentage of assessed property value that is exempt from ad valorem taxation is higher than the statewide average for the current fiscal year;

    30853. Any condition specified in Section 3091218.503, F.S., 3093that determines a state of financial emergency;

    31004. Ad valorem operating millage rate for the current year is greater than 8 mills; or

    31165. A financial condition is documented in annual statements at the end of the current fiscal year which indicates an inability to pay the permit processing fee during that fiscal year.

    3147Form 0889, December 2011, 3151http://www.flrules.org/Gateway/reference.asp?No=Ref-00061, 3153is incorporated by reference herein and available at no cost by contacting the South Florida Water Management District Clerk’s Office, 3301 Gun Club Road, West Palm Beach, FL 33406, (800)432-2045, ext. 6436 or (561)682-6436.

    3187(7) PERMIT APPLICATION PROCESSING FEES FOR MODIFICATION OR TRANSFER OF ENVIRONMENTAL RESOURCE, SURFACE WATER MANAGEMENT OR WORKS OF THE DISTRICT PERMITS FOR PROPERTIES ACQUIRED BY THE DISTRICT PURSUANT TO THE FLORIDA FOREVER WORK PLAN OR SAVE OUR RIVERS LAND ACQUISITION AND MANAGEMENT PLAN:

    3230(a) Modification of existing permits to reflect property ownership changes where no new works or modifications to an existing stormwater management system is requested.

    3254$0

    3255(b) Permit transfer pursuant to Rules 326140E-1.6107 3262and 326362-330.340, 3264F.A.C.

    3265$0

    3266Rulemaking Authority 3268373.044, 3269373.109, 3270373.113, 3271373.171, 3272373.421(2), 3273373.421(6)(b), 3274373.4131 FS. 3276Law Implemented 3278218.075, 3279373.109, 3280373.4131, 3281373.421(2), 3282373.421(6)(b), 3283403.201 FS. 3285History–New 1-8-89, Amended 1-2-91, 11-15-92, 6-1-93, 1-23-94, 10-3-95, 4-1-96, 11-8-99, 5-24-00, 6-26-02, 7-11-02, 8-10-03, 8-14-03, 11-18-07, 11-1-09, 12-15-11, 10-23-12, 10-1-13, 7-31-14, 9-7-15, 8-7-16.

     

Rulemaking Events:

Historical Versions(8)

Select effective date to view different version.