99-002581 Clarence Rowe vs. Oleander Power Project, L.P., And Department Of Environmental Protection
 Status: Closed
Recommended Order on Monday, September 27, 1999.


View Dockets  
Summary: Applicant for air construction permit made a prima facie showing that the permit should be issued, and the opposing party failed to satisfy his burden of going forward with the requisite proof.

1STATE OF FLORIDA

4DIVISION OF ADMINISTRATIVE HEARINGS

8CLARENCE ROWE, )

11)

12Petitioner, )

14)

15vs. ) Case No. 99-2581

20)

21OLEANDER POWER PROJECT, L.P., and )

27DEPARTMENT OF ENVIRONMENTAL )

31PROTECTION, )

33)

34Respondents. )

36)

37RECOMMENDED ORDER

39An administrative hearing was conducted on August 30, 1999,

48in Viera, Florida, by Daniel Manry, Administrative Law Judge,

57Division of Administrative Hearings.

61APPEARANCES

62For Petitioner: Clarence Rowe, pro se

68418 Pennsylvania Avenue

71Rockledge, Florida 32955

74For Respondent, David S. Dee, Esquire

80Oleander Power Landers & Parsons

85Project, L.P.: 310 West College Ave nue

92Tallahassee, Florida 32301

95For Respondent, Scott A. Goorland, Esquire

101Department of W. Douglas Beason, Esquire

107Environmental Assistant General Counsel

111Protection: Department of Environmental Protection

116The Douglas Building

1193900 Commonwealth Boulevard

122Mail Station 35

125Tallahassee, Florida 32399-3000

128STATEMENT OF THE ISSUE

132The issue in this case is whether the Department of

142Environmental Protection ("DEP") should issue an air construction

152permit authorizing Oleander Power Project, L.P. ("Oleander"), to

162build and operate an electrical power plant in Brevard County,

172Florida, that includes five combustion turbines and two fuel oil

182storage tanks (the "Project").

187PRELIMINARY STATEMENT

189On November 24, 1998, Oleander filed an application with DEP

199for a permit authorizing the construction of certain stationary

208sources of airborne emissions (an "air construction permit"). On

218March 26, 1999, DEP issued a "Public Notice of Intent to Issue an

231Air Construction Permit" ("Public Notice"). The Public Notice

241included attachments comprised of DEP’s draft "Air Construction

249Permit" (Permit No. PSD-FL-258; DEP File No. 0090180-001-AC)(the

"257Draft Permit"), "Technical Evaluation and Preliminary

264Determination," and "Best Available Control Technology

270Determination."

271By letter dated April 12, 1999, Petitioner requested an

280administrative hearing. On June 9, 1999, DEP referred the matter

290to the Division of Administrative Hearings ("DOAH") to conduct an

302administrative hearing.

304On June 23, 1999, Oleander filed a motion to dismiss for

315failure to comply with requirements prescribed in the Public

324Notice for a petition for administrative hearing. After hearing

333argument from both parties by telephone conference, the motion to

343dismiss was granted with leave to file an amended petition no

354later than July 19, 1999.

359On July 19, 1999, Petitioner timely filed a Petition for

369Administrative Hearing (the "Petition"). On July 27, 1999, an

379administrative hearing was scheduled for August 25, 1999, and

388subsequently rescheduled for August 30, 1999.

394At the administrative hearing, Oleander presented the

401testimony of four witnesses, each of whom was accepted as an

412expert. Mr. Richard Zwolak was accepted as an expert in land-use

423planning, land-use compatibility analyses, and socioeconomic and

430environmental impact assessments. Mr. Ken Kosky was accepted as

439an expert regarding air pollution control and best available

448control technology. Mr. Bob McCann was accepted as an expert in

459meteorology, air quality dispersion modeling, and air pollution

467impact assessments. Mr. Al Linero was accepted as an expert in

478air pollution control issues, DEP regulations that govern new

487sources of air pollution, and air permitting. Oleander submitted

496Exhibits 1-3, 5-17, 19-32, and 34-46 for admission in evidence.

506DEP did not call any witnesses or submit any exhibits for

517admission in evidence. Petitioner presented the testimony of one

526witness who was not tendered as an expert. Petitioner submitted

536Exhibits 1-12 for admission in evidence.

542Petitioner's request for public comment was granted. Five

550individuals entered un-sworn public comment on the record. The

559individuals were not placed under oath or cross-examined because

568the agency stated that it did not propose to "consider such

579material" within the meaning of Section 120.57(1)(b), Florida

587Statutes (1997). (All chapter and section references are to

596Florida Statutes (1997) unless otherwise stated.)

602The Petition included allegations of "environmental

608injustice" and harm to Petitioner's extended family and their

617progeny. Those allegations had been previously stricken from the

626Petition in response to Oleander's motion. At the administrative

635hearing, Oleander attempted to introduce evidence concerning

"642environmental justice" issues. DEP objected to the introduction

650of such evidence on the ground that DEP does not have

661jurisdiction to consider issues of environmental justice. DEP’s

669objection was sustained, but Oleander was allowed to proffer its

679evidence concerning environmental justice.

683The identity of the witnesses and exhibits, and any

692attendant rulings, are set forth in the Transcript of the hearing

703filed on September 7, 1999. Petitioner did not file a proposed

714recommended order ("PRO"). Respondent timely filed its PRO on

725September 17, 1999.

728FINDINGS OF FACT

7311. Oleander seeks an air construction permit to build and

741operate an electrical power plant in Brevard County, Florida.

750Oleander provided reasonable assurances that the Project will

758comply with all of the conditions and emissions limitations

767prescribed by DEP in the Draft Permit.

7742. The Project received adequate review from the state

783agency responsible for regulating the Project. DEP reviewed

791Oleander’s application, requested and received additional

797information concerning the Project, and independently verified

804the impacts assessments contained in the application.

8113. The Project received adequate review from Brevard

819County. Oleander executed a Stipulated Settlement Agreement with

827Brevard County (the " Brevard County Agreement") in which Oleander

837agreed to comply with restrictions concerning the Project’s hours

846of operation, minimum buffers, noise, odor, vibrations, traffic,

854and other issues. The Brevard County Agreement provides

862additional assurances that the Project will not adversely impact

871the public.

8734. Members of the public received adequate notice of the

883Project and had sufficient opportunity to make public comments.

892On March 3, 1999, DEP held a public meeting in Brevard County to

905receive public comments regarding Oleander’s application. On

912March 26, 1999, DEP issued its Public Notice of DEP’s intent to

924grant the Draft Permit to Oleander. On April 8, 1999, DEP’s

935Public Notice was published in Florida Today . On May 13, 1999,

947DEP held a second public meeting in Brevard County to receive

958public comments concerning Oleander’s application. Members of

965the public had an opportunity during the administrative hearing

974to enter their comments on the record.

9815. The Project includes the construction and operation of

990five 190 megawatt ("MW") combustion turbines that will be used to

1003generate electricity. The Project also includes the construction

1011and use of two fuel oil storage tanks, two water storage tanks,

1023an administrative building, a stormwater management system, and

1031other associated and ancillary facilities.

10366. The Project is a "peaking" power plant. It will operate

1047only during times of peak demand caused by hot or cold weather or

1060storm events.

10627. The Draft Permit authorizes Oleander to operate the

1071Project’s combustion turbines for a maximum of 3,390 hours per

1082year, or approximately 39 percent of the available hours in a

1093year. During the remainder of the year, the combustion turbines

1103will not operate and will not have any airborne emissions. Based

1114on the historical experience of other peaking power plants in

1124Florida, the combustion turbines are expected to operate less

1133than 800 hours per year.

11388. Oleander’s combustio n turbines will be the most

1147advanced turbines used in Florida for peaking service.

1155Oleander’s turbines will be more efficient, in terms of emissions

1165and producing power, than the turbines currently used at other

1175peaking plants in Florida.

11799. The Projec t will use General Electric ("GE") Frame 7FA

1192combustion turbines. These turbines are capable of complying

1200with the emission limits and requirements in the Draft Permit.

1210Oleander will hire staff or train their own staff to operate the

1222Project in compliance with the Draft Permit. Oleander’s parent

1231company already has a training program for its plant operators.

1241Oleander has operated similar projects successfully.

124710. The primary fuel for the power plant will be natural

1258gas. Natural gas is the cleanest burning of all fossil fuels.

126911. In the event that natural gas becomes unavailable, the

1279Draft Permit authorizes use of low sulfur distillate fuel oil

1289("fuel oil") for the equivalent of 1,000 hours of full-load

1302operations per year. Fuel oil contains a maximum of 0.05 percent

1313sulfur, is 35 to 50 percent more expensive than natural gas, and

1325imposes economic incentives for Oleander to minimize the use of

1335fuel oil.

133712. Water needed for the Project will be provided by

1347the City of Cocoa. Oleander will not install any on-site wells

1358to supply water to the Project. All of the wastewater from the

1370Project will be sent by pipeline to the City of Cocoa’s

1381wastewater treatment plant. The Project will not discharge any

1390industrial wastewater on-site.

139313. The Projec t will be built on a site that is

1405located northeast of the intersection of Interstate 95 ("I-95")

1416and State Road ("SR") 520 in unincorporated Brevard County (the

"1428Site"). The Site contains approximately 38 acres of land.

143814. The Site is appropriate for use as an electrical power

1449plant. The Site already is zoned for industrial purposes. The

1459surrounding areas are primarily zoned for industrial uses. An

1468existing electrical substation is located on the north side of

1478the Site. An existing electrical transmission line corridor is

1487located on the west side of the Site. Townsend Road is located

1499on the south side of the Site. An existing natural gas pipeline

1511is located nearby, on the west side of I-95, and can provide gas

1524for the Project.

152715. Residential, commercial, and industrial development

1533within a three kilometer radius of the Site is minimal. The

1544Project will be compatible with those industrial and commercial

1553land uses that are located in the area near the Site.

156416. The closest residential areas are more than 1,400 feet

1575from the Site. The Site is compatible with the closest

1585residential neighborhoods. The Site and adjacent off-Site areas

1593provide a significant buffer to the closest residential areas.

1602The Site can be developed without causing adverse impacts on

1612residential areas.

161417. Combustion turbines currently operate at many

1621locations in diverse population centers in Florida. For example,

1630combustion turbines are operated within 800 feet of the Shands

1640Hospital at the University of Florida, within 1,200 feet of

1651Cinderella’s Castle at Disney World’s Magic Kingdom, and near the

1661Lake Worth High School. Combustion turbines also are located

1670near several residential neighborhoods in the state.

167718. DEP and Oleander evaluated the Project in accordance

1686with requirements prescribed in DEP’s Prevention of Significant

1694Deterioration (" PSD") program. As part of the PSD review, a

1706determination was made of the Best Available Control Technology

1715(" BACT").

171819. A BACT determination involves a case-by-case analysis

1726of those air pollution control technologies that are feasible and

1736can achieve the maximum emission reductions. A BACT

1744determination also requires an analysis of the costs,

1752environmental impacts, and energy impacts associated with the use

1761of each one of the proposed control technologies.

176920. A BACT determination results in the establishment of an

1779emission limit for each pollutant of concern. In this case, DEP

1790determined the appropriate BACT limits for the Project’s

1798emissions of carbon monoxide ("CO"), oxides of nitrogen (" NOx"),

1811sulfur dioxide (" SO 2 "), sulfuric acid mist ("SAM"), volatile

1824organic compounds (" VOCs"), particulate matter ("PM"), and

1835particulate matter less than ten microns in diameter (" PM 10 ").

1847(PM and PM 10 are referred to herein as "PM/ PM 10 . ") BACT emission

1863limits applicable to the Project are set forth in the Draft

1874Permit, and are incorporated by reference in this Recommended

1883Order.

188421. DEP determined that when the Project operates on

1893natural gas, BACT for NOx is an emission limit of 9 parts per

1906million (" ppm"), corrected to 15 percent oxygen. This emission

1917limit is based on the use of dry low NOx (" DLN") combustion

1931technology utilized in the combustion turbines included in the

1940Project. The proposed NOx emission limit of 9 ppm is the lowest

1952emission limit in Florida for simple cycle peaking power plants

1962and sets the standard for similar facilities throughout the

1971United States.

197322. DEP determined that when the Project operates on fuel

1983oil, BACT for NOx is an emission limit of 42 ppm, corrected to 15

1997percent oxygen. This emission limit is based on the use of DLN

2009and wet injection technology. Wet injection technology involves

2017the injection of either water or steam directly into the

2027combustor to lower the flame temperature and thereby reduce the

2037formation of NOx.

204023. The U.S. Fish and Wildlife Service (" USFWS") provided

2051comments to DEP concerning the Project. In their comments, the

2061USFWS suggested that the NOx emission limit should be 25 ppm when

2073the Project is operating with fuel oil. However, the USFWS’

2083suggestion was based on the USFWS’ misreading of the provisions

2093of other PSD permits. When read correctly, those permits

2102establish the same NOx emission limit when firing fuel oil that

2113DEP established in this case, i.e., 42 ppm.

212124. In its BACT determination, DEP considered whether a

2130selective catalytic reduction (" SCR") system should be used to

2141reduce the Project’s NOx emissions. SCR is an add-on NOx control

2152system in which ammonia is injected into the exhaust gases of a

2164combustion turbine. The exhaust gases are then exposed to a

2174catalyst where the ammonia and the NOx react to form nitrogen and

2186water.

218725. SCR does not represent BACT in this case and should not

2199be required for the Project. The use of SCR would impose

2210excessive costs on the Project, adversely impact the Project’s

2219energy efficiency, and cause increased emissions of particulate

2227matter and ammonia.

223026. BACT for CO and VOCs is based on the Project’s use of

2243an advanced combustor design, i.e., DLN technology, and good

2252combustion practices. The use of an oxidation catalyst for CO

2262removal is not required because an oxidation catalyst is not cost

2273effective for the Project. BACT for PM/ PM 10 , SO 2 , and SAM is

2287based on good combustion practices and the use of clean low

2298sulfur fuels.

230027. The PSD program establishes separate ambient air

2308quality standards for Class I and Class II areas defined in

2319Florida Administrative Code Rule 62-204.360(4). (Unless

2325otherwise stated, all references to rules are to rules

2334promulgated in the Florida Administrative Code in effect on the

2344date of this Recommended Order.) The Project is located in a

2355Class II area. The Project’s impacts on ambient air

2364concentrations will be below all applicable PSD standards

2372("increments") prescribed in Rule 62-204.260(2) for Class II

2382areas.

238328. The nearest PSD Class I area is the Chassahowitzka

2393Wildlife Refuge (the "Refuge"). The Refuge is approximately 180

2403kilometers from the Site. An analysis of the Project’s impacts

2413on the Refuge is not required because the Refuge is more than 150

2426kilometers from the Site. The impacts from the Project on the

2437closest Class I area are expected to be insignificant within the

2448meaning of Rule 62-204.200(29).

245229. DEP does not require Oleander to evaluate the

2461cumulative impacts caused by the Project and other major sources

2471of air pollution in the relevant Class II area. However,

2481Oleander evaluated the Project’s impacts together with the

2489impacts of the Florida Power & Light Cape Canaveral Plant, the

2500Orlando Utilities Commission’s Indian River Plant, and the

2508Orlando Utilities Commission’s Stanton Energy Center. The

2515Project itself will not have any measurable effect on the ambient

2526conditions resulting from the operation of all of these sources.

253630. DEP has adopted prima ry and secondary Ambient Air

2546Quality Standards (" AAQS") in accordance with requirements

2555adopted by the U.S. Environmental Protection Agency ("EPA").

2565Primary standards are designed to create an adequate margin of

2575safety for the protection of the public health, including the

2585health of the young, the old, and those with respiratory diseases

2596such as asthma. Secondary standards are designed to protect the

2606public welfare from any known or anticipated adverse effects of

2616air pollution. AAQS are reviewed every five years by scientists

2626and physicians in light of the most recent scientific studies and

2637data.

263831. In Brevard County, existing air quality is better than

2648levels allowed under AAQS. Brevard County is classified as an

2658attainment area.

266032. Oleander anal yzed the Project’s potential impacts on

2669ambient air quality in Brevard County in compliance with the

2679applicable DEP requirements for such an analysis. Oleander’s

2687analysis was based on conservative assumptions intended to over-

2696estimate impacts from the Project. For example, the analysis

2705assumed that the Project would operate continuously throughout

2713the entire year, even though the Project’s annual operations will

2723be limited to a maximum of 3,390 hours. In addition, Oleander

2735assumed that the Project would use fuel oil for the entire year,

2747even though the Project will be limited to firing fuel oil for a

2760maximum of 1,000 hours per year.

276733. The Project’s maximum impacts on ambient air quality

2776will be 0.6 percent or less of the applicable AAQS for each

2788criteria pollutant. Oleander's analysis demonstrates a wide

2795margin of safety for public health and welfare.

280334. The Project’s maximum potential impacts are less than

2812the EPA "significant impact" levels. Consequently, the Project’s

2820impacts are deemed insignificant from a regulatory perspective,

2828and more detailed analyses of the Project’s impacts on ambient

2838air quality are not required under applicable PSD requirements.

284735. The Project is not expected to cause any meaningful

2857impacts on air quality in any neighborhood in Brevard County. In

2868all neighborhoods, the Project’s impacts on air quality will be

2878insignificant. Similarly, the Project’s impacts on soils,

2885vegetation, wildlife, and visibility will be insignificant. The

2893Project also will not cause any significant growth-related air

2902quality impacts.

290436. The cumulative impacts from the Project and other

2913sources of air pollution in the area will be insignificant. When

2924all of these sources are considered together, the maximum impact

2934from their combined emissions will be 50 percent or less of the

2946applicable AAQS.

294837. The PSD program does not require Oleander to perform

2958any ambient air quality monitoring for any pollutant prior to the

2969time that construction of the Project commences because the

2978Project’s air quality impacts will be less than the applicable

2988DEP de minimis levels. Pre-construction monitoring for ozone is

2997not required unless a facility will have VOC emissions equal to

3008or greater than 100 tons per year. The Project’s maximum

3018potential VOC emissions will be 64 tons per year. Therefore, the

3029Draft Permit does not require Oleander to install any ozone

3039monitors.

304038. DEP maintains two ambient air quality monitors in

3049Brevard County to measure ozone concentrations. DEP also has

3058ambient air quality monitors for ozone in Volusia, Seminole,

3067Orange, Osceola, and St. Lucie Counties.

307339. The ambient air quality data from DEP monitors

3082demonstrate that the ozone concentrations in Brevard County are

3091below the applicable AAQS. Further, the data demonstrate that

3100ozone is a regional issue because the ozone levels in the region

3112tend to rise and fall at the same time and to the same degree.

312640. A requirement for Oleander to install an additional

3135monitor in Brevard County would be unnecessary and unjustified.

3144The impacts from the Project on ozone and other ambient air

3155quality parameters are so small that the impacts could not be

3166measured with an additional monitor. An additional monitor in

3175Brevard County would provide no meaningful benefits when

3183assessing whether Brevard County is meeting the AAQS for ozone

3193and would cost between $75,000 and $100,000 a year to install and

3207operate.

320841. Emissions from the Project will not cause any

3217significant impact on the water quality of water bodies in

3227Brevard County. There will be minimal, if any, "fallout" of

3237particles into nearby waters, including the St. Johns and Indian

3247Rivers.

324842. The maximum amount of nitrogen that could be deposited

3258annually as a result of airborne NOx emissions from the Project

3269is 0.0007 grams per square meter ("g/m 2" ). By comparison, the

3282current nitrogen deposition rate from other sources in the area

3292is 0.4 g/m 2 . Thus, the Project’s impact on nitrogen deposition

3304in the area will be only a fraction of the deposition that is

3317occurring already.

331943. Airborne emissions from the Project will not cause or

3329significantly contribute to a violation of any ambient air

3338quality standard or PSD increment. The Project complies with all

3348applicable DEP air quality requirements, including the applicable

3356policies, rules, and statutes.

3360CONCLUSIONS OF LAW

336344. The Division of Administrative Hearings has

3370jurisdiction over the subject matter and the parties. The

3379parties were duly noticed for the hearing.

338645. Oleander has the ultimate burden of proof in t his

3397proceeding. Florida Department of Transportation v. J.W.C. Co.,

3405Inc. , 396 So. 2d 778, 787 (Fla. 1st DCA 1981). Oleander also has

3418the initial burden of presenting prima facie evidence that

3427Oleander has complied with all of the applicable DEP standards

3437and rules. J.W.C. 396 So. 2d at 788.

344546. If Oleander presents the requisite prima facie

3453evidence, Petitioner must present "contrary evidence of

3460equivalent quality" proving the truth of the allegations in the

3470Petition. J.W.C. 396 So. 2d at 789. Petitioner cannot satisfy

3480his evidentiary burden with speculative concerns about potential

3488or possible adverse environmental effects. See Chipola Basin

3496Protective Group, Inc. v. Florida Chapter Sierra Club , 11

3505F.A.L.R. 467, 481 (DER Final Order, May 29, 1988); J.T. McCormick

3516v. City of Jacksonville , 12 F.A.L.R. 960, 971 (DER Final Order,

3527January 22, 1990); Altman v. Kavanaugh , 15 F.A.L.R. 1588, 1576

3537(DOAH Recommended Order, adopted in pertinent part by DER Final

3547Order, November 1, 1991).

355147. Oleander presented c ompetent substantial evidence that:

3559(a) DEP properly determined BACT for the Project; (b) airborne

3569emissions from the Project will not cause or significantly

3578contribute to a violation of any ambient air quality standard or

3589PSD increment; (c) airborne emissions from the Project will have

3599no significant adverse impacts on water quality in any surface

3609waters; (d) airborne emissions from the Project will not cause

3619any significant adverse impacts on human health or the public

3629welfare; (e) the Project satisfies applicable DEP rules and

3638criteria; and (f) DEP should issue the air construction permit

3648for the Project.

365148. Petitioner failed to present "contrary evidence of

3659equivalent quality" proving the truth of the allegations in the

3669Petition. Petitioner speculated about potential impacts from the

3677Project but presented no competent substantial evidence to

3685support the allegations in the Petition.

369149. During the administrative hearing, members of the

3699public were allowed to enter comments on the record in accordance

3710with Section 120.57(1)(b). In relevant part, Section

3717120.57(1)(b) provides:

3719When appropriate, the general public may be

3726given an opportunity to present oral or

3733written communications. If the agency

3738proposes to consider such material, then all

3745parties shall be given an opportunity to

3752cross-examine or challenge or rebut the

3758material. (emphasis supplied)

376150. DOAH is not the "agency" for purposes of Section

3771120.57(1)(b). DOAH is defined separately in Section 120.52(5) as

3780the "Division." DEP is the "agency" for purposes of Section

3790120.57(1)(b). Compare , Section 120.52(1)(defining an "agency")

3797with Section 120.52(5)(defining the "Division").

380351. At the administrative hearing, five individuals were

3811allowed to comment on the Project so that DEP would have the

3823opportunity to hear additional comments from the public before

3832DEP presented its recommendation at the final hearing regarding

3841the Project. The five members of the public were not sworn or

3853placed under oath because DEP stated that it did not propose to

3865consider such material.

386852. Unsworn testimony is not competent substantial evidence

3876and cannot be used as the basis for a finding of fact. See

3889Department of Environmental Regulation v. Chemairspray, Inc. , 520

3897So. 2d 96, 97 (Fla. 4th DCA 1988); Leon Shaffer Golnick

3908Advertising, Inc. v. Cedar , 423 So. 2d 1015, 1017 (Fla. 4th DCA

39201982)("[t] rial judges cannot rely upon . . . unsworn statements

3932as the basis for making factual determinations; and [an

3941appellate] court cannot so consider them on review of the

3951record"). Accordingly, the un-sworn comments made by the public

3961at the administrative hearing cannot form the basis for a finding

3972of fact in this case.

397753. Even if the public comments at the hearing had been

3988sworn testimony, the comments were not probative of the issues in

3999this case. The five individuals who made public comments were

4009not competent to express the opinions included in the public

4019comments. Most of the individuals readily acknowledged that they

4028are not experts regarding the subjects for which they offered

4038opinions. See Warriner v. Doug Tower, Inc. , 180 So. 2d 384 (Fla.

40503rd DCA 1965)(testimony of expert on one subject was properly

4060stricken where expert acknowledged he was not qualified to

4069express an opinion regarding the issue in dispute). None of the

4080individuals who offered comments at the administrative hearing

4088established the required special knowledge, skill, experience, or

4096training to be competent to offer opinion testimony on the

4106technical issues involved in the evaluation of the Project. See

4116also Sections 90.701 and 90.702. That portion of the public

4126comments not comprised of opinion consisted of speculative

4134concerns about either possible adverse environmental impacts or

4142possible economic consequences for private property.

414854. The Petition alleges that DEP should consider

"4156environmental justice" issues when DEP evaluates the Project.

4164Petitioner alleges that the proposed agency action is

4172inconsistent with the provisions of President Clinton’s Executive

4180Order 12898, entitled "Federal Actions to Address Environmental

4188Justice in Minority Populations and Low-Income Populations."

4195Executive Order 12898 is designed to focus the attention of

4205federal agencies on "environmental justice."

421055. Executive Order 12898 requires federal agencies to

4218identify and address those situations where federal programs,

4226policies, and activities have disproportionate adverse impacts on

4234minority or low-income populations in the United States.

4242Environmental justice complaints are also evaluated by EPA’s

4250Office of Civil Rights for compliance with Title VI of the Civil

4262Rights Act of 1964, when such complaints are based on allegations

4273of discrimination against minorities resulting from the issuance

4281of certain pollution control permits.

428656. The provisions of Executi ve Order 12898 are beyond the

4297scope of this proceeding and beyond the jurisdiction of DEP and

4308DOAH. Courts have consistently held that neither DEP nor DOAH

4318has jurisdiction to consider the provisions of Executive Order

432712898. See , e.g. , Council of the Lower Keys v. Charley Toppino

4338& Sons, Inc. , 429 So. 2d 67, 68 (Fla. 3rd DCA 1983)(issuance of

4351an air pollution permit by the Florida Department of

4360Environmental Regulation "must be based solely on compliance with

4369applicable pollution control standards and rules"; DER "is not

4378required or authorized" to deny such permit because of alleged

4388non-compliance with local zoning ordinances or land use

4396restrictions); Taylor v. Cedar Key Special Water and Sewerage

4405District , 590 So. 2d 481, 482 (Fla. 1st DCA 1991)(court adopted

4416holding in Council of the Lower Keys , above, with regard to a

4428water pollution permit, and then noted that "[r] emedies apart

4438from the permitting scheme are available" to address the

4447petitioner’s claims); see also Miller v. Department of

4455Environmental Regulation , 504 So. 2d 1325, 1327 (Fla. 1st DCA

44651987)(when considering whether a project would adversely affect

4473the "property of others," pursuant to DER’s statutory authority

4482in dredge and fill cases under Section 403.918(2), DER did not

4493err by concluding that DER should not extend its review to

4504include consideration of non-environmental impacts).

450957. The issue in this proceeding is whether the Project

4519complies with state requirements for the issuance of an air

4529construction permit. Applicable requirements are set forth in

4537Chapter 403 and Rules 62-4, 62-204, 62-210, 62-212, 62-214, 62-

4547296, and 62-297. Nothing in the relevant statutes or rules

4557allows either DEP or DOAH to enforce the requirements of

4567Executive Order 12898.

457058. The undersigned sustained DEP's objection to the

4578submission of evidence by Oleander relevant to environmental

4586justice issues. Consideration of such evidence would have lacked

4595jurisdiction and would have been contrary to the law of the case

4607established in previous rulings in this proceeding. Oleander

4615proffered evidence that addressed environmental justice issues

4622generally, as well as the Project’s direct compliance with

4631Executive Order 12898.

463459. Apart from any issue of environmental justice, Oleander

4643introduced competent substantial evidence to demonstrate that the

4651airborne emissions from the Project will not have any meaningful

4661adverse impacts on any neighborhood in Brevard County. In all

4671neighborhoods, the impacts from the Project’s emissions will be

4680insignificant. The evidence also shows that the Project will be

4690compatible with, and will not adversely affect, any residential

4699neighborhood. Residential neighborhoods are distant and well-

4706buffered from the Site.

4710RECOMMENDATION

4711Based upon the findings of fact and conclusions of l aw, it

4723is

4724RECOMMENDED that:

4726DEP enter a final order granting Oleander’s application for

4735an air construction permit for the Project, subject to the

4745conditions and limitations contained in the Draft Permit.

4753DONE AND ENTERED this 27th day of September , 1999, in

4763Tallahassee, Leon County, Florida.

4767___________________________________

4768DANIEL MANRY

4770Administrative Law Judge

4773Division of Administrative Hearings

4777The DeSoto Building

47801230 Apalachee Parkway

4783Tallahassee, Florida 32399-3060

4786(850) 488-9675 SUNCOM 278-9675

4790Fax Filing (850) 921-6847

4794www.doah.state.fl.us

4795Filed with the Clerk of the

4801Division of Administrative Hearings

4805this 27t h day of September, 1999.

4812COPIES FURNISHED:

4814F. Perry Odom, General Counsel

4819Department of Environmental Protection

4823The Douglas Building

48263900 Commonwealth Boulevard, Mail Station 35

4832Tallahassee, Florida 32399-3000

4835Kathy Carter, Agency Clerk

4839Office of General Counsel

4843Department of Environmental Protection

4847The Douglas Building

48503900 Commonwealth Boulevard, Mail Station 35

4856Tallahassee, Florida 32399-3000

4859Clarence Rowe

4861418 Pennsylvania Avenue

4864Rockledge, Florida 32955

4867David S. Dee, Esquire

4871Landers & Parsons

4874310 West College Avenue

4878Tallahassee, Florida 32301

4881W. Douglas Beason, Assistant General Counsel

4887Scott A. Goorland, Assistant General Counsel

4893Department of Environmental Protection

4897The Douglas Building

49003900 Commonwealth Boulevard, Mail Station 35

4906Tallahassee, Florida 32399-3000

4909NOTICE OF RIGHT TO SUBMIT EXCEPTIONS

4915All parties have the right to submit written exceptions within 15

4926days from the date of this Recommended Order. Any exceptions to

4937this Recommended Order should be filed with the agency that will

4948issue the Final Order in this case.

Select the PDF icon to view the document.
PDF
Date
Proceedings
PDF:
Date: 11/15/1999
Proceedings: Final Order filed.
PDF:
Date: 11/12/1999
Proceedings: Agency Final Order
Date: 10/12/1999
Proceedings: Department of Environmental Protection`s Exceptions to the Recommended Order filed.
PDF:
Date: 09/27/1999
Proceedings: Recommended Order
PDF:
Date: 09/27/1999
Proceedings: Recommended Order sent out. CASE CLOSED. Hearing held 8/30/99.
Date: 09/21/1999
Proceedings: Affidavit of Court Reporter filed.
Date: 09/17/1999
Proceedings: Department of Environmental Protection`s Proposed Recommended Order filed.
Date: 09/17/1999
Proceedings: CC: Letter to C. Rowe from J. T. LaVia, III (RE: deadline for filing proposed recommended Order) (filed via facsimile).
Date: 09/17/1999
Proceedings: Notice of Filing Proposed Recommended Order by Oleander Power Project; Recommended Order (for Judge Signature); Order (for Judge Signature); Disk filed.
Date: 09/14/1999
Proceedings: Letter to D. Arter from D. Dee Re: Errors in transcript; Exhibit 1 filed.
Date: 09/08/1999
Proceedings: Letter to C. Rowe from D. Dee Re: Filing proposed recommended Order (filed via facsimile).
Date: 09/07/1999
Proceedings: (2 Volumes) Transcript of Proceedings filed.
Date: 08/30/1999
Proceedings: CASE STATUS: Hearing Held.
Date: 08/26/1999
Proceedings: Oleander Power Project`s Notice of Filing Response to Clarence Rowe`s Request for Production of Documents; Oleander Power Project`s Response to Clarence Rowe`s Request for Production of Documents filed.
Date: 08/26/1999
Proceedings: Oleander Power Project`s Notice of Serving Responses to Clarence Rowe`s First Set of Interrogatories filed.
Date: 08/26/1999
Proceedings: Letter to Judge Manry from C. Rowe Re: Order denying Extension of time filed.
Date: 08/23/1999
Proceedings: (5) Subpoena ad Testificandum (C. Rowe) filed.
Date: 08/19/1999
Proceedings: Clarence Rowe`s First Set of Interrogatories to Oleander Power Project, L.P.; Clarence Rowe`s Request for Production of Documents to Oleander Power Project, L. P. filed.
Date: 08/16/1999
Proceedings: Oleander Power Project`s Motion in Limine and Response to Rowe`s Request to Allow Public Testimony filed.
Date: 08/12/1999
Proceedings: Oleander Power Project`s Notice of Rowe`s Failure to Comply With Order Denying Extension of Time filed.
Date: 08/10/1999
Proceedings: Letter to Judge Manry from D. Dee Re: Letter dated 8/6/99; Letter to Judge Manry from C. Rowe Re: Two questions regarding hearing filed.
Date: 08/09/1999
Proceedings: Letter to Judge Manry from C. Rowe (RE: request for subpoena) filed.
Date: 08/05/1999
Proceedings: Subpoena Duces Tecum (D. Dee) filed.
Date: 08/04/1999
Proceedings: Order Denying Extension of Time sent out.
Date: 07/30/1999
Proceedings: Amended Notice of Hearing sent out. (hearing set for 9:30am; Viera; 8/30/99)
Date: 07/30/1999
Proceedings: Oleander Power Project`s Motion to Compel Discovery and Response to Rowe`s Motion for Extension of Time filed.
Date: 07/30/1999
Proceedings: Oleander Power Project`s Motion to Strike filed.
Date: 07/29/1999
Proceedings: (Petitioner) Motion for Extension of Time (filed via facsimile).
Date: 07/27/1999
Proceedings: Notice of Hearing sent out. (hearing set for 9:30am; Viera; 8/25/99)
Date: 07/19/1999
Proceedings: (C. Rowe) Petition for Administrative Hearing (filed via facsimile).
Date: 07/09/1999
Proceedings: Order sent out. (Motion to dismiss is granted with Leave to amend)
Date: 07/09/1999
Proceedings: (C. Fancy) Intent to Issue Air Construction Permit w/cover letter filed.
Date: 07/02/1999
Proceedings: Letter to Judge Manry from W. Beason Re: Requesting an Extension to respond to initial Order (filed via facsimile).
Date: 06/23/1999
Proceedings: Oleander Power Project`s Notice of Service of First Set of Interrogatories to Clarence Rowe; Oleander Power Project`s Request for Production of Documents to Clarence Rowe filed.
Date: 06/23/1999
Proceedings: Oleander Power Project`s First Set of Interrogatories to Clarence Rowe; Oleander Power Project`s Motion to Dismiss or in the Alternative Motion to Strike filed.
Date: 06/18/1999
Proceedings: Order Denying Consolidation sent out.
Date: 06/16/1999
Proceedings: Oleander Power Project`s Response to the Department of Environmental Protection`s Motion to Consolidate filed.
Date: 06/15/1999
Proceedings: Initial Order issued.
Date: 06/09/1999
Proceedings: Department of Environmental Protection`s Notice of Related Cases & Motion to Consolidate; Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Intent to Issue Air Construction Permit filed.

Case Information

Judge:
DANIEL MANRY
Date Filed:
06/09/1999
Date Assignment:
06/15/1999
Last Docket Entry:
11/15/1999
Location:
Viera, Florida
District:
Northern
Agency:
ADOPTED IN PART OR MODIFIED
 

Related DOAH Cases(s) (1):

Related Florida Statute(s) (4):

Related Florida Rule(s) (3):