97-005978
Richard L. Silvani, Dick W. Thompson, James E. And Marilyn Bates, Joyce Menzie, James M. Gibson, Claudia C. Munsell, Mr. And Mrs. Phillip E. Durst, Donald R. Sosnoshr, Mr. And Mrs. Robert L. Nelson, And Mrs. Richard Ladow vs.
Southwest Florida Water Management District And Hernando County
Status: Closed
Recommended Order on Monday, June 8, 1998.
Recommended Order on Monday, June 8, 1998.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8RICHARD L. SILVANI; DICK W. )
14THOMPSON; JAMES E. AND )
19MARILYN BATES; JOYCE MENZIE; )
24JAMES M. GIBSON; CLAUDIA C. )
30MUNSELL; MR. AND MRS. PHILLIP )
36E. DURST; DONALD R. SOSNOSHR; )
42MR. AND MRS. ROBERT L. )
48NELSON; and MRS. RICHARD )
53LADOW, )
55)
56Petitioners, )
58)
59vs. ) Case No. 97-5978
64)
65SOUTHWEST FLORIDA WATER )
69MANAGEMENT DISTRICT and )
73HERNANDO COUNTY, )
76)
77Respondents. )
79______________________________)
80RECOMMENDED ORDER
82Pursuant to notice, this matter was heard on March 17 and
93April 6, 1998, in Brooksville, Florida, by Donald R. Alexander,
103the assigned Administrative Law Judge of the Division of
112Administrative Hearings.
114APPEARANCES
115For Petitioners: Chester L. Bradshaw
120(Qualified Representative)
12218520 Bradshaw Road
125Dade City, Florida 33523
129For Petitioner: Richard L. Silvani, pro se
136( Silvani) 24419 Lanark Road
141Brooksville, Florida 34601
144For Respondent: Margaret M. Lytle, Esquire
150( SWFWMD) 2379 Broad Street
155Brooksville, Florida 34609-6899
158For Respondent: R. Bruce Snow, Esquire
164(County) William Buztrey, Esquire
16820 North Main Street, Room 462
174Brooksville, Florida 34601
177STATEMENT OF THE ISSUE
181The issue is whether Hernando County's application for an
190environmental resource permit authorizing the construction of a
198new surface water management system to serve a 7.85 acre drainage
209system improvement three miles southeast of Brooksville, Florida,
217should be approved.
220PRELIMINARY STATEMENT
222This case began on September 29, 1997, when Respondent,
231Southwest Florida Water Management District, gave notice that it
240intended to issue an environmental resource permit to Respondent,
249Hernando County, authorizing the construction of a new surface
258water management system three miles southeast of Brooksville,
266Florida. Petitioners, Richard L. Silvani, Dick W. Thompson,
274James E. and Marilyn Bates, Joyce Menzie, James M. Gibson,
284Claudia C. Munsell, Mr. and Mrs. Phillip E. Durst, Donald R.
295Sosnoshr, Mr. and Mrs. Robert L. Nelson, Mrs. Richard Ladow, and
306George Goff, all property owners in the area of the project,
317thereafter filed a Petition for Informal Hearing seeking to
326contest the proposed agency action. The petition generally
334contended that the permit application "contain[ ed] possible
342miscalculations of design," which would exacerbate existing flood
350problems in a number of respects. The petition further alleged
360that the County lacked easements for surface water storage. The
370petition was treated as a petition for a formal hearing and was
382referred by the agency to the Division of Administrative Hearings
392on December 23, 1997, with a request that an Administrative Law
403Judge be assigned to conduct a hearing. On February 26, 1998,
414George Goff filed a Notice of Withdrawal, in which he withdrew
425from participation in the case.
430By Notice of Hearing dated February 14, 1998, a final
440hearing was scheduled on March 17, 1998, in Brooksville, Florida.
450A continued hearing was held on April 6, 1998, at the same
462location.
463At final hearing, the agency's Motion in Limine and Motion
473That Facts be Taken as Established and For Other Relief were
484denied. All Petitioners except Richard L. Silvani were
492represented by Chester J. Bradshaw, a qualified representative,
500while Silvani represented himself. Petitioners presented the
507testimony of Chester J. Bradshaw, James M. Gibson, Dick W.
517Thompson, Marilyn Bates, Joyce Menzie, Jane Durst, Diane Nelson,
526Richard L. Silvani, and Julie Ann Defoe. Also, they offered
536Petitioners' Exhibit 1 and Silvani Exhibits 1 and 2. All
546exhibits were received in evidence. Hernando County presented
554the testimony of Charles D. Mixon, County Engineer and accepted
564as an expert in professional engineering; and Dale E. Cromwell,
574an engineering consultant and accepted as an expert in
583professional engineering. Also, it offered County Exhibits 1 and
5922. Both exhibits were received in evidence. The Southwest
601Florida Water Management District presented the testimony of
609C. Clay Black, a professional engineer and accepted as an expert
620in the design of surface water management systems and
629environmental resource permitting; and Julie Ann Defoe, an
637environmental scientist and accepted as an expert in wetlands and
647environmental resource permitting. Also, it offered District
654Exhibits 1-9. All exhibits were received in evidence.
662The transcript of hearing (three volumes) was filed on
671April 24, 1998. By agreement of the parties, the time for filing
683proposed findings of fact and conclusions of law was extended to
694May 26, 1998. The same were jointly filed by Respondents, and
705they have been considered in the preparation of this Recommended
715Order. On May 28, 1998, Petitioners filed a document styled as
"726Petitioners' Summary Request to Deny Permit," together with
734copies of numerous documents apparently obtained from
741Respondents' public records. The "Summary Request to Deny
749Permit" has been treated as a proposed order and has been
760considered in the preparation of this Recommended Order.
768FINDINGS OF FACT
771Based upon all of the evidence, the following findings of
781fact are determined:
784A. Background
7861. Petitioners, Richard J. Silvani, Dick W. Thompson,
794James E. and Marilyn Bates, Joyce Menzie, James M. Gibson,
804Claudia C. Munsell, Mr. and Mrs. Phillip E. Durst, Donald R.
815Sosnoski, Mr. and Mrs. Robert L. Nelson, and Mr. and Mrs.
826Richard Ladow (Petitioners), are property owners in central
834Hernando County, Florida. Respondent, Southwest Florida Water
841Managment District (District), is the state agency charged with
850the responsibility of issuing Environmental Resource Permits
857( ERP) within its jurisdictional boundaries. Respondent, Hernando
865County (County), is a local government seeking the issuance of a
876permit for the purpose of alleviating drainage and flooding
885problems in a subdivision known as High Point Gardens in the
896central part of the County.
9012. On June 11, 1997, the County filed an application with
912the District seeking authorization to construct a low earthen
921berm to help control flooding in High Point Gardens, an eighty-
932five unit residential subdivision. On September 29, 1997, the
941District gave notice of its intention to issue ERP No. 449342.01
952authorizing the "construction of a new surface water management
961system to serve a 7.85 acre drainage system improvement known as
972the Hernando County - High Point Gardens Drainage Improvements."
981The project is located off Sun Hill Lane, three miles southeast
992of Brooksville, Florida, in central Hernando County.
9993. On an undisclosed date, but in a timely fashion,
1009Petitioners filed their Petition for Informal Hearing challenging
1017the issuance of the permit. As grounds, Petitioners alleged that
1027the permit application contained "possible miscalculations of
1034design" which would "alter the natural water flow route";
"1043adversely affect several acres of natural wetlands by changing
1052hydrology of surface area"; "adversely affect adjacent uplands by
1061innundating forest areas never before flooded by heavy rainfall";
"1070not guarantee 100% flood protection to the few affected homes";
1080and "create flood problems to adjacent homes and property by
1090diverting stormwater from natural flow (north) to area east of
1100'proposed' retention area." The petition further alleged that
1108the "'proposed' area should not be normal recepient [sic] of
1118excess water from Cedar Falls subdivision" and that "all affected
1128properties are not owned or easements acquired by Hernando County
1138for surface water storage." The filing of the petition prompted
1148the initiation of this proceeding.
1153B. The Permit
11564. The High Point Gardens subdivision, which lies within
1165the Bystre Lake Basin, is a "relatively old subdivision," having
1175been built around the 1970's. There is a low area in the middle
1188of the subdivision, and it has "[s] everal sinks with a natural
1200drainage within the area." Because the thirty-square-mile basin
1208is a closed drainage basin, with no natural outflows,
"1217significant" flooding problems have been present throughout the
1225basin since at least the 1980's.
12315. In an effort to resolve flooding problems within the
1241basin, the County and District jointly sanctioned a study by a
1252consulting firm, Dames and Moore, to provide suggested
1260alternative actions to correct the problem. The firm's first
1269interim report was rendered on August 5, 1988, and a final report
1281known as the Bystre Lake Stormwater Management Master Plan was
1291rendered in August 1989.
12956. Among other things, the consultant's report recommended
1303that a berm be constructed to relieve the flooding in the High
1315Point Gardens' area. Acting on the report, the County obtained a
1326construction permit from the District in August 1991 in
1335accordance with the consultant's recommendation, but construction
1342on the project was not commenced prior to the permit expiring in
13541994. Although the consultant's report was the genesis for the
1364first permit, the plans and specifications for the new berm have
1375been modified by engineers after further study and review. It is
1386noted that the total land area of the project will be less than
1399100 acres.
14017. The High Point Gardens subdivision lies within sub-basin
1410304 of the basin. Under the new proposal, water which now comes
1422into sub-basins 304 and 406 from sub-basins 305 and 306 will be
1434stored in those latter sub-basins. The requested permit would
1443authorize the County to construct a low earthen berm along the
1454western side of sub-basin 406 and the southern boundary of sub-
1465basin 304 to help control flooding in the subdivision. The
1475proposed berm will range from one to five feet in height and
1487extend some 3,250 feet, or approximately six-tenths of a mile.
1498It will range from eight to ten feet in width with a side slope
1512of 4 to 1.
15168. The berm will impound water upstream of the berm to an
1528elevation of 90.5 NGVD, which is 1.5 feet higher than the water
1540would rise in the area under natural conditions. The water will
1551be stored in two natural ponds which are now located in the
1563project area. Once the water reaches an elevation of 90.5 NGVD,
1574which will occur only during an event exceeding a 25-year storm
1585event, three overflow structures will become operative and are
1594designed to mimic the natural water flows of the area.
16049. After the berm is constructed, all basins "downstream"
1613of the berm, including sub-basins 304, 405, and 406, will have
"1624significantly lower flood elevations than the 10, 25 and 100-
1634year storm event." That is to say, existing flooding to the
1645north and east of the proposed berm will be lessened. To the
1657extent that additional impoundment of water behind the berm will
1667occur, or flooding beyond the berm may occur during a 100-year
1678storm event, the County will acquire easements from local
1687property owners to store the additional water. Until the
1696aquisition of land occurs, construction cannot begin.
170310. There is one already disturbed wetland area near the
1713proposed construction area. No mitigation is required, however,
1721since the impact will be temporary and the area is expected to
1733naturally revegetate itself. There will be no adverse impacts to
1743fish, wildlife, or adjacent wetlands. Neither will the project
1752create any other environmental concerns. While there will be
1761some impact to upland trees caused by the impounded water, under
1772existing District rules, that impact cannot be used as a basis to
1784deny the permit.
178711. Based on generally accepted engineering principles, the
1795project is capable of being effectively performed and can
1804function as proposed. Also, the project can be effectively
1813operated and maintained. The County has the resources to
1822undertake the project in accordance with the terms and conditions
1832of the permit.
183512. The greater weight of credible and persuasive evidence
1844supports a finding that the County has given reasonable
1853assurances that all applicable criteria for the issuance of a
1863permit have been met.
1867C. Petitioners' Objections
187013. At hearing, Petitioners contended that the overflow
1878structures for the berm would alter the natural flow of water,
1889and increase the flow of water to the east of the proposed
1901project, where several Petitioners reside. As previously noted,
1909however, the more credible evidence shows that the project will
1919not increase the natural flow of water to the east of the berm.
1932More specifically, expert testimony demonstrated that the regular
1940flow through each weir in the post-development condition will not
1950be adversely greater than what occurred during the pre-
1959development condition.
196114. Petitioners also contended that the wetlands will be
1970negatively impacted by the project. Contrary expert testimony by
1979witness Defoe established, however, that there will be no
1988permanent adverse impacts to wetlands, fish, or wildlife if the
1998permit is approved.
200115. Petitioners next contended that the process was flawed
2010because very few on-site inspections of the project area were
2020made by District and County personnel, especially during the
2029rainy season, before the application was preliminarily approved.
2037There were, however, on-site inspections by District and County
2046staff and consultants, and it was not shown that the lack of
2058additional inspections affected the validity of their studies.
206616. A further contention was made at hearing that the
2076information supporting the application was insufficient and that
2084more study, including soil boring tests, should have been made.
2094As to additional soil boring tests, the evidence shows that it is
2106not a common engineering practice to perform soil testing
2115throughout the entire area that will be submerged. Therefore,
2124the existing tests were adequate to support the engineering
2133assumptions. Further, even if there were some infirmities in the
2143data and assumptions used and made in the 1989 Dames and Moore
2155report, as alleged by Petitioners, the errors or omissions were
2165minor, they were subject to later refinement by professional
2174engineers, and they did not materially affect the overall
2183validity of the current application. Finally, the application
2191file contains uncontradicted technical information supporting the
2198issuance of the permit.
220217. Petitioners' other concerns, while sincere and well-
2210intended, are not relevant to the permitting process. For
2219example, a concern that the construction of a berm will decrease
2230nearby property values, even if true, is not a consideration in
2241the permitting process. Similarly, Petitioners' valid concern
2248that some nearby upland trees will be damaged if water levels
2259rise for a prolonged period of time is not a basis under existing
2272District rules to deny the permit. At the same time, whether the
2284project is cost-effective and the best alternative for
2292alleviating flooding conditions in the area are political
2300decisions for the County, and thus they are not in issue in this
2313proceeding.
231418. Finally, Petitioners have pointed out that the County
2323has not completed acquisition of the necessary easements for the
2333project, and that until this is done, a permit should not issue.
2345However, the District has specifically provided as a condition
2354precedent to any construction work that the County finalize
2363ownership or control for all property where water levels will be
2374raised by the project.
2378CONCLUSIONS OF LAW
238119. The Division of Administrative Hearings has
2388jurisdiction over the subject matter and the parties hereto
2397pursuant to Sections 120.569 and 120.57(1), Florida Statutes.
240520. As the party seeking a permit, the County bears the
2416burden of proving by a preponderance of the evidence that the
2427application should be granted. Dep't of Transportation v. J.W.C.
2436Co., Inc. , 396 So. 2d 778, 789 (Fla. 1st DCA 1981).
244721. In order to show entitlement to a permit, the County
2458must give reasonable assurances that the permitting criteria in
2467Rules 40D-4.301, 40D-4.302, and 40D-40.302, Florida
2473Administrative Code, have been satisfied. By a preponderance of
2482the evidence, this burden has been met.
248922. The existence of possible alternative projects, the
2497project's cost effectiveness, the possible adverse impacts to
2505upland tree species, and the potential for a decrease in the
2516value of adjacent property, while well-intended concerns on the
2525part of Petitioners, are not criteria which may be considered by
2536the District in the permitting process. See , e . g ., Council of
2549the Lower Keys v. Toppino , 429 So. 2d 67 (Fla. 3d DCA 1983).
2562This being so, the application should be granted.
2570RECOMMENDATION
2571Based on the foregoing findings of fact and conclusions of
2581law, it is
2584RECOMMENDED that the Southwest Florida Water Management
2591District enter a final order granting Hernando County's
2599application for Standard General Environmental Resource Permit
2606No. 449342.01.
2608DONE AND ENTERED this 8th day of June, 1998, in Tallahassee,
2619Leon County, Florida.
2622___________________________________
2623DONALD R . ALEXANDER
2627Administrative Law Judge
2630Division of Administrative Hearings
2634The DeSoto Building
26371230 Apalachee Parkway
2640Tallahassee, Florida 32399-3060
2643(850) 488-9675, SUNCOM 278-9675
2647Fax Filing (850) 921-6847
2651Filed with the Clerk of the
2657Division of Administrative Hearings
2661this 8th day of June, 1998.
2667COPIES FURNISHED:
2669E. D. "Sonny" Vergara, Executive Director
2675Southwest Florida Water Management District
26802379 Broad Street
2683Brooksville, Florida 34609-6899
2686Chester Bradshaw
268818520 Bradshaw Road
2691Dade City, Florida 33523
2695Richard L. Silvani
269824419 Lanark Road
2701Brooksville, Florida 34601
2704Margaret M. Lytle, Esquire
27082379 Broad Street
2711Brooksville, Florida 34609-6899
2714Robert Bruce Snow, Esquire
271820 North Main Street, Room 462
2724Brooksville, Florida 34601
2727NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
2733All parties have the right to submit written exceptions to this
2744Recommended Order within fifteen days. Any exceptions to this
2753Recommended Order should be filed with the Southwest Florida Water
2763Management District.
- Date
- Proceedings
- Date: 06/10/1998
- Proceedings: Letter to M. Lytle from C. Bradshaw Re: Proposed High Point Gardens Subdivision Berm Hernando County filed.
- Date: 05/28/1998
- Proceedings: Petitioner`s Summary Request to Deny Permit Proposed High Point Gardens Berm ; Exhibits ; Permit Application for Bystre Lake Watershed Drainage Improvements filed.
- Date: 05/26/1998
- Proceedings: Respondents` Joint Argument; Respondents` Joint Proposed Recommended Order (For Judge Signature) filed.
- Date: 04/24/1998
- Proceedings: Transcript (3-volumes with cover letter, TAGGED)filed.
- Date: 04/23/1998
- Proceedings: Letter to DRA from Nancy Dewitz (RE: notice of filing transcripts/no enclosures) (filed via facisimile) filed.
- Date: 04/10/1998
- Proceedings: Letter to Judge Alexander from Margaret M. Lytke with Exhibits filed.
- Date: 04/06/1998
- Proceedings: CASE STATUS: Hearing Held.
- Date: 03/23/1998
- Proceedings: Order sent out. (hearing set for 4/6/98; 10:00am; Brooksville)
- Date: 03/19/1998
- Proceedings: Respondent, Hernando County`s Prehearing Statement filed.
- Date: 03/17/1998
- Proceedings: Hearing Partially Held, continued to date not certain.
- Date: 03/17/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Motion in Limine (filed via facisimile) filed.
- Date: 03/16/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Motion that Facts Be Taken as Established and for Other Relief (filed via facisimile) filed.
- Date: 03/13/1998
- Proceedings: (SWFWMD) Amended Notice of Taking Deposition Duces Tecum filed.
- Date: 03/13/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Prehearing Statement (filed via facisimile) filed.
- Date: 03/12/1998
- Proceedings: (SWFMD) Notice of Taking Deposition Duces Tecum filed.
- Date: 03/06/1998
- Proceedings: Letter to A. Cole from J. Bates Re: Unable to appear on 3/11 or 3/17 for deposition filed.
- Date: 03/02/1998
- Proceedings: (SWFWMD) Notice of Taking Deposition Duces Tecum filed.
- Date: 03/02/1998
- Proceedings: (SWFWMD) Notice of Filing; Notice of Withdrawal filed.
- Date: 02/13/1998
- Proceedings: (11) Respondent Southwest Florida Water Management District`s Certificate of Serving Interrogatories to Petitioners; (11) Respondent Southwest Florida Water Management District`s First Set of Interrogatories to Petitioner filed.
- Date: 02/13/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Mr. & Mrs. Robert L. Nelson; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Mr. & Mrs. Richard Ladow filed.
- Date: 02/13/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Mr. & Mrs. Phillip E. Durst; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Donald R. Soshosm filed.
- Date: 02/13/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Claudia C. Munsell; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner George Goff filed.
- Date: 02/13/1998
- Proceedings: Respondent Southwest Florida Management District`s Request for Admissions to Petitioner Joyce Menzie; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner James M. Gibson filed.
- Date: 02/13/1998
- Proceedings: Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Dick W. Thompson; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner James E. and Marilyn Bates filed.
- Date: 02/13/1998
- Proceedings: (From M. Lytle) (12) Notice of Taking Deposition Duces Tecum; Respondent Southwest Florida Water Management District`s Request for Admissions to Petitioner Richard L. Silvani filed.
- Date: 01/14/1998
- Proceedings: Notice of Hearing sent out. (hearing set for 3/17/98; 10:15am; Brooksville)
- Date: 01/09/1998
- Proceedings: Joint Response to Initial Order (filed via facsimile).
- Date: 12/31/1997
- Proceedings: Initial Order issued.
- Date: 12/23/1997
- Proceedings: Notice Of Referral; Agency Referral Letter; Petition for Administrative Hearing Florida Statutes-Section 120.569 (exhibits); Agency Action Letter filed.