Florida Administrative Code (Last Updated: October 28, 2024) |
62. Department of Environmental Protection |
D62. Departmental |
62-213. Operation Permits For Major Sources Of Air Pollution |
1(1) If requested by the applicant, the Department shall concurrently process the applications for air construction permit and Title V permit revision or permit renewal, provided:
27(a) The application for air construction permit complies with the requirements of subsections 4062-213.420(3) 41and (4), F.A.C.;
44(b) The application for air construction permit is subject to federally enforceable preconstruction review pursuant to Chapter 62-212, F.A.C.; and
64(c) A source’s responsible official waives the processing time requirements for the air construction permit to accommodate the processing time frames of the Title V permit, and the Department complies with all requirements of subsection 9962-213.430(1), 100F.A.C., prior to taking final action on the applications for air construction permit and Title V permit revision or permit renewal.
121(2) The applicant may use the same application form and set of any required copies (DEP Form No. 13962-210.900(1)140) for both the air construction and air operation permits.
150(3) The Department will create a single public notice for both the air construction and air operation permits.
168(4) The Department will issue separate air construction and air operation permits.
180(5) The Title V air operation permit must contain a compliance plan in accordance with the provisions of subsection 19962-213.440(2), 200F.A.C., for each emissions unit covered by the air construction permit, reflecting the terms of the construction permit.
218(6) If concurrent application processing is not requested, nothing precludes the Department from combining the public notice for air construction and revision or renewal of air operation permits and acting on the air construction permit and air operation permit separately, at applicant request, provided the processing time frames accommodate concurrent notice or the applicant waives the processing time requirements to accommodate concurrent notice.
281Specific Authority 283403.061, 284403.087, 285403.0872 FS. 287Law Implemented 289403.061, 290403.0872 FS. 292History–New 6-2-02.