62-17.535. Notification of Construction of Transmission Lines Not Subject to the Act  


Effective on Monday, May 24, 2010
  • 1The notification required pursuant to Section 7403.524(4), F.S., 9shall provide the following information:

    14(1) Location of the line in terms of county, or sections/townships/ranges;

    25(2) Names or identifiers of connection points, e.g. “X” switchyard to “Y” substation;

    38(3) Line size and total length; and

    45(4) If the basis of the exemption from the Act under Section 57403.524, F.S., 59is construction of any portion of the transmission line within one or more established transmission line rights-of-way, documentation of the date each such right-of-way was established by means of a deed, grant, permit, license or reservation of easement, final judgment of condemnation or other legal instrument. If documentation of the date of establishment for such a right-of-way is not specifically available, the utility shall consult with the Department as to an acceptable substitute for demonstrating the establishment of the transmission line right-of-way at least five years prior to the start of construction.

    151Rulemaking Authority 153403.523(1) FS. 155Law Implemented 157403.524(4) FS. 159History–New 5-24-10.

     