62D-5.057. Evaluation Criteria  


Effective on Sunday, August 15, 2004
  • 1Pursuant to subsection 462D-5.055(7), 5F.A.C., a total point score shall be assigned to each eligible application after an evaluation according to the application criteria which follows:

    27(1) GENERAL CRITERIA.

    30(a) The project implements the applicant’s adopted local comprehensive plan and: is included in the Capital Improvement Plan (CIP) or schedule during the current or next three (3) fiscal years:

    6020 points

    62or

     

    63is included as part of the plan through an adopted resolution committing the applicant to amend their CIP and complete the project should it receive program funds:

    9010 points

    92(b) The project would address one or more issues or goals as identified in the state comprehensive outdoor recreation plan:

    1124 points

    114(c) The project provides for a priority resource or facility need in the applicant’s planning region identified in the state comprehensive outdoor recreation plan:

    1387 points

    140(d) The applicant obtained public participation through the following methods:

    15021 maximum points

    153Presentation at an advertised public meeting held solely for the discussion of the proposed project.

    16810 points

    170Presentation at a regularly scheduled advisory board meeting responsible for park, recreation and leisure service activities.

    1867 points

    188Presentation to community organizations or neighborhood associations or opinion surveys.

    1984 points

    200(e) The applicant has the capability to develop, operate and maintain the project:

     

    213Has a full-time recreation or park department staffed to provide facility development, programming and maintenance capabilities.

    2296 points

    231or

     

    232Has demonstrated the existence of a full-time ability to provide facility development, programming and maintenance capabilities.

    2484 points

    250or

     

    251Has other means of providing facility development, programming and maintenance capabilities.

    2622 points

    264(f) The project is supported through a written cooperative agreement between the applicant and a private or public entity in which said entity agrees to furnish 10% or more of the cash, land, or labor services for the project.

    3033 points

    305(g) The project creates or enhances the development, extension or connection of local, regional, state or national parks, greenways, or trails. The project would provide for increased trail access by (a) connecting an existing, publicly owned and designated recreational trail with a project trail outside the project boundary; or (b) connecting two publicly designated trails outside of any park.

    3645 points

    366(2) DEVELOPMENT CRITERIA.

     

    369(a) The project provides for new development of entirely undeveloped park property:

    3815 points

     

    383(b) The project provides facilities identified in the priority ranked index clusters of outdoor facilities needs for renovation and/ or new construction identified within the applicant’s population density set forth in the Department’s study entitled “Infrastructure Assessment of Local Government Recreation and Park Department Facility Needs in the State of Florida”, effective December 1995, and incorporated herein by reference:

    4421. First priority ranked cluster:

    4476 points for each facility

    4522. Second priority ranked cluster:

    4575 points for each facility

    4623. Third priority ranked cluster:

    4674 points for each facility

    4724. Fourth priority ranked cluster:

    4773 points for each facility

    4825. Fifth priority ranked cluster:

    4872 points for each facility

    4926. Sixth priority ranked cluster:

    4971 point for each facility

     

    502(A project facility not listed in the priority ranked indexes will receive a score of a similar facility included in the indexes, as determined by Department staff).

    529(30) maximum points

    532(c) The project, in whole or in part, addresses the priority funding needs for new construction, renovation, or a combination of the two for the applicant’s population density identified in the Department’s study entitled “Infrastructure Assessment of Local Government Recreation and Park Department Facility Needs in the State of Florida”, identified in paragraph (2)(b) above:

    587Higher priority or combination of new construction and renovation.

    59613 points

    598Lower priority.

    6008 points

     

    602(3) ACQUISITION CRITERIA.

    605(a) The project provides for development of facilities identified in the top three priority ranked index clusters of outdoor facilities needs for new construction identified within the applicant’s population density set forth in the Department’s study entitled “Infrastructure Assessment of Local Government Recreation and Park Department Facility Needs in the State of Florida”, effective December 1995, and incorporated herein by reference:

    66615 points

    668(b) The project provides needed recreational acreage pursuant to the applicant’s adopted local comprehensive plan:

    68315 points

    685(c) The applicant has identified development of the property in their capital improvement plan (CIP) or schedule during the current or next 3 fiscal years:

    7106 points

    712or

     

    713applicant has included development of the property as part of the plan through an adopted resolution committing the applicant to amend their CIP and develop the property should it receive program funds:

    7453 points

    747(4) TRAIL CONSTRUCTION CRITERIA.

     

    751(a) The project provides for new trail construction on an entirely undeveloped park property:

    7655 points

    767(b) The project addresses one or more of the recommendations identified in the Greenways and Trails Plan:

    7846 points

    786(c) The project is located on or connects with a Florida Designated Greenway or Trail:

    8013 points

    803(d) The project implements an adopted local or regional Greenways or Trails Plan:

    8164 points

    818(e) The specific trail design demonstrates that the project will support mixed use/multi-use trail opportunities:

    8338 points

    835or

     

    836Single use recreational trail opportunities:

    8416 points

    843(f) The project addresses the priority funding needs for new construction, renovation, or a combination of the two for the applicant’s population density identified in the Department’s study entitled “Infrastructure Assessment of Local Government Recreation and Park Department Facility Needs in the State of Florida”, effective December 1995, available from the Department’s Division of Recreation and Parks, 3900 Commonwealth Boulevard, Mail Station 585, Tallahassee, Florida 32399-3000, (850) 245-2501, and incorporated herein by reference for one of the following:

    921Higher priority or combination of new construction and renovation:

    93013 points

    932Lower priority:

    9348 points

     

    936Specific Authority 938375.075 FS. 940Law Implemented 942375.075(2) FS. 944History–New 12-10-90, Formerly 16D-5.057, Amended 8-13-98, 8-23-00, 7-5-01, 8-15-04.

     