98-003640 Panhandle Industries, Inc., (Dagam Oil Company) vs. Department Of Environmental Protection
 Status: Closed
Recommended Order on Monday, February 22, 1999.


View Dockets  
Summary: Petitioner was awarded $19,119.30 as the reasonable cost incurred for site clean-up.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8PANHANDLE INDUSTRIES, INC., )

12)

13Petitioner, )

15)

16vs. ) Case No. 98-3640

21)

22DEPARTMENT OF ENVIRONMENTAL )

26PROTECTION, )

28)

29Respondent. )

31__________________________________)

32RECOMMENDED ORDER

34Pursuant to notice, the Division of Administrative Hearings,

42by its duly designated Administrative Law Judge, William J.

51Kendrick, held a formal hearing in the above-styled case on

61December 8, 1998, in Tallahassee, Florida.

67APPEARANCES

68For Petitioner: George M. Hidle, President

74Panhandle Industries, Inc.

77Post Office Box 11983

81Fort Lauderdale, Florida 33339-1983

85For Respondent: J. A. Spejenkowski, Esquire

91Department of Environmental Protection

953900 Commonwealth Boulevard

98Mail Station 35

101Tallahassee, Florida 32399-3000

104STATEMENT OF THE ISSUES

108At issue in this proceeding is the reasonable cost to be

119reimbursed Petitioner, under the provisions of Section

126376.3071(12), Florida Statutes, for the development of a

134Monitoring Only Plan (MOP) program for the Dagam Oil Company

144(DEP Facility No. 138504146), at 331 23rd Street, Miami Beach,

154Florida.

155PRELIMINARY STATEMENT

157In August 1994, Petitioner, Panhandle Industries, Inc.,

164submitted an application to the Respondent, Department of

172Environmental Protection (Department), which sought reimbursement

178for costs associated with the development of a Monitoring Only

188Plan (MOP) under the provisions of Section 376.3071, Florida

197Statutes.

198Following review, the Department ultimately issued an Order

206of Determination of Reimbursement on June 27, 1996, which

215approved for reimbursement $13,198.70 of the total of $39,412.66

226requested by Petitioner. 1

230Respondent elected to dispute the Department's decision and

238filed a petition for formal hearing pursuant to Sections 120.569

248and 120.57, Florida Statutes. On August 12, 1998, the Department

258referred the matter to the Division of Administrative Hearings

267for the assignment of an administrative law judge to conduct the

278formal hearing Petitioner had requested.

283At hearing, Petitioner called George Hidle as a witness, and

293Petitioner's Exhibits 1 through 15 and 23 through 25 were

303received into evidence. 2 The Department called as witnesses

312Diane Pickette, Brian King, Charles Williams, and Jeffrey

320Priddle, and the Department's (Respondent's) Exhibits 1 through 5

329and 7 were received into evidence. 3

336The hearing transcript was filed on December 28, 1998, and

346the parties were accorded 10 days from that date to file proposed

358recommended orders or proposed findings of fact. The parties

367elected to submit such proposals and they have been duly

377considered.

378FINDINGS OF FACT

381Background

3821. Petitioner, Panhandle Industries, Inc., is a Florida

390corporation engaged in the business of consulting, engineering

398and construction. George M. Hidle, a professional geologist

406licensed in the State of Florida, is the president and sole owner

418of the Petitioner corporation.

4222. In September 1992, Dagam Oil Company, doing business as

432Sierra Fina, employed Petitioner to do environmental assessment

440work and prepare a Contamination Assessment Report (CAR) under

449the then existing Rule 17-770.630, Florida Administrative Code,

457for a site located at 331 23rd Street, Miami Beach, Florida (DEP

469Facility No. 138504146). 4 That CAR was submitted to DERM

479(Metropolitan Dade County, Department of Environmental Resources

486Management) July 13, 1993. (Petitioner's Exhibit 1.)

4933. Pertinent to this case, the CAR provides the following

503background or historical information:

507. . . PHYSICAL SETTING

512. . . Sierra Fina is located at 331

52123rd Street in Miami Beach, Florida . . .

530The facility is bordered to the north by

538Collins Canal, to the east by the light

546commercial properties, and to the

551south/southeast by property that once

556contained Chevron and Fina service

561stations. . . .

565* * *

568. . . FACILITY HISTORY AND OPERATION

575Sierra Fina was built in 1963. The station

583originally operated as a Sunoco service

589station with a 3 bay garage. Dagam Oil

597Company purchased the facility in March 1981

604from Charles Rosenblatt. At the time the

611station had five underground fuel

616tanks. . . .

620* * *

623. . . PREVIOUS INVESTIGATIONS

628Dagam Oil Company contracted with another

634environmental company in November 1988 to

640collect groundwater samples from . . . five

648monitoring wells at the facility.

653Groundwater samples were collected on

658November 9, 1988 and analyzed by EPA Method

666602. Monitoring well MW-3 was also analyzed

673by EPA Method 610. All five of the wells had

683hydrocarbon contaminant concentrations in

687excess of state guidelines. . . .

694A discharge notification form was mailed to

701the DER and DERM on December 9, 1988, the

710date of receipt of the analytical results

717from the November 9, 1988 groundwater

723sampling event. . . .

728* * *

731. . . INITIAL REMEDIAL ACTIONS [IRA]

738[The F]ive underground storage tanks [and

744associated piping] were removed from the

750facility during March and April 1989 [, and

758replaced with four new cathodically protected

764underground petroleum storage tanks].

768Approximately 400 cubic yards of contaminated

774soil was also removed at that time. On

782March 31, 1989 a composite sample of the soil

791was collected for analysis . . . Because of

800limited space at the station, the

806contaminated soil was hauled to a Metro

813Trucking Inc. storage yard located at

819112th Avenue and 143 Street in Miami. The

827contaminated soil was landfarmed at this

833Metro Trucking facility for a period of seven

841months, during which time the soil was spread

849onto visqueen and tilled on a regular basis.

857On November 21, 1989 the soil was resampled

865and analyzed . . . Results of this second

874round of analyses met clean fill criteria.

881Also at the time of tank replacement, a

889sheen of free floating hydrocarbons was

895observed on water in the tank pit. A vac

904truck was used to skim this product from the

913pit prior to tank replacement. Approximately

9192100 gallons of oily water were removed,

926transported, and disposed of by Cliff Berry,

933Inc. . . .

937Other than these IRA activities, no other assessment or

946remediation work had been performed at the facility until

955Petitioner was employed in September 1992.

9614. Petitioner's CAR concluded that:

966Soil and groundwater at Sierra Fina are

973contaminated with gasoline and diesel

978hydrocarbons. Excessively contaminated soil

982is confined to an area at the western end of

992the station building that is approximately

99820 feet in width by 30 feet in length,

1007extending down to a water table of between

10156 and 8 feet below land s urface. No free

1025phase floating product is present on the

1032groundwater underlying this facility.

1036However, dissolved hydrocarbon contamination

1040is present in the groundwater. A dissolved

1047hydrocarbon plume is present in the western

1054half of the site. This plume measures

106180 feet in length by 60 feet in width and

1071extends to a depth of less than 22 feet below

1081land surface, yielding approximately 134,640

1087gallons of hydrocarbon contaminated water.

1092Volume calculations are based on an average

1099depth to groundwater of 7 feet below land

1107surface and an effective soil porosity of

111425%. The highest benzene (53.3 ppb) and

1121total napthalenes (752 ppb) concentrations

1126were detected in MW-12.

1130* * *

1133Groundwater within the Biscayne Aquifer

1138beneath Sierra Fina is nonpotable because of

1145salt water intrusion from the Atlantic Ocean.

1152For this reason there are no private or

1160public potable wells in the area.

1166Contamination at Sierra Fina is limited

1172onsite to the western half of the station,

1180and poses no threats to sensitive receptors

1187in the area, with the possible exception of

1195Collins Canal. The cause of hydrocarbon

1201contamination was never determined; however,

1206the most probable source, i.e. previous

1212petroleum tanks and lines, were removed in

1219March and April of 1989. Based on these

1227findings and the data presented about or

1234elsewhere in this report, it is known that

1242soil and groundwater contamination does exist

1248at this facility in concentrations that

1254exceed guidelines specified in Section 17-

1260770.730(5)FAC; however, the levels of

1265contamination may not warrant the need for

1272any extensive remediation activities at this

1278site.

12795. Petitioner's CAR was approved by DERM on October 8,

12891993, and Petitioner was directed to submit a Remedial Action

1299Plan (RAP) within 60 days. 5

13056. At the time, Mr. Hidle (Petitioner) was aware that the

1316levels of contamination were low or near target levels, and that

1327it was likely that the contamination levels would decrease

1336naturally over time. Consequently, Petitioner elected to seek

1344approval of a Monitor Only Plan (MOP), as opposed to a RAP. Such

1357choice was favored based on the nature and location of the

1368contaminants. In this regard, it was observed that the soil

1378contamination consisted of both gasoline and diesel fuel, with

1387much of the contaminated soil abutting or underneath the

1396building. Excavation and removal of the soil was not an

1406alternative because it would undermine the structural integrity

1414of the building. Moreover, given the fuel mix, vapor extraction

1424was not a viable option.

14297. Given Petitioner's choice to pursue approval of a MOP,

1439it gave notice to the Department and DERM on October 18, 1993, as

1452well as November 12, 1993, and December 2, 1993, of its intention

1464to undertake groundwater sampling and soil sampling on the site.

14748. Groundwater sampling was undertaken by Mr. Hidle between

14831:30 p.m., November 30, 1993, and 2:30 a.m., December 1, 1993, 6

1495at which time he drew water samples for laboratory analysis from

150610 monitor wells (MW) and one deep well (DW). A duplicate sample

1518was also retrieved at MWs 12R and 14, and equipment blanks were

1530also obtained for laboratory analysis.

15359. Between 8:25 p.m., December 4, 1993, and 3:40 a.m.

1545December 5, 1993, 7 Mr. Hidle and a senior technician (Martin

1556Hidle) augured 6 soil borings for use in preparing the MOP and

1568collected one soil sample for laboratory analysis.

157510. Petitioner delivered the water samples to the

1583laboratory (Envirodyne, Inc.) on December 2, 1993, and the soil

1593sample on December 6, 1993, for analysis. The laboratory

1602completed its analysis of the water samples on December 13, 1993,

1613and of the soil sample on December 14, 1993, and rendered its

1625written reports (analysis) to Petitioner. 8

163111. Upon receipt of the laboratory data, Mr. Hidle

1640completed his preparation of the MOP. (Petitioner's Exhibit 4.)

1649That MOP contained the following conclusions and recommendations:

1657The initial dissolved hydrocarbon plume

1662dimensions were based on data from

1668groundwater sampling events of January and

1674February 1993. Laboratory results from a

1680more recent sampling event (11/30/93)

1685indicate that plume size and hydrocarbon

1691compound concentrations therein have

1695decreased substantially (Table 4-2). Maximum

1700groundwater contaminant concentrations

1703decreased as follows: benzene from 53.3 ppb

1710to 11.1 ppb; BTEX from 111.7 ppb to 20.6 ppb;

1720total naphthalenes from 752 ppb to 246.1 ppb.

1728During the contamination assessment program

1733task a small area of contaminated soil was

1741found to be abutting the western end of the

1750station building (CAR, Fig. 3-1, p. 35).

1757Because of the presence of diesel compounds

1764in the groundwater, it was assumed during

1771preparation of the CAR that the soil too was

1780contaminated with diesel.

1783In early December 1993 PI Environmental

1789personnel installed six additional soil

1794borings (Figure 3-1, SB-16 through SB-21) and

1801collected one soil sample for laboratory

1807analyses. The soil borings were augered in

1814the immediate area of the previously defined

1821contaminated soil plume, and soil samples

1827were analyzed in the field by using a Foxboro

1836OVA 128. Soil samples were collected

1842vertically every two feet, beginning at one

1849foot below ground surface and continuing

1855until the water table was encountered.

1861A soil sample was collected from boring

1868SB-17 at a depth of six feet below land

1877surface. A net OVA reading of 160 ppm was

1886observed from a duplicate sample taken from

1893the same depth. The soil sample was tested

1901by EPA Methods 3540/8100 (diesel compounds)

1907and 9073 (TRPH). Laboratory results

1912indicated that all diesel compounds were

1918below laboratory detection limits, and the

1924TRPH concentration was below normal

1929background readings.

1931Soil contamination was reclassified as

1936being gasoline in origin, because no diesel

1943compounds were detected in the soil sample

1950from SB-17. Section 17-770.200(2) Florida

1955Administrative Code defines excessively

1959contaminated soil, associated with gasoline

1964contamination, as those that have a net

1971OVA/FID reading equal to or greater than

1978500 ppm.

1980From December 1993 sampling event, a

1986maximum net OVA/FID reading of 316 ppm was

1994obtained from a sample that was collected at

2002five fee below land surface in SB-17. Based

2010on these results, no excessively contaminated

2016soil was found during the most recent

2023sampling event.

2025It is the recommendation of PI

2031Environmental Inc. that a Monitoring Only

2037Plan be implemented at Sierra Fina. This

2044recommendation is based on the following

2050findings: 1) Absence in the study area of any

2059potable water wells within the Biscayne

2065Aquifer because of salt water intrusion from

2072the Atlantic Ocean 2) Absence of free phase

2080hydrocarbons 3) Absence of excessively

2085contaminated soil 4) Substantial decrease in

2091concentrations of dissolved hydrocarbon

2095compounds within the groundwater during the

2101last year, and 5) relatively low levels of

2109hydrocarbon contamination in the groundwater,

2114i.e., based on the November 30, 1993 sampling

2122event, maximum benzene of 11.1 ppb, maximum

2129BTEX of 20.6 ppb, and maximum total

2136naphthalenes of 246.1 ppb.

2140It is our recommendation that groundwater

2146from monitoring wells MW-8, MW-12R, MW-6, and

2153MW-17 be sampled on a quarterly basis.

2160Groundwater from the source area wells, MW-8

2167and MW-12R, should be analyzed quarterly by

2174EPA Methods 602 and 610. Groundwater from

2181the perimeter wells, MW-6 and MW-17, should

2188be analyzed quarterly by EPB Method 602 and

2196semiannually by EPA Methods 602 and 610.

2203Petitioner submitted the MOP to DERM on January 24, 1994.

221312. Pertinent to this case, it is observed that the MOP was

2225a brief document, consisting of only 13 pages of textual

2235material, much of which was a restatement of material contained

2245in the CAR. The balance of the report consisted of 5 "Figures"

2257(three of which were contained in the CAR and one of which is an

2271updated version of a CAR Figure); 2 "Tables" (an update of the

2283Water Table Elevation table contained in the CAR to include the

2294November 30, 1993, data, and an update of the Summary of

2305Groundwater Analyses contained in the CAR to include the

2314November 30, 1993, and December 1, 1993, data); 6 "Geologic

2324Log[s]" (a restating of the soil boring results noted in the

2335field notes for December 4 and 5, 1993); copies of the laboratory

2347(Envirodyne, Inc.'s) reports of groundwater analysis; and the

2355laboratory's report on the soil analysis. In all, while

2364apparently adequate and nicely presented, the MOP does not

2373address a complex or unique issue, and does not evidence the

2384expenditure, or need to expend, an inordinate amount of effort to

2395produce.

239613. Petitioner's MOP was disapproved by DERM on May 11,

24061994, for the following reasons:

24111. A complete round of groundwater

2417analyses, no greater than six months old, is

2425required. Therefore, all wells at this site

2432must be sampled for EPA Method 418.1, and

2440monitoring wells numbered MW-6, MW-9, MW-10,

2446MW-11, MW-13, MW-16, and MW-17 must be

2453sampled for EPA Method 610.

24582. Because diesel contamination is present

2464at this site, soil OVA readings above 50 ppm

2473are considered to indicate excessively

2478contaminated soil. Based on this OVA

2484readings obtained for your Contamination

2489Assessment Report (CAR) and this MOP,

2495excessively contaminated soil does exist at

2501this site. Since this coil could be a

2509continuing source of contamination, it must

2515be removed prior to the approval of a MOP.

2524Consequently, Petitioner was directed to submit an addendum to

2533the MOP to address those issues.

253914. On June 1, 1994, Petitioner gave notice to the

2549Department and DERM of its intent to collect groundwater samples

2559to address issues raised by DERM's MOP review letter. These

2569samples were collected by Mr. Hidle and a technician (Leo

2579Iannone) between 1:15 p.m. and 10 :00 p.m., June 15, 1994. 9

259115. Petitioner delivered the water samples to the

2599laboratory (Envirodyne, Inc.) on June 16, 1994. The laboratory

2608completed its analysis and delivered its written reports to

2617Petitioner on or about June 23, 1994.

262416. Upon receipt of the laboratory data, Mr. Hidle

2633completed the Monitoring Only Plan Addendum (Petitioner's Exhibit

26418), and submitted it to DERM on July 5, 1994. The addendum

2653addressed the additional groundwater analysis that was performed,

2661and with regard to the diesel contamination it observed, as

2671follows:

2672Soil analytical results (MOP, Page 62) are

2679below laboratory detection limits for EPA 610

2686compounds; however, because groundwater at

2691this facility is contaminated with both

2697gasoline and diesel, we are concurring with

2704DERM by reclassifying excessively

2708contaminated soil as any soil that exhibits

2715net OVA/FID readings of 50 ppm or greater,

2723per Chapter 17-770 FAC.

2727OVA/FID soil analyses were performed in

2733accordance to Panhandle Industries, Inc.

2738approved Comp QAP. Net OVA/FID soil results

2745obtained during the CAR program task are

2752shown in Figure 1-5. A maximum net OVA/FID

2760reading of 887 ppm was obtained during CAR

2768soil assessment activities which ended on

2774November 29, 1992. Figure 1-6 shows net

2781OVA/FID results obtained during the MOP

2787program task. These MOP analyses are current

2794through December 5, 1993. A maximum net

2801OVA/FID of 316 ppm was obtained during this

2809latter event. As is shown in comparison of

2817Figures 1-5 and 1-6, it can be seen that the

2827size of the soil contaminant plume and

2834OVA/FID net soil readings therein have

2840decreased significantly since initiation of

2845the CAR. Also, by observing Figure 1-6,

2852which has a scale of 1" = 20', it is evident

2863that very little soil, if any can be

2871excavated without jeopardizing the structural

2876integrity of the station building.

2881Furthermore, there exist the possibility that

2887some soil contamination may underlie the

2893building itself; therefore, soil excavation

2898would most likely result in only partial

2905removal of the contaminated soil plume.

2911The addendum concluded by recommending that the MOP be

2920implemented as originally proposed, but with additional

2927monitoring to assure a continuing decline in contamination.

293517. The addendum, like the MOP, was a brief document and

2946contains only 6 pages of textual material. The balance of the

2957addendum contains 6 "Figures" (all of which appeared in the CAR

2968or MOP); 2 "Tables" (an update of the Water Table Elevations

2979table contained in the MOP to include June 15, 1994, data, and an

2992update of the Summary of Groundwater Analyses contained in the

3002MOP to include the June 15, 1994, data); and the laboratory

3013reports of groundwater analyses. As with the MOP, the addendum

3023did not appear to address any complex or unique issues, and did

3035not evidence the expenditure, or need to expend, an inordinate

3045amount of time to produce.

305018. On August 16, 1994, and August 26, 1994, DERM and the

3062Department, respectively, approved the "monitoring only"

3068proposal.

3069The request for reimbursement

307319. Petitioner submitted its reimbursement application on

3080or about August 23, 1994, and it was apparently complete on or

3092about April 18, 1996. (Petitioner's Exhibit 11). That

3100application sought recovery of the following sums for the items

3110noted:

31116. REMEDIAL ACTION PLAN [MOP and MOP

3118Addendum] PREPARATION . . .

3123a. Personnel 31442.55

3126b. Capital Expense Items ______________

3131c. Rentals 1127.45

3134d. Mileage 68.05

3137e. Shipping 35.00

3140f. Well Drilling ______________

3144g. Permits ______________

3147h. Analysis 3680.00

3150i. Miscellaneous 1601.25

3153REMEDIAL ACTION PLAN

3156PREPARATION TOTAL 37954.30

3159* * *

316213. REIMBURSEMENT APPLICATION PREPARATION

3166Supplementary Forms

3168a. Personnel 795.00

3171b. Capital Expense Items _____________

3176c. Rentals 15.00

3179d. Mileage .80

3182e. Shipping 86.81

3185f. Well Drilling _____________

3189g. Permits _____________

3192h. Analysis _____________

3195i. Miscellaneous 60.75

3198APPLICATION PREPARATION TOTAL 958.36

3202CERTIFIED PUBLIC ACCOUNTANT

3205REVIEW FEE 500.00

3208APPLICATION GRAND TOTAL 39412.66

321219. By letter (Order of Determination of Reimbursement) of

3221June 27, 1996, the Department responded to Petitioner's

3229reimbursement request as follows:

3233We have completed review of your

3239Reimbursement Application for expenses

3243incurred during the Remedial Action

3248Plan/Monitoring Only Plan program task at

3254this site and have determined that $13,198.70

3262of the total $39,412.66 requested is

3269allowable for reimbursement. This amount

3274will be paid to the person responsible for

3282conducting site rehabilitation when

3286processing is completed by the Comptroller's

3292Office.

3293Some adjustments to the amount of

3299reimbursement requested have been made. The

3305following list details these adjustments.

3310Citations refer to the specific sections of

3317the enclosed Reimbursement Application

3321Summary Sheets:

33231. $24,766.25 in Section 6A, $259.95 in

3331Section 6C, $28.20 in Section 6D and

3338$63.25 in Section 6I were deducted

3344because the total personnel hours (413.15

3350hours) and the total cost of $39,412.66

3358claimed for performing a limited scope of

3365work consisting of 78.34 hours of field

3372activities, two rounds of analyses (59

3378samples) and two letter reports have been

3385determined to be excessive. However,

3390actual field activities (including a

3395reasonable amount of preparation), two

3400rounds of analyses and a reasonable

3406amount of personnel time to prepare two

3413letter reports have been allowed.

34182. $162.50 in Section 6A, $9.00 in

3425Section 6E and $331.15 in Section 6I were

3433deducted for costs associated with

3438providing backup for the Contamination

3443Assessment reimbursement application.

3446These costs are not reimbursable in this

3453application which is for the Remedial

3459Action Plan/Monitoring Only Plan program

3464task.

34653. $184.80 in Section 6A and $394.56 in

3473Section 6I were deducted for field

3479supplies, ice, conducting database

3483modifications and purchasing office

3487supplies, which are considered to be

3493overhead. These costs are not justified

3499in addition to the loaded personnel rates

3506which already include overhead and

3511profit.

35124. $11.76 in Section 6I was deducted because

3520the rate for reproduction ($0.99 per

3526page) has been determined to be

3532excessive. However, $0.15 (per page) has

3538been allowed based on the predominant

3544rate claimed in other reimbursement

3549applications for similar rates.

35535. $19.56 in Section 13E was deducted for

3561costs added to the application

3566preparation claimed as a markup.

3571Reimbursement for application preparation

3575is limited to actual costs only.

35816. $17.02 was added to the application grand

3589total to cover the cost of reproducing

3596the reimbursement application and

3600invoices and shipping the replacements to

3606the Department.

3608(Petitioner's Exhibit 12.)

361120. Petitioner filed a timely challenge to contest the

3620Department's decision. That challenge disputed the Department's

3627action, as set forth in paragraphs numbered 1 through 4 of the

3639letter, but Petitioner did not then, or at hearing, dispute the

3650Department's action with regard to the matters contained in

3659paragraphs numbered 5 and 6 of the Department's letter.

3668(Petitioner's Exhibit 13). Subsequently, at hearing, Petitioner

3675withdrew its request for reimbursement regarding the items

3683contained in paragraph 3 of the Department's letter.

3691(Transcript, page 101).

3694The claim for the cost of preparing the

3702reimbursement application

370421. Petitioner's claim for the cost of preparation of the

3714reimbursement application totalled $1,458.36 (including the

3721certified public accountant review fee). The Department proposed

3729to deduct $19.56 (in Section 13E), and to add $17.02 to cover

3741certain costs, as noted in the Department's letter.

3749(Petitioner's Exhibits 12 and 13). Petitioner offered no

3757objection to the Department's decision and, therefore, Petitioner

3765should be awarded $1,455.82, without the need for further

3775discussion, as the cost of preparing the reimbursement

3783application.

3784The claim for the cost of preparation of

3792the MOP and MOP Addendum

379722. Petitioner's application for reimbursement claimed

3803413.15 personnel hours ($31,442.55) were dedicated to the

3812development of the MOP (329.42 hours/$25,500.95) and the MOP

3822Addendum (83.73 hours/$5,941.60). (Respondent's Exhibit 7, and

3830Transcript, pages 188-190).

383323. In its initial review, the Department approved

384155.67 hours ($3,790.45) for the MOP and 41.92 hours ($2,538.55)

3853for the MOP Addendum, for a total award of $6,329.00.

3864Subsequently, the Department resolved to accept as reasonable,

387289 hours ($6,308.00) for the MOP and 83.73 hours ($5,941.60) for

3885the MOP Addendum, for a total award of $12,249.60 for personnel

3897costs. 10

389924. The 83.73 hours ($5,941.60) agreed to by the Department

3910for the MOP Addendum was the precise amount Petitioner requested

3920in its reimbursement application; however, the 89 hours

3928($6,308.00) accepted by the Department for the MOP is clearly

3939less than the 329.42 hours ($25,500.95) Petitioner had requested.

3949With regard to the difference, the Department views the request

3959as excessive. In contrast, Petitioner contends the time

3967requested was reasonable. Here, the Department's view has merit.

397625. To support the reasonableness of the hours (labor)

3985claimed, Petitioner pointed to the "Daily Time Log[s]" which were

3995contained within the reimbursement application, and which it

4003contended contain an accurate recording of the hours worked and

4013the task performed. (Petitioner's Exhibits 11, and Transcript,

4021pages 29 through 31). According to Mr. Hidle, all employees of

4032the company were required to keep a notepad on which they were to

4045record the job (customer), hours worked, and task performed. At

4055some future date, perhaps up to a week or more, those entries

4067were ostensibly transferred to the "Daily Time Log."

4075(Transcript, pages 29 through 31, and page 84). Consequently,

4084Mr. Hidle contends Petitioner's "Daily Time Log[s]" may be relied

4094upon to accurately reflect the hours actually worked, and that

4104those hours were reasonably expended.

410926. Here, considering the record, Mr. Hidle's testimony is

4118rejected as not credible or, stated otherwise, inherently

4126improbable and unworthy of belief. In so concluding, it is

4136observed that there is nothing of record, either in the exhibits

4147or testimony offered at hearing, that could possibly explain the

4157dichotomy between the number of hours claimed for development of

4167the MOP (329.42) and the number of hours claimed for development

4178of the MOP Addendum (83.73). Notably, neither project was

4187particularly complex, and the tasks performed were reasonably

4195alike. Similarly, it is inherently improbable, given the limited

4204field work and the product produced (the MOP), that production of

4215the MOP could require 329.42 hours or, stated differently, eight

4225and one-quarter weeks, at 40 hours per week. Finally, most of

4236the entries for which substantial blocks of time are assigned

4246contain only vague or general terms to describe the task, such as

"4258literature review," "MOP/RAP preparation," "file review," and

"4265schedule/plan/coordinate RAP/MOP." Such practice renders it

4271impossible to determine what work was actually done, whether the

4281work was duplicative, and whether the time was actually expended

4291or reasonable.

429327. Given the record, it must be concluded that the proof

4304offered by Petitioner to support the number of hours claimed for

4315development of the MOP is not credible or persuasive, and that it

4327would be pure speculation to attempt to derive any calculation or

4338meaningful estimate based on such proof. In the end, Petitioner

4348must bear the responsibility for such failure.

435528. While Petitioner's proof offers no credible basis upon

4364which to derive the number of hours dedicated to the MOP and

4376their reasonableness, Petitioner obviously dedicated time to the

4384MOP, and to the extent the record provides a reasonable basis on

4396which to predicate an award, it is appropriate to do so. Here,

4408given the lack of credibility of Petitioner's "Daily time

4417Log[s]," as well as the testimony of Mr. Hidle, to provide a

4429basis on which to derive the number of hours actually worked, and

4441then test those hours against the standard of reasonableness, the

4451only option is to award the 89 hours or $6,308.00, which the

4464Department agrees were reasonably expended.

446929. Finally, with regard to the miscellaneous cost items,

4478as opposed to personnel hours, rejected by the Department's

4487letter of June 27, 1996, it must be resolved that Petitioner

4498failed to offer, at hearing, any compelling proof that the items

4509rejected by the Department were reasonable expenditures incurred

4517in development of the monitor only program. Consequently, the

4526following sections of Petitioner's reimbursement application have

4533been reduced by the sums stated: $295.95 deducted from Section

45436C; $28.20 deducted from Section 6D; $9.00 deducted from Section

45536E; and $800.72 deducted from Section 6I.

4560The award for reimbursement

456430. Given the proof, Petitioner should be awarded the

4573following sums, for the items indicated, as reimbursement for

4582preparation of the MOP and MOP Addendum:

4589a. Personnel $12,249.60

4593b. Capital Expense Items __________

4598c. Rentals 867.50

4601d. Mileage 39.85

4604e. Shipping 26.00

4607f. Well Drilling __________

4611g. Permits __________

4614h. Analysis 3680.00

4617i. Miscellaneous 800.53

4620TOTAL 17,663.48

4623For expenses involved in preparation of the reimbursement

4631application, Petitioner should be awarded the following sums for

4640the items indicated:

4643a. Personnel $ 795.00

4647b. Capital Expense Items __________

4652c. Rentals 15.00

4655d. Mileage .80

4658e. Shipping 67.25

4661f. Well Drilling __________

4665g. Permits __________

4668h. Analysis __________

4671i. Miscellaneous 77.77

4674APPLICATION PREPARATION TOTAL 955.82

4678C ERTIFIED PUBLIC ACCOUNTANT

4682REVIEW FEE 500.00

4685TOTAL FOR APPLICATION

4688PREPARATION 1,455.82

4691In all, Petitioner should be accorded a total reimbursement of

4701$19,119.30.

4703CONCLUSIONS OF LAW

470631. The Division of Administrative Hearings has

4713jurisdiction over the parties to, and the subject matter of,

4723these proceedings. Sections 120.569 and 120.57(1), Florida

4730Statutes.

473132. Pertinent to this case, Section 376.3071, Florida

4739Statutes, provides for the reimbursement of a party who has

4749incurred costs for site cleanup. More particularly, Section

4757376.3071(12), Florida Statutes, provides:

4761(b) Conditions.–

47631. The owner, operator, or his or her

4771designee of a site which is eligible for

4779restoration funding assistance in the EDI,

4785PLRIP, or ATRP programs shall be reimbursed

4792from the Inland Protection Trust Fund of

4799allowable costs at reasonable rates incurred

4805on or after January 1, 1985, for completed

4813program tasks as identified in the department

4820rule promulgated pursuant to paragraph

4825(5)(b) . . .

4829(d) Amount of reimbursement.– The

4834department shall reimburse actual and

4839reasonable costs for site rehabilitation.

4844The department shall not reimburse interest

4850on the amount of reimbursable costs for any

4858reimbursement application. However, nothing

4862herein shall affect the department's

4867authority to pay interest authorized under

4873prior law.

487533. Also pertinent to this case, Chapter 62-773, Florida

4884Administrative Code, includes the following rule provisions:

489162-773.200 Definitions.

4893* * *

4896(11) "Integral" means costs essential to

4902completion of site rehabilitation.

4906* * *

4909(14) "Reimbursement" means payment of

4914money from the Inland Protection Trust Fund

4921to the person responsible for conducting site

4928rehabilitation for allowable costs incurred.

4933* * *

493662-773.700 Application for Reimbursement.

4940Upon completion of one or more program

4947tasks at sites with an eligible discharge,

4954the person responsible for conducting site

4960rehabilitation may apply for reimbursement of

4966allowable costs actually incurred in

4971conducting site rehabilitation. Pursuant to

4976Section 376.3071(12), F.S., payment shall be

4982made in the order in which the Department

4990receives completed applications provided

4994sufficient information has been provided to

5000determine the allowability and reasonableness

5005of all costs claimed.

500934. Here, Petitioner has requested reimbursement under the

5017provisions of Section 376.3071(12), Florida Statutes. As the

5025claimant, the burden rests on Petitioner to demonstrate

5033entitlement to compensation. Balino v. Department of Health and

5042Rehabilitative Services , 348 So. 2d 349, 350 (Fla. 1st DCA 1977)

5053("[T]he burden of proof, apart from statute, is on the party

5065asserting the affirmative issue before an administrative

5072tribunal.") See also Florida Department of Transportation v.

5081J.W.C. Co., Inc. , 396 So. 2d 778 (Fla. 1st DCA 1981).

509235. As noted in the findings of fact, Petitioner failed to

5103present credible evidence to demonstrate the number of hours

5112dedicated to the MOP or from which the number of hours reasonably

5124expended could be derived. When such proof is not forthcoming,

5134such failure is generally fatal to the claim. See e.g. Mercy

5145Hospital, Inc. v. Johnson , 431 So. 2d 687 (Fla. 3d DCA 1983), and

5158Miller v. First American Bank and Trust , 607 So. 2d 483 (Fla. 4th

5171DCA 1992). However, the Department conceded 89 hours ($6,308),

5181as reasonably incurred in the development of the MOP. Given the

5192record, the alternative offered by the Department's concession is

5201preferable to denying any reimbursement, and 89 hours ($6,308)

5211are accepted as reasonable for development of the MOP.

522036. In all, the record supports the conclusion that

5229Petitioner has demonstrated entitlement to the expenses

5236enumerated in paragraph 30, supra .

5242RECOMMENDATION

5243Based on the foregoing Findings of Fact and Conclusions of

5253Law, it is

5256RECOMMENDED that a final order be entered which awards

5265Petitioner the sum of $19,119.30, as reimbursable costs.

5274DONE AND ENTERED this 22nd day of February, 1999, in

5284Tallahassee, Leon County, Florida.

5288___________________________________

5289WILLIAM J. KENDRICK

5292Administrative Law Judge

5295Division of Administrative Hearings

5299The DeSoto Building

53021230 Apalachee Parkway

5305Tallahassee, Florida 32399-3060

5308(850) 488-9675 SUNCOM 278-9675

5312Fax Filing (850) 921-6847

5316www.doah.state.fl.us

5317Filed with the Clerk of the

5323Division of Administrative Hearings

5327this 22nd day of February, 1999.

5333ENDNOTES

53341/ Prior to hearing, the Department approved an additional

5343$5,920.60 for reimbursement and, at hearing, Petitioner withdrew

5352its request for reimbursement for the costs ($579.36) noted in

5362item 3 of the Order of Determination of Reimbursement

5371(Petitioner's Exhibit 12).

53742/ Petitioner also had marked for identification Petitioner's

5382Exhibits 16 through 18, 21, 26, and 27; however, they were not

5394accepted into evidence.

53973/ The Department also had marked for identification its

5406(Respondent's) Exhibit 6; however, it was not accepted into

5415evidence.

54164/ There are often several phases to the remediation of a site

5428contaminated by petroleum products. An early phase is the

5437contamination assessment, which assesses the severity and extent

5445of petroleum contamination in the soil and groundwater. The

5454results of this assessment are presented in the CAR. The next

5465stage in remediation may be the development of a Remedial Action

5476Plan (RAP), which proposes a design or system to remediate the

5487groundwater or soil contamination. All RAPs must contain

5495projections on the cost to remediate, the cost of the system, the

5507cost of operating the system, the duration of time the system will

5519run, and the projected life of the system. Additionally, a RAP

5530must compare the selected action against other options, regarding

5539overall cost and effectiveness. However, if sampling results

5547during the containment assessment indicate that the levels of

5556contamination are low or near target levels, such as in the

5567instant case, a RAP system may not be required and a Monitoring

5579Only Plan (MOP) may be approved. Such a plan involves monitoring

5590over time to assess whether, as expected, the levels of

5600contamination are decreasing.

56035/ Petitioner has previously been reimbursed by the Department

5612for all expenses associated with developing the CAR and those

5622expenses are not at issue in this case.

56306/ Mr. Hidle's field notes (Petitioner's Exhibit 5) reflect that

5640he left the office at 11:30 a.m., November 30, 1993; arrived at

5652the job at 1:30 p.m.; departed the job at 2:30 a.m., December 1,

56651993; and, arrived at the office at 3:15 a.m.

56747/ Mr. Hidle's field notes (Petitioner's Exhibit 5) reflect that

5684he and the technician left the office at 7:45 p.m., December 4,

56961993; arrived at the job site at 8:25 p.m.; departed the job site

5709at 3:40 a.m., December 5, 1993; and arrived at the office at

57214:30 a.m.

57238/ Each water sample was analyzed in accordance with EPA

5733Method 602 and some of the samples, but not all, were tested in

5746accordance with EPA Methods 610 and 418.1, as well as for lead.

57589/ Mr. Hidle's field notes (Petitioner's Exhibit 5) reflect that

5768he left the office (to load equipment) at 10:00 a.m., June 15,

57801994, arrived at the job site at 1:15 p.m., departed the job site

5793at 10:00 p.m., and arrived at the office at 11:00 p.m., where

5805unloading was completed at 11:30 p.m. The notes reflect the

5815technician arrived separately (at the job-site) at 1:15 p.m. and

5825departed at 10:00 p.m.

582910/ The Department's concession may have been generous; however,

5838it is accepted.

5841COPIES FURNISHED:

5843George M. Hidle, President

5847Panhandle Industries, Inc.

5850Post Office Box 11983

5854Fort Lauderdale, Florida 33339-1983

5858J. A. Spejenkowski, Esquire

5862Department of Environmental Protection

58663900 Commonwealth Boulevard

5869Mail Station 35

5872Tallahassee, Florida 32399-3000

5875Kathy Carter, Agency Clerk

5879Department of Environmental Protection

58833900 Commonwealth Boulevard

5886Mail Station 35

5889Tallahassee, Florida 32399-3000

5892F. Perry Odom, General Counsel

5897Department of Environmental Protection

59013900 Commonwealth Boulevard

5904Mail Station 35

5907Tallahassee, Florida 32399-3000

5910NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

5916All parties have the right to submit written exceptions within 15

5927days from the date of this Recommended Order. Any exceptions to

5938this Recommended Order should be filed with the agency that will

5949issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
Date: 03/29/1999
Proceedings: Final Order filed.
PDF:
Date: 03/26/1999
Proceedings: Agency Final Order
PDF:
Date: 03/26/1999
Proceedings: Recommended Order
PDF:
Date: 02/22/1999
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 12/02/98.
Date: 01/13/1999
Proceedings: Letter to Judge Kendrick from Petitioner Re: Certificate of Service on Proposed Findings of Fact filed.
Date: 01/07/1999
Proceedings: (Petitioner) Proposed Findings of Fact filed.
Date: 01/06/1999
Proceedings: Department of Environmental Protection`s Proposed Recommended Order; Disk filed.
Date: 12/28/1998
Proceedings: Notice of Filing; (Volumes 1 and 2 of 2) DOAH Court Reporter Final Hearing Transcript filed.
Date: 12/08/1998
Proceedings: CASE STATUS: Hearing Held.
Date: 12/02/1998
Proceedings: Letter to G. Hidle from J.A. Spejenkowski (RE: response to document supplemental) (filed via facsimile).
Date: 12/02/1998
Proceedings: (Petitioner) Notice and Certificate of Deliverance of Supplemental Interrogatories and/or Documents filed.
Date: 11/30/1998
Proceedings: Order sent out. (respondent to deliver responses to amended interrogatories by 12/1/98)
Date: 11/25/1998
Proceedings: (Respondent) Notice of Change of Agency Position filed.
Date: 11/23/1998
Proceedings: Respondent`s Response to Petitioner`s "Motion to Disallow Respondent`s Request of November 16, 1998"filed.
Date: 11/19/1998
Proceedings: (Petitioner) Motion to Compel; Notice and Certificate of Service of Interrogatories; Petitioner`s Amended Interrogatories to Respondent (Set 1) filed.
Date: 11/19/1998
Proceedings: (Petitioner) Motion to Disallow Respondent`s Request of November 16, 1998; Notice of Intent to Present Similar Fact Evidence at Hearing filed.
Date: 11/16/1998
Proceedings: Department of Environmental Protection`s Notice of Answers to Petitioner`s First Set of Service of Interrogatories; Respondent`s Responses to Petitioner`s Interrogatories (Set 1) filed.
Date: 11/16/1998
Proceedings: (J. Spejenkowski) Notice of Intent to Present Similar Fact Evidence at Hearing filed.
Date: 11/16/1998
Proceedings: Respondent`s Response to Petitioner`s Request for Documents (Set 1) filed.
Date: 11/12/1998
Proceedings: (DEP) Notice of Hearing; (Respondent) Emergency Motion for Status Conference Concerning Discovery filed.
Date: 10/19/1998
Proceedings: (Petitioner) Request for Production of Documents (Set I) filed.
Date: 10/19/1998
Proceedings: (Petitioner) Notice and Certificate of Service of Interrogatories; Petitioner`s Interrogatories to Respondent (Set I) filed.
Date: 10/13/1998
Proceedings: (Petitioner) Notice and Certificate of Deliverance of Interrogatories and Documents; Respondent`s Interrogatories to Petitioner (Set 1) ; Request for Production of Documents (Set 1) filed.
Date: 09/08/1998
Proceedings: Request for Production of Documents (Set 1) filed.
Date: 09/08/1998
Proceedings: Notice and Certificate of Service of Interrogatories filed.
Date: 09/01/1998
Proceedings: Notice of Hearing sent out. (hearing set for 12/8/98; 9:00am; Tallahassee)
Date: 08/27/1998
Proceedings: Joint Response filed.
Date: 08/17/1998
Proceedings: Initial Order issued.
Date: 08/12/1998
Proceedings: Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Petition for Formal Hearing; Agency Action Letter filed.

Case Information

Judge:
WILLIAM J. KENDRICK
Date Filed:
08/12/1998
Date Assignment:
08/17/1998
Last Docket Entry:
03/29/1999
Location:
Tallahassee, Florida
District:
Northern
Agency:
ADOPTED IN TOTO
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (4):

Related Florida Rule(s) (2):