40E-63.156. Conditions for Issuance for Master Permits in the EAA Basin  


Effective on Tuesday, July 3, 2001
  • 1(1) In order to obtain a permit under Part I of this Chapter, an applicant must satisfy all the following conditions:

    22(a) The permittee shall comply with all conditions required by subsections 3340E-63.136(1), 34(2) and (3), F.A.C. (Conditions for Issuance of Individual Permits in the EAA Basin); and

    49(b) The permittee shall demonstrate sufficient legal and financial capability to carry out all acts necessary to implement the terms and conditions of the Master Permit, including the ability to take necessary enforcement action.

    83(2) The number of monitoring sites required for a Master Permit may be reduced by the District provided the proposed monitoring plan can reasonably be expected to accomplish the plan rationale, including the documentation of flow and total phosphorus concentration discharged from all lands included in the Master Permit.

    132Rulemaking Authority 134373.044, 135373.113 FS. 137Law Implemented 139373.016, 140373.085, 141373.086, 142373.451, 143373.453, 144373.4592 FS. 146History–New 1-22-92, Amended 7-3-01.

     