98-003640
Panhandle Industries, Inc., (Dagam Oil Company) vs.
Department Of Environmental Protection
Status: Closed
Recommended Order on Monday, February 22, 1999.
Recommended Order on Monday, February 22, 1999.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8PANHANDLE INDUSTRIES, INC., )
12)
13Petitioner, )
15)
16vs. ) Case No. 98-3640
21)
22DEPARTMENT OF ENVIRONMENTAL )
26PROTECTION, )
28)
29Respondent. )
31__________________________________)
32RECOMMENDED ORDER
34Pursuant to notice, the Division of Administrative Hearings,
42by its duly designated Administrative Law Judge, William J.
51Kendrick, held a formal hearing in the above-styled case on
61December 8, 1998, in Tallahassee, Florida.
67APPEARANCES
68For Petitioner: George M. Hidle, President
74Panhandle Industries, Inc.
77Post Office Box 11983
81Fort Lauderdale, Florida 33339-1983
85For Respondent: J. A. Spejenkowski, Esquire
91Department of Environmental Protection
953900 Commonwealth Boulevard
98Mail Station 35
101Tallahassee, Florida 32399-3000
104STATEMENT OF THE ISSUES
108At issue in this proceeding is the reasonable cost to be
119reimbursed Petitioner, under the provisions of Section
126376.3071(12), Florida Statutes, for the development of a
134Monitoring Only Plan (MOP) program for the Dagam Oil Company
144(DEP Facility No. 138504146), at 331 23rd Street, Miami Beach,
154Florida.
155PRELIMINARY STATEMENT
157In August 1994, Petitioner, Panhandle Industries, Inc.,
164submitted an application to the Respondent, Department of
172Environmental Protection (Department), which sought reimbursement
178for costs associated with the development of a Monitoring Only
188Plan (MOP) under the provisions of Section 376.3071, Florida
197Statutes.
198Following review, the Department ultimately issued an Order
206of Determination of Reimbursement on June 27, 1996, which
215approved for reimbursement $13,198.70 of the total of $39,412.66
226requested by Petitioner. 1
230Respondent elected to dispute the Department's decision and
238filed a petition for formal hearing pursuant to Sections 120.569
248and 120.57, Florida Statutes. On August 12, 1998, the Department
258referred the matter to the Division of Administrative Hearings
267for the assignment of an administrative law judge to conduct the
278formal hearing Petitioner had requested.
283At hearing, Petitioner called George Hidle as a witness, and
293Petitioner's Exhibits 1 through 15 and 23 through 25 were
303received into evidence. 2 The Department called as witnesses
312Diane Pickette, Brian King, Charles Williams, and Jeffrey
320Priddle, and the Department's (Respondent's) Exhibits 1 through 5
329and 7 were received into evidence. 3
336The hearing transcript was filed on December 28, 1998, and
346the parties were accorded 10 days from that date to file proposed
358recommended orders or proposed findings of fact. The parties
367elected to submit such proposals and they have been duly
377considered.
378FINDINGS OF FACT
381Background
3821. Petitioner, Panhandle Industries, Inc., is a Florida
390corporation engaged in the business of consulting, engineering
398and construction. George M. Hidle, a professional geologist
406licensed in the State of Florida, is the president and sole owner
418of the Petitioner corporation.
4222. In September 1992, Dagam Oil Company, doing business as
432Sierra Fina, employed Petitioner to do environmental assessment
440work and prepare a Contamination Assessment Report (CAR) under
449the then existing Rule 17-770.630, Florida Administrative Code,
457for a site located at 331 23rd Street, Miami Beach, Florida (DEP
469Facility No. 138504146). 4 That CAR was submitted to DERM
479(Metropolitan Dade County, Department of Environmental Resources
486Management) July 13, 1993. (Petitioner's Exhibit 1.)
4933. Pertinent to this case, the CAR provides the following
503background or historical information:
507. . . PHYSICAL SETTING
512. . . Sierra Fina is located at 331
52123rd Street in Miami Beach, Florida . . .
530The facility is bordered to the north by
538Collins Canal, to the east by the light
546commercial properties, and to the
551south/southeast by property that once
556contained Chevron and Fina service
561stations. . . .
565* * *
568. . . FACILITY HISTORY AND OPERATION
575Sierra Fina was built in 1963. The station
583originally operated as a Sunoco service
589station with a 3 bay garage. Dagam Oil
597Company purchased the facility in March 1981
604from Charles Rosenblatt. At the time the
611station had five underground fuel
616tanks. . . .
620* * *
623. . . PREVIOUS INVESTIGATIONS
628Dagam Oil Company contracted with another
634environmental company in November 1988 to
640collect groundwater samples from . . . five
648monitoring wells at the facility.
653Groundwater samples were collected on
658November 9, 1988 and analyzed by EPA Method
666602. Monitoring well MW-3 was also analyzed
673by EPA Method 610. All five of the wells had
683hydrocarbon contaminant concentrations in
687excess of state guidelines. . . .
694A discharge notification form was mailed to
701the DER and DERM on December 9, 1988, the
710date of receipt of the analytical results
717from the November 9, 1988 groundwater
723sampling event. . . .
728* * *
731. . . INITIAL REMEDIAL ACTIONS [IRA]
738[The F]ive underground storage tanks [and
744associated piping] were removed from the
750facility during March and April 1989 [, and
758replaced with four new cathodically protected
764underground petroleum storage tanks].
768Approximately 400 cubic yards of contaminated
774soil was also removed at that time. On
782March 31, 1989 a composite sample of the soil
791was collected for analysis . . . Because of
800limited space at the station, the
806contaminated soil was hauled to a Metro
813Trucking Inc. storage yard located at
819112th Avenue and 143 Street in Miami. The
827contaminated soil was landfarmed at this
833Metro Trucking facility for a period of seven
841months, during which time the soil was spread
849onto visqueen and tilled on a regular basis.
857On November 21, 1989 the soil was resampled
865and analyzed . . . Results of this second
874round of analyses met clean fill criteria.
881Also at the time of tank replacement, a
889sheen of free floating hydrocarbons was
895observed on water in the tank pit. A vac
904truck was used to skim this product from the
913pit prior to tank replacement. Approximately
9192100 gallons of oily water were removed,
926transported, and disposed of by Cliff Berry,
933Inc. . . .
937Other than these IRA activities, no other assessment or
946remediation work had been performed at the facility until
955Petitioner was employed in September 1992.
9614. Petitioner's CAR concluded that:
966Soil and groundwater at Sierra Fina are
973contaminated with gasoline and diesel
978hydrocarbons. Excessively contaminated soil
982is confined to an area at the western end of
992the station building that is approximately
99820 feet in width by 30 feet in length,
1007extending down to a water table of between
10156 and 8 feet below land s urface. No free
1025phase floating product is present on the
1032groundwater underlying this facility.
1036However, dissolved hydrocarbon contamination
1040is present in the groundwater. A dissolved
1047hydrocarbon plume is present in the western
1054half of the site. This plume measures
106180 feet in length by 60 feet in width and
1071extends to a depth of less than 22 feet below
1081land surface, yielding approximately 134,640
1087gallons of hydrocarbon contaminated water.
1092Volume calculations are based on an average
1099depth to groundwater of 7 feet below land
1107surface and an effective soil porosity of
111425%. The highest benzene (53.3 ppb) and
1121total napthalenes (752 ppb) concentrations
1126were detected in MW-12.
1130* * *
1133Groundwater within the Biscayne Aquifer
1138beneath Sierra Fina is nonpotable because of
1145salt water intrusion from the Atlantic Ocean.
1152For this reason there are no private or
1160public potable wells in the area.
1166Contamination at Sierra Fina is limited
1172onsite to the western half of the station,
1180and poses no threats to sensitive receptors
1187in the area, with the possible exception of
1195Collins Canal. The cause of hydrocarbon
1201contamination was never determined; however,
1206the most probable source, i.e. previous
1212petroleum tanks and lines, were removed in
1219March and April of 1989. Based on these
1227findings and the data presented about or
1234elsewhere in this report, it is known that
1242soil and groundwater contamination does exist
1248at this facility in concentrations that
1254exceed guidelines specified in Section 17-
1260770.730(5)FAC; however, the levels of
1265contamination may not warrant the need for
1272any extensive remediation activities at this
1278site.
12795. Petitioner's CAR was approved by DERM on October 8,
12891993, and Petitioner was directed to submit a Remedial Action
1299Plan (RAP) within 60 days. 5
13056. At the time, Mr. Hidle (Petitioner) was aware that the
1316levels of contamination were low or near target levels, and that
1327it was likely that the contamination levels would decrease
1336naturally over time. Consequently, Petitioner elected to seek
1344approval of a Monitor Only Plan (MOP), as opposed to a RAP. Such
1357choice was favored based on the nature and location of the
1368contaminants. In this regard, it was observed that the soil
1378contamination consisted of both gasoline and diesel fuel, with
1387much of the contaminated soil abutting or underneath the
1396building. Excavation and removal of the soil was not an
1406alternative because it would undermine the structural integrity
1414of the building. Moreover, given the fuel mix, vapor extraction
1424was not a viable option.
14297. Given Petitioner's choice to pursue approval of a MOP,
1439it gave notice to the Department and DERM on October 18, 1993, as
1452well as November 12, 1993, and December 2, 1993, of its intention
1464to undertake groundwater sampling and soil sampling on the site.
14748. Groundwater sampling was undertaken by Mr. Hidle between
14831:30 p.m., November 30, 1993, and 2:30 a.m., December 1, 1993, 6
1495at which time he drew water samples for laboratory analysis from
150610 monitor wells (MW) and one deep well (DW). A duplicate sample
1518was also retrieved at MWs 12R and 14, and equipment blanks were
1530also obtained for laboratory analysis.
15359. Between 8:25 p.m., December 4, 1993, and 3:40 a.m.
1545December 5, 1993, 7 Mr. Hidle and a senior technician (Martin
1556Hidle) augured 6 soil borings for use in preparing the MOP and
1568collected one soil sample for laboratory analysis.
157510. Petitioner delivered the water samples to the
1583laboratory (Envirodyne, Inc.) on December 2, 1993, and the soil
1593sample on December 6, 1993, for analysis. The laboratory
1602completed its analysis of the water samples on December 13, 1993,
1613and of the soil sample on December 14, 1993, and rendered its
1625written reports (analysis) to Petitioner. 8
163111. Upon receipt of the laboratory data, Mr. Hidle
1640completed his preparation of the MOP. (Petitioner's Exhibit 4.)
1649That MOP contained the following conclusions and recommendations:
1657The initial dissolved hydrocarbon plume
1662dimensions were based on data from
1668groundwater sampling events of January and
1674February 1993. Laboratory results from a
1680more recent sampling event (11/30/93)
1685indicate that plume size and hydrocarbon
1691compound concentrations therein have
1695decreased substantially (Table 4-2). Maximum
1700groundwater contaminant concentrations
1703decreased as follows: benzene from 53.3 ppb
1710to 11.1 ppb; BTEX from 111.7 ppb to 20.6 ppb;
1720total naphthalenes from 752 ppb to 246.1 ppb.
1728During the contamination assessment program
1733task a small area of contaminated soil was
1741found to be abutting the western end of the
1750station building (CAR, Fig. 3-1, p. 35).
1757Because of the presence of diesel compounds
1764in the groundwater, it was assumed during
1771preparation of the CAR that the soil too was
1780contaminated with diesel.
1783In early December 1993 PI Environmental
1789personnel installed six additional soil
1794borings (Figure 3-1, SB-16 through SB-21) and
1801collected one soil sample for laboratory
1807analyses. The soil borings were augered in
1814the immediate area of the previously defined
1821contaminated soil plume, and soil samples
1827were analyzed in the field by using a Foxboro
1836OVA 128. Soil samples were collected
1842vertically every two feet, beginning at one
1849foot below ground surface and continuing
1855until the water table was encountered.
1861A soil sample was collected from boring
1868SB-17 at a depth of six feet below land
1877surface. A net OVA reading of 160 ppm was
1886observed from a duplicate sample taken from
1893the same depth. The soil sample was tested
1901by EPA Methods 3540/8100 (diesel compounds)
1907and 9073 (TRPH). Laboratory results
1912indicated that all diesel compounds were
1918below laboratory detection limits, and the
1924TRPH concentration was below normal
1929background readings.
1931Soil contamination was reclassified as
1936being gasoline in origin, because no diesel
1943compounds were detected in the soil sample
1950from SB-17. Section 17-770.200(2) Florida
1955Administrative Code defines excessively
1959contaminated soil, associated with gasoline
1964contamination, as those that have a net
1971OVA/FID reading equal to or greater than
1978500 ppm.
1980From December 1993 sampling event, a
1986maximum net OVA/FID reading of 316 ppm was
1994obtained from a sample that was collected at
2002five fee below land surface in SB-17. Based
2010on these results, no excessively contaminated
2016soil was found during the most recent
2023sampling event.
2025It is the recommendation of PI
2031Environmental Inc. that a Monitoring Only
2037Plan be implemented at Sierra Fina. This
2044recommendation is based on the following
2050findings: 1) Absence in the study area of any
2059potable water wells within the Biscayne
2065Aquifer because of salt water intrusion from
2072the Atlantic Ocean 2) Absence of free phase
2080hydrocarbons 3) Absence of excessively
2085contaminated soil 4) Substantial decrease in
2091concentrations of dissolved hydrocarbon
2095compounds within the groundwater during the
2101last year, and 5) relatively low levels of
2109hydrocarbon contamination in the groundwater,
2114i.e., based on the November 30, 1993 sampling
2122event, maximum benzene of 11.1 ppb, maximum
2129BTEX of 20.6 ppb, and maximum total
2136naphthalenes of 246.1 ppb.
2140It is our recommendation that groundwater
2146from monitoring wells MW-8, MW-12R, MW-6, and
2153MW-17 be sampled on a quarterly basis.
2160Groundwater from the source area wells, MW-8
2167and MW-12R, should be analyzed quarterly by
2174EPA Methods 602 and 610. Groundwater from
2181the perimeter wells, MW-6 and MW-17, should
2188be analyzed quarterly by EPB Method 602 and
2196semiannually by EPA Methods 602 and 610.
2203Petitioner submitted the MOP to DERM on January 24, 1994.
221312. Pertinent to this case, it is observed that the MOP was
2225a brief document, consisting of only 13 pages of textual
2235material, much of which was a restatement of material contained
2245in the CAR. The balance of the report consisted of 5 "Figures"
2257(three of which were contained in the CAR and one of which is an
2271updated version of a CAR Figure); 2 "Tables" (an update of the
2283Water Table Elevation table contained in the CAR to include the
2294November 30, 1993, data, and an update of the Summary of
2305Groundwater Analyses contained in the CAR to include the
2314November 30, 1993, and December 1, 1993, data); 6 "Geologic
2324Log[s]" (a restating of the soil boring results noted in the
2335field notes for December 4 and 5, 1993); copies of the laboratory
2347(Envirodyne, Inc.'s) reports of groundwater analysis; and the
2355laboratory's report on the soil analysis. In all, while
2364apparently adequate and nicely presented, the MOP does not
2373address a complex or unique issue, and does not evidence the
2384expenditure, or need to expend, an inordinate amount of effort to
2395produce.
239613. Petitioner's MOP was disapproved by DERM on May 11,
24061994, for the following reasons:
24111. A complete round of groundwater
2417analyses, no greater than six months old, is
2425required. Therefore, all wells at this site
2432must be sampled for EPA Method 418.1, and
2440monitoring wells numbered MW-6, MW-9, MW-10,
2446MW-11, MW-13, MW-16, and MW-17 must be
2453sampled for EPA Method 610.
24582. Because diesel contamination is present
2464at this site, soil OVA readings above 50 ppm
2473are considered to indicate excessively
2478contaminated soil. Based on this OVA
2484readings obtained for your Contamination
2489Assessment Report (CAR) and this MOP,
2495excessively contaminated soil does exist at
2501this site. Since this coil could be a
2509continuing source of contamination, it must
2515be removed prior to the approval of a MOP.
2524Consequently, Petitioner was directed to submit an addendum to
2533the MOP to address those issues.
253914. On June 1, 1994, Petitioner gave notice to the
2549Department and DERM of its intent to collect groundwater samples
2559to address issues raised by DERM's MOP review letter. These
2569samples were collected by Mr. Hidle and a technician (Leo
2579Iannone) between 1:15 p.m. and 10 :00 p.m., June 15, 1994. 9
259115. Petitioner delivered the water samples to the
2599laboratory (Envirodyne, Inc.) on June 16, 1994. The laboratory
2608completed its analysis and delivered its written reports to
2617Petitioner on or about June 23, 1994.
262416. Upon receipt of the laboratory data, Mr. Hidle
2633completed the Monitoring Only Plan Addendum (Petitioner's Exhibit
26418), and submitted it to DERM on July 5, 1994. The addendum
2653addressed the additional groundwater analysis that was performed,
2661and with regard to the diesel contamination it observed, as
2671follows:
2672Soil analytical results (MOP, Page 62) are
2679below laboratory detection limits for EPA 610
2686compounds; however, because groundwater at
2691this facility is contaminated with both
2697gasoline and diesel, we are concurring with
2704DERM by reclassifying excessively
2708contaminated soil as any soil that exhibits
2715net OVA/FID readings of 50 ppm or greater,
2723per Chapter 17-770 FAC.
2727OVA/FID soil analyses were performed in
2733accordance to Panhandle Industries, Inc.
2738approved Comp QAP. Net OVA/FID soil results
2745obtained during the CAR program task are
2752shown in Figure 1-5. A maximum net OVA/FID
2760reading of 887 ppm was obtained during CAR
2768soil assessment activities which ended on
2774November 29, 1992. Figure 1-6 shows net
2781OVA/FID results obtained during the MOP
2787program task. These MOP analyses are current
2794through December 5, 1993. A maximum net
2801OVA/FID of 316 ppm was obtained during this
2809latter event. As is shown in comparison of
2817Figures 1-5 and 1-6, it can be seen that the
2827size of the soil contaminant plume and
2834OVA/FID net soil readings therein have
2840decreased significantly since initiation of
2845the CAR. Also, by observing Figure 1-6,
2852which has a scale of 1" = 20', it is evident
2863that very little soil, if any can be
2871excavated without jeopardizing the structural
2876integrity of the station building.
2881Furthermore, there exist the possibility that
2887some soil contamination may underlie the
2893building itself; therefore, soil excavation
2898would most likely result in only partial
2905removal of the contaminated soil plume.
2911The addendum concluded by recommending that the MOP be
2920implemented as originally proposed, but with additional
2927monitoring to assure a continuing decline in contamination.
293517. The addendum, like the MOP, was a brief document and
2946contains only 6 pages of textual material. The balance of the
2957addendum contains 6 "Figures" (all of which appeared in the CAR
2968or MOP); 2 "Tables" (an update of the Water Table Elevations
2979table contained in the MOP to include June 15, 1994, data, and an
2992update of the Summary of Groundwater Analyses contained in the
3002MOP to include the June 15, 1994, data); and the laboratory
3013reports of groundwater analyses. As with the MOP, the addendum
3023did not appear to address any complex or unique issues, and did
3035not evidence the expenditure, or need to expend, an inordinate
3045amount of time to produce.
305018. On August 16, 1994, and August 26, 1994, DERM and the
3062Department, respectively, approved the "monitoring only"
3068proposal.
3069The request for reimbursement
307319. Petitioner submitted its reimbursement application on
3080or about August 23, 1994, and it was apparently complete on or
3092about April 18, 1996. (Petitioner's Exhibit 11). That
3100application sought recovery of the following sums for the items
3110noted:
31116. REMEDIAL ACTION PLAN [MOP and MOP
3118Addendum] PREPARATION . . .
3123a. Personnel 31442.55
3126b. Capital Expense Items ______________
3131c. Rentals 1127.45
3134d. Mileage 68.05
3137e. Shipping 35.00
3140f. Well Drilling ______________
3144g. Permits ______________
3147h. Analysis 3680.00
3150i. Miscellaneous 1601.25
3153REMEDIAL ACTION PLAN
3156PREPARATION TOTAL 37954.30
3159* * *
316213. REIMBURSEMENT APPLICATION PREPARATION
3166Supplementary Forms
3168a. Personnel 795.00
3171b. Capital Expense Items _____________
3176c. Rentals 15.00
3179d. Mileage .80
3182e. Shipping 86.81
3185f. Well Drilling _____________
3189g. Permits _____________
3192h. Analysis _____________
3195i. Miscellaneous 60.75
3198APPLICATION PREPARATION TOTAL 958.36
3202CERTIFIED PUBLIC ACCOUNTANT
3205REVIEW FEE 500.00
3208APPLICATION GRAND TOTAL 39412.66
321219. By letter (Order of Determination of Reimbursement) of
3221June 27, 1996, the Department responded to Petitioner's
3229reimbursement request as follows:
3233We have completed review of your
3239Reimbursement Application for expenses
3243incurred during the Remedial Action
3248Plan/Monitoring Only Plan program task at
3254this site and have determined that $13,198.70
3262of the total $39,412.66 requested is
3269allowable for reimbursement. This amount
3274will be paid to the person responsible for
3282conducting site rehabilitation when
3286processing is completed by the Comptroller's
3292Office.
3293Some adjustments to the amount of
3299reimbursement requested have been made. The
3305following list details these adjustments.
3310Citations refer to the specific sections of
3317the enclosed Reimbursement Application
3321Summary Sheets:
33231. $24,766.25 in Section 6A, $259.95 in
3331Section 6C, $28.20 in Section 6D and
3338$63.25 in Section 6I were deducted
3344because the total personnel hours (413.15
3350hours) and the total cost of $39,412.66
3358claimed for performing a limited scope of
3365work consisting of 78.34 hours of field
3372activities, two rounds of analyses (59
3378samples) and two letter reports have been
3385determined to be excessive. However,
3390actual field activities (including a
3395reasonable amount of preparation), two
3400rounds of analyses and a reasonable
3406amount of personnel time to prepare two
3413letter reports have been allowed.
34182. $162.50 in Section 6A, $9.00 in
3425Section 6E and $331.15 in Section 6I were
3433deducted for costs associated with
3438providing backup for the Contamination
3443Assessment reimbursement application.
3446These costs are not reimbursable in this
3453application which is for the Remedial
3459Action Plan/Monitoring Only Plan program
3464task.
34653. $184.80 in Section 6A and $394.56 in
3473Section 6I were deducted for field
3479supplies, ice, conducting database
3483modifications and purchasing office
3487supplies, which are considered to be
3493overhead. These costs are not justified
3499in addition to the loaded personnel rates
3506which already include overhead and
3511profit.
35124. $11.76 in Section 6I was deducted because
3520the rate for reproduction ($0.99 per
3526page) has been determined to be
3532excessive. However, $0.15 (per page) has
3538been allowed based on the predominant
3544rate claimed in other reimbursement
3549applications for similar rates.
35535. $19.56 in Section 13E was deducted for
3561costs added to the application
3566preparation claimed as a markup.
3571Reimbursement for application preparation
3575is limited to actual costs only.
35816. $17.02 was added to the application grand
3589total to cover the cost of reproducing
3596the reimbursement application and
3600invoices and shipping the replacements to
3606the Department.
3608(Petitioner's Exhibit 12.)
361120. Petitioner filed a timely challenge to contest the
3620Department's decision. That challenge disputed the Department's
3627action, as set forth in paragraphs numbered 1 through 4 of the
3639letter, but Petitioner did not then, or at hearing, dispute the
3650Department's action with regard to the matters contained in
3659paragraphs numbered 5 and 6 of the Department's letter.
3668(Petitioner's Exhibit 13). Subsequently, at hearing, Petitioner
3675withdrew its request for reimbursement regarding the items
3683contained in paragraph 3 of the Department's letter.
3691(Transcript, page 101).
3694The claim for the cost of preparing the
3702reimbursement application
370421. Petitioner's claim for the cost of preparation of the
3714reimbursement application totalled $1,458.36 (including the
3721certified public accountant review fee). The Department proposed
3729to deduct $19.56 (in Section 13E), and to add $17.02 to cover
3741certain costs, as noted in the Department's letter.
3749(Petitioner's Exhibits 12 and 13). Petitioner offered no
3757objection to the Department's decision and, therefore, Petitioner
3765should be awarded $1,455.82, without the need for further
3775discussion, as the cost of preparing the reimbursement
3783application.
3784The claim for the cost of preparation of
3792the MOP and MOP Addendum
379722. Petitioner's application for reimbursement claimed
3803413.15 personnel hours ($31,442.55) were dedicated to the
3812development of the MOP (329.42 hours/$25,500.95) and the MOP
3822Addendum (83.73 hours/$5,941.60). (Respondent's Exhibit 7, and
3830Transcript, pages 188-190).
383323. In its initial review, the Department approved
384155.67 hours ($3,790.45) for the MOP and 41.92 hours ($2,538.55)
3853for the MOP Addendum, for a total award of $6,329.00.
3864Subsequently, the Department resolved to accept as reasonable,
387289 hours ($6,308.00) for the MOP and 83.73 hours ($5,941.60) for
3885the MOP Addendum, for a total award of $12,249.60 for personnel
3897costs. 10
389924. The 83.73 hours ($5,941.60) agreed to by the Department
3910for the MOP Addendum was the precise amount Petitioner requested
3920in its reimbursement application; however, the 89 hours
3928($6,308.00) accepted by the Department for the MOP is clearly
3939less than the 329.42 hours ($25,500.95) Petitioner had requested.
3949With regard to the difference, the Department views the request
3959as excessive. In contrast, Petitioner contends the time
3967requested was reasonable. Here, the Department's view has merit.
397625. To support the reasonableness of the hours (labor)
3985claimed, Petitioner pointed to the "Daily Time Log[s]" which were
3995contained within the reimbursement application, and which it
4003contended contain an accurate recording of the hours worked and
4013the task performed. (Petitioner's Exhibits 11, and Transcript,
4021pages 29 through 31). According to Mr. Hidle, all employees of
4032the company were required to keep a notepad on which they were to
4045record the job (customer), hours worked, and task performed. At
4055some future date, perhaps up to a week or more, those entries
4067were ostensibly transferred to the "Daily Time Log."
4075(Transcript, pages 29 through 31, and page 84). Consequently,
4084Mr. Hidle contends Petitioner's "Daily Time Log[s]" may be relied
4094upon to accurately reflect the hours actually worked, and that
4104those hours were reasonably expended.
410926. Here, considering the record, Mr. Hidle's testimony is
4118rejected as not credible or, stated otherwise, inherently
4126improbable and unworthy of belief. In so concluding, it is
4136observed that there is nothing of record, either in the exhibits
4147or testimony offered at hearing, that could possibly explain the
4157dichotomy between the number of hours claimed for development of
4167the MOP (329.42) and the number of hours claimed for development
4178of the MOP Addendum (83.73). Notably, neither project was
4187particularly complex, and the tasks performed were reasonably
4195alike. Similarly, it is inherently improbable, given the limited
4204field work and the product produced (the MOP), that production of
4215the MOP could require 329.42 hours or, stated differently, eight
4225and one-quarter weeks, at 40 hours per week. Finally, most of
4236the entries for which substantial blocks of time are assigned
4246contain only vague or general terms to describe the task, such as
"4258literature review," "MOP/RAP preparation," "file review," and
"4265schedule/plan/coordinate RAP/MOP." Such practice renders it
4271impossible to determine what work was actually done, whether the
4281work was duplicative, and whether the time was actually expended
4291or reasonable.
429327. Given the record, it must be concluded that the proof
4304offered by Petitioner to support the number of hours claimed for
4315development of the MOP is not credible or persuasive, and that it
4327would be pure speculation to attempt to derive any calculation or
4338meaningful estimate based on such proof. In the end, Petitioner
4348must bear the responsibility for such failure.
435528. While Petitioner's proof offers no credible basis upon
4364which to derive the number of hours dedicated to the MOP and
4376their reasonableness, Petitioner obviously dedicated time to the
4384MOP, and to the extent the record provides a reasonable basis on
4396which to predicate an award, it is appropriate to do so. Here,
4408given the lack of credibility of Petitioner's "Daily time
4417Log[s]," as well as the testimony of Mr. Hidle, to provide a
4429basis on which to derive the number of hours actually worked, and
4441then test those hours against the standard of reasonableness, the
4451only option is to award the 89 hours or $6,308.00, which the
4464Department agrees were reasonably expended.
446929. Finally, with regard to the miscellaneous cost items,
4478as opposed to personnel hours, rejected by the Department's
4487letter of June 27, 1996, it must be resolved that Petitioner
4498failed to offer, at hearing, any compelling proof that the items
4509rejected by the Department were reasonable expenditures incurred
4517in development of the monitor only program. Consequently, the
4526following sections of Petitioner's reimbursement application have
4533been reduced by the sums stated: $295.95 deducted from Section
45436C; $28.20 deducted from Section 6D; $9.00 deducted from Section
45536E; and $800.72 deducted from Section 6I.
4560The award for reimbursement
456430. Given the proof, Petitioner should be awarded the
4573following sums, for the items indicated, as reimbursement for
4582preparation of the MOP and MOP Addendum:
4589a. Personnel $12,249.60
4593b. Capital Expense Items __________
4598c. Rentals 867.50
4601d. Mileage 39.85
4604e. Shipping 26.00
4607f. Well Drilling __________
4611g. Permits __________
4614h. Analysis 3680.00
4617i. Miscellaneous 800.53
4620TOTAL 17,663.48
4623For expenses involved in preparation of the reimbursement
4631application, Petitioner should be awarded the following sums for
4640the items indicated:
4643a. Personnel $ 795.00
4647b. Capital Expense Items __________
4652c. Rentals 15.00
4655d. Mileage .80
4658e. Shipping 67.25
4661f. Well Drilling __________
4665g. Permits __________
4668h. Analysis __________
4671i. Miscellaneous 77.77
4674APPLICATION PREPARATION TOTAL 955.82
4678C ERTIFIED PUBLIC ACCOUNTANT
4682REVIEW FEE 500.00
4685TOTAL FOR APPLICATION
4688PREPARATION 1,455.82
4691In all, Petitioner should be accorded a total reimbursement of
4701$19,119.30.
4703CONCLUSIONS OF LAW
470631. The Division of Administrative Hearings has
4713jurisdiction over the parties to, and the subject matter of,
4723these proceedings. Sections 120.569 and 120.57(1), Florida
4730Statutes.
473132. Pertinent to this case, Section 376.3071, Florida
4739Statutes, provides for the reimbursement of a party who has
4749incurred costs for site cleanup. More particularly, Section
4757376.3071(12), Florida Statutes, provides:
4761(b) Conditions.
47631. The owner, operator, or his or her
4771designee of a site which is eligible for
4779restoration funding assistance in the EDI,
4785PLRIP, or ATRP programs shall be reimbursed
4792from the Inland Protection Trust Fund of
4799allowable costs at reasonable rates incurred
4805on or after January 1, 1985, for completed
4813program tasks as identified in the department
4820rule promulgated pursuant to paragraph
4825(5)(b) . . .
4829(d) Amount of reimbursement. The
4834department shall reimburse actual and
4839reasonable costs for site rehabilitation.
4844The department shall not reimburse interest
4850on the amount of reimbursable costs for any
4858reimbursement application. However, nothing
4862herein shall affect the department's
4867authority to pay interest authorized under
4873prior law.
487533. Also pertinent to this case, Chapter 62-773, Florida
4884Administrative Code, includes the following rule provisions:
489162-773.200 Definitions.
4893* * *
4896(11) "Integral" means costs essential to
4902completion of site rehabilitation.
4906* * *
4909(14) "Reimbursement" means payment of
4914money from the Inland Protection Trust Fund
4921to the person responsible for conducting site
4928rehabilitation for allowable costs incurred.
4933* * *
493662-773.700 Application for Reimbursement.
4940Upon completion of one or more program
4947tasks at sites with an eligible discharge,
4954the person responsible for conducting site
4960rehabilitation may apply for reimbursement of
4966allowable costs actually incurred in
4971conducting site rehabilitation. Pursuant to
4976Section 376.3071(12), F.S., payment shall be
4982made in the order in which the Department
4990receives completed applications provided
4994sufficient information has been provided to
5000determine the allowability and reasonableness
5005of all costs claimed.
500934. Here, Petitioner has requested reimbursement under the
5017provisions of Section 376.3071(12), Florida Statutes. As the
5025claimant, the burden rests on Petitioner to demonstrate
5033entitlement to compensation. Balino v. Department of Health and
5042Rehabilitative Services , 348 So. 2d 349, 350 (Fla. 1st DCA 1977)
5053("[T]he burden of proof, apart from statute, is on the party
5065asserting the affirmative issue before an administrative
5072tribunal.") See also Florida Department of Transportation v.
5081J.W.C. Co., Inc. , 396 So. 2d 778 (Fla. 1st DCA 1981).
509235. As noted in the findings of fact, Petitioner failed to
5103present credible evidence to demonstrate the number of hours
5112dedicated to the MOP or from which the number of hours reasonably
5124expended could be derived. When such proof is not forthcoming,
5134such failure is generally fatal to the claim. See e.g. Mercy
5145Hospital, Inc. v. Johnson , 431 So. 2d 687 (Fla. 3d DCA 1983), and
5158Miller v. First American Bank and Trust , 607 So. 2d 483 (Fla. 4th
5171DCA 1992). However, the Department conceded 89 hours ($6,308),
5181as reasonably incurred in the development of the MOP. Given the
5192record, the alternative offered by the Department's concession is
5201preferable to denying any reimbursement, and 89 hours ($6,308)
5211are accepted as reasonable for development of the MOP.
522036. In all, the record supports the conclusion that
5229Petitioner has demonstrated entitlement to the expenses
5236enumerated in paragraph 30, supra .
5242RECOMMENDATION
5243Based on the foregoing Findings of Fact and Conclusions of
5253Law, it is
5256RECOMMENDED that a final order be entered which awards
5265Petitioner the sum of $19,119.30, as reimbursable costs.
5274DONE AND ENTERED this 22nd day of February, 1999, in
5284Tallahassee, Leon County, Florida.
5288___________________________________
5289WILLIAM J. KENDRICK
5292Administrative Law Judge
5295Division of Administrative Hearings
5299The DeSoto Building
53021230 Apalachee Parkway
5305Tallahassee, Florida 32399-3060
5308(850) 488-9675 SUNCOM 278-9675
5312Fax Filing (850) 921-6847
5316www.doah.state.fl.us
5317Filed with the Clerk of the
5323Division of Administrative Hearings
5327this 22nd day of February, 1999.
5333ENDNOTES
53341/ Prior to hearing, the Department approved an additional
5343$5,920.60 for reimbursement and, at hearing, Petitioner withdrew
5352its request for reimbursement for the costs ($579.36) noted in
5362item 3 of the Order of Determination of Reimbursement
5371(Petitioner's Exhibit 12).
53742/ Petitioner also had marked for identification Petitioner's
5382Exhibits 16 through 18, 21, 26, and 27; however, they were not
5394accepted into evidence.
53973/ The Department also had marked for identification its
5406(Respondent's) Exhibit 6; however, it was not accepted into
5415evidence.
54164/ There are often several phases to the remediation of a site
5428contaminated by petroleum products. An early phase is the
5437contamination assessment, which assesses the severity and extent
5445of petroleum contamination in the soil and groundwater. The
5454results of this assessment are presented in the CAR. The next
5465stage in remediation may be the development of a Remedial Action
5476Plan (RAP), which proposes a design or system to remediate the
5487groundwater or soil contamination. All RAPs must contain
5495projections on the cost to remediate, the cost of the system, the
5507cost of operating the system, the duration of time the system will
5519run, and the projected life of the system. Additionally, a RAP
5530must compare the selected action against other options, regarding
5539overall cost and effectiveness. However, if sampling results
5547during the containment assessment indicate that the levels of
5556contamination are low or near target levels, such as in the
5567instant case, a RAP system may not be required and a Monitoring
5579Only Plan (MOP) may be approved. Such a plan involves monitoring
5590over time to assess whether, as expected, the levels of
5600contamination are decreasing.
56035/ Petitioner has previously been reimbursed by the Department
5612for all expenses associated with developing the CAR and those
5622expenses are not at issue in this case.
56306/ Mr. Hidle's field notes (Petitioner's Exhibit 5) reflect that
5640he left the office at 11:30 a.m., November 30, 1993; arrived at
5652the job at 1:30 p.m.; departed the job at 2:30 a.m., December 1,
56651993; and, arrived at the office at 3:15 a.m.
56747/ Mr. Hidle's field notes (Petitioner's Exhibit 5) reflect that
5684he and the technician left the office at 7:45 p.m., December 4,
56961993; arrived at the job site at 8:25 p.m.; departed the job site
5709at 3:40 a.m., December 5, 1993; and arrived at the office at
57214:30 a.m.
57238/ Each water sample was analyzed in accordance with EPA
5733Method 602 and some of the samples, but not all, were tested in
5746accordance with EPA Methods 610 and 418.1, as well as for lead.
57589/ Mr. Hidle's field notes (Petitioner's Exhibit 5) reflect that
5768he left the office (to load equipment) at 10:00 a.m., June 15,
57801994, arrived at the job site at 1:15 p.m., departed the job site
5793at 10:00 p.m., and arrived at the office at 11:00 p.m., where
5805unloading was completed at 11:30 p.m. The notes reflect the
5815technician arrived separately (at the job-site) at 1:15 p.m. and
5825departed at 10:00 p.m.
582910/ The Department's concession may have been generous; however,
5838it is accepted.
5841COPIES FURNISHED:
5843George M. Hidle, President
5847Panhandle Industries, Inc.
5850Post Office Box 11983
5854Fort Lauderdale, Florida 33339-1983
5858J. A. Spejenkowski, Esquire
5862Department of Environmental Protection
58663900 Commonwealth Boulevard
5869Mail Station 35
5872Tallahassee, Florida 32399-3000
5875Kathy Carter, Agency Clerk
5879Department of Environmental Protection
58833900 Commonwealth Boulevard
5886Mail Station 35
5889Tallahassee, Florida 32399-3000
5892F. Perry Odom, General Counsel
5897Department of Environmental Protection
59013900 Commonwealth Boulevard
5904Mail Station 35
5907Tallahassee, Florida 32399-3000
5910NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
5916All parties have the right to submit written exceptions within 15
5927days from the date of this Recommended Order. Any exceptions to
5938this Recommended Order should be filed with the agency that will
5949issue the Final Order in this case.
- Date
- Proceedings
- Date: 03/29/1999
- Proceedings: Final Order filed.
- Date: 01/13/1999
- Proceedings: Letter to Judge Kendrick from Petitioner Re: Certificate of Service on Proposed Findings of Fact filed.
- Date: 01/07/1999
- Proceedings: (Petitioner) Proposed Findings of Fact filed.
- Date: 01/06/1999
- Proceedings: Department of Environmental Protection`s Proposed Recommended Order; Disk filed.
- Date: 12/28/1998
- Proceedings: Notice of Filing; (Volumes 1 and 2 of 2) DOAH Court Reporter Final Hearing Transcript filed.
- Date: 12/08/1998
- Proceedings: CASE STATUS: Hearing Held.
- Date: 12/02/1998
- Proceedings: Letter to G. Hidle from J.A. Spejenkowski (RE: response to document supplemental) (filed via facsimile).
- Date: 12/02/1998
- Proceedings: (Petitioner) Notice and Certificate of Deliverance of Supplemental Interrogatories and/or Documents filed.
- Date: 11/30/1998
- Proceedings: Order sent out. (respondent to deliver responses to amended interrogatories by 12/1/98)
- Date: 11/25/1998
- Proceedings: (Respondent) Notice of Change of Agency Position filed.
- Date: 11/23/1998
- Proceedings: Respondent`s Response to Petitioner`s "Motion to Disallow Respondent`s Request of November 16, 1998"filed.
- Date: 11/19/1998
- Proceedings: (Petitioner) Motion to Compel; Notice and Certificate of Service of Interrogatories; Petitioner`s Amended Interrogatories to Respondent (Set 1) filed.
- Date: 11/19/1998
- Proceedings: (Petitioner) Motion to Disallow Respondent`s Request of November 16, 1998; Notice of Intent to Present Similar Fact Evidence at Hearing filed.
- Date: 11/16/1998
- Proceedings: Department of Environmental Protection`s Notice of Answers to Petitioner`s First Set of Service of Interrogatories; Respondent`s Responses to Petitioner`s Interrogatories (Set 1) filed.
- Date: 11/16/1998
- Proceedings: (J. Spejenkowski) Notice of Intent to Present Similar Fact Evidence at Hearing filed.
- Date: 11/16/1998
- Proceedings: Respondent`s Response to Petitioner`s Request for Documents (Set 1) filed.
- Date: 11/12/1998
- Proceedings: (DEP) Notice of Hearing; (Respondent) Emergency Motion for Status Conference Concerning Discovery filed.
- Date: 10/19/1998
- Proceedings: (Petitioner) Request for Production of Documents (Set I) filed.
- Date: 10/19/1998
- Proceedings: (Petitioner) Notice and Certificate of Service of Interrogatories; Petitioner`s Interrogatories to Respondent (Set I) filed.
- Date: 10/13/1998
- Proceedings: (Petitioner) Notice and Certificate of Deliverance of Interrogatories and Documents; Respondent`s Interrogatories to Petitioner (Set 1) ; Request for Production of Documents (Set 1) filed.
- Date: 09/08/1998
- Proceedings: Request for Production of Documents (Set 1) filed.
- Date: 09/08/1998
- Proceedings: Notice and Certificate of Service of Interrogatories filed.
- Date: 09/01/1998
- Proceedings: Notice of Hearing sent out. (hearing set for 12/8/98; 9:00am; Tallahassee)
- Date: 08/27/1998
- Proceedings: Joint Response filed.
- Date: 08/17/1998
- Proceedings: Initial Order issued.
- Date: 08/12/1998
- Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Petition for Formal Hearing; Agency Action Letter filed.