99-000307
Bernard M. Campbell And Bessie H. Campbell vs.
Southern Hy Power Corporation And Department Of Environmental Protection
Status: Closed
Recommended Order on Thursday, March 2, 2000.
Recommended Order on Thursday, March 2, 2000.
1STATE OF FLORIDA
4DIVISION OF ADMINISTRATIVE HEARINGS
8BERNARD M. CAMPBELL and )
13BESSIE H. CAMPBELL, )
17)
18Petitioners, )
20)
21vs. ) Case No. 99-0307
26) OGC No. 98-3033
30SOUTHERN HY POWER CORPORATION )
35and STATE OF FLORIDA, DEPARTMENT )
41OF ENVIRONMENTAL PROTECTION, )
45)
46Respondents. )
48_________________________________)
49SARAH E. BERGER, )
53)
54Petitioner, )
56)
57vs. ) Case No. 99-0308
62) OGC No. 98-3022
66SOUTHERN HY POWER CORPORATION )
71and STATE OF FLORIDA, DEPARTMENT )
77OF ENVIRONMENTAL PROTECTION, )
81)
82Respondents. )
84_________________________________)
85SARAH E. BERGER, )
89)
90Petitioner, )
92)
93vs. ) Case No. 99-0694
98) OGC No. 99-0244
102SOUTHERN HY POWER CORPORATION )
107and STATE OF FLORIDA, DEPARTMENT )
113OF ENVIRONMENTAL PROTECTION, )
117)
118Respondents. )
120_________________________________)
121BERNARD and BESSIE CAMPBELL, )
126)
127Petitioners, )
129)
130vs. ) Case No. 99-0696
135) OGC No. 99-0247
139SOUTHERN HY POWER CORPORATION )
144and STATE OF FLORIDA, DEPARTMENT )
150OF ENVIRONMENTAL PROTECTION, )
154)
155Respondents. )
157_________________________________)
158RECOMMENDED ORDER
160A hearing was held pursuant to notice, on September 22
170through 24, 1999, in Inglis, Levy County, Florida, and on
180November 1 and 2, 1999, in Tallahassee, Florida, by Stephen F.
191Dean, assigned Administrative Law Judge of the Division of
200Administrative Hearings.
202APPEARANCES
203For Petitioners: John S. Clardy III, Esquire
210Post Office Box 2410
214Crystal River, Florida 34426-2410
218For Respondent Southern Hy Power Corporation:
224Daniel H. Thompson, Esquire
228Berger, Davis & Singerman
232215 South Monroe Street, Suite 705
238Tallahassee, Florida 32301
241For Respondent Department of Environmental Protection:
247Andrew Zodrow, Esquire
250Department of Environmental Protection
2543900 Commonwealth Boulevard
257Mail Station 35
260Tallahassee, Florida 32399-3000
263STATEMENT OF THE ISSUE
267Whether Southern Hy Power Corporation (Hy Power) has
275provided reasonable assurance, based on plans, test results, or
284other information, that its proposed h y droelectric facility will
294comply with the Management and Storage of Surface Water (MSSW)
304statutes and rules of Southwest Florida Water Management District
313(SWFWMD) and the Wetland Resource Management permit (WRM)/water
321quality certification statutes and rules of the Florida
329Department of Environmental Protection (DEP).
334PRELIMINARY STATEMENT
336Hy Power applied to DEP on August 31, 1993, for a WRM
348pe r mit/water quality certification to construct a hydroelectric
357f a cility on the Inglis By-Pass Channel immediately to the south
369of the spillway located on the Inglis Bypass Channel within the
380Town of Inglis, Levy County, Florida. On January 5, 1998, DEP
391issued a Notice of Denial of the Environmental Resource Permit.
401The re a sons for the denial included a finding that the
413application was incomplete and that the applicant failed to
422provide reasonable assu r ances that the proposed project would
432comply with the MSSW prov i sions of Part IV of Chapter 373,
445Florida Statutes, and the rules adopted thereu n der.
454In response to the notice of denial, Hy Power filed on
465Jan u ary 20, 1998, a motion for extension of time to file a
479petition for administrative proceeding to challenge the denial.
487In add i tion, on August 4, 1998, Hy Power filed with DEP an
501application for a MSSW permit. On November 6, 1998, DEP issued a
513Notice of Intent to Issue MSSW permit application number 38-
5230129249-002 to Hy Power to construct and operate its proposed
533hydroelectric f a cility. On December 21, 1998, DEP issued a
544Notice of Intent to issue WRM permit application number 38-
5542370696-3.001 for the pr o posed facility.
561On November 21, 1998, Ms. Berger filed a petition for formal
572administrative proceedings objecting to DEPs intent to issue the
581MSSW permit to Hy Power. On November 23, 1998, the Campbells
592filed a petition also challenging DEPs intent to issue the MSSW
603permit. On February 2, 1999, the Cam p bells filed a petition
615challenging that intent. DEP r e ferred the petitions to DOAH. On
627February 8, 1999, Ms. Berger also filed a petition for formal
638administrative pr o ceedings objecting to DEPs intent to issue the
649WRM permit to Hy Power to construct the facility. On March 18,
6611999, an order was entered consolidating the four petitions.
670WITNESSES
671Hy Power called the following witnesses: Richard Volkin,
679who was accepted as an expert in the areas of engineering and
691dra w ing, construction and operation of hydroelectric facilities,
700i n cluding analysis of environmental impacts associated with such
710facilities; and Douglas Smith, who was accepted as an e x pert in
723the area of environmental engineering with special expe r tise in
734geology and hydrogeology.
737DEP called the following witnesses: Ken Huntington, who was
746accepted as an expert in the areas of Environmental Resource
756Pe r mitting criteria, and environmental impacts of dredge and fill
767projects and activities; Randy Cooper, who was accepted as an
777expert in the areas of civil engineering, surface water h y drology
789and MSSW permitting criteria; Mercily Toledo, who was accepted
798as an expert in the areas of enviro n mental impacts of dredge and
812fill activities and wetland resource management permitting
819criteria; Eric Shaw, who was a c cepted as an expert in Outstanding
832Florida Water (OFW) water body classifications; Joe May, who was
842accepted as an expert in the areas of geology and hydrogeology;
853Mary Duncan, who was accepted as an e x pert in the areas of
867permitting issues with respect to impacts on the West Indian
877Manatee and the activities regulated by DEP; and Louie
886Wainwright, who is the administrator of field operations for the
896DEP Office of Greenways and Trails.
902Petitioners called the following witnesses: Linda Sloan,
909who was accepted as an expert on the requirements of the
920Comprehe n sive Plan of Inglis and Levy County; Stephen Wilson, who
932was accepted as an expert in the field of land surveying; James
944C. Bitter, who was accepted as an expert in occup a tional safety
957and technology; Bill Edwards, who was a c cepted as an expert in
970the areas of coffer dams and construction of concrete structures
980in aquatic and semi-aquatic environments; Stephen Boyes, who was
989accepted as an expert in g e ology and hydrogeology; Gary Maidhof,
1001who was accepted as an expert in the Citrus County Manatee
1012Protection Plan; David Gammon, who is Manager of Purchase Power
1022Resources for Florida Power Corporation; Kenton Lambert, who is a
1032mai n tenance and construction specialist for the DEP office of
1043Gree n ways and Trails; Bessie Campbell, one of the Petitio n ers;
1056and Sarah E. Berger, one of Petitioners.
1063EXHIBITS
1064The parties entered 12 joint stipulated exhibits into
1072ev i dence. Hy Power entered 12 e x hibits at hearing and one late-
1087filed exhibit after the hearing had adjourned. DEP entered eight
1097exhibits into evidence. Petitioners entered 15 exhibits into
1105evidence, and proffered one exhibit, a Land Surveyors Drawing,
1114which was not accepted into evidence.
1120PREHEARING STIPULATION
1122The parties filed a Joint Prehearing Stipulation on or about
1132September 22, 1999, which stipulated certain issues of law and
1142fact that described the parties to this proceeding and the
1152pro j ect that is at issue. These stipulations are included or
1164inco r porated by reference as findings of fact and conclusions of
1176law in this Recommended Order.
1181STIPULATED ISSUES OF LAW
1185The parties stipulated that pre-Environmental/Resource
1190Permitting statutes and rules (ERP) are applicable to these WRM
1200and MSSW permit proceedings. The following pre-ERP statutes and
1209rules are being utilized, relevant portions of which are set
1219forth below in Section 403.918, Florida Statutes (1991); and
1228Chapter 40D-4, Florida Administrative Code (in effect prior to
1237October 3, 1995) along with Basis of Review incorporated therein.
1247The parties also stipulated to the following:
1254Jurisdiction
1255The Di vision of Administrative Hearings has
1262juri s diction over the parties to and the subject matter
1273of this proceeding pursuant to Chapter 120, Florida
1281Statutes.
1282MSSW and WRM Permitting Criteria Generally
1288Since Hy Power filed its WRM permit application on
1297August 31, 1993, the statutes and rules applicable to
1306this proceeding are those which were in effect prior to
1316the promulgation of Environmental Resource Permitting
1322Rules by DEP on October 3, 1995, as described more
1332fully below. See Section 373.414(9), Florida Statutes.
1339MSSW Permitting Criteria
1342The criteria for review for the MSSW permit is
1351contained in Rule 40D-4.301, F.A.C., as it existed on
1360or before October 3, 1995, which stated as follows:
136940D -4.301 Conditions for Issuance of
1375Permits.
1376(1) In o rder to obtain an individual
1384construction and operation permit under this
1390chapter, an applicant must give reasonable
1396assurances that the surface water management
1402system:
1403(a) provide adequate flood protection
1408and drainage,
1410(b) will not cause adverse wat er quality
1418and quantity impacts on receiving waters and
1425adjacent lands regulated pursuant to Chapter
1431373, Florida Statutes,
1434(c) will not cause discharges which
1440r e sult in any violation, in surface waters of
1450the state, of the applicable standards and
1457crit e ria of Chapter17-3, and Rule 17-4.242,
1465(d) will not cause adverse impacts on
1472surface and groun d water levels and flows,
1480(e) will not diminish the capability of
1487a lake or other impoundment to fluctuate
1494through the full range established for it in
1502Chapter 40D-8.
1504(f) will not cause adverse environmental
1510impacts, or adverse impacts to wetlands, fish
1517and wildlife, or other natural r e sources,
1525(g)can be effectively operated and
1530mai n tained,
1533(h) will not adversely affect public
1539health and safety,
1542(i) is consistent with the requirements
1548of other public age n cies,
1554(j) will not otherwise be harmful to
1561w a ter resources within the District,
1568(k) will not interfere with the legal
1575rights of others as defined in Rule 17-40.07,
1583and
1584(l) is not against pub lic policy.
1591(2) The standards and criteria contained
1597in the Basis of Review adopted by reference
1605in Rule 40D-4.091(1) apply to the design and
1613performance of surface water management
1618sy s tems to provide the reasonable assurances
1626r e quired under Rule 40D-4.301(1). Other
1633met h ods of meeting overall objectives may be
1642pr o posed and may be considered in determining
1651whether the applicant has provided the
1657re a sonable assurances required by Rule 40D-
16654.301(1).
1666DEP AUTHORITY
1668DEP has the authority to administer the SWFWMD
1676MSSW permitting rules pursuant to an interagency
1683agre e ment with SWFWMD and §373.026, Florida Statutes.
1692WRM PERMITTING CRITERIA
1695The criteria for the WRM permit application
1702a s pects of this case are governed by Chapter 403, Part
1714VIII, the "Warren S. Henderson Wetland Protection Act
1722of 1984," including Section 403.918, Florida Statutes.
1729(1991), which states in relevant part as follows:
1737(1) A permit may not be issued under
1745ss. 403.91-403.929 unless the applicant
1750pr o vides the department with reasonable
1757assu r ance that water quality standards will
1765not be violated. . . .
1771(2) A permit may not be issued under
1779ss. 403.91-403.929 unless the applicant
1784pr o vides the department with reasonable
1791assu r ance that the project is not contrary to
1801the public interest. However, for a project
1808which significantly degrades or is within an
1815Outstanding Florida Water, as provided by
1821d e partment rule, the applicant must provide
1829reasonable assurance that the project will be
1836clearly in the public interest.
1841(a) In determining whether a project is
1848not contrary to the public interest, or is
1856clearly in the public interest, the
1862depar t ment shall consider and balance the
1870following criteria:
18721. Whether the project will adversely
1878affect the public health, safety, or welfare
1885or the property of others;
18902. Whether the project will adversely
1896affect the conservation of fish and wildlife,
1903including endangered or threatened species,
1908or their habitats;
19113. Whether the project will adversely
1917affect navigation or the flow of water or
1925cause harmful erosion or shoaling;
19304. Whether the project will adversely
1936affect the fishing or recreational values or
1943marine productivity in the vicinity of the
1950project;
19515. Whether the project will be of a
1959temporary or pe r manent nature;
19656. Whether the project will adversely
1971affect or will enhance significant historical
1977and archaeological resources under the
1982prov i sions of s. 267.061; and
19897. The current condition and relative
1995value of functions being performed by areas
2002affected by the proposed activity.
2007(b) If the applicant is unable to
2014ot h erwise meet the criteria set forth in this
2024subsection, the department, in deciding to
2030grant or deny a permit, shall consider
2037mea s ures proposed by or acceptable to the
2046appl i cant to mitigate adverse effects which
2054may be caused by the project. . . .
2063The WRM permitting criteria are also governed by
2071Rule Chapters 62-4 (Permits), 62-302 (Surface Water
2078Quality Standards), 62-312 (Dredge and Fill Activities)
2085and 62-521 (Wellhead Protection), Florida
2090Administrative Code.
2092The u se of the property to generate hydroelectric
2101power is compatible with Section 253.7829(2), Florida
2108Statutes, which states:
2111The development of hydroelectric power is a
2118compatible use of greenway land and may be
2126considered by the Board of Trustees of the
2134Internal Improvement Trust Fund as an
2140allo w able use within the greenways of Lake
2149Rou s seau and the lower Withlacoochee River,
2157pr o vided that such hydroelectric power
2164complies with all requisite state and federal
2171enviro n mental and water management standards.
2178POST-HEARING
2179An original Transcript has been filed with the Division of
2189Administrative Hearings. Both sides filed proposed findings in
2197the form of Proposed Recommended Orders which were read
2206considered. Counsel for Petitioners, John S. Clardy, withdrew as
2215counsel, and an order was entered striking certain of
2224Petitioners' pleadings as an improper and untimely effort to
2233adduce additional evidence relating to the credibility of
2241witnesses.
2242FINDINGS OF FACT
2245STIPULATED FINDINGS OF FACT
22491. By Joint Prehearing Stipulation the parties agreed to
2258the following description of the pa r ties and the project:
2269PARTIES:
22702. The Department of Environmental Protection (the
2277Department) is a government agency in the State of Florida
2287existing by virtue of Section 20.255, Florida Statutes, and
2296operating pursuant to Chapters 253, 373, 376, and 403, Florida
2306Statutes, and T i tle 62, Florida Administrative Code. Under an
2317interagency agreement with SWFWMD, the Department also implements
2325Title 40D, Florida Administrative Code. The Department is
2333located in Tallahassee, Florida, and it has a district office in
2344Tampa, Florida, which district includes Levy County.
23513. Southern Hy Power Corporation is a Florida Corporation
2360whose principal offices are located at 7008 Southwest 30th Way in
2371Gainesville, Florida.
23734. Betty Berger is an interested party with a mailing
2383a d dress of Post Office Box 83, Inglis, Florida.
23935. The Campbells are an interested party with a mailing
2403a d dress of 245 Palm Street, Inglis, Florida.
24126. Hy Power applied on A ugust 31, 1993, to the Department
2424for a WRM permit/water quality certification to construct a
2433h y droelectric facility on the Inglis By-Pass Channel. The
2443pro j ect is located in Section 12, Township 17 South, Range 16
2456East, within the town of Inglis in Levy County. The facility
2467consists of a powerhouse located on the south side of the channel
2479measu r ing about 28 feet wide by 115 feet long, drawing water from
2493the Inglis By-Pass Channel, passing it through a single-pit type
2503tu r bine and discharging downstream of the Inglis By-Pass Spillway
2514Dam.
25157. Hy Power applied on August 4, 1998, to the Department
2526for a MSSW permit for the same proposed hydroelectric facility on
2537the Inglis By-Pass Channel.
2541DESCRIPTION OF PROPOSED PROJECT
25458. The project involves the construction of an intake
2554structure, powerhouse, and tailrace on a 0.61-acre area located
2563on the south side of the existing Inglis By-Pass Spillway. The
2574facility will take advantage of the existing hydrostatic head
2583that exists on either side of the Spillway Dam, to generate
2594ele c tricity.
25979. The powerhouse will be constructed below grade and will
2607contain a single megawatt turbine and generating unit. The
2616i n take structure will divert flows from the upstream side of the
2629Spillway Dam through the powerhouse and back into the By-Pass
2639Channel. A small one-story control building and low profile
2648su b station will be constructed above grade within the boundaries
2659of the project area.
266310. The hydroelectric project is considered to be a "Run of
2674the River" type of facility because it can only use that water
2686which flows down the existing channel. The geometry of the
2696cha n nel restricts flow to a certain amount, therefore the project
2708cannot create or use flows above those that the By-Pass Channel
2719can provide. The overall authority for control of water levels
2729in Lake Rousseau and flow to the lower Withlacoochee River will
2740remain with the DEP.
274411. Lake Rousseau was created in 1909 when the Inglis Dam
2755was constructed across the Withlachoochee River for the purposes
2764of hydroelectric generation. The dam impounds over 11 miles of
2774the Withlachoochee River and forms a lake approximately 3,000 to
27854,000 acres in size. Prior to construction of the Barge Canal,
2797water released from the Inglis Dam would flow down the lower
2808po r tion of the Withlachoochee River about 10 miles before
2819entering into the Gulf of Mexico.
282512. In the mid to late 1960's the Army Corps of Engineers
2837(ACOE) built a portion of the Cross Florida Barge Canal between
2848the Gulf of Mexico and Lake Rousseau. The canal severed the
2859Withlachoochee River dow n stream of the Inglis Dam causing its
2870flow to be diverted into the Barge Canal and then into the Gulf.
2883In order to maintain the flow of freshwater from Lake Rousseau to
2895the lower segment of the River, the 8,900-foot long Inglis By-
2907Pass Channel and Spil l way were constructed. The resulting
2917downstream flow ensures navigation in the lower portion of the
2927River and sustains its freshwater and estuarine environment.
293513. The water level in Lake Rousseau is generally
2944mai n tained at an elevation of 27.5 feet above mean sea level
2957(msl) by a combination of the Inglis Dam, the Inglis Lock, which
2969is located in the Barge Canal, and the By-Pass Channel Spillway.
2980These water control features are known collectively as the Inglis
2990Project Works. The water levels in the lower Withlachoochee
2999River immediately to the west of the By-Pass spillway are close
3010to sea level. The resulting head provides the potential energy
3020needed to drive the proposed generator turbine. Under normal
3029conditions the majority of water released from Lake Rousseau
3038flows over the Spillway Dam into the lower segment of the River.
3050According to the DEP Office of Greenways and Trails (OGT), the
3061maximum capacity of the existing By-Pass Channel Spillway is
30701,540 cubic feet per second. The hydroelectric project will
3080divert whatever flow is allowed around the existing spillway
3089through the turbine and back into the channel.
309714. When the Cross Florida Barge Canal project was
3106cancelled in the 1990's, the ACOE transferred owne r ship of the
3118property to the State of Florida Board of Trustees, who in turn
3130has leased the property to the DEP for use as the Cross Florida
3143Greenbelt State Recreation and Conservation Area. Management of
3151this property, the control of river flow and lake levels, and
3162operation of the Inglis Project Works are exercised by the DEP's
3173OGT. The OGT utilizes a document entitled "Water Control Plan
3183for Inglis Project Works," dated September 1994, as a guide to
3194operating the structures. The Water Control Plan is incorporated
3203as part of the MSSW intent to issue.
321115. On or about April 25, 1995, the Governor and Cabinet,
3222sitting as the Board of Trustees of the Internal Improvement
3232Trust Fund ("Trustees"), approved a request from Hy Power to
3244su b lease 0.61 acres of Greenway property at the project site for
3257the purpose of providing electric power. The request was
3266challenged by Berger and the Campbells, and resulted in an
3276administrative hearing held on November 3, 1995.
328316. As a result of the hearing, Administrative Law Judge
3293Larry Sartin entered a Recommended Order on July 12, 1996, that
3304the Board enter an order approving execution by the DEP of the
3316proposed sublease and dismissing the petition of Berger and the
3326Campbells. The Recommended Order was approved by the Trustees in
3336its entirety in a Final Order dated April 12, 1996 ("Final
3348O r der"). Berger v. Southern Hy Power Corporation et al. , Case
3361No. 95-3589.
336317. A copy of the Final Order is listed as an exhibit to
3376this Stipulation, and the Findings of Fact and Conclusions of Law
3387co n tained therein are adopted herein. As previously ruled by the
3399undersigned, the previous Final Order is res judicata as to
3409Petitioners in this case, who are collaterally estopped from
3418challenging any of the findings of fact or conclusions of law
3429contained in the previous Final O r der. Petitioners reserve the
3440right to litigate issues of fact and law not addressed in the
3452Findings of Fact or Conclusions of Law contained in that Final
3463Order with regard to the permittabi l ity of this project under the
3476WRM and MSSW permitting proposals, and to raise objections as to
3487relevance to this proceedings of any of the Findings of Fact or
3499Conclusions of Law in the Final Order.
350618. On February 21, 1995, Hy Power filed application with
3516the Federal Energy Regulatory Commission (FERC) for a conduit
3525exemption from the licensing requirements of Part I of the
3535Fe d eral Powers Act (FPA) for the proposed project. Petitioners
3546and various other persons filed protests with FERC in opposition
3556to the project.
355919. On April 21, 1997, FERC issued an Order Granting
3569Co n duit Exemption, a copy of which is listed as an exhibit to
3583this Stipulation. Petitioners in this case are collaterally
3591estopped from challenging any of the findings or conclusions
3600contained in that Order Granting Conduit Exemption. Petitioners
3608reserve the right to litigate issues of fact and law not
3619addressed in the Findings of Fact or Conclusions of Law contained
3630in that Order Granting Conduit Exemption with regard to the
3640permittability of this project under the WRM and MSSW permitting
3650proposals, and to raise objections as to relevance to this
3660proceedings of any of the findings or co n clusions in the Order
3673Granting Conduit Exemption.
3676FACTS ADDUCED AT HEARING
3680OUTLINE OF PROJECT
368320. The proposed project calls for the construction of a
3693water retention structure along the existing By-Pass spillway,
3701the excavation of a large hole in which the powerhouse and
3712turbine would be constructed "in-the-dry" south of the existing
3721dam, and a millrace below the proposed project to return the
3732water back into the existing water course.
373921. Conflicting testimony was received regarding the facts
3747surrounding the construction of the project. These included:
3755whether the proposed project will touch the existing wing walls
3765of the existing dam; whether the water retention structure is a
3776coffer dam; whether the proposed water retention structure will
3785safely retain the water; whether the powerhouse and turbine have
3795sufficient negative buoyancy to stay in the ground; whether the
3805proposed excavation will weaken the existing dam; and whether the
3815de-watering of the excavation site will adversely impact ground
3824and surface water.
3827PROJECT DESIGN AND ENGINEERING
383122. Engineering for the project was directed by witness
3840Richard A. Volkin, a professional engineer and president and CEO
3850of Engineering Company, Inc., based in Canton, Massachusetts.
3858Mr. Volkin has extensive national and international e x perience in
3869the design, management, and operation of hydroelectric
3876facilities.
387723. Other engineers in Mr. Volkins firm worked on the
3887pr o ject under Mr. Volkins direct supervision, including John
3897May, who became registered as a professional engineer in Florida
3907in order to sign and seal the engineering drawings for the
3918project, which he initially did around 1994. Mr. May became ill
3929and r e tired in 1998.
393524. Because of the length of time the application process
3945has taken and the fact that Mr. May retired, there was a time
3958while the application was pending, when Hy Power's design team
3968was without a registered Florida engineer. When this was brought
3978to the attention of Hy Power, Hy Power substituted Steven
3988Crockett for Mr. May as the Florida-registered professional
3996engineer of record for the project. DEP routinely accepts an
4006applicants changing its e n gineer of record during the course of
4018permit application or co n struction.
402425. Mr. Crockett is a civil and structural engineer who has
4035considerable experience in preparing dam structural designs.
4042Mr. Crockett independently reviewed and evaluated the engineering
4050drawings for the project. Mr. Crockett resealed the dra w ings by
4062using his drawn seal and signing the plans because his embossed
4073seal was not readily available and time was of the essence.
4084Mr. Crockett has advised DEP that he is now engine er of record
4097for the project, using the appropriate DEP forms.
410526. Mr. Volkins firm performed all of the studies required
4115by the various agencies, including a geotechnical study of the
4125area, a 50-year analysis of water flow in and out of the Lake
4138Rousseau regime, and water quality evaluations of water in the
4148By-Pass Channel.
415027. The ACOE performed deep hole borings of the soils
4160(a p proximately 36-40 feet below sea level) in the area of the
4173pro j ect site to determine soil stabilization conditions at the
4184site when they were constructing the Inglis Project Works. The
4194soil conditions found can reasonably be expected to be similar
4204today.
420528. Mr. Volkins company also took its own eight-foot deep
4215surface core samples. The purpose of those samples was to verify
4226the ACOE data. The new core samples verified the original core
4237samples.
423829. Mr. Volkin also reviewed the ACOEs engineering
4246dra w ings developed from construction of the Spillway Dam. These
4257show that the dam is founded on limestone bedding that has been
4269stabilized with concrete. The hydroelectric facility will be
4277constructed adjacent to and south of the dam structure and
4287adjacent to and north of the barge canal. The same type of
4299limestone bedrock is found in the area of the proposed
4309construction.
431030. The facility design includes an intake channel on the
4320upstream channel and a tailrace downstream. Those are the only
4330structures that will be constructed next to the By-Pass Channel.
434031. The construction of the facility itself will be "in the
4351dry." Hy Power will use coffer dams to seal off the construction
4363site from the By-Pass Channel, so that there will not be water
4375leakage from the Channel into the construction site. Water from
4385the By-Pass Channel will enter the power plant when the coffer
4396dams are lifted and the water is a l lowed to flow into the
4410facility.
441132. The Petitioners presented the testimony of Bill
4419Edwards, an individual with considerable experience in the
4427construction of bridges, cofferdams, and similar concrete
4434structures in aquatic and semi-aquatic conditions. Mr. Edwards
4442is a former hard-hat diver who worked all over the world and
4454worked in Florida for many years prior to his retirement. Based
4465upon his experience and expertise in construction related to
4474projects of this type, his testimony is credible and worthy of
4485consideration.
448633. Mr. Edwards pointed out that if the proposed water
4496retention structure did not touch the wing wall of the existing
4507dam, it could not keep the water out and would not have the
4520strength that it needed to retain the water.
452834. Hy Powers witnesses explained that the retention
4536structure would be set close enough to the existing wing wall
4547that waterproofing materials could be placed between the two
4556structures to keep the water out. Further, that the existing
4566plans did not show interior bracing which would be included for
4577structural strength and integrity. In sum, the retention
4585structure will be in contact with existing dams wing wall, but
4596will be free standing and not dependent upon the strength of the
4608wing wall for its strength.
461335. Mr. Edwards pointed out that a cofferdam by definition
4623has walls on all sides of the structure. The structure proposed
4634by Hy Power did not have walls all the way around the proposed
4647excavation. In rebuttal, Hy Power presented evidence that its
4656plans were conceptual, design drawing and not construction plans.
4665Hy Power represented that in actuality it would put as many walls
4677as were necessary to keep the water out of the hole it intended
4690to excavate.
4692a sh racks will be constructed at the intake
4701stru c tures to protect aquatic life and make sure that trash and
4714veg e tation do not enter the intake structure or go down river.
4727The trash rack bars will be two inches on center, which the U.S.
4740Fish and Wildlife Service has determined as the appropriate size
4750for the protection of fish.
475537. The turbine blades are "double regulated," and ope r ate
4766generally between 60 and 90 revolutions per minute. The d e sign
4778enables the turbine to operate at a constant speed to gene r ate a
4792consistent flow of electricity, notwithstanding the fact that the
4801flow of the water may vary. The blade speed is not very fast,
4814and the 2.5-meter blades pr o vide a two to three-foot opening.
4826This design acts to prevent fish mortality.
483338. Ther e are four ways to shut off the flow of water
4846through the proposed structure: close the pitch of the blades,
4856close the wicket gates, allow the counter balance to the wicket
4867gates to kick in and automatically close the gates, and close off
4879the main gates. This is a fail safe system ("four level
4891r e dundancy") designed to work upon any failure.
490139. Once water goes through the generator, its velocity is
4911reduced to no greater than its intake rate which is a maximum of
4924three feet per second. This prevents the water being di s charged
4936from the tailrace from causing erosion. If the head of water in
4948the dam produces a flow exceeding three feet per second, it can
4960be diverted over the other dams which will be functional.
497040. The power plant will be encased in con crete, except for
4982a small access way that enables a person to go down a set of
4996stairs to the plant. It will be a sealed, waterproof structure,
5007as required by FERC and the ACOE. This will prevent penetration
5018of groundwater, or flood waters in the event a ma s sive flood
5031overtops the plant. The only water entering the powerhouse will
5041be through the turbine tunnel for power ge n eration purposes.
505241. Mr. Edwards pointed out that the powerhouse was a
5062closed structure and as such would have positive buoyancy, that
5072is, it would float. Mr. Edwards pointed out that the proposed
5083site is between the barge canal and By-Pass spillway and there is
5095a great deal of groundwater and potentiometric pressure in the
5105existing water table. In sum, there is a unlimited supply of
5116groundwater at the site, and powerhouse could float out of the
5127ground just like an empty swimming pool. Hy Power presented
5137rebuttal evidence that the weight of the building, the turbine,
5147and the water flowing through the turbine would be close to
5158negative buoyancy, and they would add additional weight to the
5168structure as necessary to keep it in place.
517642. The project is designed to generate three megawatts of
5186electric power which is enough electricity to serve between 300
5196and 3000 homes, depending on usage.
520243. The project is designed to be unmanned. This is common
5213for facilities such as this. The plant can be operated by remote
5225control, unlike the existing controls at the By-Pass Dam, which
5235are operated manually. DEP can access, monitor, and control
5244remotely the generator's operation to include shutting the
5252facility down at any time.
525744. There will be remote sensors to monitor water
5266elev a tions. Flood protection will improve because of the ability
5277of DEP to manage water flow from a remote location. If there is
5290any major disruption, the plant will shut itself down.
529945. The project is classified as "green power." In other
5309words, it generates natural energy without any disruption to the
5319environment.
532046. The project will have minimal to no impact on the
5331env i ronment. There will be no significant changes in water
5342quality compared to existing conditions as a r e sult of either
5354construction or operation of the facility.
5360WRM Permit Criteria
536347. Hy Power has provided reasonable assurances that the
5372proposed project will not cause a violation of state water
5382qua l ity standards of Section 403.918(a), Florida Statutes (1991).
5392The parties stipulated that turbidity and dissolved oxygen were
5401the two surface water quality issues of concern in this
5411procee d ing.
541448. The receiving water body is the Inglis By-Pass Channel.
5424The Inglis By-Pass Channel is a Class III surface water. The
5435project is not l o cated in a OFW. While the lower Withlacoochee
5448River is an OFW, the OFW designation runs up the natural river
5460itself, and does not include the Spillway Dam, tailrace, or the
5471remainder of the By-Pass Channel. There would be no degradation
5481of water quality at the point of contact with the Withlacoochee
5492River OFW.
549449. The DEP and FERC looked specifically at potential for
5504tu r bidity and dissolved oxygen in determining whether the project
5515would violate state water quality standards. The standards for
5524turbidity and dissolved oxygen will not be violated.
553250. Because the By-Pass Dam is an under flow structure, a
5543minimum of oxygenation currently occurs as water flows through
5552the existing dam. The proposed project runs the water
5561underground through the generator; however, Hy Power will measure
5570the dissolved oxygen below the dam in the Lower Withlacoochee
5580River. In the event there is any lowering of dissolved oxygen,
5591Hy Power can install a "sparge ring" to reoxygenate the water
5602going through the turbine so that dissolved oxygen remains at
5612current levels.
561451. No turbidity will be added to the receiving water as a
5626result of the project, because water velocity is low and the
5637structure is encased in concrete and rip-rap.
564452. The only other potential for turbidity would occur when
5654the coffer dams are removed after construction is co m plete. The
5666coffer dams can be removed with the generator closed to permit
5677any turbidity to settle. The amount of siltation that might
5687occur when the generator is opened would be insignificant.
569653. Where a project is not in a OFW, an applicant must
5708pr o vide reasonable assurance that the project will not be
5719contrary to public interest. See Section 403.918(2), Florida
5727Statutes (1991). Hy Power has provided such assurances.
573554. The project will not directly affect public health,
5744safety or welfare, or the property of others. See Section
5754403.918 (2)(a)1., Florida Statutes. There are concerns relating
5762to the structural integrity of the proposed facility and adjacent
5772structures which are discussed extensively below.
577855. The project will have no adverse impact upon the
5788co n servation of fish and wildlife, including threatened and
5798enda n gered species and their habitat. See Section 403.918
5808(2)(a)2., Florida Statutes.
581156. While manatees are not likely to be found at the
5822pro j ect site, the installation of the trash racks will eliminate
5834any potential adverse impact on manatees. In fact, the racks
5844will be an improv e ment over the current unprotected Spillway Dam.
5856DEP procedures require a specific manatee control plan be
5865implemented to deal with site specific concerns.
587257. The project will not adversely affect navigation or the
5882flow of the water or cause harmful erosion or shoaling. See
5893Section 403.918(2)(a)3., Florida Statutes.
589758. The project will not adversely affect fishing or
5906re c reation values or marine productivity in the vicinity of the
5918pr o ject. See Section 403.918(2)(a)4., Florida Statutes.
592659. The perm a nent project and its construction will cause
5937no significant environmental impacts. See Section
5943403.918(2)(a)5., Florida Statutes.
594660. There will be no adverse impacts to significant
5955hi s torical and archeological resources. Section 403.918(2)(a)6.,
5963Florida Statutes.
596561. With regard to the impact on current conditions and
5975relative value of functions being performed by the areas affected
5985by the proposed activity, there will be no negative impacts. See
5996Section 403.918(2)(a)7., Florida Statutes. Improvement will
6002result from better control of water flow at the project site,
6013installation of trash racks and implementation of green power.
6022THE FORESEEABLE ADVERSE SECONDARY OR CUMULATIVE IMPACTS
602962. Potential adverse secondary impacts related to power
6037transmission are addressed through the fact that there is an
6047existing power line corridor that can be used to transmit the
6058electricity. Any need to change the corridor could be addressed
6068by subsequent DEP permi t ting. Cumulative impacts are not at
6079issue.
608063. Mr. Gammon, with Florida Power, acknowledged that the
6089current electric company, presumably Florida Power, would be
6097r e quired by FERC to transport the electricity generated by Hy
6109Power over its existing corridor and poles.
611664. No final decision has been made regarding how to acces s
6128the site with equipment during construction. Several feasible
6136construction options exist, and there are se v eral ways of
6147accessing the site with heavy equipment vehicles and without
6156impacting wetlands. Any final dec i sion would be subject to DEP
6168approval.
616965. Since the project meets the public interest criteria of
6179Section 403.918(2)(a), Florida Statutes, and wetland impacts are
6187minimal, the project is permittable without the need for
6196mitigation. See Section 403.918(2)(b), Florida Statutes.
620266. The ACOE has issued a permit for the facility. The
6213permit varies slightly from the DEP intent to issue in the use of
6226reinforced concrete rather than rip-rap on the bottom half of the
6237intake channel. This is to comply with ACOE prefe r ence, but the
6250variation has only an environmental benefit.
625667. Counsel for Petitioners sought to elicit testimony from
6265Linda Sloan, Executive Director of the Withlacoochee Regional
6273Planning Council, with regard to compliance of the proposed
6282pro j ect with the Town of Inglis Comprehensive Plan and Land
6294Develo p ment Code. Such compliance is not relevant to this
6305proceeding. At any rate, Ms. Sloan conceded that any prohibition
6315that might apply in the Land Development Code to construction of
6326the pr o posed facility could potentially be alleviated by
6336exemption or variance provisions in the Code.
6343MSSW PERMIT CRITERIA
634668. The project will provide adequate flood protection and
6355drainage in the conventional sense. See Rule 40D-4.301(1)(a),
6363Florida Administrative Code. Because the amount of impervious
6371area is minimal, runoff from the project will not in any way
6383contribute to increased flooding or adversely impact drainage
6391pa t terns.
639469. The total amount of impervious area of the facility is
6405less than that of a single-family residence. SWFWMD rules do not
6416even require MSSW permits for single-family res i dences because
6426the impact is not significant. The only purpose for requiring a
6437MSSW permit for the project is to review the projects potential
6448downstream impacts to the watershed, not stormwater runoff from
6457the facility itself.
646070. The project will not cause adverse water quality or
6470w a ter quantity impacts on adjacent lands in violation of Chapter
6482373, Florida Statutes, or cause a discharge that violates state
6492water quality standards. See Rule 40 D-4.301(1)(b), Florida
6500Administrative Code.
650271. As indicated by the WRM water quality findings above,
6512the project will not generally violate state surface water
6521quality sta n dards. See Rule 40 D-4.301(1)( c), Florida
6531Administrative Code.
653372. The project will not generally cause adverse impact on
6543surface or groundwater levels or flows. See Rule 40 D-
65534.301(1)(d), Florida Administrative Code.
655773. Since the project is a run-of-the-river, it will not
6567diminish the capability of a lake or other impoundment to
6577fluct u ate through the full range established for it under Chapter
658940D-8, Florida Administrative Code.
659374. The project will not cause adverse environmental
6601i m pacts, or adverse impacts to wetlands, fish, and wildlife or
6613other natural resources.
661675. The project can be effectively operated and maintained.
6625See Rule 40D-4.301(1)(g), Florida Administrative Code. The
6632project is a slow speed, low maintenance facility. The design
6642concept is well established and has been successfully used for
6652many years.
665476. Possible adverse affects to public safety are discussed
6663below.
666477. The project is consis tent with the requirements of
6674other public agencies. See Rule 40D-4.301(1)(i), Florida
6681Administrative Code.
668378. Potential harm to water r e sources within the SWFWMD are
6695discussed below. See Rule 40D-4.301(1)(j), Florida
6701Administrative Code.
670379. Th e proposed project generally will not interfere with
6713the legal rights of others. See Rule 40D-4.301(1)(k), Florida
6722Administrative Code.
672480. The proposed project is not against public policy. See
6734Rule 40D-4.301(1)(l), Florida Administrative Code.
673981. The project complies with the requirements contained in
6748the Basis of Review. See Rule 40D-4.301(2), Florida
6756Administrative Code.
675882. There is a dispute as to whether the project was within
6770or at the edge of the 100-year flood plain. This dispute is
6782related to how one interprets the rule as it relates to the
6794millrace and the location of the facility which is under ground.
6805In the conventional sense, the project is not in the flood plain.
6817Further, the project is designed in such a way, that it is
6829waterproof if it were topped with water.
683683. While in the past SWFWMD may have had concerns that the
6848project might cause downstream flooding, SWFWMD currently has no
6857such concerns, given the run-of-the-river status of the proposed
6866project. The operation of the project will not cause downstream
6876flooding.
687784. The DEP included in its intent to issue, conditions
6887co n tained in the sublease between Hy Power and the DEP in order
6901to ensure that the facility would remain run-of-the-river, would
6910comply with the water control plan, and would otherwise comply
6920with the terms of the sublease. The DEP has final control over
6932water flow and can revoke the permit or othe r wise take
6944enforcement action against Hy Power if Hy Power fails to comply
6955with the water control plan.
6960GROUNDWATER IMPACTS
696285. Operation of the project will not cause groundwater
6971contamination or otherwise have adverse groun d water impacts.
6980Some concerns about groundwater during excavation of the
6988construction site were raised. The conflicting evidence received
6996regarding them is discussed below.
700186. An area of concern was the de-watering plan for the
7012project. Everyone agrees there will be some water seepage into
7022the construction site that will have to be pumped out. The
7033parties disagree regarding the amount of water that will have to
7044be removed. Their estimates of amount of water to be removed
7055vary because their estimates of size and over-all depth of the
7066site vary.
706887. Petitioners presented credible evidence that a
7075potential exists for the construction site to have a large
7085quantity of water because of its location between two sources of
7096surface water (the By-Pass Channel and Barge Canal), because of
7106the makeup of the subsurface, and because of the depth of the
7118construction.
711988. Hy Power credibly represents that if excessive
7127groundwater is found, it can address the adverse impacts through
7137its de-watering plan that would have to be filed with FERC and
7149DEP. The technology exists to address the de-watering of the
7159project. Such plans are routinely considered by DEP after a
7169construction permit is issued and before de-watering occurs.
717789. There is very little evidence of sinkhole activity in
7187the project area, and the construction activities are not
7196e x pected to cause any sinkhole activity.
7204NOISE POLLUTION
720690. Mr. Bitter expressed concerns that FERC would require
7215the facility to install a very loud siren that would result in
7227sudden noise adverse to the well-being of neighbors. Mr. Bitter
7237is unfamiliar with FERC siren requirements at run-of the-river
7246hydroelectric facilities.
724891. In contrast, Mr. Volkin, who has substantial exper i ence
7259in this area, testified that the only alarm device that would be
7271required would be for the protection of the workers du r ing
7283construction.
728492. The purpose of the alarm is to warn persons below a dam
7297spillway of a change in the volume of water being let out of the
7311impoundment. In the case of a run-of-the-river facility, the
7320volume is near constant, changing only gradually.
732793. Therefore, even if a warning siren had to be installed
7338its use would be limited to significant changes in flow or
7349testing. This would not constitute a nuisance.
735694. Further, the facility is located in the vicinity of the
7367Crystal River Nuclear Power Plant which has its own warning
7377sirens. It would be prudent to make any warning devices required
7388for this structure significantly different from those at the
7397nuclear plant and to limit their use.
7404DAM SAFETY AND FERC REVIEW
740995. In reviewing whether Hy Powers applications complied
7417with the relevant permitting criteria, the DEP took into
7426consi d eration the review of the facility already performed by
7437FERC. FERC will also be responsible for reviewing the project as
7448it is being co n structed.
745496. Mr. Edwards also raised concerns about the structural
7463stability of the By-Pass Dam itself. This has been a subject of
7475concern by those responsible for the dam, and a survey of the
7487structure was conducted in 1993, referred to as the Greiner
7497Report.
749897. The Greiner Report identified specific maintenance
7505problems that have been and are being addressed by the DEP.
7516However, DEPs maintenance plan does not address specifically the
7525possibility that the weight of the dam over time has caused some
7537shifting in the dam.
754198. Hy Power has only a few core borings and only one at
7554the location of the generator. Hy Power is using the ACOEs
7565original borings, as confirmed by several new ones, to develop
7575its preliminary plans.
757899. The DEP considered FERC and the ACOE as responsible
7588agencies for determining the structural integrity of the dam.
7597DEP has taken FERCs review of this facility into consi d eration
7609as part of DEPs own permitting review. It is normal for DEP to
7622rely on outside sources and agencies for assistance in
7631determining compliance with DEP pe r mitting criteria such as
7641public health and safety, and it is reasonable for DEP to do so
7654in this instance. Most states do not have the full capability to
7666evaluate dam safety, and so they rely on FERC and ACOE.
7677100. On April 21, 1997, the pro ject received a conduit
7688e x emption from FERC. The application process is illu s trated in
7701Hy Power Exhibit 11.
7705101. Hy Power su b mitted to DEP detailed information about
7716the dam, the associated stru c tures and the proposed project which
7728had been reviewed by FERC and the ACOE, the two agencies in the
7741United States who are responsible for dam stru c ture design,
7752control, and administration. Included in the package was the
7761Greiner Report and Hy Powers review of it.
7769102. FERC evaluated the project, the In glis By-Pass Dam
7779structure, and the proximity of the project to the Dam in
7790relation to structural impact, upstream and downstream impacts,
7798water quality, and environmental issues.
7803103. Mr. Edwards raised concerns regarding the ability of
7812the limestone bedrock to sustain additional construction in the
7821area of proposed construction. This is a material issue in the
7832controversy which impacts several aspects of the proposed
7840construction.
7841104. Mr. Edwards pointed out that the barge canal channel
7851was constructed with the use of explosives that caused a
7861fracturing of limestone bedrock. He pointed out that the steel
7871panels, which Hy Power proposes to drive into the bedrock to
7882construct the water retention structure necessary to excavate the
7891hole into which the turbine and powerhouse would be placed, will
7902further fracture this bedrock. This creates two potential
7910dangers. It could permit water to move under and around the
7921bottoms of the panels, potentially scouring the loosened material
7930from the base of the panels and making them unstable and subject
7942to failure. It could weaken the entire southern wing of the
7953existing spillway dam. Mr. Edwards opined that this could result
7963in catastrophic failure of the dam or the coffer dam.
7973105. Such a failure would cause major destruction and loss
7983of life to those persons living and working in and along the
7995lower Withlacoochee River.
7998106. Hy Power presented rebuttal evidence that it could and
8008would, if necessary, inject concrete into the limestone to
8017stabilize it and avoid the concerns raised by Mr. Edwards.
8027107. FERC specifically evaluated concerns raised by project
8035opponents over the poor physical condition of the By-Pass Channel
8045Spillway structures, relying particularly on the 1993 Greiner
8053Report. FERC noted that the DEP had entered into a contract to
8065correct any deficiencies listed in the Greiner Report, which "did
8075not conclude that the deficiencies at the By-Pass Spillway
8084threaten downstream life and property."
8089108. The FERC review concluded that the dam was safe. To
8100ensure safety, FERC is requi r ing that Hy Power do a complete
8113stability analysis of the dam prior to any construction.
8122Articles 301 and 302 of the FERC exemption ensure that all final
8134drawings and specifications be submitted to FERC prior to
8143construction, along with a suppor t ing design report consistent
8153with FERCs Engineering Guidelines; that FERC can require changes
8162to assure a safe and adequate pro j ect; and that Hy Power must
8176also submit approved coffer dam co n struction drawings and
8186specifications at least 30 days prior to starting co n struction.
8197109. FERC has its own engineering staff who will go to the
8209site and do their own analysis, along with the ACOE, of the dam
8222and structures, prior to any construction commencing. This is a
8232detailed design review evaluation so that the latest information
8241on the dam will be made known immediately prior to co n struction,
8254and will prevent any catastrophic event from happe n ing. Under
8265FERC procedures, FERC requires the applicant to obtain the DEP
8275permits prior to requiring applicant to submit more detailed
8284constru c tion designs for FERC's consideration. These more
8293detailed designs in turn will be su b ject to further review by DEP
8307and FERC.
8309110. It is assumed that Hy Power will comply with the post-
8321permitting procedures and requirements, and will present
8328complete, detailed construction drawings for FREC and DEP
8336approval. Hy Powers failure to complete the process would
8345result in denial of a construction permit.
8352CONCLUSIONS OF LAW
8355111. The Division of Administrative Hearings has
8362jurisdi c tion over the parties to and the subject matter of this
8375procee d ing pursuant to Section 120.57(1), Florida Statutes.
8384The applicant has the burden of providing reasonable assurance
8393that the proposed project will not violate DEP Rules. Rule 62-
84044.070(1), Florida Administrative Code; Florida Department of
8411Transportation v. J.W.C. Company , 396 So. 2d 778 (Fla. 1st DCA
84221981).
8423112. The applicant's burden is "one of reasonable
8431assu r ances, not absolute guarantees." Manasota-88, Inc., v.
8440Agrico Chemical , 12 FALR 1319, 1325 (DER 1990). In assessing the
8451risk to resources, DEP is not required to assume a "worst case
8463scenario" unless such a scenario is "reasonably foreseeable."
8471Rudloe v. Gulf Specimen Co., Inc. v. Dickerson Bayshore, Inc. and
8482DER , 10 FALR 3426 (DER 1988). Reasonable assurances must deal
8492with reasonably foreseeable contingencies. The necessary
8498reaso n able assurance in a particular case that a proposed project
8510will comply with applicable air or water quality standards is a
8521mixed question of fact and law that must be made, in the final
8534anal y sis, by DEP. See, e.g., Sierra Club, et al. v. Department
8547of Env. Protection, et al ., 18 F.A.L.R. 2257, 2260 (Fla. DEP
85591996); Save Our Suwannee, Inc. vs. Piechocki and Dept. of Env.
8570Protection , 18 F.A.L.R. 1467, 1471 (Fla. DEP 1996); VQH
8579Development, Inc. v. Dept. of Environmental Protection, et al .,
858915 F.A.L.R. 3407, 3438 (Fla. DEP 1993); Barringer, et al v. E.
8601Speer and Associates, Inc., and Department of Environmental
8609Regulation , 14 F.A.L.R. 3660, 3667 n. 8 (Fla. DER 1992).
8619113. Simply raising "concerns" or speculation about what
"8627might occur" is not enough to carry a petitioner's burden. See
8638Chipola Basin Protective Group, Inc. v. Florida Department of
8647E n vironmental Protection , 11 F.A.L.R. 467, 480-81 (DER 1988).
8657Once the applicant has presented its evidence and made a
8667preliminary showing of reasonable assurances, the challenger must
8675present "contrary evidence of equivalent quality" to that
8683presented by the permit applicant. J.W.C. supra , 396 So. 2d at
8694789.
8695114. Thus, a permit applicant is not required by Florida
8705law to provide an "absolute guarantee" that a proposed project
8715will comply with all applicable air or water quality standards.
8725Piechocki , supra , 18 F.A.L.R. at 1472 (Fla. DEP 1996); Powell v.
8736U.S. Navy and Dept. of Env. Protection , 15 F.A.L.R. 3386, 3394
8747(Fla. DEP 1993).
8750115. No third party, merely by filing petition seeking
8759a d ministrative hearing, should be permitted to require an
8769applicant to completely prove anew all items in application "down
8779to [the] last detail." J.W.C. , supra , 396 So. 2d at 789. "The
8791Petitioner must identify the areas of controversy and allege a
8801factual basis for contention that the facts relied upon by the
8812applicant fall short of carrying the 'reasonable assurances'
8820burden cast upon the applicant." Id.
8826116. Under the system of regulation applicable to projects
8835of this type, the applicant obtains several permits from more
8845than one regulatory entity and from the same regulatory entity as
8856the project progresses. At the level this controversy is joined,
8866the applicant has not been able to address specifically each
8876concern raised by Petitioners; however, the applicant has
8884indicated that it must, in order to obtain added permits from
8895FERC and from DEP, present plans which do specifically address
8905these concerns. At this level of review, this constitutes
8914reasonable assurance under the regulatory scheme.
8920117. Rule 40D-4.301, Florida Administrative Code, requires
8927that in order to o b tain a permit "an applicant [for a MSSW
8941permit] must give re a sonable assurances" that the specific
8951permitting criteria will be met. As discussed in the Findings of
8962Fact section of this Recommended Order, Hy Power has provided
8972reasonable assurance that the proposed project will comply with
8981the MSSW permit r e quirements contained in Rule Chapter 40D-4,
8992Florida Administrative Code (in effect prior to October 3, 1995),
9002along with the Basis of Review inco r porated therein.
9012118. Under the permit criteria contained in Section
9020403.918, Florida Statutes (1991), and rules promulgated
9027thereunder, an applicant must first demonstrate that DEP water
9036quality standards will not be violated. Section 403.918(1),
9044Florida Statutes (1991). Hy Power has met that burden in this
9055proceeding.
9056119. Rule 62-4.242, Florida Administrative Code, applies
9063OFW standards to any proposed activity or discharge that is
9073within an OFW or signif i cantly degrades an OFW. Since discharge
9085from the project takes place outside of the Lower Withlacoochee
9095River OFW and will not significantly degrade the OFW, the OFW
9106permitting criteria do not apply, and DEP must determine whether
9116the project is not contrary to the public interest, based upon a
9128consideration and balancing of the seven fact tests set forth in
9139Section 403.918 (2)(a), Florida Statutes (1991).
9145120. Hy Power has provided reasonable assurance that the
9154proposed project is not co n trary to the public interest under
9166Section 403.918(2)(a), Florida Statutes (1991). This is
9173demonstrated both by the factual findings that there will be no
9184adverse impacts associated with the seven public interest
9192criteria, as well as the legislative findings in Section
9201253.7829(2), Florida Statutes, that development of hydroelectric
9208power is a compatible use of the project area.
9217121. The permitting agency cannot consider non-
9224environmental factors to reject a project under the "public
9233health, safety, or welfare or property of others" prong of the
9244public interest test. See Miller v. Department of Environmental
9253Regulation , 504 So. 2d 1325 (Fla. 1st DCA 1987); Taylor v. Cedar
9265Key Sewage Di s trict , 590 So. 2d 481 (Fla. 1st DCA 1991); Grove
9279Island, Ltd. v. Department of Environmental Regulation , 454 So.
92882d 571 (Fla. 1st DCA 1984); Counsel of the Lower Keys v. Charlie
9301Toppino and Sons, Inc. , 429 So. 2d 67 (Fla. 3rd DCA 1983). The
9314public interest test is limited in scope only to environmental
9324impacts associated with the seven factors set forth in Section
9334403.918(2)(a), Florida Statutes (1991), and that list of seven
9343factors is exclusive and exhaustive. Vo n Wagoner v. Department of
9354Transportation , 18 FALR 2277, 2285 (DEP 1996), affd sub nom ,
9364Save Anna Maria, Inc., v. Department of Transportation , 700
9373So. 2d 113, 116 (Fla. 1st DCA 1997).
9381122. In particular, DEP cannot consider whether a project
9390complies or does not comply with a local governments
9399comprehe n sive plan. Taylor , supra .; Charlie Toppino , supra .
9410Cf ., Florida Bay Initiative, Inc., et al. v. Fla. Dept. of
9422Transportation, et al ., 19 FALR 3712, 3719 (SFWMD 1997). The
9433issue of the proposed projects compliance with the Inglis
9442comprehensive plan and land development regulations is therefore
9450irrelevant to this procee d ing.
9456123. Petitioners have argued that the engineering diagrams
9464prepared on behalf of Hy Power should be stricken for two
9475reasons: first, they were not properly dated as required by
9485Section 471.025, Florida Statutes; and secondly, Mr. John May,
9494the original project engineer, no longer has a Florida P.E.
9504license.
9505124. DEP rules do not require that engineering drawings be
9515dated, only that they be signed and sealed. See Rule 62-
95264.050(3), Florida Administrative Code. The original drawings
9533were validly signed and sealed by Mr. May. The subsequent
9543drawings were signed and sealed by Mr. May, but he was no longer
9556registered in Florida. Furthermore, failure of an engineer to
9565date his drawings does not render them inadmissible. As stated
9575in Cape Development v. City of Cocoa Beach , 192 So. 2d 766, 769
9588(Fla. 1966), the law sets forth the procedure a professional
9598engineer may take to authenticate his drawings; it does not
9608purport to prescribe any requirements to make a drawing
9617admissible in ev i dence. Since the parties have stipulated that
9628authentication is not necessary for admissibility of documents
9636authentication is not at issue.
9641125. To the extent there was any technical d e ficiency in
9653the engineering drawings, they were cured by their being resealed
9663by Mr. Crockett, who also resealed the MSSW appl i cation so that
9676he would be designated as engineer of record. The Board of
9687Professional Engineers authorizes a successor profe s sional
9695engineer to adopt as his own the work of another engineer. See
9707Rule 61G15-27.001, Florida Administrative Code. In addition, DEP
9715rules authorize pe r mit modifications, see Rule 62-4.080(2),
9724Florida Administrative Code, and it is common for DEP to allow
9735engineering changes during the course of a pe r mit processing. To
9747require otherwise would be irrational and u n reasonable.
9756126. Petitioners have argued that the engineering drawings
9764do not have sufficient specificity to warrant a finding of
9774re a sonable assurance. Engineering drawings alone, however, are
9783not the only criteria for determining reasonable assurance.
9791Compare , for example, Hamilton County Commissioners v. TSI
9799Southeast , 12 FALR 3774, 3800 (DER 1990), affd sub nom , Hamilton
9810Co. v. State Dept. of Env. Reg. , 587 So. 2d 1378 (1st DCA 1991),
9824in which the Depar t ment concluded:
9831Although reasonable assurances can be shown
9837in part by having specific engineering
9843dra w ings and other design details in evidence
9852in support of an application, their absence
9859is not fatal to a showing of reasonable
9867assu r ances. Here, testimony by the
9874manufacturer, himself, who had extensive
9879experience with the installation, operation
9884and manufacture of such facilities as that
9891proposed . . . is, in the absence of evidence
9901to refute it, an adequate showing of
9908reasonable assurance that all emission
9913standards and the ambient air policy of DER .
9922. . will be met. Reasonable assurances can
9930be demonstrated by designs and plans stamped
9937appropriately by professional engineers
9941licensed in Florida, in part, and can also be
9950shown by competent expert test i mony, as was
9959done here.
9961Accord , Haile Community Association v. Fla. Rock Industries , 96
9970ER FALR 133 (DEP 1996).
9975127. Any additional information necessary to provide
9982reaso n able assurance that the proposed facility would comply with
9993the applicable permit standards can properly be provided at the
10003hea r ing. See McDonald v. Department of Banking and Finance , 346
10015So. 2d 569, 584 (Fla. 1st DCA 1977) (a petition for a formal
10028120.57 hearing commences a de novo proceeding , and because the
10038procee d ing is intended to formulate final agency action and not
10050to r e view action taken earlier and preliminarily, the hearing
10061officer may consider changes or other circumstances external to
10070the a p plication). See also Hamilton County Commissioners , supra ,
10080587 So. 2d at 1387; JWC , supra , 396 So. 2d at 787-788.
10092128. Petitioners have also objected to the DEPs reliance
10101on FERC in determining reasonable assurance. It is entirely
10110appr o priate, however, for the DEP to rely on the regulatory
10122decisions of other agencies in making its reasonable assurance
10131determin a tions Save Anna, supra , 700 So. 2d at 117. While the
10144cited district court opinion referred to DEPs reliance on a
10154permitting decision of SWFWMD, the underlying Final Order makes
10163clear that reliance on the public safety decision of another
10173agency, acting within the scope of its specific jurisdiction and
10183expertise, is also a p propriate:
10189[W]hen the Department weighs and balances
10195safety considerations in determining whether
10200proposed dredging and filling as part of a
10208DOT road project satisfies the [public safety
10215component of the] public interest balancing
10221test of former paragraph 403.918(2)(a) . . .,
10229DOTs opinion of the safety of the design
10237should be given great weight and acceptance
10244by the Department absent compelling evidence
10250of error or omission. Vonwagoner , supra , 18
10257FALR at 2288-2289. (Emphasis added.)
10262There was no compelling evidence of error or omission in this
10273case that would justify any disregard of FERCs determination
10282that the proposed project could be safely constructed.
10290129. No party has objected to the general and specific
10300co n ditions associated with the proposed permit. There is
10310sufficient basis in both fact and law to impose the requirements
10321as set forth in the general and specific conditions. Prudence
10331dictates that DEP require as part of the permitting and design
10342process, additional core borings in the area of intended
10351construction. This would be a source of needed information about
10361the stability of the limestone bedrock in that area and surface
10372water.
10373130. Because of the significant issues raised by
10381Petitioners and because of the catastrophic consequences of a dam
10391or coffer dam failure, special attention should be given to
10401review of the additional permits and to each of the concerns
10412raised by the Petitioners.
10416131. The sought permit, along with the incorporated ge n eral
10427conditions and specific conditions, to include those recommended
10435above, should be issued.
10439RECOMMENDATION
10440Based upon the foregoing Findings of Fact and Conclusions of
10450Law set forth herein, it is
10456RECOMMENDED:
10457That the DEP enter a Final Order that i s sues the two permits
10471challenged in this proceedings, WRM Permit No. 38-237096-3.001
10479and MSSW Permit No. 38-0129249-002, subject to the conditions
10488contained in the Intents to Issue in the r e spective WRM and MSSW
10502Permits and as described in the Recommended Order.
10510DONE AND ENTERED this 2nd day of March, 2000, in
10520Tallahassee, Leon County, Florida.
10524STEPHEN F. DEAN
10527Administrative Law Judge
10530Division of Administrative Hearings
10534The DeSoto Building
105371230 Apalachee Parkway
10540T allahassee, Florida 32399-3060
10544(850) 488-9675 SUNCOM 278-9675
10548Fax Filing (850) 921-6847
10552www.doah.state.fl.us
10553Filed with the Clerk of the
10559Division of Administrative Hearings
10563this 2nd day of Marc h, 2000.
10570COPIES FURNISHED:
10572Daniel H. Thompson, Esquire
10576Berger Davis & Singerman
10580215 South Monroe Street, Suite 705
10586Tallahassee, Florida 32301
10589Andrew Zodrow, Esquire
10592Department of Environmental Protection
105963900 Commonwealth Boulevard
10599Mail Station 35
10602Tallahassee, Florida 32399-3000
10605John S. Clardy, III, Esquire
10610Crider Law Firm
10613Plantation Point
10615521 West Fort Island Trail, Suite A
10622Crystal River, Florida 34429
10626Teri Donaldson, General Counsel
10630Department of Environmental Protection
106343900 Commonwealth Boulevard
10637Mail Station 35
10640Tallahassee, Florida 32399-3000
10643Kathy Carter, Agency Clerk
10647Department of Environmental Protection
106513900 Commonwealth Boulevard
10654Mail Station 35
10657Tallahassee, Florida 32399-3000
10660Bernard M. Campbell
10663Bessie H. Campbell
10666245 Palm Street
10669Post Office Box 159
10673Inglis, Florida 34449
10676Sarah E. Berger
10679Post Office Box 83
10683Inglis, Florida 34449
10686NOTICE OF RIGHT TO SUBMIT EXCEPTIONS
10692All parties have the right to submit written exceptions within 15
10703days from the date of this recommended order. Any exceptions to
10714this recommended order should be filed with the agency that will
10725issue the final order in this case.
- Date
- Proceedings
- Date: 05/17/2000
- Proceedings: Notice of Agency Appeal filed. (filed by: Petitioners)
- Date: 04/24/2000
- Proceedings: Final Order filed.
- Date: 03/14/2000
- Proceedings: Letter to Judge Smith from R. Spetz Re: Reasons for recinding the Hydro Plant on the Withlacoochee River filed.
- Date: 03/13/2000
- Proceedings: Letter to Judge Dean from R. Spetz Re: Hydro Plant filed.
- PDF:
- Date: 03/02/2000
- Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 09/22-24/99 and 11/1-2/99.
- Date: 02/25/2000
- Proceedings: (F. Ffolkes) Notice of Substitution of Counsel for Department of Environmental Protection filed.
- Date: 01/24/2000
- Proceedings: (B. & B. Campbell) Motion to Accept Post-Hearing Submittals filed.
- Date: 01/21/2000
- Proceedings: Order Granting Motion to Strike sent out.
- Date: 01/21/2000
- Proceedings: (D. Thompson) Motion to Strike and for Sanctions (filed via facsimile).
- Date: 01/19/2000
- Proceedings: (S. Berger) Motion filed.
- Date: 01/10/2000
- Proceedings: (D. Thompson) Response to Motion to Strike and Motion to Strike and for Sanctions (filed via facsimile).
- Date: 01/05/2000
- Proceedings: (Petitioners) Motion to Strike w/exhibits filed.
- Date: 01/05/2000
- Proceedings: (S. Berger, B. & B. Campbell) Public Comment Appendix w/exhibits filed.
- Date: 12/28/1999
- Proceedings: (D. Thompson) Motion to Strike Motion Not to Strike (filed via facsimile).
- Date: 12/27/1999
- Proceedings: (Petitioner) Motion Not to Strike filed.
- Date: 12/16/1999
- Proceedings: Motion to Strike (filed via facsimile).
- Date: 12/10/1999
- Proceedings: Letter to S. Berger from W. Schmidt Re: Investigation of the professional conduct of D. Smith; Letter to S. Berger from J. Ongley Re: Complaint (filed via facsimile).
- Date: 12/02/1999
- Proceedings: (J. Clardy) Notice of Withdrawal of Counsel; Petitioners` Proposed Recommended Order; Disk filed.
- Date: 11/30/1999
- Proceedings: Disk (Hy Power-DEP Joint PRO) filed.
- Date: 11/29/1999
- Proceedings: Joint Proposed Recommended Order of Southern Hy Power Corporation and Florida Department of Environmental Protection (For Judge Signature) filed.
- Date: 11/29/1999
- Proceedings: Notice of Filing Joint Proposed Recommended Order of Southern Hy Power Corporation and Florida Department of Environmental Protection filed.
- Date: 11/18/1999
- Proceedings: Notice of Filing; (Volumes 6-9 of 9) DOAH Court Reporter Final Hearing Transcript filed.
- Date: 11/12/1999
- Proceedings: (D. Thompson) Exhibits filed.
- Date: 11/01/1999
- Proceedings: CASE STATUS: Hearing Held.
- Date: 10/29/1999
- Proceedings: Motion to Strike (Respondent) filed.
- Date: 10/28/1999
- Proceedings: Letter to Judge Dean from Vicki Phillips (RE: opposition to any project which has the possibility of degrading the gorundwaters of Citrus County) filed.
- Date: 10/27/1999
- Proceedings: Petitioner`s Exhibits filed.
- Date: 10/08/1999
- Proceedings: Order Designating Hearing Location sent out.
- Date: 09/22/1999
- Proceedings: CASE STATUS: Hearing Partially Held, continued to 11/1/99; 9:30am; Tallahassee)
- Date: 09/10/1999
- Proceedings: Respondent Department of Environmental Protection`s Response to Petitioners` Second Request for Production of Documents (filed via facsimile).
- Date: 08/16/1999
- Proceedings: (J. Ckardy) Cettificate of Service on New Witnesses and further information on the case filed.
- Date: 08/16/1999
- Proceedings: (Petitioners) Notice and Certificate of Service of Petitioner`s Second Request for Production of Documents filed.
- Date: 07/16/1999
- Proceedings: (J. Clardy) Unopposed Motion for Continuance filed.
- Date: 07/09/1999
- Proceedings: Letter to Judge Dean from unsigned Re: Requesting subpoenas filed.
- Date: 06/23/1999
- Proceedings: (DEP) Notice and Certificate of Service of Answers to Interrogatories; Respondent Department of Environmental Protection`s Response to Petitioner Sarah E. Berger`s First Request for Production of Documents filed.
- Date: 06/18/1999
- Proceedings: Petitioners` Response to the Insufficiency of Respondent Southern HY Power`s Production of Documents and Motion to Compel Respondent Southern HY Power to Produce Documents filed.
- Date: 06/16/1999
- Proceedings: Petitioners` Response to the Insufficiency of Respondent Southern HY Power`s Production of Documents and Motion to Compel Respondent Southern HY Power to Produce Documents (filed via facsimile).
- Date: 06/08/1999
- Proceedings: Petitioner Sara E. Berger`s First Response to Request for Production of Documents filed.
- Date: 06/03/1999
- Proceedings: Order Granting Continuance and Re-scheduling Hearing sent out. (hearing set for September 22-24, 1999; 10:00am; Inglis)
- Date: 05/28/1999
- Proceedings: (Southern) Unopposed Motion for Continuance (filed via facsimile).
- Date: 05/26/1999
- Proceedings: (J. Clardy) Notice of Appearance; Petitioners` Response to Motion in Limine and Memorandum (filed via facsimile).
- Date: 05/25/1999
- Proceedings: (J. Clardy) Notice of Appearance (filed via facsimile).
- Date: 05/25/1999
- Proceedings: Petitioner Sarah E. Berger response to Respondents Southern HY Power Corporation and Florida State of Deparment of Environmental Protection request for manatee information (untitled) filed.
- Date: 05/24/1999
- Proceedings: Letter to Judge Dean from S. Berger Re: Responding to Daniel H. Thompson request to compel production of documents by Bernard & Bessie Campbell filed.
- Date: 05/24/1999
- Proceedings: Petitioner Sarah E. Berger gives notice to Respondents Southern HY Power and State of Florida Department of Protection that the issues in the MSSW Intent to Permit and the Wetland Resource Intent to Permit can be under five categories (untitled) filed.
- Date: 05/24/1999
- Proceedings: Petitioner Sarah E. Berger`s Responseto Respondent Department of Environmental Protection` Interrogatories; Motion to Only Have a Phone Conference filed.
- Date: 05/24/1999
- Proceedings: Petitioner Sarah E. Berger`s Response to Respondent Department of Environmental Protection Request for Production of Documents filed.
- Date: 05/24/1999
- Proceedings: Petitioner Sarah E. Berger Objects to Respondent Southern HY Power Corporation Objections to Her First Set of Interrogatories filed.
- Date: 05/24/1999
- Proceedings: (B. Campbell) Interrogatories Dated 4/23/99 DEP-Documents to be Produced"; Interrogatory II Dated 4/23/99 DEP First Interrogatories filed.
- Date: 05/20/1999
- Proceedings: (D. Thompson) Motion for Prehearing Conference; Motion in Limine and Memorandum filed.
- Date: 05/20/1999
- Proceedings: Respondent Southern HY Power Corporation`s Objections to Petitioner Sarah E. (Betty) Berger`s First Set of Interrogatories filed.
- Date: 05/17/1999
- Proceedings: Letter to Judge Dean from B. Campbell, S. Berger Re: Responding to D. Thompson request to compel production of documents (filed via facsimile).
- Date: 05/17/1999
- Proceedings: (S. Berger) Notice and Certificate of Service to Respondents Southern HY Power Corporation and State of Florida Department of Environmental Protection filed.
- Date: 05/17/1999
- Proceedings: (S. Berger) Notice and Certificate of Request for Production of Documents to Respondent State of Florida Department of Environmental Protection filed.
- Date: 05/17/1999
- Proceedings: (S. Berger) Notice and Certificate of of First Request for Production of Documents to Respondent Southern HY Power Corporation filed.
- Date: 05/17/1999
- Proceedings: Respondent Southern HY Power Corporation`s Amended Motion to Compel Answers to Interrogatories From Petitioners Bernard M.Campbell and Bessie H. Campbell (filed via facsimile).
- Date: 05/17/1999
- Proceedings: Respondent Southern HY Power`s Amended Motion to Compel Petitioners Bernard M. Campbell and Bessie H. Cambpell to Produce Documents (filed via facsimile).
- Date: 05/12/1999
- Proceedings: Letter to Mr.Thompson from B. & B. Campbell Re: Requesting legal status of Southern Hy Power and Hy Power Corporations (filed via facsimile).
- Date: 05/06/1999
- Proceedings: (S. Berger) Notice and Certificate of Service of Interrogatories to Respondent State of Florida Department of Environmental Protection filed.
- Date: 05/06/1999
- Proceedings: (S. Berger) Notice and Certificate of Seravice of Interrogatories to Respondent Southern HY Power Corporation filed.
- Date: 04/28/1999
- Proceedings: Respondent Southern HY Power Corporation`s Second Request for Production of Documents to Petitioner Sarah E. (Betty Berger filed.
- Date: 04/28/1999
- Proceedings: Respondent Southern HY Power Corporation`s Second Request for Production of Documents to Bernard M. Campbell and Bessie H. Campbell filed.
- Date: 04/27/1999
- Proceedings: Respondent Southern Hy Power`s Motion to Compel Petitioners Bernard M. Campbell and Bessie H. Campbell to Answer Interrogatories (filed via facsimile).
- Date: 04/27/1999
- Proceedings: Respondent Southern Hy Power`s Motion to Compel Petitioners Bernard M. Campbell and Bessie H. Campbell to Produce Documents (filed via facsimile).
- Date: 04/27/1999
- Proceedings: Respondent Southern Hy Powser`s Motion to Compel Petitioner Sarah E. Berger to Produce Documents (filed via facsimile).
- Date: 04/27/1999
- Proceedings: Respondent Southern Hy Power`s Motion to Compel Petitioner Sarah E. Berger to Answer Interrogatories (filed via facsimile).
- Date: 04/27/1999
- Proceedings: Letter to Judge Dean from B. Campbell (Re: request for subpoenas) (filed via facsimile).
- Date: 04/23/1999
- Proceedings: (DEP) Notice and Certificate of Service of Interrogatories to Petitioners, Bernard M. Campbell and Bessie H. Campbell filed.
- Date: 04/23/1999
- Proceedings: (DEP) Notice and Certificate of Service of Interrogatories to Petitioner, Sarah E. Berger filed.
- Date: 04/23/1999
- Proceedings: Respondent Department of Environmental Protection`s First Request for Production of Documents to Petitioner`s, Bernard M. Campbell and Bessie H. Campbell filed.
- Date: 04/23/1999
- Proceedings: Respondent Department of Environmental Protection`s First Request for Production of Documents to Petitioner, Sarah E. Berger filed.
- Date: 04/19/1999
- Proceedings: First Set of Interrogatories of Respondent Southern HY Power Corporation to Petitioners Bernard M. Campbell and Bessie H. Campbell filed.
- Date: 04/12/1999
- Proceedings: Letter to Judge Dean from S. Berger Re: Intent to permit by DEP filed.
- Date: 03/18/1999
- Proceedings: (D. Thompson) Notice of Propounding First Set of Interrogatories on Petitioner Sarah E. (Betty) Berger; Notice of Propounding First Set of Interrogatories on Petitioners Bernard M. Campbell and Bessie H. Campbell filed.
- Date: 03/18/1999
- Proceedings: Order of Consolidation andNotice of Hearing sent out. (Consolidated cases are: 99-000307, 99-000308, 99-000694, 99-000696; hearing set for June 9-11, 1999; Inglis)
- Date: 03/16/1999
- Proceedings: (D.Thompson) Notice of Propounding First Set of Interrogatories on Petitioners Bernard M.Cambpell and Bessie H. Campbell (filed via facsimile).
- Date: 02/24/1999
- Proceedings: (DEP) Motion to Consolidate (Cases requested to be consolidated: 99-307, 99-308, 99-694, 99-696) filed.
- Date: 02/10/1999
- Proceedings: Department of Environmental Protection`s Response to Initial Order filed.
- Date: 01/27/1999
- Proceedings: Initial Order issued.
Case Information
- Judge:
- STEPHEN F. DEAN
- Date Filed:
- 01/22/1999
- Date Assignment:
- 01/27/1999
- Last Docket Entry:
- 05/17/2000
- Location:
- Inglis, Florida
- District:
- Northern
- Agency:
- ADOPTED IN TOTO