Florida Administrative Code (Last Updated: November 11, 2024) |
60. Department of Management Services |
60GG. Florida Digital Service |
60GG-1. Department of Management Services Project Management and Oversight |
1(1) In the Planning phase, the Agency develops and approves detailed project planning documents.
15(2) The matrix provided below lists planning activities and documents required for the project based on the project’s Risk and Complexity (R&C) Category.
38(a) Specific document types, templates, or formats are not prescribed – any documentation that contains the information specified in the requirements below is acceptable.
62(b) This documentation, whether created separately or combined as a s73ingle document, constitutes the Project Management Plan.
80PLANNING PHASE ‒ Requirements by Risk & Complexity Category
894
903
912
921
93Project Scope
95Required ‒ Clearly delineate the project scope, specifically what is in scope, what is out of scope, project objec114tives, and deliverables. This will determine scope baselines and variances. Discuss how the project scope and objectives trace back through the Project Charter to initial project documents such as the Schedule IV-B.
146Document the approach for project execution (identify the Software Development Life Cycle model that will be used – such as Agile, waterfall, etc.) Identify assumptions and constraints.
173Required 174‒ Summarize the project scope (in scope and out of scope).
1854
1863
1872
1881
189Work Breakdown Structure (WBS)
193Required – Document the hierarchical and incremental decomposition of the project into phases, deliverables, and work packages. Identifies all the tasks re215quired to deliver the total project scope of work to produce each deliverable. Tasks must be decomposed into subtasks until they can be estimated, observed, and evaluated.
242Not Required
2444
2453
2462
2471
248Project Organizational and Governance Structure
253Required – Document a representation of the project from an organizational perspective. Include an organization chart with stakeholder and governance structures identified. Include a detailed description of the project and the Agency’s governance process with roles, r290esponsibilities, and approval authorities identified for project documents or artifacts, including any processes for final product acceptance. Include reporting and escalation parameters for variances in baseline schedule, cost, and scope.
320Required ‒ Ident323ify the project stakeholders and the responsibilities for decision-making and escalation.
3344
3353
3362
3371
338Resource Plan
340Required ‒ Document the resources required to complete the project and how these resources will be acquired.
357For human resources – identify p363roject roles, skills, number, and resource type required, and specify the method(s) for acquiring new personnel or incorporating and backfilling the current responsibilities of existing personnel.
389For equipment or materials ‒ identify types, quantities, an398d purpose, and specify the method(s) for acquiring equipment or materials.
409Recommended: List the number and type of resources anticipated and what, if any, resources must be procured.
4264
4273
4282
4291
430Schedule Management Plan
433Required ‒ Document the approach to 439create an integrated master schedule that encompasses the total scope of the project and identifies the projects critical path. Describe the process for establishing and changing the schedule baseline. Describe the responsibilities, timeframes, and methods to manage, update and report progress (including Earned Value Analysis) throughout the project.
487Recommended 488‒ Document the approach to create an integrated master schedule that encompasses the total scope of the project and identifies the projects critical path.
5124
5133
5142
5151
516Project Schedule
518Required ‒ Develop and maintain an integrated master project schedule tha529t identifies the total project scope of work (including milestones and deliverables); is task, 543resource, and cost 546loaded; identifies the project critical path, is baselined and updated with project progress; and contains the information necessary to provide earned value analysis and support schedule and cost performance index (SPI and CPI) variance analysis and reporting.
583Required 584‒ Develop, and maintain a schedule that identifies the total project scope of work, assigned resources, and task start and end dates.
6064
6073
6082
6091
610Project Budget
612Required ‒ Develop and maintain a Project Budget, which must include specific fiscal year cost t628otals over the life of the project and the overall total cost of the project. Also include a description of the funding source(s) for the Project and a breakdown of the Project costs by major expense categories.
665Required – Develop and maintain a Project Budget, which must include specific fiscal year cost totals over the life of the project and the overall total cost of the project.
6954
6963
6972
6981
699Project Spending
701Plan
702Required 703‒ Develop and maintain a Project Spending Plan, which, as a component of the Project Budget, must include monthly planned (baselined) and actual expenditures (by expenditure or expenditure category) for each fiscal year.
736Required ‒ Document current fiscal 741year planned expenditures and actual expenditures by month and Fiscal Year total to date. Include other expenditure detail as required for the Project Status Report.
766Recommended ‒
768Document current fiscal year planned expenditures and actual expenditures b778y month and Fiscal Year total to date.
7864
7873
7882
7891
790Communications Management Plan
793Required ‒ Identify the project information requirements of stakeholders and detail what, when, and how information will be collected and reported.
814This will include the respo819nsibility, frequency, format, and distribution method for meeting summaries, project status reports, project governance meetings, and stakeholder communications, including reporting variances in schedule, cost, or scope and emerging risks or issues. Document the location of the project repository.
857Include documentation for Decision Tracking and Action Item Tracking (see Rule 60GG-1.006, F.A.C. 870‒ Monitoring and 873Controlling874).
875Required ‒ Identify the project information requirements of stakeholders and detail what, when, and how information will be collected and reported.
8964
8973
8982
8991
900Change Management Plan
903Required ‒ Document the change control proc910ess and documentation involved in identifying, analyzing impacts, escalating, approving, and managing project change requests related to the project’s schedule, cost, or scope baselines, or a change to project deliverables (see Rule 60GG-1.006, F.A.C. ‒ Mo946nitoring and 948Controlling949).
9504
9513
9522
9531
954Quality Management Plan
957Required ‒ Document the processes and procedures for ensuring quality planning, quality assurance, and quality control are all conducted.
976Required ‒ Document any method(s) for ensuring customer acceptance of the product or service.
9904
9913
9922
9931
994Deliverable Acceptance Plan
997Required ‒ Document each deliverable, the acceptance criteria for each deliverable, and the deliverable acceptance process (including roles and responsibilities).
1017Required ‒ List the deliverables and the person(s) responsible for approving deliverables.
10294
10303
10312
10321
1033Risk Management
1035Plan
1036Required ‒ Document the process for the descriptive identification (listing), evaluation (probability and impact), prioritization, and response to risks (specified mitigation strategies for each risk), as well as the nature of any time sensitivity to risks that may impact the project. Identify the roles and responsibilities of individuals assigned to risks. Identify and document the process to be used for tracking, periodic review, and update of Risks (see Rule 60GG-1.006, F.A.C. ‒ Monitoring and 1110Controlling1111).
1112Required ‒ Describe the method for monitoring and controlling risk.
11224
11233
11242
11251
1126Issue Management
1128Plan
1129Required ‒ Document the process for (and the documentation of) the identification, evaluation, management, and resolution to issues impacting the project. Identify and document the process to be used for tracking, periodic review, and update of Issues (see Rule 60GG-1.006, F.A.C. ‒ Monitoring and 1173Controlling1174). Identify the roles and responsibilities of project staff.
1183Required ‒ Describe the method for monitoring and addressing issues.
11934
11943
11952
11961
1197Procurement Management Plan
1200Required ‒ If procurement is required by the project, document any products or services needed, identify the specific products and services to be purchased, along with the appropriate purchasing methods, rules, and statutes affecting these activities.
1236Required ‒ List any procurements required for the project.
12454
12463
12472
12481
1249Organizational Change Management Plan
1253Required ‒ Document the impact of delivering the project’s products to the user organization and individual users; the readiness of the user organization and individual users to accept those changes; and describe and plan the action necessary to facilitate those changes.
1294Required ‒ Document the impact of delivering the projects products to the user organization and the individual users.
1312Recommended – Document the impact of delivering the projects products to the user organization and the individual users.
13304
13313
13322
13331
1334Florida Cybersecurity Standards
1337Required – Compliance with rule Chapter 60GG-2, F.A.C.
13454
13463
13472
13481
1349Requirements Traceability Matrix
1352(RTM)
1353Required ‒ Prepare a document (usually a table) that links high-level design and requirements with detailed requirements, detailed design, test plan, and test cases.
1377The RTM ensures that all requirements are identified and correctly linked (from high-level to detailed and technical levels) throughout the project.
1398Required ‒
1400Document Requirements.
1402Planning Gate R&C Assessment
1406Required
1407(3) The Agency must complete the Planning Gate R&C Assessment at the end of the Planning phase 1424(see Rule 142660GG1427-1.002 ‒ Risk and Complexity Assessment, F.A.C.)1434. This Assessment will confirm or adjust the project’s risk and complexity levels and the resulting R&C Category, validate Planning management control requirements, and set management control requirements for the subsequent Execution and Monitoring and 1469Controlling 1470phases.
1471Rulemaking Authority 1473282.0051(6) 1474FS1475. Law Implemented 1478282.0041, 1479282.0051 FS. History‒New 7-16-15, Amended 8-1-16, Formerly 74-1.004.