97-005978 Richard L. Silvani, Dick W. Thompson, James E. And Marilyn Bates, Joyce Menzie, James M. Gibson, Claudia C. Munsell, Mr. And Mrs. Phillip E. Durst, Donald R. Sosnoshr, Mr. And Mrs. Robert L. Nelson, And Mrs. Richard Ladow vs. Southwest Florida Water Management District And Hernando County
 Status: Closed
Recommended Order on Monday, June 8, 1998.


View Dockets  
Summary: County gave reasonable assurances that rule criteria for construction permit met.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8RICHARD L. SILVANI; DICK W. )

14THOMPSON; JAMES E. AND )

19MARILYN BATES; JOYCE MENZIE; )

24JAMES M. GIBSON; CLAUDIA C. )

30MUNSELL; MR. AND MRS. PHILLIP )

36E. DURST; DONALD R. SOSNOSHR; )

42MR. AND MRS. ROBERT L. )

48NELSON; and MRS. RICHARD )

53LADOW, )

55)

56Petitioners, )

58)

59vs. ) Case No. 97-5978

64)

65SOUTHWEST FLORIDA WATER )

69MANAGEMENT DISTRICT and )

73HERNANDO COUNTY, )

76)

77Respondents. )

79______________________________)

80RECOMMENDED ORDER

82Pursuant to notice, this matter was heard on March 17 and

93April 6, 1998, in Brooksville, Florida, by Donald R. Alexander,

103the assigned Administrative Law Judge of the Division of

112Administrative Hearings.

114APPEARANCES

115For Petitioners: Chester L. Bradshaw

120(Qualified Representative)

12218520 Bradshaw Road

125Dade City, Florida 33523

129For Petitioner: Richard L. Silvani, pro se

136( Silvani) 24419 Lanark Road

141Brooksville, Florida 34601

144For Respondent: Margaret M. Lytle, Esquire

150( SWFWMD) 2379 Broad Street

155Brooksville, Florida 34609-6899

158For Respondent: R. Bruce Snow, Esquire

164(County) William Buztrey, Esquire

16820 North Main Street, Room 462

174Brooksville, Florida 34601

177STATEMENT OF THE ISSUE

181The issue is whether Hernando County's application for an

190environmental resource permit authorizing the construction of a

198new surface water management system to serve a 7.85 acre drainage

209system improvement three miles southeast of Brooksville, Florida,

217should be approved.

220PRELIMINARY STATEMENT

222This case began on September 29, 1997, when Respondent,

231Southwest Florida Water Management District, gave notice that it

240intended to issue an environmental resource permit to Respondent,

249Hernando County, authorizing the construction of a new surface

258water management system three miles southeast of Brooksville,

266Florida. Petitioners, Richard L. Silvani, Dick W. Thompson,

274James E. and Marilyn Bates, Joyce Menzie, James M. Gibson,

284Claudia C. Munsell, Mr. and Mrs. Phillip E. Durst, Donald R.

295Sosnoshr, Mr. and Mrs. Robert L. Nelson, Mrs. Richard Ladow, and

306George Goff, all property owners in the area of the project,

317thereafter filed a Petition for Informal Hearing seeking to

326contest the proposed agency action. The petition generally

334contended that the permit application "contain[ ed] possible

342miscalculations of design," which would exacerbate existing flood

350problems in a number of respects. The petition further alleged

360that the County lacked easements for surface water storage. The

370petition was treated as a petition for a formal hearing and was

382referred by the agency to the Division of Administrative Hearings

392on December 23, 1997, with a request that an Administrative Law

403Judge be assigned to conduct a hearing. On February 26, 1998,

414George Goff filed a Notice of Withdrawal, in which he withdrew

425from participation in the case.

430By Notice of Hearing dated February 14, 1998, a final

440hearing was scheduled on March 17, 1998, in Brooksville, Florida.

450A continued hearing was held on April 6, 1998, at the same

462location.

463At final hearing, the agency's Motion in Limine and Motion

473That Facts be Taken as Established and For Other Relief were

484denied. All Petitioners except Richard L. Silvani were

492represented by Chester J. Bradshaw, a qualified representative,

500while Silvani represented himself. Petitioners presented the

507testimony of Chester J. Bradshaw, James M. Gibson, Dick W.

517Thompson, Marilyn Bates, Joyce Menzie, Jane Durst, Diane Nelson,

526Richard L. Silvani, and Julie Ann Defoe. Also, they offered

536Petitioners' Exhibit 1 and Silvani Exhibits 1 and 2. All

546exhibits were received in evidence. Hernando County presented

554the testimony of Charles D. Mixon, County Engineer and accepted

564as an expert in professional engineering; and Dale E. Cromwell,

574an engineering consultant and accepted as an expert in

583professional engineering. Also, it offered County Exhibits 1 and

5922. Both exhibits were received in evidence. The Southwest

601Florida Water Management District presented the testimony of

609C. Clay Black, a professional engineer and accepted as an expert

620in the design of surface water management systems and

629environmental resource permitting; and Julie Ann Defoe, an

637environmental scientist and accepted as an expert in wetlands and

647environmental resource permitting. Also, it offered District

654Exhibits 1-9. All exhibits were received in evidence.

662The transcript of hearing (three volumes) was filed on

671April 24, 1998. By agreement of the parties, the time for filing

683proposed findings of fact and conclusions of law was extended to

694May 26, 1998. The same were jointly filed by Respondents, and

705they have been considered in the preparation of this Recommended

715Order. On May 28, 1998, Petitioners filed a document styled as

"726Petitioners' Summary Request to Deny Permit," together with

734copies of numerous documents apparently obtained from

741Respondents' public records. The "Summary Request to Deny

749Permit" has been treated as a proposed order and has been

760considered in the preparation of this Recommended Order.

768FINDINGS OF FACT

771Based upon all of the evidence, the following findings of

781fact are determined:

784A. Background

7861. Petitioners, Richard J. Silvani, Dick W. Thompson,

794James E. and Marilyn Bates, Joyce Menzie, James M. Gibson,

804Claudia C. Munsell, Mr. and Mrs. Phillip E. Durst, Donald R.

815Sosnoski, Mr. and Mrs. Robert L. Nelson, and Mr. and Mrs.

826Richard Ladow (Petitioners), are property owners in central

834Hernando County, Florida. Respondent, Southwest Florida Water

841Managment District (District), is the state agency charged with

850the responsibility of issuing Environmental Resource Permits

857( ERP) within its jurisdictional boundaries. Respondent, Hernando

865County (County), is a local government seeking the issuance of a

876permit for the purpose of alleviating drainage and flooding

885problems in a subdivision known as High Point Gardens in the

896central part of the County.

9012. On June 11, 1997, the County filed an application with

912the District seeking authorization to construct a low earthen

921berm to help control flooding in High Point Gardens, an eighty-

932five unit residential subdivision. On September 29, 1997, the

941District gave notice of its intention to issue ERP No. 449342.01

952authorizing the "construction of a new surface water management

961system to serve a 7.85 acre drainage system improvement known as

972the Hernando County - High Point Gardens Drainage Improvements."

981The project is located off Sun Hill Lane, three miles southeast

992of Brooksville, Florida, in central Hernando County.

9993. On an undisclosed date, but in a timely fashion,

1009Petitioners filed their Petition for Informal Hearing challenging

1017the issuance of the permit. As grounds, Petitioners alleged that

1027the permit application contained "possible miscalculations of

1034design" which would "alter the natural water flow route";

"1043adversely affect several acres of natural wetlands by changing

1052hydrology of surface area"; "adversely affect adjacent uplands by

1061innundating forest areas never before flooded by heavy rainfall";

"1070not guarantee 100% flood protection to the few affected homes";

1080and "create flood problems to adjacent homes and property by

1090diverting stormwater from natural flow (north) to area east of

1100'proposed' retention area." The petition further alleged that

1108the "'proposed' area should not be normal recepient [sic] of

1118excess water from Cedar Falls subdivision" and that "all affected

1128properties are not owned or easements acquired by Hernando County

1138for surface water storage." The filing of the petition prompted

1148the initiation of this proceeding.

1153B. The Permit

11564. The High Point Gardens subdivision, which lies within

1165the Bystre Lake Basin, is a "relatively old subdivision," having

1175been built around the 1970's. There is a low area in the middle

1188of the subdivision, and it has "[s] everal sinks with a natural

1200drainage within the area." Because the thirty-square-mile basin

1208is a closed drainage basin, with no natural outflows,

"1217significant" flooding problems have been present throughout the

1225basin since at least the 1980's.

12315. In an effort to resolve flooding problems within the

1241basin, the County and District jointly sanctioned a study by a

1252consulting firm, Dames and Moore, to provide suggested

1260alternative actions to correct the problem. The firm's first

1269interim report was rendered on August 5, 1988, and a final report

1281known as the Bystre Lake Stormwater Management Master Plan was

1291rendered in August 1989.

12956. Among other things, the consultant's report recommended

1303that a berm be constructed to relieve the flooding in the High

1315Point Gardens' area. Acting on the report, the County obtained a

1326construction permit from the District in August 1991 in

1335accordance with the consultant's recommendation, but construction

1342on the project was not commenced prior to the permit expiring in

13541994. Although the consultant's report was the genesis for the

1364first permit, the plans and specifications for the new berm have

1375been modified by engineers after further study and review. It is

1386noted that the total land area of the project will be less than

1399100 acres.

14017. The High Point Gardens subdivision lies within sub-basin

1410304 of the basin. Under the new proposal, water which now comes

1422into sub-basins 304 and 406 from sub-basins 305 and 306 will be

1434stored in those latter sub-basins. The requested permit would

1443authorize the County to construct a low earthen berm along the

1454western side of sub-basin 406 and the southern boundary of sub-

1465basin 304 to help control flooding in the subdivision. The

1475proposed berm will range from one to five feet in height and

1487extend some 3,250 feet, or approximately six-tenths of a mile.

1498It will range from eight to ten feet in width with a side slope

1512of 4 to 1.

15168. The berm will impound water upstream of the berm to an

1528elevation of 90.5 NGVD, which is 1.5 feet higher than the water

1540would rise in the area under natural conditions. The water will

1551be stored in two natural ponds which are now located in the

1563project area. Once the water reaches an elevation of 90.5 NGVD,

1574which will occur only during an event exceeding a 25-year storm

1585event, three overflow structures will become operative and are

1594designed to mimic the natural water flows of the area.

16049. After the berm is constructed, all basins "downstream"

1613of the berm, including sub-basins 304, 405, and 406, will have

"1624significantly lower flood elevations than the 10, 25 and 100-

1634year storm event." That is to say, existing flooding to the

1645north and east of the proposed berm will be lessened. To the

1657extent that additional impoundment of water behind the berm will

1667occur, or flooding beyond the berm may occur during a 100-year

1678storm event, the County will acquire easements from local

1687property owners to store the additional water. Until the

1696aquisition of land occurs, construction cannot begin.

170310. There is one already disturbed wetland area near the

1713proposed construction area. No mitigation is required, however,

1721since the impact will be temporary and the area is expected to

1733naturally revegetate itself. There will be no adverse impacts to

1743fish, wildlife, or adjacent wetlands. Neither will the project

1752create any other environmental concerns. While there will be

1761some impact to upland trees caused by the impounded water, under

1772existing District rules, that impact cannot be used as a basis to

1784deny the permit.

178711. Based on generally accepted engineering principles, the

1795project is capable of being effectively performed and can

1804function as proposed. Also, the project can be effectively

1813operated and maintained. The County has the resources to

1822undertake the project in accordance with the terms and conditions

1832of the permit.

183512. The greater weight of credible and persuasive evidence

1844supports a finding that the County has given reasonable

1853assurances that all applicable criteria for the issuance of a

1863permit have been met.

1867C. Petitioners' Objections

187013. At hearing, Petitioners contended that the overflow

1878structures for the berm would alter the natural flow of water,

1889and increase the flow of water to the east of the proposed

1901project, where several Petitioners reside. As previously noted,

1909however, the more credible evidence shows that the project will

1919not increase the natural flow of water to the east of the berm.

1932More specifically, expert testimony demonstrated that the regular

1940flow through each weir in the post-development condition will not

1950be adversely greater than what occurred during the pre-

1959development condition.

196114. Petitioners also contended that the wetlands will be

1970negatively impacted by the project. Contrary expert testimony by

1979witness Defoe established, however, that there will be no

1988permanent adverse impacts to wetlands, fish, or wildlife if the

1998permit is approved.

200115. Petitioners next contended that the process was flawed

2010because very few on-site inspections of the project area were

2020made by District and County personnel, especially during the

2029rainy season, before the application was preliminarily approved.

2037There were, however, on-site inspections by District and County

2046staff and consultants, and it was not shown that the lack of

2058additional inspections affected the validity of their studies.

206616. A further contention was made at hearing that the

2076information supporting the application was insufficient and that

2084more study, including soil boring tests, should have been made.

2094As to additional soil boring tests, the evidence shows that it is

2106not a common engineering practice to perform soil testing

2115throughout the entire area that will be submerged. Therefore,

2124the existing tests were adequate to support the engineering

2133assumptions. Further, even if there were some infirmities in the

2143data and assumptions used and made in the 1989 Dames and Moore

2155report, as alleged by Petitioners, the errors or omissions were

2165minor, they were subject to later refinement by professional

2174engineers, and they did not materially affect the overall

2183validity of the current application. Finally, the application

2191file contains uncontradicted technical information supporting the

2198issuance of the permit.

220217. Petitioners' other concerns, while sincere and well-

2210intended, are not relevant to the permitting process. For

2219example, a concern that the construction of a berm will decrease

2230nearby property values, even if true, is not a consideration in

2241the permitting process. Similarly, Petitioners' valid concern

2248that some nearby upland trees will be damaged if water levels

2259rise for a prolonged period of time is not a basis under existing

2272District rules to deny the permit. At the same time, whether the

2284project is cost-effective and the best alternative for

2292alleviating flooding conditions in the area are political

2300decisions for the County, and thus they are not in issue in this

2313proceeding.

231418. Finally, Petitioners have pointed out that the County

2323has not completed acquisition of the necessary easements for the

2333project, and that until this is done, a permit should not issue.

2345However, the District has specifically provided as a condition

2354precedent to any construction work that the County finalize

2363ownership or control for all property where water levels will be

2374raised by the project.

2378CONCLUSIONS OF LAW

238119. The Division of Administrative Hearings has

2388jurisdiction over the subject matter and the parties hereto

2397pursuant to Sections 120.569 and 120.57(1), Florida Statutes.

240520. As the party seeking a permit, the County bears the

2416burden of proving by a preponderance of the evidence that the

2427application should be granted. Dep't of Transportation v. J.W.C.

2436Co., Inc. , 396 So. 2d 778, 789 (Fla. 1st DCA 1981).

244721. In order to show entitlement to a permit, the County

2458must give reasonable assurances that the permitting criteria in

2467Rules 40D-4.301, 40D-4.302, and 40D-40.302, Florida

2473Administrative Code, have been satisfied. By a preponderance of

2482the evidence, this burden has been met.

248922. The existence of possible alternative projects, the

2497project's cost effectiveness, the possible adverse impacts to

2505upland tree species, and the potential for a decrease in the

2516value of adjacent property, while well-intended concerns on the

2525part of Petitioners, are not criteria which may be considered by

2536the District in the permitting process. See , e . g ., Council of

2549the Lower Keys v. Toppino , 429 So. 2d 67 (Fla. 3d DCA 1983).

2562This being so, the application should be granted.

2570RECOMMENDATION

2571Based on the foregoing findings of fact and conclusions of

2581law, it is

2584RECOMMENDED that the Southwest Florida Water Management

2591District enter a final order granting Hernando County's

2599application for Standard General Environmental Resource Permit

2606No. 449342.01.

2608DONE AND ENTERED this 8th day of June, 1998, in Tallahassee,

2619Leon County, Florida.

2622___________________________________

2623DONALD R . ALEXANDER

2627Administrative Law Judge

2630Division of Administrative Hearings

2634The DeSoto Building

26371230 Apalachee Parkway

2640Tallahassee, Florida 32399-3060

2643(850) 488-9675, SUNCOM 278-9675

2647Fax Filing (850) 921-6847

2651Filed with the Clerk of the

2657Division of Administrative Hearings

2661this 8th day of June, 1998.

2667COPIES FURNISHED:

2669E. D. "Sonny" Vergara, Executive Director

2675Southwest Florida Water Management District

26802379 Broad Street

2683Brooksville, Florida 34609-6899

2686Chester Bradshaw

268818520 Bradshaw Road

2691Dade City, Florida 33523

2695Richard L. Silvani

269824419 Lanark Road

2701Brooksville, Florida 34601

2704Margaret M. Lytle, Esquire

27082379 Broad Street

2711Brooksville, Florida 34609-6899

2714Robert Bruce Snow, Esquire

271820 North Main Street, Room 462

2724Brooksville, Florida 34601

2727NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

2733All parties have the right to submit written exceptions to this

2744Recommended Order within fifteen days. Any exceptions to this

2753Recommended Order should be filed with the Southwest Florida Water

2763Management District.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 06/18/2004
Proceedings: Notice of Entry of Final Order SWF 98-10 filed.
PDF:
Date: 06/18/2004
Proceedings: Final Order filed.
PDF:
Date: 06/23/1998
Proceedings: Agency Final Order
Date: 06/10/1998
Proceedings: Letter to M. Lytle from C. Bradshaw Re: Proposed High Point Gardens Subdivision Berm Hernando County filed.
PDF:
Date: 06/08/1998
Proceedings: Recommended Order
PDF:
Date: 06/08/1998
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 04/06/98.
Date: 05/28/1998
Proceedings: Petitioner`s Summary Request to Deny Permit Proposed High Point Gardens Berm ; Exhibits ; Permit Application for Bystre Lake Watershed Drainage Improvements filed.
Date: 05/26/1998
Proceedings: Respondents` Joint Argument; Respondents` Joint Proposed Recommended Order (For Judge Signature) filed.
Date: 04/24/1998
Proceedings: Transcript (3-volumes with cover letter, TAGGED)filed.
Date: 04/23/1998
Proceedings: Letter to DRA from Nancy Dewitz (RE: notice of filing transcripts/no enclosures) (filed via facisimile) filed.
Date: 04/10/1998
Proceedings: Letter to Judge Alexander from Margaret M. Lytke with Exhibits filed.
Date: 04/06/1998
Proceedings: CASE STATUS: Hearing Held.
Date: 03/23/1998
Proceedings: Order sent out. (hearing set for 4/6/98; 10:00am; Brooksville)
Date: 03/19/1998
Proceedings: Respondent, Hernando County`s Prehearing Statement filed.
Date: 03/17/1998
Proceedings: Hearing Partially Held, continued to date not certain.
Date: 03/17/1998
Proceedings: Respondent Southwest Florida Water Management District`s Motion in Limine (filed via facisimile) filed.
Date: 03/16/1998
Proceedings: Respondent Southwest Florida Water Management District`s Motion that Facts Be Taken as Established and for Other Relief (filed via facisimile) filed.
Date: 03/13/1998
Proceedings: (SWFWMD) Amended Notice of Taking Deposition Duces Tecum filed.
Date: 03/13/1998
Proceedings: Respondent Southwest Florida Water Management District`s Prehearing Statement (filed via facisimile) filed.
Date: 03/12/1998
Proceedings: (SWFMD) Notice of Taking Deposition Duces Tecum filed.
Date: 03/06/1998
Proceedings: Letter to A. Cole from J. Bates Re: Unable to appear on 3/11 or 3/17 for deposition filed.
Date: 03/02/1998
Proceedings: (SWFWMD) Notice of Taking Deposition Duces Tecum filed.
Date: 03/02/1998
Proceedings: (SWFWMD) Notice of Filing; Notice of Withdrawal filed.
Date: 02/13/1998
Proceedings: (11) Respondent Southwest Florida Water Management District`s Certificate of Serving Interrogatories to Petitioners; (11) Respondent Southwest Florida Water Management District`s First Set of Interrogatories to Petitioner filed.
Date: 02/13/1998
Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Mr. & Mrs. Robert L. Nelson; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Mr. & Mrs. Richard Ladow filed.
Date: 02/13/1998
Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Mr. & Mrs. Phillip E. Durst; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Donald R. Soshosm filed.
Date: 02/13/1998
Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Claudia C. Munsell; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner George Goff filed.
Date: 02/13/1998
Proceedings: Respondent Southwest Florida Management District`s Request for Admissions to Petitioner Joyce Menzie; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner James M. Gibson filed.
Date: 02/13/1998
Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Dick W. Thompson; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner James E. and Marilyn Bates filed.
Date: 02/13/1998
Proceedings: (From M. Lytle) (12) Notice of Taking Deposition Duces Tecum; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Richard L. Silvani filed.
Date: 01/14/1998
Proceedings: Notice of Hearing sent out. (hearing set for 3/17/98; 10:15am; Brooksville)
Date: 01/09/1998
Proceedings: Joint Response to Initial Order (filed via facsimile).
Date: 12/31/1997
Proceedings: Initial Order issued.
Date: 12/23/1997
Proceedings: Notice Of Referral; Agency Referral Letter; Petition for Administrative Hearing Florida Statutes-Section 120.569 (exhibits); Agency Action Letter filed.

Case Information

Judge:
D. R. ALEXANDER
Date Filed:
12/23/1997
Date Assignment:
12/31/1997
Last Docket Entry:
06/18/2004
Location:
Brooksville, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (2):

Related Florida Rule(s) (2):